IT UpdateNovember 12, 2015
Agenda
Opening Remarks James Gleason
IT Update Alex Tulchinsky
IT Advisory Committee (ITAC) Background Formed in 2012 under Bob Merion’s leadership
Committee charter “Assist the UNOS CAC in fulfilling its oversight duties for UNOS operations
by providing external expertise regarding information technology efforts…”specifically . . .
Assists the CAC to develop a strategic plan for Information Technology (IT) needs of the corporation and oversees the execution of the IT plan
Identifies strategic priorities in IT, and assists the CAC in setting standards for organizational IT performance
Oversees the work of the corporation in fulfilling the IT-related requirements of the OPTN contract.
ITAC 2014/15 Composition
ITAC Chair:
ITAC members from UNOS board (3 voting members, serving 2 years):
ITAC 2014/15 Composition (cont’d)
ITAC advisors from the IT community (3 non-voting members, serving 2 years):
• Haris F. Basit• Arthur (Art) L. Glasgow• Rick Hasz
ITAC UNOS staff and board leadership :
ITAC Past Accomplishments Performed an assessment of UNOS IT organization & leadership
Performed an assessment of current and future IT workload
Reviewed past and planned IT delivery performance
Recommended leadership and organizational improvements
Recommended significant UNOS IT staff increase/development
Recommended IT process improvements
Oversee the implementation of board approved IT actions supporting those recommendations
Provided direct access and consultation with user community
ITAC 2014/15 Goals
Oversee the implementation of board approved IT actions and supporting recommendations to include . . . Continued recruitment to full staff Oversee continued IT organizational and process improvements Monitor system development and service delivery per schedules Insure continued leadership and financial support for IT effort across fiscal
calendars Provide client and expert guidance for IT futures Insure service is anchored in client need and satisfaction Continued IT translation services to the CAC and UNOS board (i.e. make IT
communications user understandable)
Projects
Customers
Technology
Data
Culture
IT Update
June 2014 – November 2014
Jun-13 & Prior Non-BoD
Nov-13
2014 2015Q2 Q3 Q4 Q1 Q2
April May June July Aug Sept Oct Nov Dec Jan Feb March April May June
Uniform National Pancreas Allocation HLA Equiv.
Donor Screening w/ Qualified Specimens Improve Vessel
TIEDI C# Conversion TIEDI and OMB Changes Patient Safety – Living Donor Events
KAS - Phase I Revised Kidney Allocation System (KAS) - Phase II HLA C & HLA DBQ Clarify A2-A2B
KPD - Phase 4 (EW/WF) Ped Liver Remove ICU Req & Modify Liver Hepatoblastoma
LAS & Diagnosis Data Element <12 Update DCD
Integrate DonorNet Import/Export into ETT Update PDDTE
Membership Inactive Screening
TIEDI and OMB Changes
Re-Instate No Appeal
2014 2015 2016
Q4 Q1 Q2 Q3 Q4 Q1
Oct Nov Dec Jan Feb March April May June July Aug Sept Oct Nov Dec Jan Feb March
(#4) Improve Vessel Disposition Reporting
Add Serum Sodium to MELD Score Deceased Donor HLA Typing
TIEDI and OMB Changes
Living Liver Donor Follow-up (#1) Require Reporting Whether Donor Screening Tests are Completed Using Qualified Specimens
Pancreas Serum Lipase
KAS Phase II HLA C & HLA DBQ
Patient Safety - Living Donor Events
Imminent & Eligible Death
Aborted Living Donor Recovery
(#2) HLA Equivalency Tables
Histo Policy
KPD Histo Testing Policies
LAS & Diagnosis Data Element <12 Ped Liver ICU Req & Liver Hepatoblastoma
(#3) Potential Donor-Derived Disease Transmission Reporting
Review Min Screening Req for Deceased Donor Clarify A2-A2B
Membership Inactive Screening
2015 Projects Timeline
ABO Blood Type Policy Mods
Donation after Circulatory Death
Reinstate "No Appeal / No Withdrawal
Proposal to Align OPTN Policies with 2013 PHS Guidelines
Modify Pediatric Heart Allocation HCC Exception Score Cap
Delay HCC Exception Score
Consent to Authorize
HOPE Act Living
HOPE Act Deceased
Jun-13 & Prior Nov-14
Nov-13 Non-BoD
Jun-14 HOPE Act
HOPE Act Prep Work
HOPE Act Impacts
Screening Requirements for Deceased Donor2013 PHS Guidelines
HOPE Act
Serologies Affecting Match Run AppearanceInfectious Disease Verification Process
Wai
tlist
Don
orN
etM
atch
Patie
nt S
afet
yM
embe
rshi
pTr
ansN
etTI
EDI
KPD
Historical Perspective
2013 – End of Year
1Y [2012]
< 1Y [2013]
3Y [2010]
2Y[2011]
5Y[2008]
4Y[2009]
21 – Pipeline 39,010 hours
2 – In Progress7650 hours
2000
4000
6000
8000
10,000
12,000
14,000
16,000
18,000
20,000
0
IT E
ffort
Est
imat
e in
Hou
rs
Age [year of BOD approval]
10,530 (5)
10,940 (4)
7650 (2)
2240 (3)
9090(4) 6210
(5)
2013 – In Progress1)Kidney Waiting Time Modifications2)Update the Calculated PRA (CPRA)
2014 – End of Year Projection
1Y [2013]
< 1Y [2014]
3Y [2011]
2Y[2012]
5Y[2009]
4Y[2010]
24 – Pipeline 24,620 hours
5 – In Progress16,560 hours
2000
4000
6000
8000
10,000
12,000
14,000
16,000
18,000
20,000
0
IT E
ffort
Est
imat
e in
Hou
rs
Age [year of BOD approval]
16,690 (12)
800 (3)1430 (1)
1180 (2)3150
(3)
7Delivered
22,740hours300 (1)300 (1)
7350 (1)
2240 (3)
5940 (1)
1540 (1)
290 (1)290 (1)
2014 – Completed1)Kidney Waiting Time2)Update CPRA3)Reorganize hemodynamic data on Heart Justification form4)Modify Requirements for Mandatory HTLV-I/II5)Patient Safety Reporting6)PA/KP Allocation7)KAS – coming December 4th
2014 – In Progress1)Ped Lung Diagnosis – Other Specify 2)TIEDI OMB 3)Revise LAS4)Potential Donor Derived Disease Transmission reporting5)Living Liver Donor Follow-up
2015 – End of Year Projection
1Y [2014]
< 1Y [2015]
3Y [2012]
2Y[2013]
5Y[2010]
4Y[2011]
6 + ? – Pipeline 7560 hours + ?
3 – In Progress1740 hours
2000
4000
6000
8000
10,000
12,000
14,000
16,000
18,000
20,000
0
IT E
ffort
Est
imat
e in
Hou
rs
Age [year of BOD approval]
21Delivered
35,880hours
1620 (2)
7560 (6) 120 (1)120 (1)
2015 – Completed1.Ped Lung Diagnosis Other Specify 2.Reinstate No Appeal/No Withdraw3.Donor Screening using Qualified Specimens (#1)4.TIEDI OMB 5.Require HLA C and HLA DQB6.Patient Safety System - Living Donor7.Clarify A2/A2B 8.Ped Liver Remove ICU9.Ped Liver Hepatablastoma10.Revise LAS 11.Consent to Authorization
12. Vessel Disposition Reporting (#4)13. Potential Donor-Derived Disease
Transmission Reporting (#3)14. Imminent and Eligible Death 15. HLA Equivalency Tables (#2)16. Minimum Screening for Deceased
Donors17. Add Serum Sodium to MELD 18. Comprehensive Histo Compatibility
Rewrite19. Living Liver Donor Follow-up 20. 2013 PHS Guideline Review 21. HOPE Act - June 2015?
2015 – In Progress1)Donation after Circulatory Death2)Cap HCC @ 343)Delay HCC
2015 – End of Year Projection
1Y [2014]
< 1Y [2015]
3Y [2012]
2Y[2013]
5Y[2010]
4Y[2011]
6 + ? – Pipeline 7560 hours + ?
3 – In Progress1740 hours
2000
4000
6000
8000
10,000
12,000
14,000
16,000
18,000
20,000
0
IT E
ffort
Est
imat
e in
Hou
rs
Age [year of BOD approval]
2 year totalprojects delivered
28 58,620 hours
(including HOPE Act)
1620 (2)
7560 (6) 120 (1)120 (1)
Customers
Technology
Current State
Small Changes …
Become Big Efforts…
User Interface &Application Layer
Business Logic & Data Layer
Request
Database
Business Logic
Front End
User Interface
Target State
Business Logic
Business Logic
Business Logic
Front End
Front End
Database Database
Modular Services operating independently of one another
Small changes have limited impact
Algorithm layer
Datalayer
Request
Information Security Update
Disaster Recovery & Business Continuity
Data
Information Architecture
Automate Collect
Exchange
Organize Analyze
Format
Store
Culture