IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

39
IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS

Transcript of IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

Page 1: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

IT PROJECTS(UNDER CAO/FOIS)

FIRST QUARTER REVIEW

********

PROGRESS AND CONCERNS

Page 2: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

APPROACH

1. PRESENT PROJECT SPECIFIC DETAILS WITH AREAS REQUIRING BOARD’S INTERVENTION

2. SHARE OUR VISION ON GENERAL ISSUES-INFRASTRUCTURE,TRAINING AND INSTITUTIONALISION

Page 3: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

IMPORTANT PROJECTS

1. FOIS

2. COA

3. ICMS

4. CMS

Page 4: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

GENERAL ISSUES

V-SAT EXPANSION

INFRASTRUTURE -BLDGS

TRAINING

SETTING UP OF CONTROLS

Page 5: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

ISSUES-FOIS

V-SAT INSTALLATION AT 203 TMS SITES

EQUIPMENTS AVAILABILITY

RAILWAY’S INVOLVEMENT

CHANGED TRAFFIC PATTERN

Page 6: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

FOIS TMS Module

524* locations on IR

212 locations on VSAT

324 locations online covering 376 sites

126 locations printing RR online covering 176 sites

Around 1100 PCs and 400 printers supplied so far

668 PCs and 612 printers under supply

*(3 locations of SR – 1 as P2, 1 closed, 1 HOM port location didn’t commission at all.)

Page 7: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

TMS VSAT locations

212 TMS locations have to be commissioned on VSATs by IRPMU

Railway Board’s target was June 2006. IRPMU’s revised target is Sept 2006

53 VSATs have been installed upto 30.06.06

37 of these were commissioned upto June 2006

The target for July 2006 is for commissioning 64 locations on VSAT

Target for 118 (64+53) locations is 15th Aug 2006

72 locations have been commissioned upto 10.08.06

Page 8: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

IMPACT ON TARGET-FOIS

V-SAT DEPENDENT TMS SITES(212) WILL TAKE LONGER TO STABLISE

RESPONSE TIME ISSUES (1500 vs700 msecs)

CHANGE IN HUB FROM VENDOR’S TO OUR OWN (Realignment of each dish)

Page 9: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

DECISION/ASSITANCE-FOIS

Nomination of 2 Rates Inspectors by each zone to CAO/FOIS for verification of referential database and testing of software changes due to rates circulars

Board’s directive for AT/generator supply from station to TMS site

Page 10: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

STATUS-COA

Pilot project under trial at Madurai and Trivandrum divisions of SRDOMs/SrDOMs visiting TVC/MDU and their reports being sent to CRIS continuously for necessary changes/enhancementsTender for customization of software for IR under finalization in CRIS. Tender for hardware and roll out to 23 divisions also under finalization in CRIS (Phase I)Strategy for roll out – In three phases Phase I – SR, SCR, SWR, CR, ECOR, SECR Phase II – WR, WCR, NCR, NR, NWR Phase III – SER, ER, ECR, NER. NFR

Page 11: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

ISSUES-COAIntegration with dataloggers

Links with RFID/GPS based tracking systems

Integration with FOIS, COIS, CMS and other public interface systems like NTES, Call centers etc

Record keeping of Control chart information – policy for archival

Page 12: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

IMPACT ON TARGET-COA

Board’s target for IR (76 locations) – Mar 2007

Latest review with CRIS indicates that software and hardware may become available by Dec 2006

Roll out @ 7 divisions per month

Mar 2007 21 divisions

Jun 2007 42 divisions

Dec 2007 76 divisions

Page 13: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

DECISION/ASSITANCE-COA

Telecom and C&IS directorates to decide terms and conditions for acquisition of interface software from Datalogger suppliers

Safety and C&IS directorates to help freeze archival policy

Page 14: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

STATUS-ICMSEnhanced scope

Punctuality Module Implemented on IR. Migrated module will be given

for testing by the end of July 2006

Coaching Stock Management Module Being implemented in three phases Software ready and under field trials at

Nizamuddin & Chennai Ready for roll out

Timetabling Module Time table simulation module’s system

requirements under discussion

Page 15: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

STATUS-ICMS

Enhanced scope (contd)

Coaching Stock Maintenance Module Scope of Mechanical module has been enhanced

from capturing of coaching depot maintenance related activities to automation of C&W department

It covers 154 depots & 975 coaching locations. Scope of Electrical Maintenance module defines

only 8 technical modules developed by NR under MIS projects. It also does not give assessment of hardware & user specifications.

Page 16: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

ICMS – Coaching Stock Management Module

Phase I – 114 terminals at 41 locations Target for implementation 31st Aug 2006

Phase II - 78 terminals at 34 locations Target for implementation 31st Oct 2006

Phase III - 128 terminals at58 locations Target for implementation 31st Dec 2006

Training 186 staff from 136 locations trained so far Training labs being set up to take care of additional

training needsEquipment Thin clients and printers supplied to all locations Datacom equipment- 57 LAN extenders supplied. Rest

under supply UPSs to be procured by zonal railways – implementation

held up for want of UPSs 14 locations commissioned – NR-1, WR-9, SECR-3 & SR-1 107 locations have been provided connectivity.

Page 17: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

ISSUES-ICMS

Purchase of UPS – zonal railwaysSupply of datacom equipment by CRIS

Freezing the scope of Mechanical & Electrical Maintenance Modules – Railway Board

450 pair modems PO placed. Supply in a month

144 pair LAN extenders

Supply completed

112 routers TC negotiation

Page 18: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

IMPACT ON TARGET-ICMS

Three months delay due to supply of UPS and datacom equipment

Mar 2007 Phase I & II – 192 locations

Jun 2007 All 320 locations

Page 19: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

DECISION/ASSITANCE-ICMS

C&IS directorate to facilitate freezing of scope for Mechanical & Electrical Maintenance Modules in view of dropping of work from MIS

C&IS directorate to sanction & release funds for time tabling module.

Page 20: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

STATUS-CMS

Detailed estimate of Rs 38.16 crores sanction by Railway Board.

302 lobbies to be covered, out of which 261 are integrated lobbies.

Target for completion 7.3.2007

Page 21: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

STATUS-CMSApplication under development and testing for Freight module Coaching, shunting and pilot module Suburban module

Site Preparation Lump sum sanctioned @ Rs 1,31,728 for major and Rs

82,890 for minor lobbies Target for readiness Aug 2006

Terminal Equipment Under vetting Target of Phase I supply - Dec 2006

Datacom Equipment Under vetting. Will be procured through CRIS

Training Core group and core implementers will be trained at CRIS Core group identified on all 16 zonal railways Training labs being set up at 5 locations

Page 22: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

ISSUES - CMS

Difference in interpretation of Board’s circulars by zonal railways in calculation of running allowance

Page 23: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

IMPACT ON TARGET-CMS

Board’s target – 302 sites by Mar 2007

Latest review with CRIS indicates software and hardware will be available only by Dec 2006.

Going by the FOIS and other roll out experience, commissioning of 30 sites per month would be a reasonable target

March 2007 100 sites

Dec 2007 202 sites

Page 24: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

DECISION/ASSITANCE-CMS

Nomination of Committee of ED s of Electrical, Mechanical, Personnel & Finance for practice to be adapted for computation of running allowance and other issues / business reengineering

Page 25: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

GENERAL ISSUES- V-SAT

HECL CONTRACT-235(+ OR- 25%)

TOTAL NEED-477

HUB CAPACITY-500 (CAN GO UPTO 1000)

TRANSPONDER HIRING ISSUE

Page 26: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

Problems relating to the VSAT Network

•Poor Application Response Time owing to High Round Trip Time (RTT)

•RTT varies between 1600 – 2400 ms for a 1000 Byte Packet Size vis-à-vis the desirable value of 1200-1400 ms.

•High Delay Variation i.e. Jitter leading to inconsistency in the Application Response Time.

Page 27: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

VSAT Issues Contd..

•Voice communication facility not yet provided at the VSAT sites.

•Video Conference requirement between CRIS & zonal Rly. Hqrs. not addressed.

•Requirement of providing connectivity to a FOIS location using a terrestrial link from the VSAT based location not met.

•Backhaul Link Failure leads to total outage of all VSAT based locations. For instance, complete failure from 14:00 hrs on 26.06.06 to 10:20 hrs of 27.06.06

Page 28: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

VSAT Service Levels

•VSAT Network to operate using Shared Hub Services from HECL till Railway owned Hub is commissioned.

•Service Level Agreement w.r.t. Quality of Service (QoS) not available with the user

•Bandwidth Allocations/ Channel Access Mechanism on the Outbound & Inbound channels not known

•Status report of Captive Hub Project not available.

Page 29: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

VSAT Migration to our own HUB•Migration Plan for shifting the Remote VSATs to our own HUB needs to be worked out while specifying the following parameters:

- Service disruption due to re-alignment of Antenna/Tx-Rx Frequency at each remote site.

- Time required for establishing end-to-end connectivity between remote site and the

FOIS datacentre

- Overall Stabilization of the VSAT Network

Page 30: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

GENERAL ISSUES -INFRASTRUTURE

INVESTMENT

SPACE-BLDG

MANPOWER

DISASTER TOLERANCE

Page 31: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

GENERAL ISSUES -TRAINING

CURRICULAM IN TRAINING INSTITUTES-TRAFFIC,MECHANICAL,ELECTRICAL-MPP DTE’S ROLE

ADDITIONALTRAINING CENTERS –5 (DLI,SC,BB,HWH,TPJ)

Page 32: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

Growth of IT projects in IR

IR’s capital budget for IT is Rs. 273 crore in 2006-07

It is projected to increase to about Rs. 900 crore to Rs. 1200 crore by 2010 – 2011

To make this scale of operation possible, requirement of space and other facilities for CRIS and FOIS organization needs to be significantly increased

Page 33: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

Statement of Expenditure of the Projects under CAO/FOIS

YEAR EXPENDITURE

(Rs. in Crores)

2000 – 2001 22.8

2001 – 2002 30.4

2002 – 2003 17.4

2003 – 2004 17.0

2004 – 2005 30.4

2005 – 2006 40.0

Page 34: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

Anticipated increase in strength of FOIS and space requirement

Year

Approx IT budget

(Rs. Crore)FOIS manpower

(total)

Manpower based in

HQ

Bare seating

space (sq m)

Support space

Training areas,

central control

room etc.

Total space requiremen

t (sq m)

2006-07 300 264 140 420 420 210 1050

2007-08 360 317 160 480 480 240 1200

2008-09 450 396 200 600 600 300 1500

2009-10 540 475 240 720 720 360 1800

2010-11 650 572 290 870 870 435 2175

2011-12 800 704 360 1080 1080 540 2700

Page 35: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

Projected growth of manpower in CRIS

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

2006 2007 2008 2009 2010 2011

Year

Trainees

Procurement staff

Support staff

IT/HW

Help Desk

N/W

DBA

Implementers (full-time)

Developers

Managers

Page 36: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

SPACE - CRIS location

Page 37: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

SPACE – Area with Railways

Page 38: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

Required facilities for expansion

Secure areas in redRestricted areas in orange Open access in

green

Page 39: IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.

THANK YOU