IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.
-
Upload
amaya-chauncey -
Category
Documents
-
view
217 -
download
4
Transcript of IT PROJECTS (UNDER CAO/FOIS) FIRST QUARTER REVIEW ******** PROGRESS AND CONCERNS.
IT PROJECTS(UNDER CAO/FOIS)
FIRST QUARTER REVIEW
********
PROGRESS AND CONCERNS
APPROACH
1. PRESENT PROJECT SPECIFIC DETAILS WITH AREAS REQUIRING BOARD’S INTERVENTION
2. SHARE OUR VISION ON GENERAL ISSUES-INFRASTRUCTURE,TRAINING AND INSTITUTIONALISION
IMPORTANT PROJECTS
1. FOIS
2. COA
3. ICMS
4. CMS
GENERAL ISSUES
V-SAT EXPANSION
INFRASTRUTURE -BLDGS
TRAINING
SETTING UP OF CONTROLS
ISSUES-FOIS
V-SAT INSTALLATION AT 203 TMS SITES
EQUIPMENTS AVAILABILITY
RAILWAY’S INVOLVEMENT
CHANGED TRAFFIC PATTERN
FOIS TMS Module
524* locations on IR
212 locations on VSAT
324 locations online covering 376 sites
126 locations printing RR online covering 176 sites
Around 1100 PCs and 400 printers supplied so far
668 PCs and 612 printers under supply
*(3 locations of SR – 1 as P2, 1 closed, 1 HOM port location didn’t commission at all.)
TMS VSAT locations
212 TMS locations have to be commissioned on VSATs by IRPMU
Railway Board’s target was June 2006. IRPMU’s revised target is Sept 2006
53 VSATs have been installed upto 30.06.06
37 of these were commissioned upto June 2006
The target for July 2006 is for commissioning 64 locations on VSAT
Target for 118 (64+53) locations is 15th Aug 2006
72 locations have been commissioned upto 10.08.06
IMPACT ON TARGET-FOIS
V-SAT DEPENDENT TMS SITES(212) WILL TAKE LONGER TO STABLISE
RESPONSE TIME ISSUES (1500 vs700 msecs)
CHANGE IN HUB FROM VENDOR’S TO OUR OWN (Realignment of each dish)
DECISION/ASSITANCE-FOIS
Nomination of 2 Rates Inspectors by each zone to CAO/FOIS for verification of referential database and testing of software changes due to rates circulars
Board’s directive for AT/generator supply from station to TMS site
STATUS-COA
Pilot project under trial at Madurai and Trivandrum divisions of SRDOMs/SrDOMs visiting TVC/MDU and their reports being sent to CRIS continuously for necessary changes/enhancementsTender for customization of software for IR under finalization in CRIS. Tender for hardware and roll out to 23 divisions also under finalization in CRIS (Phase I)Strategy for roll out – In three phases Phase I – SR, SCR, SWR, CR, ECOR, SECR Phase II – WR, WCR, NCR, NR, NWR Phase III – SER, ER, ECR, NER. NFR
ISSUES-COAIntegration with dataloggers
Links with RFID/GPS based tracking systems
Integration with FOIS, COIS, CMS and other public interface systems like NTES, Call centers etc
Record keeping of Control chart information – policy for archival
IMPACT ON TARGET-COA
Board’s target for IR (76 locations) – Mar 2007
Latest review with CRIS indicates that software and hardware may become available by Dec 2006
Roll out @ 7 divisions per month
Mar 2007 21 divisions
Jun 2007 42 divisions
Dec 2007 76 divisions
DECISION/ASSITANCE-COA
Telecom and C&IS directorates to decide terms and conditions for acquisition of interface software from Datalogger suppliers
Safety and C&IS directorates to help freeze archival policy
STATUS-ICMSEnhanced scope
Punctuality Module Implemented on IR. Migrated module will be given
for testing by the end of July 2006
Coaching Stock Management Module Being implemented in three phases Software ready and under field trials at
Nizamuddin & Chennai Ready for roll out
Timetabling Module Time table simulation module’s system
requirements under discussion
STATUS-ICMS
Enhanced scope (contd)
Coaching Stock Maintenance Module Scope of Mechanical module has been enhanced
from capturing of coaching depot maintenance related activities to automation of C&W department
It covers 154 depots & 975 coaching locations. Scope of Electrical Maintenance module defines
only 8 technical modules developed by NR under MIS projects. It also does not give assessment of hardware & user specifications.
ICMS – Coaching Stock Management Module
Phase I – 114 terminals at 41 locations Target for implementation 31st Aug 2006
Phase II - 78 terminals at 34 locations Target for implementation 31st Oct 2006
Phase III - 128 terminals at58 locations Target for implementation 31st Dec 2006
Training 186 staff from 136 locations trained so far Training labs being set up to take care of additional
training needsEquipment Thin clients and printers supplied to all locations Datacom equipment- 57 LAN extenders supplied. Rest
under supply UPSs to be procured by zonal railways – implementation
held up for want of UPSs 14 locations commissioned – NR-1, WR-9, SECR-3 & SR-1 107 locations have been provided connectivity.
ISSUES-ICMS
Purchase of UPS – zonal railwaysSupply of datacom equipment by CRIS
Freezing the scope of Mechanical & Electrical Maintenance Modules – Railway Board
450 pair modems PO placed. Supply in a month
144 pair LAN extenders
Supply completed
112 routers TC negotiation
IMPACT ON TARGET-ICMS
Three months delay due to supply of UPS and datacom equipment
Mar 2007 Phase I & II – 192 locations
Jun 2007 All 320 locations
DECISION/ASSITANCE-ICMS
C&IS directorate to facilitate freezing of scope for Mechanical & Electrical Maintenance Modules in view of dropping of work from MIS
C&IS directorate to sanction & release funds for time tabling module.
STATUS-CMS
Detailed estimate of Rs 38.16 crores sanction by Railway Board.
302 lobbies to be covered, out of which 261 are integrated lobbies.
Target for completion 7.3.2007
STATUS-CMSApplication under development and testing for Freight module Coaching, shunting and pilot module Suburban module
Site Preparation Lump sum sanctioned @ Rs 1,31,728 for major and Rs
82,890 for minor lobbies Target for readiness Aug 2006
Terminal Equipment Under vetting Target of Phase I supply - Dec 2006
Datacom Equipment Under vetting. Will be procured through CRIS
Training Core group and core implementers will be trained at CRIS Core group identified on all 16 zonal railways Training labs being set up at 5 locations
ISSUES - CMS
Difference in interpretation of Board’s circulars by zonal railways in calculation of running allowance
IMPACT ON TARGET-CMS
Board’s target – 302 sites by Mar 2007
Latest review with CRIS indicates software and hardware will be available only by Dec 2006.
Going by the FOIS and other roll out experience, commissioning of 30 sites per month would be a reasonable target
March 2007 100 sites
Dec 2007 202 sites
DECISION/ASSITANCE-CMS
Nomination of Committee of ED s of Electrical, Mechanical, Personnel & Finance for practice to be adapted for computation of running allowance and other issues / business reengineering
GENERAL ISSUES- V-SAT
HECL CONTRACT-235(+ OR- 25%)
TOTAL NEED-477
HUB CAPACITY-500 (CAN GO UPTO 1000)
TRANSPONDER HIRING ISSUE
Problems relating to the VSAT Network
•Poor Application Response Time owing to High Round Trip Time (RTT)
•RTT varies between 1600 – 2400 ms for a 1000 Byte Packet Size vis-à-vis the desirable value of 1200-1400 ms.
•High Delay Variation i.e. Jitter leading to inconsistency in the Application Response Time.
VSAT Issues Contd..
•Voice communication facility not yet provided at the VSAT sites.
•Video Conference requirement between CRIS & zonal Rly. Hqrs. not addressed.
•Requirement of providing connectivity to a FOIS location using a terrestrial link from the VSAT based location not met.
•Backhaul Link Failure leads to total outage of all VSAT based locations. For instance, complete failure from 14:00 hrs on 26.06.06 to 10:20 hrs of 27.06.06
VSAT Service Levels
•VSAT Network to operate using Shared Hub Services from HECL till Railway owned Hub is commissioned.
•Service Level Agreement w.r.t. Quality of Service (QoS) not available with the user
•Bandwidth Allocations/ Channel Access Mechanism on the Outbound & Inbound channels not known
•Status report of Captive Hub Project not available.
VSAT Migration to our own HUB•Migration Plan for shifting the Remote VSATs to our own HUB needs to be worked out while specifying the following parameters:
- Service disruption due to re-alignment of Antenna/Tx-Rx Frequency at each remote site.
- Time required for establishing end-to-end connectivity between remote site and the
FOIS datacentre
- Overall Stabilization of the VSAT Network
GENERAL ISSUES -INFRASTRUTURE
INVESTMENT
SPACE-BLDG
MANPOWER
DISASTER TOLERANCE
GENERAL ISSUES -TRAINING
CURRICULAM IN TRAINING INSTITUTES-TRAFFIC,MECHANICAL,ELECTRICAL-MPP DTE’S ROLE
ADDITIONALTRAINING CENTERS –5 (DLI,SC,BB,HWH,TPJ)
Growth of IT projects in IR
IR’s capital budget for IT is Rs. 273 crore in 2006-07
It is projected to increase to about Rs. 900 crore to Rs. 1200 crore by 2010 – 2011
To make this scale of operation possible, requirement of space and other facilities for CRIS and FOIS organization needs to be significantly increased
Statement of Expenditure of the Projects under CAO/FOIS
YEAR EXPENDITURE
(Rs. in Crores)
2000 – 2001 22.8
2001 – 2002 30.4
2002 – 2003 17.4
2003 – 2004 17.0
2004 – 2005 30.4
2005 – 2006 40.0
Anticipated increase in strength of FOIS and space requirement
Year
Approx IT budget
(Rs. Crore)FOIS manpower
(total)
Manpower based in
HQ
Bare seating
space (sq m)
Support space
Training areas,
central control
room etc.
Total space requiremen
t (sq m)
2006-07 300 264 140 420 420 210 1050
2007-08 360 317 160 480 480 240 1200
2008-09 450 396 200 600 600 300 1500
2009-10 540 475 240 720 720 360 1800
2010-11 650 572 290 870 870 435 2175
2011-12 800 704 360 1080 1080 540 2700
Projected growth of manpower in CRIS
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
2006 2007 2008 2009 2010 2011
Year
Trainees
Procurement staff
Support staff
IT/HW
Help Desk
N/W
DBA
Implementers (full-time)
Developers
Managers
SPACE - CRIS location
SPACE – Area with Railways
Required facilities for expansion
Secure areas in redRestricted areas in orange Open access in
green