IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director...

21
IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008

Transcript of IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director...

Page 1: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

IT in Nuclear Decommissioning:Minimising Exposure to Risk

Mark Biagi, Strategic Projects Director 10th March 2008

Page 2: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Introduction

Case study 1:Leningrad Nuclear

Power PlantCase study 2:Japan NuclearFuels Limited

Case study 3:Hanford WasteTreatment Plant

Page 3: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

• Operating from 1966 to 2015• Preparing for SAFSTOR• Creating a decommissioning

database for future generations based on Bentley technology

• Researching ways of presenting and organising information

• “An information system for decommissioning is absolutely required.”- Neolant

Case study 1– Leningrad NPP, Neolant

Page 4: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Page 5: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Page 6: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Case study 1 – Summary

Information volume

Information integrity

1966 1967 1973 ~2015 ~2106time

Comprehensibility

Longevity

Standardisation

Page 7: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Standardisation – ISO 15926

Page 8: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

• Integrated engineering system based on Bentley technology since 2002

• Major 2D – 3D legacy data translation

• 3D decommissioning system based on MicroStation and Navigator

• Security and accountability documentation

Case study 2 – JNFL, Japan Nuclear Fuels Limited

Reprocessing Plant

Uranium Enrichment

Page 9: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

解体手順計画グループ構造を維持した切断

Page 10: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Page 11: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Case Study 2 – Summary

Risk minimised through:− Work breakdown structure

optimisation− Advanced simulations− Immersive visualisation− Container optimisation

− Special WBS research project underway with a major nuclear equipment vendor

Page 12: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

• 53M gallons of radioactive liquid waste stored in 177 underground tanks

• World’s largest radioactive waste treatment vitrification plant

• Distributed engineering environment, 3 design centres, largest ProjectWise deployment to date

• Complex project, on the scale of 2 nuclear power plants

Case study 3– Bechtel, Hanford Waste Treatment Plant

Hanford WTP

Page 13: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

WTP Project Primary Design Office

Richland, WA

WTP Project Remote Design Office

San Francisco, CA

WTP Project Remote Design Office

Fredrick, MD

High-level waste facility model

Pre-treatment facility model

MasterDB

Oracle ReplicationTechnology

Page 14: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Case Study 3 – Summary

Risk minimised through:− Distributed enterprise work

sharing− Remote collaboration of best

available resources

− Associated construction with decommissioning

Page 15: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Summary of case studies

Case study 1:Leningrad Nuclear

Power Plant

Preparing for decommissioning:

•Information system for future generations•Change management

Case study 2:Japan NuclearFuels Limited

Actively decommissioning:

•Optimisation•Simulation•WBS•Planning

Case study 3:Hanford WasteTreatment Plant

Construction associated with decommissioning:

•Work sharing•Remote collaboration

Page 16: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Decommissioning challenge

Year NPP’s to decommission

Capacity to replace (MWe)

Equivalent New Build

5 26 11,942 12

10 115 75,649 76

15 196 130,028 130

20 328 249,246 249

25 373 309,908 310

(Assumes average 40 year NPP lifespan and 1000MWe new build)

Units

0

5

10

15

20

25

30

35

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 2 21 2 2 2 2 2 2 2 2 3 31 3 3 3 3 3 3 3 3 4 41

Data source: IAEACurrent NPP age profile (Total = 437)

Nu

mb

er

30

15

00 20 40Age (years)

Page 17: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Comprehensive Portfolio

Page 18: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

ASME III Class 1 Piping Systems

ADLPipe

Design and AnalysisBentley AutoPIPE

STAAD.ProBentley WinNOZLBentley PlantFlow

Bentley PULSAutoPLANT PDW

Bentley ArchitecturalBentley Structural

PlantSpace Isometrics PlantSpace Design SeriesPlantSpace Orthographics

PlantSpace SupportModeler

Haested WaterCADBentley Rebar

Haested PondPakPW Schedule Simulation

PW Interference ManagerPower Civil

Bentley CloudWorxNuclear QA&R *

Configuration Management and CollaborationProjectWisePW LifeCycle ServerISO 15926Bentley I/RAS BPW NavigatorAXSYS.IntegrityBentley RedlineBentley ViewPW Plot OrganizerPDF Composer

Control and Communication Systems

Bentley I&WBentley Hookups

Bentley Inside Plant

FEEDAXSYS.ProcessAXSYS.EngineBentley P&IDData ManagerDatasheetsPlantWise

Bentley Nuclear Solutions

* Bentley maintains a nuclear QA subscription program which meets all applicable requirements of 10CFR50 App. B, 10CFR21, ASME NQA-1 and ANSI N45.2.  Both AutoPIPE and STAAD.PRO software are covered under Bentley Nuclear QA program and widely used for safety-related applications.

Page 19: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

A few of our nuclear customers

Page 20: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

European Nuclear Forum 2008, BrusselsCopyright © Bentley Systems 2008

Conclusion

• Minimising risk through IT in nuclear decommissioning:− Today it’s about digitisation, decommissioning databases,

remote collaboration, work packaging, simulation, visualisation− Tomorrow it will be about open standard interoperability of

information and tools for lifecycle engineering management, and nuclear strength management of change

• Bentley is a leading IT provider in the nuclear engineering market

Leningrad NPP

JNFL Hanford WTP

Page 21: IT in Nuclear Decommissioning: Minimising Exposure to Risk Mark Biagi, Strategic Projects Director 10 th March 2008.

Thank you.