Isolation Valve Installation Readiness
Trevor Smith/Mark Nichols 11 May 2010
MC 252 Incident Response
![Page 2: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ef05503460f94c01423/html5/thumbnails/2.jpg)
2
Problem Statement
Capping of the well with the dual ram or isolation valve assembly will require:
•stabbing into a flange opening which may be obstructed by debris and flowing oil and gas
•aligning and bolting up a flange connection which is designed for make-up on the drill floor
•and performing this for the first time at 5000ft water depth, suspended from a drill rigProposal: perform onshore and/or onshore trials to
maximize probability of success
![Page 3: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ef05503460f94c01423/html5/thumbnails/3.jpg)
MC 252 Site Overview
![Page 4: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ef05503460f94c01423/html5/thumbnails/4.jpg)
Top of BOP Stack
![Page 5: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ef05503460f94c01423/html5/thumbnails/5.jpg)
Mule Shoe Detail
![Page 6: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ef05503460f94c01423/html5/thumbnails/6.jpg)
Readiness Summary
Flex Joint Capping Method - Readiness Status DRAFT
Item Comment Status Item Comment Status
Equipment Valve Assembly Issued to D&C at Berwick Ram Assembly Assembly by D&C at BerwickRunning Assembly Being assembed Running Assembly Being assembed
Pressure Cap Status unknown Pressure Cap Status unknownROV Tools Available - location to be confirmed ROV Tools Available - location to be confirmed
Vessels ROV Vessel Vessel TBD - briefing required ROV Vessel Vessel TBDMODU DDII Briefing required MODU DDII
Procedures Riser Removal Being updated by BP to Rev1 Riser Removal Being updated by BPFlange Removal Being developed by BP Eng. Flange Removal Being developed by BP Eng.Valve Running Developed by BP D&C Valve Running Developed by BP D&CFlange Make-up Being developed by BP Eng. Flange Make-up Being developed by BP Eng.
Trials Onshore Not in plan Onshore Not in planSite to be selected - BP Fourchon? Site to be selected - BP Fourchon?
Subsea Not in plan Subsea Not in planTest Stump/Mat: build & deploy Test Stump/Mat: build & deploy
Readiness Review Peer Review Peer Review
Legend Ready for useIn progress - on track
Potential risk 11-May-2010
Isolation Valve Dual Ram BOP
![Page 7: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ef05503460f94c01423/html5/thumbnails/7.jpg)
Trial Objectives & Site Suitability
Issue to be checked or tested Onshore Test Suitability
Subsea Test Suitability
Alignment pin & plug make-up risks Risk of seal damage Befit or risk from pins & plug use Mule shoe engagement with pipe debris Flange rotation & bolt release ROV tool access & function/speed ROV crew familiarization & training Rig crew familiarization &training Ability to stab with rig X Ability to keep flange alignment during make-up
X
Flow effect on seals X XStabbing under flow X X
![Page 8: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ef05503460f94c01423/html5/thumbnails/8.jpg)
Schedule
DRAFTActivities
Draft objectives
Establish plan
Fabricate Test Stump
Onshore Trial
Develop Trial Procedures
Approve Trial Procedures
Set-up Trial Site
Perform Onshore Trials
Modify Valve/Ram Assemblies
Ship Assemblies to DD-II
Offshore Trial
Ship Test Stump & Install on Seabed
Run DD-II Riser with Cap Assembly
Perform Trial
Modify Procedure
Go/No-Go Decision
Well Capping
Riser Cutting
Cap Well
22 23 24 2518 19 20 21Sun Mon Tue
11 12 13 14 15 16 17Wed Thu Fri SatSat Sun Mon TueTue Wed Thu Fri
![Page 9: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.](https://reader035.fdocuments.in/reader035/viewer/2022072016/56649ef05503460f94c01423/html5/thumbnails/9.jpg)
Other Issues
• Decide if trials are necessary, if so which & when
• Define Accountabilities
• Confirm ROV vessel for flange unbolting
• Confirm ROVs for flange make-up (DD2 or other support vessel)