IPEK energy GmbH Development and Implementation of a Wind Farm

56
1 IPEK energy GmbH Development and Implementation of a Wind Farm 3rd International Conference on Alternative Energy & Power ICAEP 28 March 2009

description

3rd International Conference on Alternative Energy & Power ICAEP. IPEK energy GmbH Development and Implementation of a Wind Farm. 28 March 2009. Content. Company Profile Wind energy - an introduction Steps to install a wind farm Selection of wind turbines - PowerPoint PPT Presentation

Transcript of IPEK energy GmbH Development and Implementation of a Wind Farm

Page 1: IPEK energy GmbH Development and Implementation of a Wind Farm

1

IPEK energy GmbH

Development and Implementation of a Wind Farm

3rd International Conference onAlternative Energy & Power ICAEP

28 March 2009

Page 2: IPEK energy GmbH Development and Implementation of a Wind Farm

2

Content

Company Profile

Wind energy - an introduction

Steps to install a wind farm

Selection of wind turbines

Selected wind turbine for ZORLU: VENSYS

Project implementation

Page 3: IPEK energy GmbH Development and Implementation of a Wind Farm

3

Content

Company Profile

Wind energy - an introduction

Steps to install a wind farm

Selection of wind turbines

Selected wind turbine for ZORLU: VENSYS

Project implementation

Page 4: IPEK energy GmbH Development and Implementation of a Wind Farm

4

IPEK energy GmbH

We

are an independent engineering & consultancy company

support you from acquisition to turnkey ready construction of renewable power generation systems world wide

offer skilful support with international financing and after commissioning

take the technical business management

are very flexible and act in close cooperation with our clients exactly to the requirements of the international markets

Page 5: IPEK energy GmbH Development and Implementation of a Wind Farm

5

Key Services

Engineering & Consulting acquire suitable sitesdesign of whole wind farm (micro-siting, electrical, civil)complete permitting proceduresnegotiate required Power Purchase Agreement (PPA)organize international fundingsupervision of construction till take over of the plancontrol operations management

Wind Measuring standard IEC confirm measuring trough Wind Mastand SODAR measuring

Bankable Feasibility Studies Due Diligence Emissions Trading

Page 6: IPEK energy GmbH Development and Implementation of a Wind Farm

6

Osman Ipek – Managing Director

Electrical Engineer (Main Branch Renewable Energies)Active in Wind Branch since 2000

project developmentproject managementproject implementationengineeringdue diligencemeasurement and monitoring systemswind resource assessmentteaching and education, concepts; strategies; system layout

18 Wind farm Projects realizedMore than 800MW projects developed in 6 countriesDue Diligence of more than 220MW wind projectsFeasibility studies for more than 40 wind farmsCurrently on going Projects of >400MW in Turkey, Romania and Pakistan

Page 7: IPEK energy GmbH Development and Implementation of a Wind Farm

7

Countries of Work Experience

Page 8: IPEK energy GmbH Development and Implementation of a Wind Farm

8

Membership/ Partners

Memberships Partners

German Wind Energy Association

The Association of German Engineers

Pakistan Wind Energy Association

WINDTEST Grevenbroich GmbH

Page 9: IPEK energy GmbH Development and Implementation of a Wind Farm

9

Company Profile

Wind energy - an introduction

Steps to install a wind farm

Selection of wind turbines

Selected wind turbine for ZORLU: VENSYS

Project implementation

Page 10: IPEK energy GmbH Development and Implementation of a Wind Farm

10

A wind turbine obtains its power input by converting the force of the wind into a torque acting on the rotor blades

The amount of energy which the wind transfers to the rotor depends

- on the density of the air- the rotor area- and the wind speed.

In other words you can get more energy:

- the "heavier" the air- the “bigger” the rotor- the “higher” the wind speed

How does it work

Page 11: IPEK energy GmbH Development and Implementation of a Wind Farm

11

690V

Components of a Wind Turbine

Page 12: IPEK energy GmbH Development and Implementation of a Wind Farm

12

Components of Wind Turbine

Page 13: IPEK energy GmbH Development and Implementation of a Wind Farm

13

Company Profile

Wind energy - an introduction

Steps to install a wind farm

Selection of wind turbines

Selected wind turbine for ZORLU: VENSYS

Project implementation

Page 14: IPEK energy GmbH Development and Implementation of a Wind Farm

14

12 Steps to install a wind farm

1. WIND ASSESSMENT... available wind data will be used to estimate how much

energy the wind farm will produce.

2. WIND FARM DESIGNWind data combined with topographical information to design

the wind farm..... to model wind flow, ... turbine performance... sound levels ... to optimize the location of WTG ... design the access roads... turbine foundations ... local electric network... grid connection

Page 15: IPEK energy GmbH Development and Implementation of a Wind Farm

15

3. ENVIRONMENTAL STUDY... to identify any impacts on landscape, plants and wildlife,

soil and water, land use, aviation, telecommunications, etc.

4. LAND ACQUISITION... to negotiate “option” agreements to use land

5. PERMITTING AND PUBLIC CONSULTATION... seek municipal, provincial and federal permits before the

project can go ahead. ... meet the local communities to present the project, solicit

their feedback and seek community support.

12 Steps to install a wind farm

Page 16: IPEK energy GmbH Development and Implementation of a Wind Farm

16

6. ECONOMIC AND FINANCIAL ANALYSIS… demonstration of the economic viability of the project to raise

the funds… estimate the cost of turbines and their installation, as well as

roads, electrical system, operation and maintenance, etc.... estimate the income by using the energy production of the

wind farm over the lifetime of the project

7. MANUFACTURINGWTG parts are manufactured and pre-assembled into the main

components at the factory and shipped to the wind farm site where the final assembly will take place.

12 Steps to install a wind farm

Page 17: IPEK energy GmbH Development and Implementation of a Wind Farm

17

8. SITE PREPARATIONThe wind farm site will be prepared before the WTG will arrive to

site. ... access roads, clear the areas where turbines will be erected... preparation of the foundations (do the excavating; installing

the formworks; pouring concrete)

9. CONSTRUCTIONAfter arrival of all components, the assembly can take place by

using a crane to erect the tower and install the nacelle and rotor with its hub and blades. Same time the electrical works will be performed

12 Steps to install a wind farm

Page 18: IPEK energy GmbH Development and Implementation of a Wind Farm

18

10. COMMISSIONINGThe wind farm will tested before becoming fully operational.

11. OPERATION AND MAINTENANCEA variety of skill sets are required to ensure the effective operation of a Wind Farm (activities be performed on a regular basis throughout the project’s, monitoring and analyzing performance, performing preventive maintenance and repairs on the turbines)

12. …..

12 Steps to install a wind farm

visit Hall 1 – A36

Page 19: IPEK energy GmbH Development and Implementation of a Wind Farm

19

Steps from LOI to Implementation

Page 20: IPEK energy GmbH Development and Implementation of a Wind Farm

20

Company Profile

Wind energy - an introduction

Steps to install a wind farm

Selection of wind turbines

Selected wind turbine for ZORLU: VENSYS

Project implementation

Page 21: IPEK energy GmbH Development and Implementation of a Wind Farm

21

On Site Wind Measuring (example)

Page 22: IPEK energy GmbH Development and Implementation of a Wind Farm

22

Compliance with the site wind conditionsSpecific costs (e. g. costs per kWh)Readiness of supplier to offer turbines Commitment to the marketDelivery timeWarranties: power curve, availability, grid complianceCompleteness of technical documentationTrack record of WTG modelCompany: position in market, financial strength, etc. Operation and Maintenance conceptCrane availability

Selection Criteria for Wind Turbines

Page 23: IPEK energy GmbH Development and Implementation of a Wind Farm

23

Different size of WTGs / Cost per kW

WTG: 1MW, 70m hub

WTG: 2MW, 100m hub

Page 24: IPEK energy GmbH Development and Implementation of a Wind Farm

24

Large wind farm vs. smal wind farm

Source: www.awea.org

Page 25: IPEK energy GmbH Development and Implementation of a Wind Farm

25

Selection Criteria for Wind Turbines

Availability of 400t cranes is higher than 600t

WTG <2MW should be selected for Pakistan

Page 26: IPEK energy GmbH Development and Implementation of a Wind Farm

26

Company Profile

Wind energy - an introduction

Steps to install a wind farm

Selection of wind turbines

Selected wind turbine for ZORLU: VENSYS

Project implementation

Page 27: IPEK energy GmbH Development and Implementation of a Wind Farm

27

No Gearbox

Synchronous Generator Self Cooling

No Pitch gear

Selected Wind Turbine: VENSYS

Page 28: IPEK energy GmbH Development and Implementation of a Wind Farm

28

Generator is fully encased

(protected against dust/sand)

Generator & Cooling system

Page 29: IPEK energy GmbH Development and Implementation of a Wind Farm

29

Maintenance

friendly

No Crane needed

AC Pitch motor

Capacitor instead Batteries

Less maintenance

Page 30: IPEK energy GmbH Development and Implementation of a Wind Farm

30

Compliance with the site wind conditions Specific costs (e. g. costs per kWh) Readiness of supplier to offer turbines Commitment to the market Delivery timeWarranties: power curve, availability, grid compliance Completeness of technical documentation Track record of WTG model Company: position in market, financial strength, etc. Operation and Maintenance concept Crane availability

Selection Criteria for Wind Turbines

- the shortest delivery time comparing to other- OK

- OK

- OK- optimal

- OK- OK

- OK- OK

– Less maintenance- OK for 400t crane

Page 31: IPEK energy GmbH Development and Implementation of a Wind Farm

31

Draft Time Table

Page 32: IPEK energy GmbH Development and Implementation of a Wind Farm

32

Company Profile

Wind energy - an introduction

Steps to install a wind farm

Selection of wind turbines

Selected wind turbine for ZORLU: VENSYS

Project implementation

Page 33: IPEK energy GmbH Development and Implementation of a Wind Farm

33

WF site of Zorlu together with neighbors FFC and Masterwind

North

Page 34: IPEK energy GmbH Development and Implementation of a Wind Farm

34

Wind resource map at 69m

Page 35: IPEK energy GmbH Development and Implementation of a Wind Farm

35

Wind resource map at 85m

Page 36: IPEK energy GmbH Development and Implementation of a Wind Farm

36

Wind turbine siting

Page 37: IPEK energy GmbH Development and Implementation of a Wind Farm

37

Noise and Shadow analysis

Page 38: IPEK energy GmbH Development and Implementation of a Wind Farm

38

Scales of noise emissions

150

140

130

120

110

100

90

80

70

60

50

40

30

20

10

Jet Airplane

Industrial Noise

Typewriter

Leaf FallWhispering

Air Hammer

Inside Car

Home

Office

Wind Turbine

Jet Airplane

Industrial Noise

TypewriterTypewriter

Home

Whispering

Air Hammer

Inside Car

Wind Turbine

Page 39: IPEK energy GmbH Development and Implementation of a Wind Farm

39

85m wind measuring mast of ZORLU

The highest wind measuring mast in Pakistan

Page 40: IPEK energy GmbH Development and Implementation of a Wind Farm

40

Ground Breaking Ceremony ZORLU

January 2007

Page 41: IPEK energy GmbH Development and Implementation of a Wind Farm

41

Transportation study

Page 42: IPEK energy GmbH Development and Implementation of a Wind Farm

42

Transport problems identified and solved

Page 43: IPEK energy GmbH Development and Implementation of a Wind Farm

43

Implementation - Soil Study

Page 44: IPEK energy GmbH Development and Implementation of a Wind Farm

44

Implementation- Seismic Study

Page 45: IPEK energy GmbH Development and Implementation of a Wind Farm

45

Implementation - Public Consultation

Page 46: IPEK energy GmbH Development and Implementation of a Wind Farm

46

Impressions

Page 47: IPEK energy GmbH Development and Implementation of a Wind Farm

47

Foundation works

Page 48: IPEK energy GmbH Development and Implementation of a Wind Farm

48

Wind Farm cabling

Page 49: IPEK energy GmbH Development and Implementation of a Wind Farm

49

Coordination Meetings & start of Installation

Page 50: IPEK energy GmbH Development and Implementation of a Wind Farm

50

Installation of WTG

Page 51: IPEK energy GmbH Development and Implementation of a Wind Farm

51

Installation

Page 52: IPEK energy GmbH Development and Implementation of a Wind Farm

52

Internal electrical works

Page 53: IPEK energy GmbH Development and Implementation of a Wind Farm

53

Pakistan first wind turbine

Page 54: IPEK energy GmbH Development and Implementation of a Wind Farm

54

The first wind farm of Pakistan

Page 55: IPEK energy GmbH Development and Implementation of a Wind Farm

55

Thank you for your attention

Page 56: IPEK energy GmbH Development and Implementation of a Wind Farm

56

Contact

IPEK energy Pakistan Pvt. Ltd.

89/II Khayaban-e-ShujaatDHA Phase VI

Karachi - PakistanTel.:   +92.21.543 20 91Fax:   +92.21.543 20 92

For any further information please contact us:

www.ipek-energy.com