Closing Conference for IPA 128287 - Partnership Actions on Environment
IPA Power Scotland Conference
-
Upload
smarter-grid-solutions -
Category
Technology
-
view
23 -
download
1
Transcript of IPA Power Scotland Conference
Overview
♦Background
♦DER integration and contribution to the system
♦Security and balancing in Microgrids
♦Conclusions
2
3
Background: Example ANM Scenario
Product: ANM 50
Generation export of real power raises voltage at point of
connection and along the feeder resulting in AVC scheme
operation and low voltage measurements on parallel
feeders.
Operation:
• Real-time monitoring at PCC, end of line voltage on
lowest voltage feeder and at the substation.
• Curtail real-power when beyond voltage design limits
• Regulate the production or absorption of reactive power
• Adjust the target voltage of the on load tap change
controller
Primary
Substation 1
SCADA / DMS
Generator
Generator
Existing
generation
outside of ANM
system
ANM enabled
generator
within control
of ANM system
i v i v
Generator
Generator
i v
Generator
i v
v
ANM 50
Generator
i v
Generator
i v
AVC
Scheme
ANM 50
DER integration and contribution to the system What have we learned about DER integration and the role of Active Network Management (ANM) in the last year?
4
5
Cambridgeshire
Challenge Increase grid capacity, reduce time to connect and cost of connection for distributed generation in Cambridgeshire. Technical challenges include thermal overloads and localised voltage rise constraints.
Solution
♦ Non-firm actively managed grid connections for distributed generation using ANM 100.
♦ Integration with Dynamic Line Rating relays and Quad Booster Control System.
Delivered Benefits
♦ 15 generators (55 MW) accepted ANM connection offers out of the 24 connection offers made
♦ Reduction of CAPEX in connection offers of 75-95% to individual generators
♦ Aggregate saving of £44m
♦ 29 week decrease in connection time. EPN licence area heat map for DG
connections
Cambridgeshire ANM area Norwich ANM
area launched
Dec 2014
following
success of
Cambridgeshire
6
Cambridgeshire H
igh
leve
l sc
he
ma
tic o
f Ca
mb
ridg
es
hire
so
lutio
n
Connection costs and estimated curtailment levels for
normal connection versus ANM connection
DLR
AVC
M
M
M
M
M
Power Flow Constraint B
AVC
Client
RTU
Client
RTU
Power Flow Constraint C
Voltage Constraint B
Voltage Constraint A
SCADA (Control Room)
Generator 1
Generator 3
Generator 4
Generator 2
Generator 5
Power Flow Constraint A
RF MeshIEC 61850
IEC 61850
IEC 61850
IEC 61850
IEC 61850
IEC 61850
7
London
Challenge Demonstrate how ANM can be used to increase visibility of
distributed generation, improve security of supply, manage
different DER types and avoid demand driven reinforcement.
Solution
♦ ANM 100 configured to second by second manage
export and import of distributed generation (20+ MWs
from CHP), demand aggregators (3 aggregators) and EV
charging (50 charge points totaling 600 kW).
Delivered Benefits
♦ A third more distributed energy plants to export power to
urban networks
♦ £43m of savings identified through the visibility and
contribution of Distributed Generation to security of
supply.
Example trace of ANM delivering autonomous demand response
8
London
Technical overview of the ANM trials
EHV
HV
DG Control
System
Primary User
Interface
RTU Measurement
Points
Primary Substation
Local Demand
Response Site
Central ANM Controller
M M M Central Demand Response
Control Centre
Low Carbon London
Operational Data Store
UKPN
SCADA
Modbus/IP
(VPN)
TCP/IP
TCP/IP
various
DNP3/IP
ANM Data Historian
GPRS
Electric Vehicle
Charging Network
Operator
Electric Vehicle
Charging
Infrastructure
Modbus/IP
(VPN)
DG Control
System
Local Distributed Generation Site
various
GPRS
Power
Current
HV/LV Network
9
Skegness and Corby
Challenge
Roll-out ANM connections for DG customers within 6 months.
Technical challenges include thermal and voltage constraints
for wind and PV developments.
Solution
♦ Non-firm actively managed grid connections for distributed
generation using ANM 100.
♦ ANM 100 delivered and operational within 3 months.
♦ Consultancy services, capacity analysis and training to
build internal knowledge and capability.
Delivered Benefits
♦ Skegness: several generation connection offers accepted
♦ Corby: several generation connection offers accepted
♦ Several 10’s MW generation connection acceptances
♦ Other ANM areas scheduled
SGS and WPD engineers commissioning the
Skegness ANM system
10
Skegness and Corby
Single line diagram of the Skegness network
showing ANM connecting generation with
thermal and voltage constraint locations.
11
South-East Scotland
Challenge
♦ To increase the speed and cost of connection for DG projects (e.g. PV, wind and thermal) in the South East of Scotland.
♦ Reduce wasted engineering effort in connection quotations which are not accepted (currently >90%)
♦ Technical challenges include thermal overloads and voltage.
Solution
♦ ANM-enable grid supply points with ANM 100 to manage distribution and transmission constraints
♦ Deliver an online capacity analysis tool for distributed generation customers to screen connections before applying
Status
♦ Customer connection portal in trial and being rolled out across the area by June 2015
♦ 3 grid supply points ANM-enabled and integrated to existing communications and SCADA ready for distributed generator connections
Available Capacity
Limited capacity
No capacity
ANM enabled area
Project area and constrained circuits for distributed generation
connections
12
Online Capacity Analysis Tool
Online customer self-service planning tool
Example results page from the customer self-service tool
showing benefits of an ANM connection
13
Shetland Isles
Challenge
Develop and manage the non-interconnected island grid
more efficiently and increase role of renewable energy in
meeting future energy needs.
Technical challenge includes stability, primary reserve,
network operation and thermal overload constraints.
Solution
♦ Actively manage new generator output against stability
and security constraints and schedule new controllable
demand to reduce renewables curtailment and enhance
system operation
♦ Distributed Energy Resources integrated include domestic
demand (2 MW of flexible electrical heat demand and 16
MWh of energy storage); several MW of new renewable
generation and battery energy storage.
Delivered Benefits
♦ 5 generators accepted ANM connections (8.5MW)
Population ~23,000
Demand 11 – 47 MW
Diesel generation at Lerwick Power Station
(50+ MW) but reaching end of life and requires
replacement
Energy supply and frequency response from
Sullom Voe Oil Terminal but mainly there to
serve local load and cannot be guaranteed in
the long term.
Platform and
application
components used
to deliver the
Shetland ANM
system
14
Shetland Isles
ANM Functions
♦ Forecasting of network constraints based on load and generation forecasts
♦ Calculation of day ahead schedules for all controlled devices with an objective of maximising renewable contribution
♦ Real time (second by second) balancing to calculate and issue override signals to respond to unforeseen events, changes in conditions and short term variations
♦ Management of system stability to identify configurations that may result in unacceptable oscillatory behaviour and set operating limits, including frequency response characteristics
Domestic
demand side
management
scheduling and
set up screen
Multiple system
constraints
managed
through ANM
Security and balancing in Microgrids What do we really mean by microgrids and what do they really contribute?
15
Microgrids in IEEE 1547.4
♦Microgrids contain generation and load
♦Ability to disconnect from and parallel with wider system
♦Different scales from customer to substation, local to wider area
♦ Intentionally planned
16
Applying ANM learning to Microgrids
ANM products and applications are suited to managing the interaction between multiple Microgrids and the network operator and energy supplier Provide visibility and control of individual/collective DER
Manage network constraints, voltage profiles and schedule devices
Local balancing of supply, demand and storage
Respond to system events and real-time conditions
Deliver “mission critical” coordinated control, fail safe functionality and redundancy of key elements in the end-to-end system
Manage the process of intentional islanding and also mitigate the risks of unintentional islanding and reconnection
Example Layout of ANM for Microgrids
18
Generator
Energy Storage System
Circuit Microgrid
Generator
Facility Microgrid
Energy Storage System
Substation Microgrid
Microgrid Controller
Microgrid Controller
Microgrid Controller
DMS
ANM Application
DERMS
Historical Database
Conclusions
♦ In the context of: ♦ Clear need for developments in transmission, larger scale generation,
system operation and markets ♦ Clear desire to harness the full range of Scotland’s energy resources
♦Tangible progress has been made on renewable integration challenges - especially in distribution systems
♦Parallel track on ‘Vision 2’ (decentralised model) gaining credence
♦DER management experience can be rolled into decentralised energy solutions with empowering flows of information to secure customer supplies
19
Who is Smarter Grid Solutions?
♦ Successful smart grids manage large volumes of fast-changing data. The traditional operator-in-the-loop approach won’t cut it anymore. To resolve the grid challenges of a low carbon world, we need real-time, autonomous, deterministic control technology. That’s why we exist.
♦ Founded in 2008
♦ 7,000 sqft HQ in Glasgow with development and test infrastructure
♦ Offices in New York and London
♦ Over 50 engineers dedicated to the development and deployment of Active Network Management
♦ Over 10 years in development in collaboration with utility customers and one of Europe’s leading power systems universities (University of Strathclyde)
20
21
SGS Timeline R
esearc
h p
roje
ct
com
mences
Fie
ld trial of
auto
nom
ous
ge
ne
ratio
n c
on
tro
l
Com
pany f
ounded
UK
’s fir
st
fully
opera
tional
sm
art
grid –
Ork
ney R
PZ
Key r
ole
in D
G f
or
security
of
supply
, dem
an
d r
espon
se
and E
V inte
gra
tion
First
pro
ject in
main
land
Euro
pe
Blo
om
be
rg N
ew
Energ
y
Fin
ance P
ioneer,
secure
d
majo
r new
pro
jects
with U
K
Pow
er
Netw
ork
s a
nd S
SE
PD
and fir
st
manor
pro
ject
with
SP
Energ
y N
etw
ork
s
First
pro
jects
with W
este
rn
Pow
er
Dis
trib
ution a
nd
Nort
hern
Pow
erg
rid
First
pro
jects
with
Co
n
Edis
on, S
outh
ern
Com
pany
and N
ort
hern
Ire
land
Ele
ctr
icity.
Launch o
f N
YC
offic
e. F
irst
fram
ew
ork
contr
act
win
for
AN
M r
oll-
ou
t
with S
SE
PD
22
What do SGS do?
Products Consultancy, Analysis,
Tools and Training
Systems Integration and
Support
Active Network
Management software
• Strategic Consultancy
• Power systems analysis
• ANM system design
• Online capacity analysis
tool
• Desktop capacity analysis
tool
• ANM planning and
operational training
• Services to support the
deployment of Active
Network Management
• Ongoing support and
maintenance of
operational systems
Project Lifecycle
23
SGS ANM products to address DER integration challenges
Real power control for thermal
constraints
Real power control for upper
voltage limits
Demand Response and Peak
Reduction
Real and reactive power control and
AVC scheme coordination
Voltage limit (high and low) and
power flow constraints
Real power control for thermal or
voltage constraints
Real power control to maximise
connection
AN
M 1
00
AN
M 5
0
Co
nn
ect+
Aimed at GSP and 10’s or 100’s of
MWs of managed capacity
Aimed at primary substation and
10’s of MWs of capacity
Aimed at Grid Edge devices and
entry point to ANM