Investment project of “NAVOIAZOT” Investment project of “NAVOIAZOT” Joint Stock CompanyJoint Stock Company
Bakhtiyor B. BotirovBakhtiyor B. BotirovDirector GeneralDirector General
General information about the companyGeneral information about the company
Type of ownership:Type of ownership: joint stock joint stock companycompany
Number of personnel:Number of personnel: 9816 9816 peoplepeople
Total production areas:Total production areas: 361.63 361.63 hectareshectares
Date of establishment of the Date of establishment of the enterprise:enterprise: 1964 1964
Information about the projectInformation about the project
Purpose of the project: The main purpose of the Purpose of the project: The main purpose of the project is to establish new ammonia and urea project is to establish new ammonia and urea production linesproduction lines
Total cost of the project: about 450ml USDTotal cost of the project: about 450ml USD
Share of Uzbek party: 51%Share of Uzbek party: 51%
Share of foreign party: 49%Share of foreign party: 49%
Information about the productionInformation about the production
Type of productionType of production:: Production of mineral fertilizers, chemical fibers, Production of mineral fertilizers, chemical fibers, chemical reagents for mining industry.chemical reagents for mining industry.
Production capacitiesProduction capacities
Name of a goodName of a goodAnnual Annual
capacity capacity (tons/year)(tons/year)
Price per Price per unit (in USD)unit (in USD)
Volume of Volume of annual annual
turnover (in turnover (in USD)USD)
Ammonium nitrateAmmonium nitrate 950000950000 106106 100700000100700000
Acrylic fiberAcrylic fiber 2300023000 16001600 3680000036800000
Acetic acidAcetic acid 2500025000 350350 87500008750000
Cyanic sodiumCyanic sodium 70007000 1092.51092.5 76475007647500
ThioureaThiourea 600600 23002300 13800001380000
K-4 preparationK-4 preparation 50005000 15001500 75000007500000
Potential of the companyPotential of the company
Buildings and Constructions:Buildings and Constructions:
Name of the objectName of the object Measure Measure unitunit Total areaTotal area
Total area of the enterpriseTotal area of the enterprise hectare hectare 652,0056652,0056
Including those covered with Including those covered with production areasproduction areas hectarehectare 361361,,6363
Area of roofed storagesArea of roofed storages
Area of open storagesArea of open storages
Subsidiary productions (objects Subsidiary productions (objects of engineering provision)of engineering provision) hectarehectare 260,5260,5
Potential of the companyPotential of the company
Engineering Communications:Engineering Communications:
Name of the Name of the resourceresource
Measure Measure unitunit
Const per Const per unit (in unit (in soums)soums)
Annual need Annual need for the for the
creation of creation of productionproduction
HeatingHeating GkalGkal 11352 11352 45550 45550
Heat waterHeat water GkalGkal 11352 11352 1560015600
Home cold waterHome cold water mm3 3 212,03 212,03 2300000 2300000
Water for technical Water for technical needsneeds
mm33 66,53 66,53 2917000029170000
Natural gasNatural gas ThousandThousand mm33
34500 34500 586180586180
ElectricityElectricity thousand thousand Kwatt/houKwatt/hou
rr
28,2 28,2 18000001800000
SewerageSewerage ThousandThousand mm33
70,0 70,0 4746047460
LocationLocation
Distance fromDistance from KilometersKilometers
The administrative centerThe administrative center 33
Rail roadRail road Own railway trackOwn railway track
Automobile road and encirclingAutomobile road and encircling highwayhighway 66
Information on the proposed projectInformation on the proposed project
Name of the project:Name of the project: Urea-ammonia production complexUrea-ammonia production complex
Purpose of the project:Purpose of the project: The main purpose of the The main purpose of the project is establishing urea-ammonia producing project is establishing urea-ammonia producing complex with production capacities listed below:complex with production capacities listed below:- ammonia – 667 000 tons per year- ammonia – 667 000 tons per year- urea – 1 073 000 tons per year- urea – 1 073 000 tons per year
Total cost of the project:Total cost of the project: 450450 million USD million USD
Including:Including:- - Purchasing Equipment for refurbushingPurchasing Equipment for refurbushing – – 227227 ml ml USDUSD-construction-set up worksconstruction-set up works – 103 million USD– 103 million USD
THANK YOU THANK YOU FOR YOUR ATTENTION!FOR YOUR ATTENTION!
Joint Stock Company “NAVOIAZOT” Joint Stock Company “NAVOIAZOT”
Address:Address: 5 Navoi street, Navoi, Uzbekistan 5 Navoi street, Navoi, Uzbekistan
706800706800
Director General:Director General: Mr. Mr. Bakhtiyor B. BotirovBakhtiyor B. Botirov
Telephone: Telephone: (+99843622) 292200(+99843622) 292200
Fax:Fax: (+99843622) 237580(+99843622) 237580 Contact person:Contact person: Mr. Nusrat Soliev Mr. Nusrat Soliev