INVESTIGATION OF THE CRITICAL SUCCESSFUL...

113
INVESTIGATION OF THE CRITICAL SUCCESSFUL FACTORS (CSFs) OF BUSINESS PROCESS REENGINEERING (BPR) IN THE CONTEXT OF ENTERPRISE RESOURCE PLANNING (ERP) PROJECT IN SMEs A study submitted in partial fulfillment of the requirements for the degree of MSc Information Systems at THE UNIVERSITY OF SHEFFIELD by GEORGIOS MICHAIL September 2012

Transcript of INVESTIGATION OF THE CRITICAL SUCCESSFUL...

INVESTIGATION OF THE CRITICAL SUCCESSFUL FACTORS (CSFs)

OF BUSINESS PROCESS REENGINEERING (BPR) IN THE CONTEXT

OF ENTERPRISE RESOURCE PLANNING (ERP) PROJECT IN SMEs

A study submitted in partial fulfillment

of the requirements for the degree of

MSc Information Systems

at

THE UNIVERSITY OF SHEFFIELD

by

GEORGIOS MICHAIL

September 2012

1

Abstract

Background: An ERP implementation implies fundamental and structural organizational

change. BPR is considered as the predominant technique for restructuring the business

processes of an organization. Moreover, BPR is recognized as one of the major key

factors of a successful ERP implementation. However, how to make the BPR a successful

case while the decision for ERP implementation has been taken is not well studied.

Aims: The study aimed to identify the critical factors of a successful BPR in the ERP

context for SMEs and also categorize the factors into the relevant categories which are

also aimed to be explored. Finally, the consequences for not meeting and satisfying the

CSFs are investigated too.

Methods: In order to answer the research question the study followed the inductive

approach of research. The data collection was conducted by using a qualitative method of

semi-structured interviews. As a case study of the research, a Cypriot SMEs has been

taken. The interview data were analyzed using the thematic analysis with a priori coding.

Results: The study identified 29 CSFs differentiating them into four categories namely

change management, process, product and people whereas a total of 27 consequences

were identified as the result for not meeting the CSFs. Each one of the categories is more

or less related to organizational and/or technological perspective and therefore it has

relevance with the ERP system, top management or the organizational mechanism to

support the overall project.

Conclusions: Finally, the four categories are inextricably linked with the basic two

stakeholders of the project, top managers and project team while all the CSFs within the

four categories in general play an equally important role for a successful BPR

implementation in ERP project. If they are not satisfied, the impact will be extremely

negative for the project and SMEs in general.

2

Acknowledgements

By the end of this study I can surely say that it was one of the most difficult projects I

ever had in my life. The need to succeed was obvious and therefore the difficulty was in

high level. Although, at the same time this dissertation has proved many important things

to my self. It is very meaningful for me and I believe is the passport to follow the

professional career I want.

I would like to express my deep gratitude to the people supported me during the period of

the dissertation building. First of all, I would sincerely like to thank my supervisor Dr.

G.C. Alex Peng for his extremely helpful guidance and determinant support and

assistance during the whole study. Dr. Peng offered to me the opportunity to work

professionally with real time limits. He was very patient and always eager to hear my

problems and difficulties. His guidance and recommendations were the keys to finish my

dissertation appropriately. Many thanks to EKA Group and ERP Vendor company but

special thanks to Vina Koliandri, Systems and Controls manager in EKA Group who was

the liaison between me the case company (EKA Group) and the vendor company.

Secondly, I offer my best regards to the professors of Information School and Computer

Science department of the University for the great academic support and atmosphere in

general during this year.

Finally, I huge thank to my family and especially my girlfriend Georgia for their

continuous support and patience. Undoubtedly, a part of the success belongs to them and

I will always be thankful them.

3

Table of contents

List of figures and tables ..................................................................................................... 5

Chapter 1: Introduction ....................................................................................................... 6

1.1. Background .............................................................................................................. 6

1.2. Research question and objectives ............................................................................ 8

1.3. Research methodology ............................................................................................. 9

1.4. Dissertation outline ................................................................................................ 10

Chapter 2: Literature Review ............................................................................................ 11

2.1 Introduction ............................................................................................................. 11

2.2 Enterprise Resource Planning Systems ................................................................... 11

2.2.1 ERP Definition and Overview ......................................................................... 11

2.2.2 ERP in SMEs ................................................................................................... 13

2.2.3 ERP in Cyprus.................................................................................................. 15

2.2.4 CSFs of ERP systems implementation and their distinction ........................... 16

2.3 Business Process Re-engineering (BPR) ................................................................ 20

2.3.1 BPR Definition and Overview ......................................................................... 20

2.3.2 BPR methodologies ......................................................................................... 21

2.3.3 CSFs of BPR implementation .......................................................................... 22

2.3.4 BPR and IT ...................................................................................................... 26

2.4 BPR in ERP context ................................................................................................ 28

2.4.1 BPR in the ERP lifecycle ................................................................................. 28

2.4.2 Organizational Change versus ERP package customization ........................... 30

2.4.3 CSF for BPR in ERP context ........................................................................... 32

2.5 Summary ................................................................................................................. 34

Chapter 3: Methodology ................................................................................................... 35

3.1. Introduction ............................................................................................................ 35

3.2. Research approach ................................................................................................. 35

3.3. Qualitative approach .............................................................................................. 36

3.4. The Case study ....................................................................................................... 37

3.5. Data Collection ...................................................................................................... 39

4

3.5.1. Interview ......................................................................................................... 39

3.5.2. Interview design .............................................................................................. 40

3.5.3. Participants ...................................................................................................... 40

3.5.4. Interview administration ................................................................................. 41

3.6. Qualitative Data Analysis ...................................................................................... 42

3.7. Summary ................................................................................................................ 44

Chapter 4: Findings ........................................................................................................... 45

4.1 Introduction ............................................................................................................. 45

4.2 Motivations to BPR in ERP project ........................................................................ 45

4.3 The Critical Successful Factors (CSFs) .................................................................. 48

4.3.1 Change Management CSFs .............................................................................. 48

4.3.2 Process CSFs .................................................................................................... 54

4.3.3 Product CSFs ................................................................................................... 61

4.3.4 People CSFs ..................................................................................................... 67

4.4 Overall Findings Discussion ................................................................................... 76

Chapter 5: Conclusions ..................................................................................................... 77

5.1. Introduction ............................................................................................................ 77

5.2. Conclusion of the study ......................................................................................... 77

5.3. Limitations ............................................................................................................. 79

5.4. Recommendations for future research ................................................................... 80

Word Count: 15 089.......................................................................................................... 80

References ......................................................................................................................... 81

Appendix A: ...................................................................................................................... 90

Appendix B: Ethics and other student forms .................................................................. 100

5

List of figures and tables

Figures

Figure 2.1: ERP system architecture……………………………………………………..12

Figure 2.2: Percentage of papers presenting different topics…………………………….17

Figure 2.3: Summary of CSFs in BPR implementation …………………………......…..25

Figure 2.4: An eight-step framework for a successful BPR implementation...………….26

Figure 2.5: The role of IT in BPR………………………………………………………..27

Figure 2.6: The performance of BPR in ERP implementation…………………………..30

Figure 2.7: Extend of organization change versus extend of ERP software change…….32

Figure 2.8: BPR concerns in ERP context……………………………………….………33

Figure 3.1: The research wheel: inductive approach trend………………………………37

Figure 3.2: Connections between main theme, sub-themes and codes………….……….44

Figure 4.1: Concept map of Change Management category CSFs………………………54

Figure 4.2: Concept map of Process category CSFs…………………………….……….61

Figure 4.3: Concept map of Product category CSFs…………………………….……….67

Figure 4.4: Concept map of People category CSFs…………………………...…………76

Figure 5.1: Empirical investigation model of CSFs for BPR in ERP project……………79

Tables

Table 2.1: Number of Enterprises in Cyprus and the percentage of SMEs…………...…16

Table 2.2: ERP CSFs from the literature linked to authors………………………...……20

Table 3.1: Positions of interviewees………………………………………………..……42

Table 3.2: The five stages used in thematic analysis………………………………...…..43

6

Chapter 1: Introduction

1.1. Background

In the highly competitive business world of recent years, organizations try to respond to

the new technological standards by changing their business environment by adopting

configurable information systems (IS) to integrate and improve in general their business

practices. An Enterprise Resource Planning (ERP) is the predominant IS of the market as

the solution to new modernized era. ERP is “a configurable information systems package

that integrates information and information-based processes within and across functional

areas in an organization” (Kumar and Hillegersberg, 2000). Nevertheless, the ERP

implementation has a tremendous impact on the business processes’ (BPs) performance

and productivity because of the complexity of the system. This fact becomes critical

especially for small and medium sized enterprises (SMEs) whose business flexibility and

resources are limited. Therefore, organizations should perform a reengineering procedure

of their business practices to smooth ERP’s application impact. This procedure is known

as Business Process Reengineering (BPR).

BPR is a very popular concept because is considered as one the most important

techniques and management tools for transforming and restructuring the BPs of an

organization in order to improve the quality and achieve greater efficiency (Davenport,

1993; Hammer and Champy, 1993. And that can be more easily achieved by involving

information technology. Having in mind that ERP is an information system that provides

integration and automation of information across the organizational processes (Ross et

al., 2006), it is obvious that there is an inextricable link between those two terms, BPR

and ERP.

Furthermore, ERP attracts a lot of companies because it implies fundamental and

structural organizational change. The core BPs of an organization are embedded in an

ERP system and these represent the best practices from which companies expect to get

benefit (Boudreau and Robey, 1999). Some of the benefits are the cost reduction by

7

improving the inefficient areas and processes, better integration along the departments

and produce information in a real time environment (Davenport, 1998; Wallace, 2001).

The AMR Research (2007) reported that the ERP market total revenue in 2006 was

grown by 14% ($ 28.8 billions) from 2005. They also estimated that the total revenue will

be continuously increasing during the five year period from 2006 – 2011 reaching the

spectacular number of $ 47.7 billions. Moreover ERP leads to a substantial organizational

change and unique kind of technological change. Therefore it is highly important for an

organization to reengineer its business process in order to fit with the ERP.

The Critical Successful Factors (CSFs) of ERP implementation have been discussed and

studied very extensively from previous researchers (Esteves and Pastor, 2001). Moreover,

BPR is considered by the researchers as one of the most crucial CSFs of the ERP

implementation projects (Bancroft et al., 1998; Jarrar et al., 2000; Nah et al., 2001).

However, the BPR is not a straightforward task or a simple panacea to achieve a

successful implementation within time and budget due to the fact that is a very complex

project and requires universal support and control management especially when it is

implemented as parallel task of the general ERP project. In this direction, extremely little

research has been done on the analysis of the CSFs of BPR having relation with ERP

project and the impact of not only for SMEs but for large organizations too.

Consequently, there is a gap of knowledge in how to make BPR in ERP project to

become a successful case. Therefore the proposed study aims to investigate the CSFs of

BPR in the context of ERP project particularly for SMEs. This aspect will be the

inventive and critical point of the proposed research and it will try to address it.

8

1.2. Research question and objectives

In response to the general research aim the proposed project attempts to answer the

following question:

“What are the Critical Successful Factors (CSFs) of Business Process Reengineering

(BPR) in the context of Enterprise Resource Planning (ERP) project in SMEs?”

In order to answer and fulfill the research aim of the study the above question the

following research objectives should be established:

a. A general literature review-investigation on BPR and its relationship with ERP

implementation project will be carried out

b. Identify a set of the general areas-categories of CSFs of BPR in ERP context

c. Identify more specifically the CSFs for the successful BRR within these general

areas-categories

d. Identify the consequences for the organization for not meeting and satisfy the

CSFs that have been found.

In detail the literature review is used to acquire the basic knowledge from the most

influential researchers of the field who are related with BPR and ERP concepts. The

information from their findings and reviews in the literature will be a source of

knowledge for the proposed study along with the experts from the case company who are

going to be asked high level questions about the discussed concepts. Therefore the

method of case study will be used. Interviews will be carried out in order to present the

current situation of the company and to understand the way that the experts think and

theorize about the successful implementation of BPR in ERP context. Consequently, the

findings will guide organizations on fundamental corporate issues which are associated

with the ERP implementation helping them for a more efficient preparation for the BPR

and ERP implementation projects along with more chance to succeed.

9

1.3. Research methodology

One of the most critical parts of the study in order to fulfill the research objectives is to

conduct the appropriate research methodology. The study follows the inductive approach

of research. First of all, the literature review helped the researcher to obtain the

appropriate knowledge about the issues related with BPR and ERP projects. Also,

reviewing the literature, potential categories had been identified in order to differentiate

and categorize the CSFs, concluding to the final categorization with 4 dimensions.

The phenomenon under investigation requires data which cannot be measured and

quantified. Its nature requires a qualitative approach of data collection in order to have a

deep understanding of people perceptions and experiences regarding the CSFs of the

project (Silverman, 2001). Therefore, the qualitative approach for data collection is being

followed. Moreover, the data were collected from a single case study, a SME company

named EKA Group. EKA is a multibusiness company based in Cyprus. Its operations

have mainly to do with retail and trading divisions. EKA implemented an ERP system

called SAP Business One in 2006. At that time, the company also implemented BPR as a

result of the ERP project.

The data collection was conducted using the qualitative method of semi-structure

interviews. The flexibility of that type of interviews gave the interviewer the opportunity

to discuss freely any potential issues were emerged at any time following the structure of

the interview (Flick, 1998). Finally, the interview data were analyzed using the thematic

analysis with a priori coding which is a very useful method for identifying codes and

reporting the patterns within the data collected (Braun and Clarke, 2006).

10

1.4. Dissertation outline

Five different chapters are used to structure and separate the dissertation. The first

chapter introduces the main concepts of the study, ERP and BPR. It is an overview of

what has been done by researchers of the field in general and explains where is the gap in

the current literature that in which the study’s aim to contribute. Secondly, the next

chapter provides a review of the most relevant literature to obtain the appropriate

understanding about the concepts and related issues. The literature review is divided in

three parts: ERP systems, BPR and BPR in ERP context. That sequence helps the reader

to increase its understanding and relate those concepts efficiently. Chapter three presents

the research methodology followed to carry out the dissertation. Research approach, data

collection and analysis are being discussed. The findings are illustrated at the fourth

chapter. This chapter emphasizes at the CSFs have been identified for a successful BPR

in ERP project. Also the consequences are presented and the whole findings are

illustrated using concept maps for each category. An overall findings discussion is also

provided. Finally, the last chapter is the conclusions. This chapter draws up an overview

of the findings using a higher level of discussion. Additionally, implications and

limitations along with recommendations for future research are discussed.

11

Chapter 2: Literature Review

2.1 Introduction

In this section the existing literature review papers, studies and reports of the most

influential authors of both concepts, ERP and BPR, from 1990’s until today are

presented. The main purpose of the literature review is to present a comprehensive review

around the ERP and BPR fields and show their recursive relationship regarding the

existing publications. Moreover, some of the most important ERP research topics are

introduced such the ERP in SMEs and CSF of ERP implementation and BPR

implementation too. Also the current situation of Cypriot ERP market is presented. Then

the BPR concept is coming to the microscope introducing topics like the BPR

methodologies, its relation with information technology and the role of BPR in ERP

implementation.

2.2 Enterprise Resource Planning Systems

2.2.1 ERP Definition and Overview

As a result of the fact that ERP attracts the interest of researchers from diverse research

fields, there is a huge literature about the definition of ERP and its application context.

Although, one of the first researchers who tried to define these “enterprise systems” was

Thomas H. Davenport. According to Davenport (1998) an enterprise system is a

“commercial software package promise the seamless integration of all the information

flowing through a company - financial and accounting information, human resource

information, supply chain information, customer information”.

During the last decade many researchers have also tried to define the enterprise resource

planning systems in a parallel way but including more specific and synchronous features

12

because of the new capabilities of the system. Ross et al. (2006) stated that ERP is a

business management tool that can be used to integrate the BPs and functions in an

enterprise comprising integrated sets of comprehensive software presenting a holistic

view of the organization. Moreover, it incorporates all the individual elements of an

organization into a customizable off the shelf package providing high levels of

automation and integration all of the BPs enabling share common data along the entire

organization and real time access to information (Nah et al., 2001; Schlichter and

Kraemmergaard, 2010; Soh et al., 2000). Typically, as shown in the figure 2.1, ERP

system supports departmental integration of all BPs and operations in an organization.

The departments have better communication each other because of the information can be

shared more easily as a result of the central database through the client-server

architecture (Davenport, 1998; Tsamantanis and Kogetsidis, 2006:121)

Figure 2.1: ERP system architecture

13

Markus and Tanis (2000) stressed out that ERP systems have some very important

characteristics which make them differ from the traditional IS. It has already mentioned

the integration is one of them. Additionally, ERP systems are designed as the best

practices to support and fit to the BPs of the organization (Klaus et al., 2000). In order to

ensure best practices the closest cooperation between the users and vendor should be a

fact along with comprehensive knowledge by the vendor’s side (Soh et al., 2000).

Therefore, ERP systems have some crucial characteristics that make them differ from

other systems.

The unique character of the ERP system makes organizations to wonder why to

implement such expensive solution. The reasons are vary. Markus and Tanis (2000:180)

categorized these reasons into technical and business reasons. For example the desire of a

company to reduce the operating cost makes it to invest in ERP systems. Furthermore, a

lot of firms face the problem of maintaining their aging legacy systems which leads to

extra costs. Davenport (1998) supports this notion by saying “maintaining many different

computer systems leads to enormous costs-for storing and rationalizing redundant data,

for rekeying and reformatting data from one system for use in another, for updating and

debugging obsolete software code, for programming communication links between

systems to automate the transfer of data”. When consultants are trying to explain the need

of implementing an ERP system to the management of a company in order to persuade

and motivate them to invest in the system, these kinds of variations – technical and

business – should be taken into account and be explained very well.

2.2.2 ERP in SMEs

According to Deep et al. (2008) ERP system is viewed by small and medium enterprises

(SME) as the primordial way to initially increase their market value and achieve the

competitive advantage at the end. Moreover, Gable and Stewart (1999) argued that ERP

is the best way for SMEs to reengineer their BPs and finally leading to the same

14

advantages. In the past, technological and economic reasons restrict SMEs by

implementing an ERP system and therefore ERP adoption rate was extremely low in

contrast to the rate of large companies. However, in recent years, the reduction of IT cost

along with the popularity and attractive benefits and price of ERP systems, there has been

a significant growth in the ERP use by SMEs (Christofi et al., 2009; Deep et al., 2008).

One of the most controversial issues in the literature has to do with SMEs and their

relation with ERP systems, is the high proportion of ERP project failures (Deep et al.

2008; Doom et al., 2010). Christofi et al. (2009) pointed out that SMEs have relatively

simple organizational structure in comparison to large companies. In the same direction

Doom et al. (2010) concluded that SMEs lack of formalization of their procedures and

therefore their business structure is not well defined. The latter fact leads to unclear

objectives and to a general to confusion of how an ERP system can improve the business

performance achieving the competitive advantage. Similarly, SMEs have very often

limited resources and capital and therefore is more likely to not be able to resist in losses

and impacts caused by a potential ERP failure (Christofi et al., 2009). So they have to

address any drawbacks and problems especially when these problems have to do with

their operations and BPs in order to increase the probability of a successful ERP

implementation.

Finally Loh and Koh (2004) reported that “SMEs should critically consider having an

efficient change management programme and culture, and efficient software

development, testing and troubleshooting to ensure a successful ERP implementation”.

Hence, when an SME is embarking in ERP selection and implementation should be

aware of the current situation of the market and to be able to analyze and understand its

organizational structure too (Deep et al., 2008; Everdingen et al., 2000).

15

2.2.3 ERP in Cyprus

Currently the ERP market in Cyprus is relatively small compared to the other European

countries. Nevertheless, the spectacularly continuous growth of ERP systems adoption

around the world the last ten years forced Cypriot firms to start adopting them. The two

main facts that led local companies to this direction were initially the entrance of Cyprus

in the European Union in 2004. This fact opened the European markets to the local firms

and increased the levels of competition in the island. Secondly and most importantly, the

cost of ERP implementation is much lower now as a result of the advancement of

information technology which played a vital role in the rise of ERP use in Cyprus

(Tsamantanis and Kogetsidis, 2006).

According to the Cypriot ministry of commerce industry and tourism (2012) the

overwhelming majority of Cypriot firms are SMEs with the spectacular percentage of

99,8%. The latter number is confirmed by statistics that were published by the European

Commission (2011), as shown in the table 2.1. Therefore the vendors are working with

ERP solutions especially for SMEs. SAP and Oracle are currently the vendors with

highest market share in Cyprus following the European pattern (Jacobson et al., 2007)

Source: European Commission (2011)

Table 2.1: Number of Enterprises in Cyprus and the percentage of SMEs

16

2.2.4 CSFs of ERP systems implementation and their distinction

One of the most famous research topics of ERP research domain is devoted to the

implementation aspect of the system. According to Schlichter and Kraemmergaard

(2010), the highest percentage of research (30%) focuses on implementation aspect, as

shown in the figure 2.2. In fact, when researchers refer to the implementation of ERP

systems, the concept of critical successful factors of the implementation is implied as the

prime issue involved with it (Loh and Koh, 2004; Schlichter and Kraemmergaard, 2010).

Source: Schlichter and Kraemmergaard (2010)

Figure 2.2: Percentage of papers presenting different topics

A large number of researchers tried to identify and categorize the CSFs of ERP

implementation (Al Mashari et al., 2003; Doom et al., 2010; Esteves and Pastor, 2000;

Loh and Koh, 2004; Nah et al., 2001). The researchers used different methodologies such

literature reviews, case studies and interviews. When they try to identify the CSFs the

17

first thing that they need to do is to identify a set of higher level categories-groups. Of

course there is some overlapping between the different approaches used by the

researchers. For example, in order to structure the CSFs, Doom et al. (2010) divided them

into five groups based on the following subjects:

a) Scope, goals and vision

b) Culture, support and communication

c) Infrastructure

d) Approach

e) Project Management

On the other hand, Snider et al. (2009) analyzed the CSFs grouping them into three

categories having in mind the ERP life cycle stages:

1. Pre-implementation CSFs

2. Implementation CSFs

3. Post-Implementation CSFs

A similar approach identifying CSFs of ERP implementation based on the ERP lifecycle

was followed by Loh and Koh (2004) who divided the typical ERP lifecycle into four

specific phases. The phases are:

1. Chartering

2. Project

3. Shakedown

4. Onward and upward

During the first phase decisions are being taken about the solution constraints and for the

definition of the business care. At the second phase the end users are getting up while at

the third phase the system is being stabilizing eliminating the errors and bugs. Finally the

18

last phase has to do with the system maintenance, user support and upgrade of the system

with the newer versions.

After an extensive literature review the following CSFs have been found in the literature

from 1999 until the recent years. The table 2.2 afterwards illustrates a summary of the

most important CSFs. Each CSF is linked to specific author(s) that they have identified

them as a CSF. Some of them have been commonly identified by several researchers.

Although, as shown in the table 2.2, one of the most frequent CSFs has been identified by

researchers is BPR (as shown in Table 2.2).

Furthermore, each one of these CSFs is linked with a particular implementation phase of

ERP life cycle while at the same time a factor can be apparent in the whole

implementation of the project (Loh and Koh, 2004; Nah and Delgado, 2006; Snider et al.,

2009). For example, the clear vision and scope of the project is more inherent during the

pre-implementation phase. However, top management support and commitment is a must

CSF which is inherent throughout the entire project (Nah and Delgado, 2006).

Doom et al. (2009) argued that some of the CSFs of large organizations and SMEs are

similar to a large extent but on the other hand may not have the same consequences and

impacts. Moreover some CSFs may also differ from company to company and that fact

should be identified by the consultants at the pre-implementation phase. Hence, all CSFs

have a particular significance during the ERP implementation especially in SMEs.

Finally, among all these CSFs of ERP implementation, BPR is one of the most important

as it is cited by the majority of the researchers of the that research topic. However, how to

make BPR in ERP project a successful case has not been well study and therefore the

project becomes particularly important because it aims to explore this further.

19

Table 2.2: ERP CSFs from the literature linked to authors

CSF

Author(s)

Top

man

agem

ent

support

Chan

ge

Man

agem

ent

BP

R

Cle

ar v

isio

n,

scope

and

goal

s

Pro

ject

Man

agem

ent

Pro

ject

Tea

m

com

posi

tion

Act

ive

use

r

involv

emen

t

Use

r tr

ainin

g

Com

mu-

nic

atio

n

ER

P v

endor-

pac

kag

e

Soft

war

e

Dev

elopm

ent

met

hodolo

gy

Monit

or

and

eval

uat

ion

Al-Mashari et

al. (2003)

Doom et al.

(2010)

Esteves and

Pastor (2000)

Loh and Koh

(2004)

Nah et al.

(2001)

Nah and

Delgado

(2006)

Rosario (2000)

Snider et al.

(2009)

Stefanou

(1999)

Umble et al.

(2003)

Zhang et al.

(2003)

20

2.3 Business Process Re-engineering (BPR)

2.3.1 BPR Definition and Overview

BPR is currently considered as one the best drivers to manage the organizational change

helping the enterprises to survive in the highly competitive environment of today

(Motwani et al., 1998). There are several interpretations of BPR that have been provided

by authors. For example, Hammer and Champy (1993:32) have described BPR as “the

fundamental rethinking and radical redesign of BPs to achieve dramatic improvements in

critical, contemporary measures of performance, such as cost, quality, service and speed”.

According to Davenport (1993) BPR has promoted the analysis and design of processes

and work flows between and within organizations. Similarly, other researchers, such as

Talwar (1993), have focalized on the streamlining and restructuring the current BPs,

structure and way of working within an organization. However, there is some confusion

in the literature regarding the terms used to refer to the BPR (Simpson et al., 1999;

Valentine et al., 1998; Valiris and Glykas, 1999). Synonymous terms like reengineering,

redesign, renovation, improvement and transformation are used by researchers. Valiris

and Glikas (1999) suggested that the reengineering needs to be differentiated in the

literature. It means radical change where the BPs of the entire organization are reshaped.

On the other hand, revisionist BPR or process improvement is to focus on a smaller scope

of change and that change will be incremental. According to Grant (2002), the Hammer’s

famous definition of BPR is too limited because it ignores some major points of BPR like

people, structure and information technology.

The last two decades BPR had an explosive dissemination. And that happened because of

two major reasons. The first was the publication of the book by Hammer and Champy

(1993) entitled “Reengineering the Corporation: A Manifesto for Business Revolution”.

The second reason was the need of business world to change the way of doing business in

order to survive in the highly competitive world formed in 1990’s improving its

profitability and market share (Hammer and Champy 1993; Martin and Cheung, 2000).

21

The concept of BPR has significantly increased its popularity amongst the businesses all

over the world in a relatively short period of time (O'Neill and Sohal, 1999). The heavy

promotion which was exerted by business consultants has leaded BPR in a new road,

gaining importance as the new companies develop new methods of cross inter-

organizational coordination and alliances (Attaran, 2004). BPR adds value and leads to

innovation as a result of the knowledge employees and best knowledge BPs.

2.3.2 BPR methodologies

A large piece of the literature is devoted to the methodologies that are used for BPR.

Each methodology has specific steps during the process examination in order to identify

the non-value adding events and the existing bottle necks and then proceed with the

reengineering of the BP and improve its performance (Ghan and Choi, 1997).

Furthermore some authors went a step forward and proposed specific steps for a

methodology. For example, Davenport et al. (1993) listed the following five steps in his

BPR method: identifying process for innovation, identifying change levers, developing

process visions, understanding existing processes and designing and prototyping the new

process. Some other researchers identified more steps BPR methodologies. Kale

(2000:136) proposed eight steps methodology for instance whereas Jacobson et al. (1995)

proposed four steps BPR methodology.

As it was mentioned before there is confusion in the scope and interpretation of the

organizational change. In other words, what does R mean in fact? According to Bancroft

et al. (1998) and Esteves et al. (2002) whatever the scope and methodology are there are

two dimensions in a BPR initiative:

1. Magnitude of change

2. Scale of the change effort involved

The first dimension refers to the streamlining a BP. Bancroft et al. (1998) explains that

“Streamlining a business process implies making incremental changes to the current

22

process to increase quality, decrease cycle time, or reduce cost. Reinventing a BP means

scrapping the current one and creating a process that truly meets the needs of the

company”. The second dimension – scale of the change effort involved – refers to the

proportion of the organization involved in the BPR implementation. So, when more

people and departments participate in the change, then the higher complexity of effort

and the greater the scale of change is (Bancroft et al., 1998). Therefore, whatever the R

means BPR projects are based on these two dimensions.

2.3.3 CSFs of BPR implementation

As it mentioned before, BPR concept had a significant growth the last two decades.

However, despite that fact, many organizations implemented BPR projects did not

achieve the intended result. BPR often fails to perform the expected output of managers

and consultants. Hammer and Champy (1993) concluded with the estimation that a 50 to

70 per cent of BPR implementations do not achieve the results they seek. The reasons

vary from organization to organization. Therefore, the BPR implementation process

needs to be driven and checked against the success factors in order to ensure a successful

implementation of the project (Al-Mashari and Zairi, 1999).

Reviewing the relevant literature about the CSFs of BPR implementations, it can be said

that there are not many studies in the literature related to the CSFs of BPR

implementation. Al-Mashari and Zairi (1999) categorized the factors into five subgroups

illustrating the various dimensions of organizational change related to BPR:

1. Change Management

2. Management competency and support

3. Organizational structure

4. Project planning and management

5. IT infrastructure

Each one of these dimensions has specific success factors, as shown very well in figure

2.3. The factors related with change management for instance, involve social, human and

23

cultural changes into working environment such as effective communication, training and

education and motivation (Al-Mashari and Zairi, 1999; Hammer and Champy, 1993).

Factors like strong leadership, risk management and championship are related to the

second dimension, management competency and support whereas organizational

structure is influenced by effectiveness of BPR teams, job integration and the

appropriateness allocation of responsibilities within an organization. Furthermore, a

successful BPR implementation is inextricably linked with the effective project

management too. This dimension includes factors such as the alignment of corporate

strategy with BPR strategy and the use of effective project management tools and

techniques. Finally, IT infrastructure has a major role in BPR implementation as a major

component of that enables BPR. (Al-Mashari and Zairi, 1999; Attaran, 2004;

Subramoniam et al. 2009).

24

Source: Al-Mashari and Zairi (1999)

Figure 2.3: Summary of CSFs in BPR implementation

25

Moreover, Miers (2006) proposed an eight-step framework in order to achieve and ensure

the successful outcome of BPR implementation. The steps are shown in the figure 2.4.

Source: Miers (2006)

Figure 2.4: An eight-step framework for a successful BPR implementation

The framework proposed by Miers (2006) follows an iterative approach. The results of

each iteration are continuously measured for better evaluation and optimization. Again,

IT is a vital component for this approach. This is the reason that BPR and its relation with

IT has attracted many researchers and practitioners (Al-Mashari and Zairi, 1999; Attaran,

2004; Ghan and Choi, 1997; Subramoniam et al. 2009).

26

2.3.4 BPR and IT

Undoubtedly modern information technology has tremendous capabilities. It has deeply

penetrated in organizations which are trying to minimize their costs and improve their

quality and services in order to be more efficient and competitive. BPR helps

organizations to achieve all these business objectives. Therefore, there is a close

relationship between IT and BPR (Hammer and Champy, 1993).

IT capabilities including network and communication technologies, information access

quality and real time information can play a vital role in creating or improving the BPs.

Davenport (1993) stressed out that BPR requires a broad view of business activity but at

the same time equally important is the view of IT. Similarly, Ghan and Choi (1997) and

Subramoniam et al. (2009) maintained that IT is the key enabler BPR. Now technology

should be used more extensively and BP can be changed fundamentally and not partially.

Also, Ghan and Choi (1997) explained how IT can help BPR using the what/how

distinction, as shown in figure 2.5.

Source: Ghan and Choi (1997)

Figure 2.5: The role of IT in BPR

In addition, Davenport and Short (1998), presented a seven step procedure for IT driven

BPR implementation. The steps are:

27

1. Prioritize process objectives

2. Identify the process to redesigned

3. Understand and measure/benchmark the process

4. Identify the right IT method

5. Design and build prototype

6. Test the reengineered process

7. Implement the changed process.

In the same way, this seven-step procedure was followed by Subramoniam et al. (2009)

who also pointed out that when IT is heavily implicated in the BP change, BPR is less

likely to fail.

Finally, the rapid evolution of IT creates many opportunities for organization to change

their potential wrong functions and processes and improve their business image. IT

driven BPR can help companies in achieving specific goals such as better business

performance, easy communication and high level of information share across the

functional levels of the company. Nevertheless, IT is a strange case and without the

appropriate leadership and management support BPR may fail resulting in unexpected

consequences for the companies (Attaran, 2004).

28

2.4 BPR in ERP context

2.4.1 BPR in the ERP lifecycle

Gill and Johnson (1997:27) said that “… it is evident that if we have the expectation that

doing A, B will happen, then by manipulating the occurrence of A we can begin to

predict the influence to the occurrence of B.” Moreover Kerlinger and Lee (2000)

reinforced this view by saying that when we trying to examine relationships between two

variables the purpose is to find out, predict and finally control these relationships. In this

case BPR and ERP are two concepts that are absolutely linked.

The recursive relationship between BPR and ERP has made numerous studies to be

conducted having one of these two or both terms in their microscope. When the

researchers approach the ERP research area, the majority of them focuses on the

implementation topic and therefore on CSFs of ERP. More interesting is the fact that one

of the most cited and important CSF in ERP implementation projects is the BPR

(Bancroft et al., 1998; Nah et al., 2001). Esteves and Pastor (2000) pointed out that

“comprehensive BPR is related with the alignment between business processes and the

ERP business model and associated best practices”. Therefore for a successful ERP

implementation, an organization needs to redesign its business BPs (Figure 2.6).

29

Source: Tsai (2010)

Figure 2.6: The performance of BPR in ERP implementation

An interestingly controversial issue has to do about the appropriate time of

implementation of BPR having in mind an ERP system will be in place. So, when is the

right time for BPR? Before, after or during the ERP implementation? A survey conducted

by Subramoniam et al. (2009) answers the latter question by saying that the most

effective way in reengineering the BPs of an organization is the simultaneous

implementation of BPR and ERP. Similarly, with the previous study this direction goes

another survey conducted by the Chemical Marketing Reporter (1996). The survey

included 220 European companies implementing SAP and it proved that the most

powerful and effective method for business improvement is the simultaneous

implementation of BPR and ERP. In contrast to previous statements, Schniederjans and

Kim (2003) reported that the dominating implementation sequence as being successful to

follow in the future ERP implementation is firstly BPR and the ERP implementation.

Also, they stressed out that most appropriate chronological stage is at the beginning of

ERP lifecycle and therefore at the pre-implementation stage. Nonetheless, the question

becomes more interesting because in a study conducted by Martin and Cheung (2005) it

was supported that the BPR pays after ERP implementation and therefore at the post-

implementation stage. The project demonstrated, as the authors pointed out, that BPR can

30

achieve “dramatic improvements” in quality, cost, speed and service after the ERP

implementation and companies have the opportunity to leverage the existing ERP system

to ameliorate the return on the investment. Furthermore, O’Leary (2000) said that each

one of these approaches has a set of advantages and disadvantages. When ERP is selected

after the implementation of the BPR the system must be highly customized to fit the BPs

of the organization. This fact increases the cost many times and it is more suitable for

large organizations with large capital and financial recourses who they need system

absolutely compatible with their strategy gaining a bigger share in the market. If ERP is

selected before, the implementation of BPR is driven by the chosen system and as a result

the costs are lower because of the none or least change done on the ERP (O’Leary, 2000).

2.4.2 Organizational Change versus ERP package customization

Frequently, during the pre-implementation of ERP lifecycle, managers face a serious

dilemma. They have to decide whether their company should implement the ERP system

“as is” and adopt the functionality and procedures of it or to customize the system to the

functional requirements of the company (Jarrar et al., 2000). Nevertheless, Subramoniam

et al. (2009) concluded that ERP systems can meet only 80% of the organization’s

functional requirements while the cost of ERP customization will be raised significantly.

According to O’Leary (2000) in practice, the most famous solution with a percentage of

41% is to reengineer the BPs to fit the ERP package whereas the selection of ERP

package that fits the BPs and customize it a little has 37%. For example, when Rolls

Royce selected to implement a SAP ERP well known as SAP R/3, managers faced the

business problem that the aforementioned ERP software package in order to work

successfully needs a rigid business structure. So, they decided to change the business

practices to fit SAP R/3 system. As a result, Rolls Royce changed completely the way

that did business. Also, any potential modifications to the ERP system would have cost a

fortune to the company because firstly the newer versions of the system would have been

31

very difficult to install and secondly in terms of implementation resources, the cost of

SAP R/3 modification would has been increased significantly (Yusuf et al., 2004).

O’Leary (2000) made a distinction between “small-r” and “big-R”. As shown in figure

2.7, small-r means that very little changes take place in both business and ERP package

and the company implements a tight-fitting ERP system. On the other hand, big-R the

organization makes changes in both ERP software and its BPs to meet its functional

meets. Of course, according to figure 2.7, there are two more areas-cases. The first one is

when the BPs are changed extensively and the change on ERP software is minimal and

the second case when the business BP change is minimal and the scale of change on ERP

software is big. Each one of these areas has advantages

Source: O’Leary (2000)

Figure 2.7: Extend of organization change versus extend of ERP software change

and disadvantages. However, as Subramoniam et al. (2009) said, as we move from the

left bottom quadrant to the top right to quadrant, the rate of a successful BPR in ERP

implementation is being reduced. Therefore, the movement of the arrow shows the

highest success probability to the highest failure rate.

32

2.4.3 CSF for BPR in ERP context

The CSFs of both ERP and BPR implementations have been discussed in previous

sections. Also, the CSFs have been distinguished between several categories such as

change management, organization structure and culture and IT. However, there are not

any studies relating those CSFs of BPR with ERP projects. Although, a study of Esteves

at al. (2002) can be considered as an exception. The latter study identified four main BPR

concerns in ERP context based on the literature. These concerns, as figure 2.8 shows, are

the following:

1. Change management dimension

2. Process dimension

3. People dimension

4. Product dimension

Source: Esteves et al. (2002)

Figure 2.8: BPR concerns in ERP context

Change Management Dimension: this dimension emphasizes mostly on human and social

changes and cultural adjustments need to be done by the management of the company in

order deal with the new and more effective BP process. Critical decision should be taken

by the management such the appropriate time for BPR. Other critical decisions have to do

33

with the potential of change the culture of the company in order to fit to the new BPs and

motivate the employees to change their habits and behavior in their working area.

Process Dimension: here an extensive analysis of the current BPs is taken place and also

the implementation strategy is decided by the project team. The results will help the

project team to define which processes should be change, what processes are interrelated

and how is the team going to align the BP with ERP functions. Some critical factors of

that dimension are the use or not of external consultants and the alignment of the BPs to

the new ERP system which is very important factor in successful projects.

People Dimension: people and more specifically managers, operational staff and

consultants are very important during the project. So, apart of the selection of the most

appropriate consultancy team, employee involvement is critical too. Of course, the

support and commitment of top managers with continuous and effective communication

with the stakeholders of the project has a vital role. Finally, training and education of the

users is particularly important aspect too.

Product Dimension: The crucial role of IT infrastructure and IT experts, which have been

covered in a previous section, are involved in this dimension. IT can enhance the BPR

strategy in order to be more clear and detailed. Although the project team and

organization in general must adequately understand and identify the enabling

technologies for BPR. Finally, the selection of ERP package is massively important

because the selection will affect the level of ERP customization. It was mentioned before

that a potential ERP customization with the current BP will increase the cost of the ERP

significantly while at the same time no such major changes will be done on the BPs.

Furthermore, if the company intents to reengineer its BPs in a specific direction and the

ERP package cannot be customized to support direction that will result in a fail

implementation. So, the level of customization is a factor that needs to be consider as one

of the most critical in order to find and implement the right ERP package with the best

alignment with the BPs.

34

However, again, these dimensions seem to be a little general and as a result nothing

certain and can be said about the specific factors affecting the success of BPR

implementation in ERP project. Therefore, that fact seems to be a research gap that needs

to be explored in more depth and addressed by the researchers (Esteves at al., 2002).

2.5 Summary

The chapter gives a comprehensive review of the main concepts that are going to be

under investigation. The most important issues have to do with BPR and its relationship

with ERP implementation, are presented based on the findings of influential authors of

the field. The main two facts that ERP systems can meet only 80% of the organization’s

functional requirements (Subramoniam et al., 2009) and that a 50 to 70 per cent of BPR

implementations do not achieve the results they seek (Hammer and Champy, 1993)

become particularly critical to SMEs in which is more likely to have limited assets and

therefore a potential BPR failure may lead to ERP implementation failure with disastrous

impacts for the enterprise. All in all, BPR is considered by the researchers as one of the

most crucial CSFs of the ERP implementation projects (Bancroft et al., 1998; Jarrar et al.,

2000; Nah et al., 2001). Nevertheless extremely little research has been done on the

analysis of the CSFs of BPR having relation with ERP implementation life-cycle and the

impact of it. Therefore this aspect will be the inventive and critical point of the proposed

research and it will try to address it.

35

Chapter 3: Methodology

3.1. Introduction

The aim of this chapter is to give a comprehensive explanation of the research

methodology used in the study, by describing the entire research strategy and approaches

were followed for the research design, the data collection method and the data analysis.

Specifically, using an inductive approach, interviews were selected as the qualitative

instrument for the data collection and the method of thematic analysis was used for the

qualitative analysis. Finally, the strategy of a single case study was followed in order to

have a deep and empirical investigation of BPR in ERP project.

3.2. Research approach

In order to select the most appropriate research approach to answer the research question

and meet the research objectives with reasonable evidence variety of methods were used.

The researcher evaluated the two research approaches: inductive and deductive (figure

3.1). These two approaches have a major difference. Deductive starts with a theory based

on it a researcher concludes to a testable hypothesis and data are being collected using a

quantitative approach (Flick, 1998; Saunders et al., 2003).

On the contrary, inductive approach follows a bottom-up approach. It starts with data

collection using a more qualitative approach such as interviews (Silverman, 2001). The

phenomenon under investigation required the appropriate amount of data to be gathered

and analyzed efficiently in order to generate a theoretical understanding. In other words,

the researcher after the review of the relevant literature collected the data and performed

a systematic data analysis and set up the relationship between the findings and research

objectives of the study (Hayes, 2000). The researcher evaluated the two approaches and

followed the following inductive steps:

36

a) Establish a theoretical background having a critical view of the relevant literature

and theories

b) Select the appropriate case study and obtain an empirical data

c) Data analysis of data and obtain empirical knowledge

d) Generate a posteriori theoretical framework based on the analyzed data

Figure 3.1: The research wheel: inductive approach trend (Rudestam and Newton,

1992:5)

Consequently, the researcher adopted the inductive approach as the most appropriate

method to investigate the CSFs of BPR in ERP context.

3.3. Qualitative approach

Choosing the appropriate method between qualitative and quantitative methods always

depends on the outcomes and findings of the study (Silverman, 2001). Again, differences

between the approaches are quite apparent. Quantitative method emphasizes on the

37

quantification of data collected and analyzed whereas data collected using a qualitative

approach can not be quantified and are involved research texts rather than figures,

statistics and numbers (Flick, 1998; Silverman, 2001).

The researcher carried out the qualitative approach for several reasons. First of all,

because of the nature of inductive approach, the qualitative method can be supported

more efficiently and therefore it can be combined with it very well. Secondly, qualitative

approach tends to be used for investigation of participants’ beliefs and perspectives about

social phenomena when the boundaries between the phenomenon and context are not so

clear, such as BPR implementation in ERP context.

Moreover, the study tried to explore phenomena and issues that cannot be measured.

People’s perspectives about the CSFs of BPR cannot be measured because there is not

enough literature to identify and conclude with a set of reliable for investigation CSFs.

Finally, Flick (1998) claims that qualitative research is suitable for interpretation of

respondents’ perceptions and attitudes since it studies human and social phenomena into

working environment. Participants have been interviewed according to the different

departments and BP of the case company that they work for. This fact also confirms what

Flick (1998) said and empowers his claim.

3.4. The Case study

According to Baxter and Jack (2008) a qualitative case study is a strategy “which is

taking into consideration how a phenomenon is influenced by the context within which it

is situated”. Yin (2003) reinforces this statement by saying that a case study investigates

a phenomenon whose boundaries and context are not so clear evident. Therefore, the

research project used the strategy of a single case study as the most applicable approach

to achieve the research objectives due to the fact that ERP implementation is very closely

related to its application context and BPR as a consequence.

38

The case company is “EKA Group” which is a Cypriot multibusiness SME with

operations also in Greece and Dubai. It is considered as a retail and also trading

organization with industrial products, construction operations and specialized

constructions. EKA Group sells building materials (e.g ceramics, wood, stonecrete),

sanitary ware, swimming pools and construction systems.

EKA Group was selected due to the fact that it has a relatively recent (2006) BPR

implementation as a result of the ERP system entire project. Having multiple business

requirements and problems with its BPs’ efficiency, EKA has fully implemented the top

brand SAP Business One ERP package along the key functional divisions in order to

integrate all company locations, departments and BPs to support its operations. SAP

Business One is specifically designed for SMEs. Consequently, EKA Group was taken

under evaluation and finally is an appropriate case study for the proposed project.

Furthermore, the ERP implementation vendor company which was responsible for BPR

was involved in the study. The aforementioned company is referred as ERP

Implementation Vendor Company in order to protect its anonymity. The company is a

partner of SAP AG and provides services and solution of the German company. Its

operations have to do especially with IT and business consulting and management. The

people of the vendor company as professionals know the case in depth and their

contribution was extremely positive. So, the vendor company is associated with the top

brand of the field and therefore the successful implementation in EKA Group makes the

case study more complete and appropriate to meet the objectives of the study.

39

3.5. Data Collection

3.5.1. Interview

As it was mentioned before the inductive research approach will be followed. Therefore

the collection of data was achieved by using the main qualitative research method of

interviews. Interview is a technique that allows in depth face to face discussion with the

participant and helps the researcher to understand people thoughts, experiences and

feelings about the given topic (Saunders et al., 2003). It is also a technique that helps the

researcher to have a better understanding of peoples’ thoughts and focus on the key

objects those he intents to explore during the interview session (Punch, 2005).

Normally, three different types of interviews are being applied depending on the project

aim and objectives. Structured interviews in which the research strictly defines exactly

what is going to be discussed and therefore the content is predefined (Hayes, 2000). On

the other hand, the type of unstructured interview is being also used by several

researchers. This type includes more general questions and there is no in advance

specification. The conversation is more flexible and spontaneous and question can

amend at any time of the interview (Punch, 2005).

The last type is the semi-structured interview which attracts the majority of the

researchers. This type can be seen as a mixture of the two previous types. It allows an

open but at the same time structured discussion and therefore questions can potentially

emerge more easily (Flick, 1998). This type offers flexibility to add any new questions

during the interview process and generally it combines the benefits of the other two

types. Subsequently, the type of semi-structured interviews was adopted by the researcher

to exploit the combination of those benefits.

The face to face approach was used to conduct the interviews. Face to face way was

preferred by researcher because it allows in depth discussions with high rates of response

by interviewees. It also offers the opportunity to interviewer to make the appropriate

40

explanations for the best understanding of the question while at the same time interviewer

can take any gesture or face expressions by interviewees (Frey and Oishi, 1995).

3.5.2. Interview design

First of all the main aspects related to BPR and ERP of the most relevant literature and

the most influential authors will be carried out concluding to a general literature review.

In order to categorize the CSFs and also structure and guide the conversation with

interviewees, 4 predefined categories were used from the study of Esteves et al. (2002)

about the dimensions related to BPR in ERP implementation.

In addition, in order to achieve efficient exploration of the CSFs and their consequences

the interview script was structured according to the 4 categories. Categories were

explored one by one following four types of questions (Saunders et al., 2003; Yates,

2004):

Initiating questions for open the discussion about the predefined categories,

Follow-up questions for encouraging participants to expand on a specific answer

given by them without changing the topic,

Trigger questions for stimulating and trigger and refocus participants’ thinking to

get an efficient response and

Closed questions in order to confirm interviewees’ opinion by making them to

answer yes or no.

Consequently, the final interview script was established by using the above mentioned

design (Appendix A1)

3.5.3. Participants

The interview script was also designed based on the diversity of interviewees and their

position in the company. People from different departments (sales, warehouse, financial,

purchasing) have been interviewed. Furthermore, in order to obtain the best

41

understanding and develop a holistic view about the factors affected the success of BPR

in ERP project and finally meet the objectives, interviews involved people from all the

levels of the company (top and departmental managers, IT staff and operational staff).

Twenty semi-structured interviews were conducted. Eighteen with EKA staff and two

with vendor’s company consultants (Table 3.1).

EKA Group ERP Implementation

Vendor Company

CEO

Top Managers

Systems and Control Manager

IT Administrator

Departmental Managers

Sales

Financial

Warehouse

Purchase and Logistics

Operational Staff

Sales Clerks

Purchasing Clerks

Credit-Accountants

Office Administrator

Project Manager – Consultant

ERP Implementation Consultant

1

2

1

1

1

1

1

1

4

2

2

1

1

1

Total 18 2

Table 3.1: Positions of interviewees

3.5.4. Interview administration

Participants were assigned into groups according to the structure of the organization.

Therefore people from different levels of the organizational pyramid and departments

who are involved in the new BPs and interact with the system have been interviewed. The

interviews were digitally recorded using a professional recorder after obtaining the prior

permission and consent of interviewees. Interviews duration varied from 20 minutes to 1

hour and the collection lasted 5 days. The transcription of interviews was carried out at

the end of each day in order to enhance the reliability of data given (Saunders et al.,

42

2003). Finally, the open ended questions with no time limits offered the interviewee the

opportunity to express his/her view in depth. This fact made the analysis and comparison

of interviews easier.

3.6. Qualitative Data Analysis

After the collection of the data the approach of qualitative thematic analysis will be

performed. Braun and Clarke (2006:79) pointed out that thematic analysis is “a method

for identifying, analyzing and reporting patterns (themes) within data”. By analyzing the

interviews with that method, codes and themes should emerge. Also, thematic analysis

was combined with a priori coding of the four predefined categories identified in

Esteves’ et al. (2002) project. Moreover, adopting the principles of Braun and Clarke’s

(2006) study about thematic analysis, the five steps were followed are shown in table 2.3.

Stages Description

1. Familiarization with collected

data

2. Coding the data

3. Connection of codes and

identification of themes

4. Reviewing themes and concept

maps generation

5. Producing the findings report

The researcher read the interviews transcription many times

in order to acquaint himself with data.

Using the codes came out from data and the a priori coding,

the researcher developed a coding scheme.

Connecting the codes according their relations and

relevance and start grouping them to themes.

Check weather themes are related with the coded quotes

and start generating concept maps.

Final reporting of analyzed data using the selected quotes

relating them to the research question, aim and objectives.

Table 3.2: The five stages used in thematic analysis

During the second stage code related to the CSFs, motivations and consequences were

identified. These codes were revised again and again and therefore some of them have

43

been deleted or merged. So, the initial coding scheme has been established (Appendix

A2). In addition, in order to highlight the hierarchy between themes (main and sub-

themes) and codes and the relationship between CSFs and the consequences for not

meeting them the initial coding scheme was updated to the final coding scheme

(Appendix A3).

Also, concept maps were established to represent and organize the findings emerged

from the analysis. The CSFs of each factor is linked with the consequences for not

meeting it according to the coding scheme. Concept maps were produced as shown in the

figure 3.2.

Main theme Sub-theme Code (CSF) Code (Consequence)

Figure 3.2: Connections between main theme, sub-themes and codes

A limitation of thematic analysis is that sometimes the themes are not fully distinguished

and that happens because they are not “internally coherent, consistent and distinctive”

(Braun and Clarke, 2006:96). So after the analysis of the data true statements based on

the evidence gathered will be resulted.

Finally, all interviews were conducted in Greek. Also, the data transcription was done in

Greek. Although, the data analysis was conducted in English based on the Greek

transcriptions. Consequently, in order to avoid any mistakes and misinterpretations in

translation and increase the trustworthiness of the data, only selected quotations were

translated to support and findings.

Change

Management CSFs

e.g Sufficient

stimulation of

staff receptiveness

e.g Inadequate staff

involvement

CSF of BPR

in ERP

44

3.7. Summary

All in all, the study used the inductive approach to meet the research objectives with

reasonable evidence. Initially, the theoretical background gave the appropriate theoretical

knowledge to the researcher about the concepts of BPR and ERP implementations and

related issues, in order to select the suitable case to obtain the qualitative data. Moreover,

the five stages of qualitative thematic analysis allowed obtaining empirical knowledge

and generating a framework about the CSFs and their consequences based on the

analyzed data.

45

Chapter 4: Findings

4.1 Introduction

Due to the large number and diverse features of CSFs, the identification of them was very

time-consuming task. Although, in order to frame and structure the outcomes with a

meaningful way, CSFs have been identified are categorized into four predefined

dimensions – categories. CSFs are divided into the following categories:

1. Change Management CSFs: five CSFs

2. Product CSFs: eight CSFs

3. Process CSFs: five CSFs

4. People CSFs: eleven CSFs

Besides the CSFs that belong to a specific category and they have a major part of the

findings chapter, the motivations to implement BPR in ERP project were identified too.

Also, the consequences for not meeting each one of the CSFs are discussed.

Consequently, apart from the motivations which are presented first, a total of twenty-nine

CSFs and twenty-seven consequences were identified by analyzing the interview data.

Finally, in response to 2.2.5 session there is a further discussion at the end of each

category about the relevance of each dimension to the project lifecycle.

4.2 Motivations to BPR in ERP project

The factors actually motivate companies to reengineer their BPs are differ from

organization to organization. As discussed in the literature review chapter, BPR is

considered as one of the most critical factors of a successful ERP implementation.

Therefore the motivation to facilitate business and make ERP project a successful case is

one of the most basic reasons of BPR in ERP implementations (Nah et al., 2001; Nah et

46

al., 2006). This aforementioned fact is confirmed by the Systems and Controls manager

of EKA:

We wanted to ensure that ERP system would have been successfully

implemented. In order to increase the probabilities of success we

reengineered our BPs based in order to support the proposed functionality

and best practices of the system. That was a basic motivation (Systems

and Control Manager, EKA).

Moreover, other factors related to the performance of internal operations and therefore

operational efficiency propel enterprises to BPR. Al-Mashari and Zairi (1999) stress that

when organizations try to streamline their BPs, apart from the operational efficiency

improvement they also try to reduce BP cycle time and its cost too. As a result

operational efficiency is interrelated with performance and productivity of employees and

business in general. Having these, benchmarking and decision making which play a vital

role in organization life seem to be supported more satisfactorily. CEO of EKA

reinforced this notion by saying:

Some of the most important motivations for BPR were to improve the

current situation of the operations which was not as efficient as we wanted

to be. […] Our aims before the decision for implementing an ERP system

were to improve the efficiency of all functional areas, to reduce BPs cycle

time and costs and thus to help our staff to increase its productivity and

performance within BPs. Now, the decision made by management proved

to be the best securing our company’s competitiveness for the future

(CEO, EKA).

Further analysis of the interview data showed additional factors motivated EKA to BPR.

Senior managers claimed that the company was motivated by factors such as the accuracy

and integrity of information and also integration of systems and data along the

departments of organization.

47

Many times at the past we had problems with sales order processing, stock

control and job costing. An order for example may have lasted the double

time than the normal duration. Apart from that, sometimes an order was

placed but the stock was not updated and the products were not in stock.

That cost a lot of money to the company. Therefore, we wanted to change

everything that caused these kinds of problems. The integration of our

information systems with real time and accurate information were some of

our basic needs (Sales Manager, EKA).

Summarizing the factors motivated the case company to reengineer its BP in ERP

implementation we have the following motivations:

Facilitate business and ERP project

Improve operational efficiency

Accurate information across departments

Integration between systems and departments

Streamline BPs

Cost reduction

Reduce response time

Increase staff productivity and performance

Improve management reporting – decision making and benchmarking

48

4.3 The Critical Successful Factors (CSFs)

4.3.1 Change Management CSFs

BPR implementation in ERP projects has a significant impact on human and social

related side of an organization. Thus, a successful implementation of such project

requires large organizational changes not only in the structure but also changes in the

culture of the company (Zabjek et al., 2009). This statement came true in the case of

EKA too. For the implementation in the case-company the following five critical factors

have been identified which affected the project success positively, facilitating a

harmonious insertion of the new BPs in business environment. Also, the consequences

for not meeting each factor are presented (Figure 4.1).

Competent reward and motivation systems

The organizational change brought by reengineering the majority of the BPs in EKA

Group was relatively considerable. As a result, employees had many difficulties in

adopting these changes.

In order to motivate its staff having a smooth insertion in the new BPs and

also increasing their productivity management divided us into several

groups. The group with the highest levels of performance was given as a

reward a journey to a foreign country of their choice. That choice of the

management was proved very smart (Systems and Controls Manager).

As clearly shown in that statement, top management tried to encourage and motivate the

staff using an incentive system confirming what Towers (1994) pointed out about reward

and motivation systems.

Towers (1994) also explains that when something goes wrong in BPR then the

consequences are emerged like a chain pattern. That was confirmed by interviewees’

49

attitude when they had been asked about the consequences for not meeting a specific

CSF. “If there was no reward system then our involvement would have been very little

and not enough for the company needs. Inadequate involvement would have possibly

caused conflict between BPs” (Sales Manager, EKA).

Sufficient stimulation of staff receptiveness

Apart from the major changes in processes BPR requires a fundamental thinking of how

people within and without the company are managed. The majority of interviewees

responded that the management of the company tried to stimulate their receptiveness in

order to think about changes positively preparing them appropriately for the BPR. While

the level of acceptance is high, the employees become and remain not only positive to

BPR related change but also flexible, eager and pro-active (Jackson, 1997). “The

managers tried to make us feel more confident about the changes. From my point of view

that attitude eliminated my worries and suspicion and finally I was willing to change my

previous boring working routine” (Invoicing Clerk, EKA Group).

The consequences of this factor are similar to the reward motivation systems because of

the interrelated nature of the two factors. It is widely accepted that if management does

not try to stimulate its staff receptiveness, the staff will resist to the change initially. Even

if staff tries to involve in the project, that involvement will be inadequate. That will cause

a project delay too.

Create a new effective culture

Organizational culture includes values, beliefs and organizational behavior in general

(Nah et al., 2001). This is why is extremely important in successful BPR implementation.

It is not a simple task to change the culture of a company and develop a new more

effective one in a few days.

50

The creation of a new more effective organizational culture was one of the

most major tasks. We tried to inculcate a new positive attitude to

employees and prepare the appropriate conditions for their working

environment. The new BPs along with ERP functions required a new

effective culture. Co-operation and co-ordination between actors within

the company are now two new values based on the new culture and the

new processes. If we had not done that the philosophy of the company

would have been remain as it was before which was very different from

the philosophy required by such organizational changes (Overseas

Business development Manager, EKA Group).

Therefore, it is clearly emerged that top management of the case company tried to

develop a new more effective culture based on the new BP adding more value to the

company and using a decentralized and participative way of working.

If the company had failed to introduce an effective culture based on BPR related changes

then philosophy of the company would not have been the required to support the changes

and the staff would have been remained unwilling to the new business environment.

Sufficient customer focus

Customer expectations should always be in the epicenter for the BPs in which customer is

involved. Therefore, organizations should reengineer the processes in order to improve

the quality of customer services (Chang, 1994). Chang’s statement is confirmed by Sales

clerks’ responses as shown below:

The combination of the new BPs and ERP system changed not only my

life but also the customer’s. The new processes show a clear focus to

customers. The sale order processing for instance is extremely improved.

The cycle time was reduced and I believe the customer satisfaction is at

the highest level (Sales Clerk, EKA Group).

51

As shown, the company focused on customer needs. That fact increased accountability of

the entire process and not only the part that the customer is involved, enhancing finally

customer responsiveness.

As stated by participants “some of the consequences like customer dissatisfaction, are

quite obvious” (Accountant, EKA). But at the same time that means the reengineering

strategy is ill-defined and therefore the value added to the new BPs is minimum (Sales

Clerk, EKA).

Clear vision and scope – explicit BPR plan

Clear vision, objectives and scope of the project were perceived as major factor by top

management – interviewees. Undoubtedly, such important project with so many changes

across the organization, requires a very clear short and long-term plan to succeed (Al-

Mashari and Zairi, 1999).

In order to steer and coordinate the project appropriately we produced a

precise BPR plan based on the ERP system, including the potential

tangible and strategic benefits. The plan also outlined the cost and the

proposed resources that probably needed (CEO, EKA Group).

“If the plan was not clear the consequences would have been very harmful for the project

and company in general. […] Apart from the higher cost and project delay the

reengineered BPs would have been inefficiently and insufficiently changed” (Systems

and Control Manager, EKA Group). The above statement demonstrates that the

consequences for not meeting that factor have a damaging impact on the project.

52

Further Discussion

As discussed above at the beginning of this session, change management dimension has

to do with the human and social side of the BPR implementation. If someone has a quick

look at the CSFs of this category he will realize what the interviewees indirectly said

about the change management and its relation to the project lifecycle. If the project

lifecycle is divided into pre-implementation, implementation and post-implementation

phases (see 2.2.5), the CSFs of this category are particularly apparent during pre-

implementation stage of BPR lifecycle and therefore. That does not mean the change

management pays only at the first stage of BPR. In contrast, it still be apparent during the

whole project but with less focus.

53

Figure 4.1: Concept map of Change Management category CSFs

Change

Management

CSFs

Sufficient

stimulation of

staff receptiveness

Competent

reward and

motivation systems

Create a new

effective culture

Clear vision and

scope – explicit

BPR plan

Sufficient

customer focus

Staff reluctance and resistance to

change

Conflicts

between BP

Inadequate staff

involvement

Hire / loss (un)

necessary

staff

Reengineer

ing plan and

strategy is

ill-defined

The selected

ERP system cannot support

the new

philosophy and culture of the

company

Low level of

customer services –

customer

dissatisfaction

Wrong

selection of BP to be

reengineered

Low value-

added to

BP

Reengineering plan

and

strategy is ill-defined

Higher cost than

expected

Reengineerin

g plan and strategy is ill-

defined

Low value-

added to

BP

Project fund

and resources are

insufficient

Project

delays

Project

delays

Staff

reluctance and resistance

to change

Inadequate

staff

involvement

Staff

reluctance and

resistance to change

54

4.3.2 Process CSFs

The process that is going to be followed for the BPR in ERP context is extremely major

for the BPR success (Esteves et al., 2002). Therefore, the CSFs of this category are

relevant with the process-strategy that the project team with the top management of the

case organization are going to follow for a successful implementation (Figure 4.2).

Process CSFs are indirectly referred to the human factor too. Although, the relevance is

not so close. Finally, this category can potentially create BP blueprints in which the

previous BPs are defined and the new BPs are being built.

Efficient BP seminars-workshops across divisions

Stemberger and Kovacic (2008:261) stressed out the significance of assessing the

situation of the company early in the project getting adequate details about the BP. That

can be achieved more sufficiently by calling the staff of the company and having a

comprehensive discussion with them.

We were called by the project team to join a workshop to discuss various

points about the BPs of our division where important points about the

project was explained to us using the approach of case studies. If we had

not attended this workshops maybe we would not have been persuaded to

change the our routine (Shipping Purchasing Coordinator, EKA Group).

From the data analysis, it is emerged that this kind of seminars and workshops proved

quite important especially for the employees understanding. Furthermore BP workshops

helped amazingly the project team to have a better understanding of the entire company

and its current BP.

Interviewees also claimed that the consequences if a project does meet this CSF have to

the BP and inappropriate analysis and assessment and secondly with them. “BP

55

workshops helped us to have a better understanding of the scope of the project”

(Invoicing Clerk).

Define the inefficient BPs which must change

Defining which BPs are inefficient in order to follow what the system proposes is a one

of the initial steps of the reengineering process and a critical component of a successful

BPR (Motwani et al, 1998). The less time-consuming and non-profitable BPs with lowest

added value should be immediately changed and fit system’s functionality. For that,

process gaps and bottlenecks should be identified as early as possible.

We tried to evaluate every single BP and examine at which points the

process should have been changed or modified. Moreover, we established

benchmarks and baselines for future evaluation of the same BP. […] That

task was extremely important. The final decision with BP changed had a

positive impact on the project success (ERP Implementation Consultant,

ERP Vendor Implementation Company).

From the above mentioned statement it becomes clear that defining which BP must

change for the fine-tuning between BP and system has a crucial role as an initial step of

the BPR.

As one of the prime steps of the reengineering process it is obvious that any omissions

will have extremely negative consequences and gaps between the supported and required

functionality for the project. “I believe one the most important consequences is the gap

that is going to be generated between what the company wants to do and what can be

done. That fact causes low integration between departments and therefore additional

effort from us”. Some significant consequences arise from that IT Administrator’s

response.

56

Adequate staff involvement based on processes

When the BP are reengineered the staff of the company should actively and sufficiently

involved (Jackson, 1997). Human factor affects the BPR but organization staff is equally

affected by BPR too. So, staff from all levels of the company must involve in

reengineering based on the processes that they work for or belong in because not only for

the knowledge and experience they have about BPs but also because any mistakes and

errors will affect individuals.

Adequate staff involvement will help the project team to make the

appropriate decision in general. If the staff do involve sufficiently the

analysis of BP will be insufficient and then the wrong BP will be selected

for reengineering (Warehouse Manager, EKA Group).

Subsequently, the response of warehouse manager illuminates the importance of the

factor by stressing out that the wrong selection of BPs and insufficient BP analysis will

be the consequences for not meeting the factor.

Appropriate allocation of roles and responsibilities

The management of the company having the appropriate consultancy from the vendor

should allocate roles and responsibilities to the right person within the company who

have the relevant knowledge to manage the task or role given to them. A clear and formal

allocation of roles will simplify the project significantly.

The allocation of roles and responsibilities to the experts based on the

needs of the Reengineering process and ERP project in general was a

significant action to control and direct the change […] Key users in

specific cases were very helpful (Chief Accountant, EKA).

[…] the consequences will have a primary impact on us, the staff, because

if the allocation is not the appropriate some of us should put an additional

57

effort. Moreover, there is a possibility for us to loss our job as unnecessary

staff for the new BPs (Office Administrator, EKA).

It becomes clearer now that the above-mentioned factor with key users in several points

of the company during the project is necessary for the project success. The importance is

also reflected in office administrator’s response about the consequences. The staff of the

company will be the first stakeholder affected negatively by not meeting the factor.

Adequate integration between BP and jobs

Adequacy of human resources and their integration with the various BP is another factor

that seems to be equally important to reengineering process success. Job orientation

should be based on the new BP and that was early understood by top management of

EKA Group. “The alignment between the potential BP and jobs was a difficult task but

we did it carefully and finally successfully. Yet, we hire people to support the new BP

and that also supports fine integration” (CEO, EKA Group)

New staff was recruited with specific skills and knowledge with the staff

existed in the company helped not only supporting the project but also

supporting the company especially in the post implementation phase. But

if had not do that the human resources would not have been allocated

appropriately and the integration between departments would have been

remained at the same low level (Overseas Business Development

Manager).

So, it is evidence that organization should pay attention into this point and recruit or find

people inside the company because if it does not the conflict between BPs will still be

apparent and therefore integration between BPs and departments will not be the required

for the project success.

58

Continuous Monitoring and evaluation

The continuous monitoring and evaluation of the project progress is a prerequisite factor

for a successful BPR (Motwani et al, 1998). BPR efforts should be measured against the

objectives and plan produced during the pre-implementation phase. If something does not

follow what was decided, it must be modified or redesigned accordingly. What Motwani

et al. (1998) pointed out seems to be valid in the case of EKA Group. “The use of the

appropriate methodology allowed us to monitor and evaluate the project progress

continuously. Inefficient monitoring of the project could have been caused delays and

therefore the cost would have been increased” (Project Manager – Consultant, ERP

Implementation Vendor).

Proper implementation sequence between BPR and ERP

The debatable issue of the literature review chapter about the implementation sequence of

BPR and ERP is being answered here by the case company. Subramoniam et al. (2009)

concluded that the proper approach is the simultaneous implementation of BPR and ERP.

The project team followed that approach implementing BPR during the whole ERP

project. However, BPR was apparent mostly at the early stages of ERP lifecycle.

It is more appropriate to put more reengineering efforts at the pre-

implementation stage of ERP lifecycle when everything is being assessed

and analyzed. Although, during entire lifecycle of ERP it is reasonable to

have BPR procedures until the needs of BP are finally covered (ERP

implementation Consultant, ERP Implementation Vendor Company).

The participants and especially those from the vendor company argued that the

consequences are more technical rather than human or organizational. “If you follow a

wrong sequence then the supported functionality by the system to not fit with the new

BPs. Also the cost of the project will be higher than expected to be ”(ERP

Implementation Consultant). So, it clearly emerged that inappropriate sequence between

59

BPR and ERP will cause a gap between BPs and the system and therefore the integration

between them could have not been achieved.

Proper implementation strategy

Apart from the proper implementation sequence companies should follow the proper

implementation strategy. In EKA case step by step strategy was followed successfully.

The step by step implementation strategy that is proposed by ASAP

methodology helped to continuously evaluate the project with tools that

provides. It also helped us to streamline the implementation and as a result

the BPs of the company too (ERP Consultant, ERP Implementation

Vendor Company).

The aforementioned strategy confirms what Schniederjans and Kim (2003) said about the

predominate success implementation strategy for a successful BPR. If the step by step

strategy is not followed then the consequences will have to do with the integration

between departments, BPs and the supported by the system functionality. “The modules

of the system will not be integrated with the BPs of the department and therefore the

value added to the BPs will be minimal” said the Implementation Consultant of Vendor

Company mentioning the most important consequences.

Further Discussion

Process category CSFs has relevance with whole implementation lifecycle. It cannot be

said securely that process dimension is more relevant with a specific phase. Although,

looking at each separate factor and participants allegations about them it can be said that

is a little more apparent at the pre-implementation phase. The last two CSFs of the

category for example, have to be decided early in the project. Nevertheless, process

dimension is also relevant with the other two phases. For instance, continuous monitoring

and evaluation is obvious that it never stops during the project.

60

Figure 4.2: Concept map of Process category CSFs

Process CSFs

Appropriate

allocation of roles

and responsibilities

Adequate staff

involvement

based on

processes

Adequate

integration

between BP and

jobs

Proper

implementation

sequence between

BPR and ERP

Define the

inefficient business

processes which

must change

Efficient Business

Process seminars-

workshops across

divisions

Proper

implementation

strategy

Continuous

Monitoring and

evaluation

Low integration

of BP between

departments

Inadequate

analysis and BP

assessment

Wrong team

formation

Hire / loss (un)

necessary staff

Inefficient training

and education –

low skilled staff

Project delays

Staff reluctance

and resistance to

change

Higher cost

than expected

Additional

effort from

employees

Gap between functionality

supported and required

functionality

Low integration

of BP between

departments

Project fund and

resources are

insufficient

Inadequate staff

involvement

Reengineering

plan and strategy

is ill-defined

Low integration

of BP between

departments

Conflicts

between BP

Staff reluctance

and resistance to

change

Low integration of BP

between departments

Additional

effort from

employees

Inefficient training

and education –

low skilled staff

Additional

effort from

employees

Inappropriate use

of IT as enabler

for BPR

Low value-

added to BP

Wrong selection of

BP to be

reengineered

Wrong selection of

BP to be

reengineered

Low value-

added to BP

Hire / loss (un)

necessary staff

Inefficient training

and education –

low skilled staff

Low integration

between BP and ERP

package (modules)

Low value-

added to BP

Gap between functionality

supported and required

functionality

Low value-

added to BP

Project delays

Inadequate staff

involvement

Low integration

between BP and ERP

package (modules)

61

4.3.3 Product CSFs

CSFs related to the product can be defined as the factors related to the technical

perspective and the product specification. Normally, product’s CSFs have close

relationship with ERP system which is the actual and tangible product. Issues like the

selection of ERP package and the vendor of it have a more focus. Although, other critical

factors have to with ERP customization, IS integration along the department and BP of

the company are also related to that category (Figure 4.3).

Suitable ERP package selection

The selection of the appropriate ERP system plays a vital role in facilitating the BPR

efforts (Stemberger and Kovacic, 2008:261). “[…] the decision for the appropriate ERP

system was very difficult. We just wanted a system with best practices embedded, having

appropriate alignment with our BPs” (CEO, EKA Group). Apart from those two specific

criteria, IT Administrator of the company continued:

Moreover the scalability of the system was important issue too. Of course,

the stability of product was another criterion in order to make the right

decision.

The above statements confirmed what Siriginidi (2000) supported about the selection of

the appropriate system and the criteria a company should take into account. Although, the

adequacy in modules and functionality and therefore the compatibility and capabilities of

the system to support the entire business area and needs of the company as a SME had a

crucial role for the ERP package final decision.

“If the ERP package is not the suitable for the organization and does not support what the

BPs was suppose to do, the consequences will affect the integration between BPs and

ERP modules.

62

Suitable ERP Implementation vendor selection

Selecting the suitable ERP package does not mean at the same time that a company

selected the appropriate ERP vendor. The decision for the latter is equally critical with

the previous factor. The analysis of interview data indicated that the EKA Group wanted

an EPR Implementation with specific characteristics. The first was the vendor company

to have a consistent temperament and philosophy in order to match with the philosophy

of EKA. Secondly, the prospects of the vendor were very was excellent because it was

associated with the top brand of the field “EKA Group has always been associated with

the top brands” (CEO, EKA Group). Thirdly and most importantly, EKA tried to find a

company with the lowest level of instability looking the history of candidate vendors.

Our experience with our partners shows that we should always the history

of the company we are going to have business with. The stability of ERP

vendor was at lowest level and that made us feel more confident with them

(Systems and Control Manager, EKA Group).

The consequences for meeting that factor can have an extremely negative impact on the

project which may fail at the end. Particularly, the level of instability can have the

greatest impact on project failure. “If the vendor is not the appropriate the communication

will ineffective and their support will be inefficient” (IT Administrator, EKA). Thus,

looking the statements above it is surely emerged that EKA paid much attention on the

ERP vendor selection in order to have better chance to succeed.

Effective IT infrastructure

As discussed in 2.3.4 session, IT infrastructure is considered by many researchers as a

vital enabler and therefore a critical component for a successful BPR (Al-Mashari and

Zairi, 1999; Siriginidi, 2000; Subramoniam et al., 2009). That fact was early realized by

management of EKA. Having the consultancy of IT people in the company and the

external consultants they upgraded the IT infrastructure efficiently to support the new

processes and changes brought by ERP system in general. New hardware such as

63

computers, servers, databases and networks of the latest generation of technology was

bought.

Our previous IT infrastructure could not support the requirements of the

new processes and ERP system in general. The need to introduce new

hardware was obvious. There is no doubt that the new infrastructure had a

positive impact on productivity and it reduced significantly the time cycle

of our BPs (IT Administrator, EKA Group).

The response of the IT administrator who has better knowledge and expertise on such

issues illuminates that the case company had seriously taken into account the factor of IT

infrastructure.

“If we had not changed our infrastructure our plan could have not been supported

sufficiently and the cost of the project would have been increased significantly. That

would have led the project to failure and the organization in a very difficult situation”.

The answer of IT Administrator who responded in a similar way with Logistics Manager

of the company outlines the consequences for not meeting this factor.

Adequate ERP customization

ERP customization to suit the BPs needs is considered as an inevitable task (Nah et al.,

2001). On the other hand, Holland et al. (1999) supported the notion that organizations

should change their processes to suit the ERP package with minimum customization.

However, EKA’s project did not follow Holland’s opinion in full. The majority of the

BPs were designed according the processes embedded within the system but at the same

time, ERP customization was neither minimal nor extensive. ERP was customized

whenever was necessary for the best was tuning of the processes and also to add extra

functionality within the processes.

64

Most of the BPs were mapped to ERP’s. In certain cases processes were

supported with customization and/or custom development (Project

Manager – ERP Consultant, ERP Implementation Vendor Company)

In specific cases we customized the system to fit processes. Sometimes

that was quite painful because of the strange nature of EKA and its

multiple divisions (ERP Implementation Consultant, ERP Implementation

Vendor Company).

The interviewees claimed that the consequences for not meeting this factor are related to

the integration between BP, ERP system and departments. “If we had not customized the

system the integration between departments would have been very low” said a

Departmental Manager of EKA Group.

The above statements are clear evidence that the system customization done on the

system was adequate and sufficient to fit the BPs and support the business needs

whenever was necessary. Therefore, this is a critical factor for a successful BPR

implementation in ERP projects too.

Adequate information systems integration

Organizations apart from ERP system have some other information systems (IS)

installed. BP are linked with these IS in many points. EKA has a CRM which is

integrated not only with its BP but also with the ERP system. “This recursive relationship

between systems has an impact on the information transferred within BP. That

information should be always accurate, consistent and in the place that it should be at

specific point in time (Systems and Control Manager, EKA Group). From that view the

CSF is arisen. The integration between IS should be in adequate levels in order to

contribute to a successful implementation. Inadequate IS integration can cause inefficient

decision making especially for the top management. Low integration means not real time

information which can increase of course the cost of a wrong decision.

65

Further Discussion

Having a quick glance at the critical factors of this category and having in mind what

interviewees said about them it can be said that product dimension is more apparent at the

second phase of the project lifecycle, the implementation phase. That conclusion is

mainly come from the fact that ERP system is partly customized to fit BP and to be

integrated with the rest IS of the organization. So, there is a clear development –

construction of a tangible product which is more related to the implementation phase.

However, product dimension is also related with the other two phases but it reaches a

peak in the middle phase.

66

Figure 4.3: Concept map of Product category CSFs

Product CSFs

Effective IT

infrastructure

Suitable ERP

Implementation

vendor selection

Adequate

ERP

customization

Suitable ERP

package

selection

Adequate

information

systems integration

Project delays

Higher cost

than

expected

Insufficient- bad

communication

between staff and vendor’s

consultants

Low

integration between BP

and ERP

package (modules)

Low

integration of BP

between

departments

Gap between

functionality supported and

required

functionality

Low

integration of BP between

departments

Incorrect data to the

system –

low data quality

Managers get

incorrect reporting –

information

Inefficient

decision making

Low

integration between

BP and

ERP package

(modules)

Inappropri

ate use of IT as

enabler for

BPR

Higher cost

than expected

Project

fund and resources

are

insufficient

Inefficient support by

vendors

consultants

Reengineer

ing plan and

strategy is

ill-defined

Additional

effort from employees

Project fund and resources

are

insufficient

The selected ERP system cannot

support the new

philosophy and culture

Wrong

selection of BP to be

reengineered

67

4.3.4 People CSFs

People CSFs can be defined as the factors which are inextricably dependent and linked

with the human factor (Esteves et al., 2002). Some examples are the factors have to do

with top managers, consultants and project team in general (Figure 4.4). However, the

management of BPR implementation in ERP projects is an extremely dangerous

challenge. Everything is decided by top managers who have the greatest direct influence

on the project because of their decision power. Therefore the majority of CSFs belongs to

this category. Although, that fact does not imply that this dimension is more vital for the

project success because all the four dimensions are equally important.

Sufficient Top management support and commitment

Top management support and commitment as a CSF was mentioned by all participants as

the one of the predominant factors which led the company to a successful BPR

implementation.

One of the 3 key factors affected the success of the BPR in ERP project

was the top management support of the company during the whole project

lifecycle. (ERP Implementation Consultant, ERP Vendor Company).

Top management of EKA using various methods tried to persuade, guide and support the

staff of the company for the best results. In order to that, they gained a clear

understanding of the goals, benefits, limitations, risks and needs of the project.

The top management support was the cornerstone of our success. An

example of the great support given by top managers was the unbelievable

patience that they showed in order to help the most difficult to teach

employees trying to identify and improve their weaknesses (Sales

Manager).

68

Finally, CEO of EKA reinforced what Holland et al. (1999) said about the top managers

who should have the appropriate know-how of their company and what is going on

around it, which is really important. “It is not only to take the decision to it. You have to

be able to do it, you have to be about it”.

Again, the consequences for not meeting that factor have a negative impact on the project

progress and therefore its success. “If top management does not give sufficient support

the project will not have many chances to be successful. The plan will be unclear and

resources and fund needed will be underestimated and insufficient”. Logistics Manager’s

response demonstrates the ill-defined reengineering plan and strategy and insufficient

project and resources are the most important consequences for not meeting this factor.

Sufficient staff education and training

The role of education and training is considered by Al-Mashari and Zairi (1999) as a

major for BPR implementation success. From the data analysis it emerged that this factor

was taken by project team and staff very seriously. Management of EKA made clear that

all employees of the company would have been educated and trained as much as was

needed to the new BP and system.

The project team spent many hours to train us. It was really painful for all.

But it was a must priority. Therefore, our skills and knowledge about the

new BP and the ERP system have been improved significantly. We also

became more computer literate and we can manage each procedure with

better results. […] If those sessions were not conducted I believe we

would have resisted more to change the way of working and therefore we

our skills would have not been the same as they are now (Accountant,

EKA).

This quote shows that the training sessions took place in the company were extremely

helpful for the staff to develop the appropriate skills and adapt to the new working

69

environment. Also, it emerges that the consequences of a potential insufficient staff

education and training have to do with their skills and the level of staff acceptance

Effective communication between stakeholders inside the company

Effective communication between the actors and departments inside the company has a

vital role in facilitating the reengineering efforts (Nah et al., 2001). That communication

was perceived as a crucial factor by all interviewees too.

The communication between us during the project was excellent. We

persuaded the staff that for any problems or worries about the project and

the company in general to not hesitate to talk with us. Key users – steering

committee – in several points of the company always had a continuous and

comprehensive communication. If that communication was missing the

analysis and assessment of BPs would have been inadequate (CEO, EKA

Group).

As it can be seen, the efficient communication during the project is essential for all levels

and all audiences within an organization. If that good communication is missing then the

analysis of the BPs is negatively affected.

Effective communication with the stakeholders outside the company.

Effective communication should be apparent and continuous between actors inside the

company and the project team which is outside the company. There is strong need of

communication between the project team and top management especially at the first

phase of the project in order to define the scope and the BPR plan in general. Although,

the frequent and rich communication should be a fact also in trainings session between

the project team and staff. “The communication with the project team was excellent. For

anything I needed I had the chance to contact with them at any time” (Sales Clerk, EKA

Group), confirming what it was mentioned above. If the communication is poor the

70

project is more possible to delay and support from vendor consultants will not be

efficient.

Appropriate project team formation

Another one important piece of BPR success in ERP projects is the appropriate team

formation. The composition of the team is always relevant with size of the company and

complexity of its BP (Holland et al., 1999). As it was mentioned previously EKA is a

medium-size enterprise. Although, the complexity of its BP was quite high. “EKA is

quite complex, multifaceted organization with operations abroad, with industrial

products, construction operations and specialized constructions” (CEO, EKA Group).

Therefore the composition of the team was affected.

Apart from vendor’s consultants and IT experts, people inside the

company like BP owners and key users were included in the team. Our

company had a total commitment in the project and new people was hired

to support the project. [...] The wrong team formation has negative impact

on the project duration and staff required for the project (ERP

Implementation Consultant, ERP Vendor Company).

The above statement of the vendor’s consultant shows clearly that project formation is a

very critical factor for the project success. If it is not met the project may delay again and

secondly qualified staff from both companies may be fired as unnecessary or to hire staff

seem necessary but actually is not.

Efficient supervision by external Project Manager

Analyzing the interview data another key component emerged for the project success was

the efficient supervision by the third party project manager who was recruited by EKA.

Indeed, an external project manager with great familiarity with such projects can

potentially supervise more carefully and efficiently the project and give additional

71

support to the project team. It also can be the liaison between the management of the

project team giving the appropriate guidelines to meet the deadlines and pass the

milestones.

“If we had not recruited external project manager the project may not have the

appropriate monitoring and therefore the evaluation would have been different.

Consequently the project may have delayed” said the CEO of EKA stressing the

consequences if that factor is not met.

Efficient Risk management

BPR in ERP project requires an efficient risk management. There are several risks that

may occur during the reengineering efforts. The majority of respondents claimed that the

one of the most dangerous risks is associated with the level of receptiveness of staff to the

changes. Moreover, the time needed for the staff to assimilate the new style of working

should be managed appropriately. “The possibility of a big confusion and operational

disruption until the staff start adapting to the changes is high. This high risk has to do

mostly with post-implementation phase. But it has passed successfully as a result of the

good risk management provided by management” (Overseas Business Development

Manager, EKA). Therefore efficient risk assessment and management is a critical factor

throughout the project lifecycle.

Efficient sponsorship and project fund

Apart from the human resources the project need an efficient financial sponsorship and

fund. It should be a major priority within the company and the management should have

the power to fund and support the project efficiently. “The project fund was a top priority

for the company during the project. If it was not then the project may have cancelled

because of its high cost” was the response of CEO of the company that clearly

illuminates the importance of the factor.

72

Strong top management leadership

Strong leadership exercised by top management is crucial component not only for the

reengineering efforts but also for the whole company life in general (Jackson, 1997).

Indeed, participants and especially the operational staff who can judge impartially

confirmed that top management provide strong and visible leadership with having at the

same time a deep understanding of each stage of the project.

I think the decisions of the management throughout the project

implementation were correct. But the final decision to change the way of

doing business was a result of hours of study and very good negotiations.

Every single task was faced with the strong leadership. Therefore, I

believe the management showed the appropriate leadership for this project

(Shipping and Purchasing Coordinator, EKA).

Consequently, strong leadership is another feature than has a positive impact on the

successful BPR implementation. For not meeting that factor the project fund and

resources need will be affected and underestimated and also the staff reluctance to change

will be higher.

Continuous and sufficient support by people inside the company – key users

The use of BPR teams with BPR owners and key users for each process has a central role

during the BPR efforts. Two of their basic duties of those teams are to help the project

team to analyze and then define each process a help the staff who have difficulties with

new BP and related changes. Interviewees also claimed that key users in specific areas

facilitated the project with their continuous coordination and general support. If that was

missing staff resistance to change would have been in a higher level and of course

education of staff would have not been the same. Therefore, the staff will be low skilled

as a consequence.

73

Continuous and sufficient support by the vendor consultants

There is no doubt that the knowledge, expertise and experience of vendor’s consultants

who have familiarity with this kind of project can be proved critical. Indeed, the ongoing

consultancy given by vendor consultants during the whole project has been mentioned by

all interviewees.

The consultancy given by the vendor company was unbelievably helpful.

They were very kind and always eager to help anytime we wanted help.

(Operations and Construction assistant, EKA Group)

They provided a great consultancy during the project and after the delivery

of it. Especially in training sessions their performance was excellent.

Although, some years later, for everything we need about maintenance or

general support are always eager to help us (IT Administrator, EKA

Group).

From the above statements it is evidently emerged that support given by vendor

consultants has a vital role to play in such projects and managers should think about it

carefully because it is also related with the appropriate vendor selection.

“Without the support and from the consultants with their very helpful education and

training sessions the staff would have been less skilled and unwilling to work and learn

the new BP and related changes” (Systems and Control Manager, EKA). From that

statement emerges the most important consequences those have to especially the staff

acceptance and its skills after the implementation.

74

Further Discussion

The People category has eleven CSFs which is largest number of CSFs among the four

categories that CSFs are divided into. As a consequence, people dimension has relevance

with all three phases of the project lifecycle. Some of the factors, efficient top

management support and factors have to do with communication for examples, have the

exactly the same focus during the project. In other words, if one of those factors is

missing in implementation phase for instance, the project may not be successful.

Although, some other factors are more apparent at the last phase such efficient trainings

session on the final BPs. Of course, training can start from the first phase but it is more

relevant with last phase. Again, efficient risk management is more related with the pre-

implementation phase but it cannot be ignored in the other stages. All in all, people CSFs

are equally relevant with all phases and therefore whole implementation of BPR.

75

Figure 4.4: Concept map of People category CSFs .

People CSFs

Effective

communication with

stakeholders who are outside the company

Effective

communication between

stakeholders inside

the company

Appropriate project team

formation

Efficient

supervision by

external Project Manager (third

party)

Sufficient

education and

training

Efficient

sponsorship and project fund

Efficient Risk

management

Sufficient Top

management support and

commitment

Strong top

management leadership

Continuous and

sufficient

support by the vendor

consultants

Continuous and

sufficient

support by people inside the

company – key

users

Staff reluctance

and resistance to change

Project delays

Inadequate

analysis and BP assessment

Inefficient

support by vendors

consultants

Hire / loss (un)

necessary staff

Inefficient

training and

education – low skilled staff

Inappropriate

monitoring and evaluation

Project delays

Staff reluctance

and resistance

to change

Low skilled staff

Additional effort from

employees

Project delays

Higher cost

than expected

Higher cost

than expected

Project delays

Wrong

selection of BP

to be

reengineered

Inadequate analysis and BP

assessment

Wrong team

formation

Cancelation

of the project

Staff reluctance and resistance

to change

Project fund and resources

are insufficient

Additional effort

from employees

Inefficient training

and education – low skilled staff

Inefficient training and education – low

skilled staff

Additional

effort from

employees

Inadequate analysis

and BP assessment

Staff reluctance

and resistance to

change

Project fund and resources

are insufficient

76

4.4 Overall Findings Discussion

Overall, from EKA Group case-study have been identified 29 CSFs divided into four

categories: Change Management, Product, Process and People. As it was mentioned at

the beginning of this session all categories and therefore all CSFs are equally critical and

important and they should be taken into account very seriously before, during and after

the project implementation in order to help SMEs to successfully implement such a

massively important project.

The identified CSFs of each category can be related to different perspectives and angles.

For example, CSFs of change management dimension are more related to the

organizational mechanism of the management to change the current situation of the

company. The second dimension’s CSFs are related to a diverse technical and

organizational perspective. The project team is the major actor of that category but

always has the support of the top management Also it is related to the users as the

involvement of them is very critical for the project success. On the other hand, product

dimension is more technical oriented whereas the final category is more human oriented

because of the universal involvement of the top management. Subsequently, in order to

achieve a successful implementation of BPR in ERP project those different angles should

be taken under consideration. The diversity of these aspects confirms what CEO of EKA

said about the project. “That project was not just some changes and a system in place. It

was the genesis of a new business world for our company”.

Finally, the consequences emerged from interviewees responses for each factor can help

especially SMEs to have a deeper understanding when they decide to go-live with such

difficult project like BPR in EPR context.

77

Chapter 5: Conclusions

5.1. Introduction

The last chapter of the study provides a summary of the entire research in the context of

research aim and objectives. In addition, the limitations of research are presented as well.

Finally, the chapter concludes with a discussion about future research by presenting some

recommendations.

5.2. Conclusion of the study

This study reports an in-depth exploration and discussion about the successful

implementation of BPR in ERP project. The study identified a set of CSFs divided into

four categories. The categories are change management, process, product and people.

CSFs are summarized in Figure 5.1.

The four categories play an equally important role for the successful BPR. Despite that

fact, the people category for instance has more CSFs to be considered while at the same

time product dimension has less. The difference at the total number of CSFs between

categories is a notable fact because each category has its own relationship and way of

connection with the stakeholders of the project and the different parts of it. More

specifically, the CSFs found can be related with top management and the project team.

On the first hand, CSFs related to top management are particularly linked with the

mechanism that top managers are going to follow to guide the project from organizational

perspective. For example, the important role of top management can be seen in many of

their decisions. Another example, the selection of vendor company in such major project

or how to prepare to stimulate the staff receptiveness, are two important highly important

decisions should be taken from the top management. On the other hand, the CSFs related

to the project team are more related to technological perspective because they have to do

mainly with the

78

Figure 5.1: Empirical investigation model of CSFs for BPR in ERP project

Change Management

CSFs

Process CSFs

Product CSFs

People CSFs

Competent reward and motivation systems

Create a new effective culture

Sufficient stimulation of staff receptiveness

Clear vision and scope –

explicit BPR plan

Sufficient customer

focus

Proper implementation

strategy

Continuous Monitoring

and evaluation

Adequate staff involvement based on

processes

Efficient Business

Process seminars-workshops across

divisions

Adequate integration

between BP and jobs

Proper implementation

sequence between BPR and ERP

Define the inefficient business processes

which must change

Appropriate allocation of

roles and responsibilities

Suitable ERP

Implementation vendor selection

Effective IT infrastructure

Suitable ERP package selection

Adequate ERP

customization

Adequate information

systems integration

Sufficient education and

training

Effective communication

between stakeholders inside the company

Effective communication with stakeholders who

are outside the company

Appropriate project team formation

Continuous and

sufficient support by

people inside the

company – key users

Efficient supervision by

external Project Manager (third party)

Strong top management leadership

Sufficient Top

management support and

commitment

Efficient sponsorship

and project fund

Efficient Risk management

Continuous and

sufficient support by the

vendor consultants

CSF of BPR in ERP

79

system and its integration with the BPs of the company. The project team should be in the

position to monitor the whole implementation efficiently by identifying potential gaps

and having immediate remedy actions to solve potential problems.

In conclusion, the importance of a successful BPR as a part of the ERP implementation

project should be acknowledged particularly by SMEs. Many researchers and specialists

of the field acknowledge that BPR is critical factor of a successful ERP implementation.

However, how to make BPR a successful case in order to increase the chances of a

successful ERP implementation seems that it has not been well study by researchers and

as a result BPR is not taken under a serious consideration by companies. The

consequences of this fact have an extremely negative impact on the project and the

company too. That becomes particularly important for SMEs whose financial resources

are limited and therefore the future of the company may be in uncertainty.

5.3. Limitations

That research has two limitations. The first one which is more major is one of the most

typical limitations of case study researches. As mentioned in the methodology chapter

the study follows the single case study approach to answer the research question. The

model produced is just an empirical model and not theoretical based on the single case

study. Therefore, the findings of this research strategy can be disputed because are just

empirical. The second limitation of the study is that the interviews were conducted in

Greek. The transcription is also in Greek. Therefore, in order to avoid the

misinterpretations in translation and increase the trustworthiness of the data, only

selected quotations were translated to support and findings. Although, this is a minor

limitation of the study.

80

5.4. Recommendations for future research

As a result of the first limitation of the study, the researcher strongly recommends the

future researchers to include the multiple case study strategy and include more cases to

validate the findings of this study. In response to the latter, they can also use

questionnaires to ask the participants about the CSFs have been identified in this study

ratifying the findings. Moreover, the potential negative impact for not satisfying each

factor can be also investigated by using case studies with fail implementations of BPR in

ERP projects. Finally, the last suggestion for future studies is to examine how inherent

the identified CSFs are, in each phase of the ERP implementation project dividing it into

pre-implementation, implementation and post-implementation phases using a quantitative

approach.

Word Count: 15 089

81

References

Al-Mashari, M., Al-Mudimig, A. and Zairi, M. (2003), “Enterprise resource planning: a

taxonomy of critical factors”, European Journal of Operational Research, Vol. 146 No.

2, pp. 352-64.

Al-Mashari, M. and Zairi, M. (1999). “BPR implementation process: an analysis of key

success factors and failure factors”, Business Process Management Journal, 5 (1).

Al-Mashari, M. and Zairi, M. (2000). “Supply-chain Re-engineering Using Enterprise

Resource Planning (ERP) Systems: An Analysis of a SAP R/3 Implementation Case”,

International Journal of Physical Distribution & Logistics Management, 30(3/4), pp.296-

313.

Attaran, M., (2004). “Exploring the relationship between information technology and

business process reengineering”, Information & Management, 41(5), 585–596

Bancroft, N. et al. (1998). “Implementing SAP R/3”, 2nd ed., Manning Publications.

Baxter, P and Jack, S. (2008) “Qualitative Case Study Methodology: Study design and

implementation for novice researchers”, The Qualitative Report, 13(4), 544-559.

Boudreau, M.C. & Robey, D. (1999). “Organizational transition to enterprise resource

planning systems: theoretical choices for process research”. In Proceedings of the 20th

international conference on Information Systems (ICIS '99). Association for Information

Systems, Atlanta, GA, USA, pp.291-299.

Braun, V. & Clarke, V. (2006). Using thematic analysis in psychology, Qualitative

Research in Psychology, 3, 77-101.

82

Chang, R.Y., (1994). “Improve processes, reengineer them, or both?” Training and

Development, 48(3), 54–58.

Chemical Marketing Reporter, (1996). “SAP Software Implementation Works Best with

Reengineering”, 250(8), 16.

Christofi, M. & Nunes, M.B. & Peng, G. C. (2009). “Identifying and improving deficient

business processes to prepare SMEs for implementation”. In: Proceedings of the UK

Academy for Information Systems (UKAIS) 14th

Annual Conference, St Anne’s College,

University of Oxford, 31 March – 01 April.

Davenport, T. (1993). “Process Innovation: Reengineering Work Through Information

Technology”, Harvard Business School Press, Boston

Davenport, T. H. (1998). "Putting the Enterprise into the Enterprise System," Harvard

Business Review, July-August, 1998, 121-131.

Davenport, T.H. and Short, J.E. (1998), “The new industrial engineering: information

technology and business process redesign”, IEEE Engineering Management Review,

26(3), 46-59.

Deep, A., Guttridge, P., Dani, S. and Burns, N. (2008). Investigating factors affecting

ERP selection in made-to-order SME sector, Journal of Manufacturing Technology

Management, 19(4), 430-446.

Doom, C., Milis, K., Poelmans, S., and Bloemen, E., (2010), "Critical success factors for

ERP implementations in Belgian SMEs", Journal of Enterprise Information Management,

23(3), 378 – 406

Esteves, J. & Pastor, J. (2000). "Towards the Unification of Critical Success Factors for

ERP implementations", 10th Annual BIT conference, Manchester, UK., November 2000.

83

Esteves J. & Pastor J. (2001). “Analysis of Critical Success Factors Relevance along SAP

Implementation Phases”, Americas Conference on Information Systems.

Esteves, J. & Pastor, J. & Casanovas, J. (2002), “Monitoring business process redesign in

ERP implementation projects” In: Proceedings of the AMCIS 2002, paper 125.

European Commission – Enterprise and Industry, (2011), “SBA Fact Sheet - Cyprus”.

EU.

Everdingen, Y.V., Hillegersberg, J.V. and Waarts, E.V. (2000). ERP adoption by

European midsize companies, Communications of the ACM, 43(4), 27-31.

Flick, U. (1998). An Introduction to Qualitative Research. Sage Publications: London.

Frey, H. and Oishi, M. (1995). How to Conduct Interview by Telephone and In Person.

London: Sage Publications.

Gable, G. and Stewart, G. (1999), “SAP R/3 implementation issues for small to medium

enterprises”, In: Proceedings of the 5th Americas Conference on Information Systems,

Milwaukee, WI, pp. 779-81.

Garner Group, (1999) “The ERP Vendors Market” Brisbane, October 1999.

Ghan, L.S. and Choi, F.C., (1997) “A conceptual and analytical framework for business

process reengineering” Int. J. Production Economics, 50, 211-223

Hammer, M. and Champy, J. (1993). Reengineering the corporation:a manifesto for

business evolution, Harper, Collins Publishers

Hayes, N. (2000). Doing psychological research: Gathering and Analysing Data. USA:

Open University Press.

84

Holland, C., Light, B. and Gibson, N. (1999). “A Critical Success Factors Model for

Enterprise Resource Planning Implementation”. In: Proceedings of the 7th

European

Conference on Information Systems, Copenhagen, Denmark. 1, pp.273-97

Jackson, N. (1997), “Business process re-engineering '96”, Management Services,

February, 34-36.

Jacobson, S., Shepherd, J., D’Aquila, M. and Carter, K. (2007) “The ERP Market Sizing

Report, 2006–2011”, Market Service Report, Boston: AMR Research Inc.

Jarrar Y. and Aspinwall, E. (1999). “Business Process Re-engineering: Learning from

Organizational Experience”, Total quality management, 10(2), pp. 173-186.

Jarrar, Y.F., Al-Mudimigh, A. and Zairi, M. (2000). “ERP implementation critical

success factors - the role and impact of business process management”. In: Proceedings

of IEEE International Conference on Management of Innovation and Technology

(ICMIT), Singapore, 12-15 November 2000.

Jarrar Y., and Aspinwall, E. (1999). “Business Process Re-engineering: Learning from

Organizational Experience”, Total quality management, 10(2), pp. 173-186.

Klaus, H., Rosemann, M. and Gable, G. (2000). "What is ERP?". Information Systems

Frontiers, 2 (2), 141-162.

Koch, C. (2001a), “BPR and ERP: realizing a vision of process with IT”, Business

Process Management Journal, 7(3), 258-65.

Kumar, K. and Hillegersberg, J. (2000). ERP experiences and evolution,

Communications of the ACM, 43(4), 23-26.

85

Loh, T.C. and Koh, S.C.L. (2004). “Critical elements for a successful enterprise resource

planning implementation in small-and medium-sized enterprises”. International Journal

of Production Research, 42(17), 3433-3455.

Markus, M. and Tanis, C. (2000). "The enterprise systems experience-from adoption to

success". Framing the domains of IT research: Glimpsing the future through the past,

173, 173-207.

Martin, I. and Cheung, Y., (2005),"Business process re-engineering pays after enterprise

resource planning", Business Process Management Journal, 11(2), 185 - 197

Miers, D. (2006). “The Keys to BPM project success” BPTrends, Einx Consulting Ltd,

January 2006

Ministry of commerce industry and tourism. (2012), Small medium sized enterprises

[Online]. Cyprus: Republic of Cyprus.

http://www.mcit.gov.cy/mcit/mcit.nsf/dmlsme_en/dmlsme_en?OpenDocument

[Accessed 23 June 2012]

Motwani, J., Kumar, A., Jiang, J. and Youssef, M., (1998), "Business process

reengineering: A theoretical framework and an integrated model", International Journal

of Operations & Production Management, 18(9), 964 – 977

Nah, F.F., Lau, J.L. and Kuang, J. (2001). “Critical factors for successful implementation

of enterprise systems”, Business Process Management Journal, 7(3), 285-296.

Nah, F.F.H. and Delgado, S. (2006), “Critical success factors for enterprise resource

planning implementation and upgrade”, Journal of Computer Information Systems, 46(5),

99-113.

86

O’Leary, D.E. (2000), Enterprise Resource Planning Systems, Cambridge University

Press, Cambridge

O'Neill, P. and Sohal, A.S. (1999). Business process reengineering: a review of recent

literature, Technovation, 19, 571-581.

Phipps, D. (2000). “IT Strategies for E-Business That Work”. Presented at the

Proceedings of Symposium Itexpo – Gartner Group, Orlando, Florida

Punch, F. K. (2005). Introduction to Social Research: Quantitative and Qualitative

Approaches. Sage Publications: London.

Rosario, J. G., (2000). “On the leading edge: critical success factors in ERP

implementation projects”. Business World, 17 May, 15–29.

Ross, J.W., Weill, P. and Robertson, D. (2006), Enterprise Architecture as Strategy,

Harvard Business School Press, Boston, MA, 1 August.

Rudestam, K. E. and Newton, R. R. (1992) Surviving your dissertation, Sage

Saunders, M., Lewis, P. and Thornhill, A. (2003). Research methods for business

students. 3rd

Edtion, Pearson Education Limited, Harlow.

Schlichter, B. R. and Kraemmergaard, P. (2010),"A comprehensive literature review of

the ERP research field over a decade", Journal of Enterprise Information Management,

23(4), 486 - 520

Schniederjans, J.M. and Kim, G.C., (2003),"Implementing enterprise resource planning

systems with total quality control and business process reengineering: Survey results",

International Journal of Operations & Production Management, 23(4), 418 – 429

87

Shtub, A. (1999), “Enterprise Resource Planning (ERP): The Dynamics of Operations

Mangement”, Kluwer Academic Publishers, Boston.

Silverman, D. (2001). Interpreting Qualitative Data: Methods for Analysing Talk, Text

and Interaction. 2nd ed. Sage Publications: London.

Siriginidi, S.R., (2000), “Enterprise resource planning in reengineering business”,

Business Process Management Journal, 6 (5), 376 – 391

Snider, B., Silveira, G., and Balakrishnan., J, (2009), “ERP implementation at SMEs:

analysis of five Canadian cases”, International Journal of Operations and Production

Management, 29(1), pp. 4-29.

Soh, C., Kien, S.S. and Tay-Yap, J. (2000), “Cultural fits and misfits: is ERP a universal

solution?”, Communications of the ACM, Vol. 43 No. 4, pp. 47-51

Stefanou, C. J., (1999), “Supply chain management (SCM) and organizational key factors

for successful implementation of enterprise resource planning (ERP) system”. In:

Proceedings of the Americas Conference on Information Systems (AMCIS), pp. 800–

818.

Stemberger, M.I. and Kovacic, A., (2008), “The Role of Business Process Modelling in

ERP Implementation Projects”. Computer Modeling and Simulation, 2008. UKSIM

2008. Tenth International Conference. 1-3 April 2008, 260-265.

Subramoniam, S., Tounsi, M and Krishnankutty, K.V. (2009). “The role of BPR in the

implementation of ERP systems”, Business Process Management Journal, 15(5),

Cambridge

88

Talwar, R., (1993). Business re-engineering—A strategy-driven approach. Long Range

Planning, 26(6), 22–40

Tsai, W., Chen, S., Hwang, E.T.Y. and Hsu, J., (2010),” A Study of the Impact of

Business Process on the ERP System Effectiveness”, International Journal of Business

and Management Vol. 5, No. 9; pp. 26-37.

Towers, S. (1994), Business Process Re-engineering: a Practical Handbook for

Executives, Stanley Thomas Ltd, Cheltenham.

Tsamantanis, V. and Kogetsidis, H., (2006), "Implementation of enterprise resource

planning systems in the Cypriot brewing industry", British Food Journal, Vol. 108 Iss: 2

pp. 118 – 126

Umble, J., Haft, R. and Umble, M. (2003). Enterprise resource planning: Implementation

procedures and critical success factors, European Journal of Operational Research,

146(2), 16 April 2003, 241-257

Valiris, G. and Glykas, M. (1999) “Critical Review of Existing BPR Methodologies”,

Business Process Management journal, 5(1), 65-86.

Wallace, T.F. (2001), “Enterprise Resource Planning: Making It Happen, The

Implementers” Guide to Success with ERP, John Wiley & Sons, New York.

Yin, R. K. (2003). Case study research: design and methods, 3rd

edtion. SAGE

Publications, California.

Yusuf, Y., Gunasekaranb, A. and Abthorpe, M.S. (2004). “Enterprise information

systems project implementation: A case study of ERP in Rolls-Royce”, International

Journal of Production Economics, 87, 251-266.

89

Zabjek, D., Kovacic A. and Stemberger, I.M. (2009). “The influence of business process

management and some other CSFs on successful ERP implementation”, Business Process

Management Journal, 15(4), 588 - 608

Zhang, L., Lee, M., Zhang, Z. and Banerjee, P. (2003), “Critical success factors of

enterprise resource planning systems implementation success in China”, Proceedings of

36th Hawaii International Conference on System Sciences, Big Island, HI, 10.

90

Appendix A:

A1. Interview Script

Section 1: General questions

1.1. What is your position in the company and what responsibilities do you have?

Talk about your daily routine

1.2. From your point of view, what were the most important motivations to

implement an ERP system?

Follow-up question:

1.2.1 How important was the need to change the previous business process in

order to be more efficient and why?

1.3. What aspects were thoroughly considered before the ERP project and were

followed-up or reconsidered during the project?

1.4. Have the business process you work in changed significantly? Why/ why not?

Explain.

Section 2: BPR critical successful factors (CSFs) in ERP context

A. Change Management Dimension

2.1. What activities have been conducted in order to change your organizational

structure and culture and thus make the company and yourself in general more

ready for the BPR?

91

Trigger questions:

2.1.1. When organizations decide to perform BPR (ERP) employees of the

company must accept the new business process as the people who are going to

perform these processes. What have you done to increase the level of acceptance

by the employees for the new business processes?

2.1.2. What are the critical factors that you need to consider in order to make it

happen successfully? What are the consequences for not meeting these

factors?

2.1.3. Did your company develop a new reward and recognition system in

response to the BPR changes? What would have been the consequences if you

had not given any reward?

Follow-up questions:

2.1.4. If we divide the ERP implementation into pre, implementation and post-

implementation which phase has more BPR activities inside? When they answer

you ask: What happened first? BPR or ERP (pre or implementation or post)? Why

did you follow that sequence?

2.1.5. What did you do to identify the risks related to BPR and ERP and how did

you manage them?

2.1.6. What was the role of the customer during the change? Was there a focus on

customer needs?

92

B. Process Dimension (Departmental staff and IT - not for Top managers)

2.2 What procedures have been followed inside the company in order to achieve a

successful BPR?

2.3 What changes happened in the business processes of your department-section?

What is your opinion about them now?

Trigger questions:

2.2.1. How did you identify the inefficient business processes and decide which of

them must be changed?

2.2.2. To what extent the existing business processes and the business processes

supported by ERP system were matched? Examples and percentage

2.2.3. How was the gap between that required and supported functionality

between has to do with the business processes closed? Was that approach

successful?

2.2.4. What was the role of the external consultants in that process? How did they

contribute? What are the consequences if that support was missing?

93

C. Product Dimension (IT – top and vendor)

2.3 How has the ERP system affected the BPR?

Trigger questions:

2.3.1. What actually happened? Did you design your business processes based on

the ERP functions or did you customize the ERP system to support your business

processes? Exlpain and highlight the factors lead to the success. What are the

consequences of not meeting these factors?

2.3.2. How flexible was that change and what was the role of the external

consultants?

2.3.3. What was the role of the current IT infrastructure in BPR? What was the

impact of your IT infrastructure and the IT department? If IT was not in place to

enable BPR what would have been the consequences?

Follow-up questions:

2.3.4. What tools and techniques were used to monitor, evaluate the project

progress? What are the consequences of inefficient monitoring and evaluation?

2.3.5 How many ERP process have been changed – Did you changed many

processes in order to support the business processes of the company?

Why or why not? Is that a critical factor that affects the success of BPR?

94

D. People Dimension

2.4 How have the people within and outside the company affected the BPR related to

ERP project? What are factors lead to the success?

Trigger questions:

2.4.1. What was the role of top management when the BPR activities were being

conducted? What are the consequences if top management support was missing?

2.4.2. How do you describe the relationship and communication between top

managers and project team?

2.4.3. How do you describe the relationship and communication your supplier

during the implementation and after the implementation? What are the

consequences of a bad – insufficient communication during a project?

2.4.4. How was the team formation affected by the situation of the business

processes in the company? Was that team created specifically for that project?

Follow-up:

2.4.4 How do you think the size of the company can lead to any factors that affect

the success of BPR activities?

95

Appendix A2: Initial Coding Scheme

Code Definition

1. Integration between systems and departments

2. Streamline business processes

3. Cost reduction

4. Reduce response time

5. Increase staff productivity and performance

6. Improve management reporting – decision

making

7. Facilitate business and ERP project

8. Improve operational efficiency

9. Accurate information across departments (stock,

job costing)

10. Clear vision and scope – explicit BPR plan

11. Define the inefficient business processes which

must change

12. Adequate staff involvement based on processes

(suggestions and feedback from them)

13. Competent reward and motivation systems

14. Sufficient stimulation of the staff receptiveness

15. Create a new effective culture

16. Sufficient customer focus

17. Appropriate allocation of roles and

responsibilities (key users)

18. Continuous Monitoring and evaluation

19. Adequate integration between BP and jobs in

the organization

20. Efficient Business Process seminars-workshops

across divisions

21. Proper implementation sequence between BPR

and ERP

22. Proper implementation strategy

23. Suitable ERP package selection

24. Suitable ERP Implementation vendor selection

25. Effective communication (continuous and

comprehensive) between stakeholders inside the

company

26. Effective communication between the

stakeholders of the company and stakeholders

outside the company.

27. Project team formation

28. Efficient supervision by external Project

Manager (third party)

29. Education and sufficient training

30. Efficient Risk management

31. Top management support and commitment

32. Effective IT infrastructure

33. Adequate ERP customization

34. Adequate information systems integration

35. Sponsorship and efficient BPR – ERP fund

36. Continuous and sufficient support by the vendor

consultants (post implementation mostly)

37. Low integration between BP and ERP package

(modules)

Texts describe the need of integration between systems and departments

Texts describe the need of streamlining the business processes within the

company

Texts describe the need of cost reduction

Texts describe the need of time response reduction

Texts describe the need to increase the performance of the staff

Texts describe the need to improve the management reporting and decision

making

Texts describe the need to make the ERP project become successful

Texts describe the need to improve the operational efficiency

Texts describe the need of accuracy of data across departments

Texts about the vision and scope of the project

Texts about defining the business processes that must change

Texts about involvement of staff to BPR project

Texts about staff involvement based on business processes they work in

Texts describe the ways of motivating and rewarding staff

Texts about stimulation of receptiveness of staff

Texts about the new culture of the company

Texts about the customer focus given during the project

Texts about the allocation of roles and responsibilities

Texts about the evaluation and monitoring during the

Texts about integration of jobs and BP for the best allocation of roles

Texts about the workshops and seminars took place across divisions

Texts about implementation sequence (BPR and ERP)

Texts about the implementation strategy

Texts about ERP package in general (modules and compatibility)

Texts about the ERP implementation vendor selection

Texts about the communication of people inside the company

Texts about the communication of stakeholders inside and people outside

the company

Texts describe the team formation of the project

Texts about the efficient supervision done by external Project manager

Texts about training and education given to staff and managers

Texts about risk management practises used from the managers

Texts about top management support given throughout the project

lifecycle

Texts about the effective use of IT infrastructure within the company

Texts about customization done on ERP system to follow BP

Texts about integration of BP with the rest IS within the company

Texts about BPR-ERP fund and sponsorship used.

Texts about support given by the vendor consultants

Texts referred to low integration between ERP and BP

96

38. Low integration of BP between departments

39. Staff reluctance and resistance to change

40. Incorrect data to the system – low data quality

41. Managers get incorrect reporting – information

42. Inefficient decision making

43. Project delays

44. Reengineering plan and strategy is ill-defined

45. Insufficient/bad communication between staff

and vendor’s consultants

46. Low value-added to BP

47. Additional effort from employees

48. Conflicts between BP

49. Wrong selection of BP to be reengineered

50. Inadequate analysis and BP assessment

51. Higher cost than expected

52. Wrong team formation

53. Hire unnecessary staff (to support the new BP) /

loss qualified staff (seemed unnecessary for the

new BP)

54. Low level of customer services – customer

dissatisfaction

55. Inefficient support by vendors consultants

56. Inadequate staff involvement

57. Inappropriate monitoring and evaluation

58. Cancelation of the project

59. Inefficient training and education – low skilled

staff

60. The selected ERP system cannot support the

new philosophy and culture of the company

61. Gap between functionality supported and

required functionality

62. Project fund and resources are insufficient

63. Inappropriate use of IT as enabler for BPR

64. Strong top management leadership

65. Continuous and sufficient support by people

inside the company – key users (post mostly)

Texts referred to low integration of BP between departments

Texts referred to the resistance of employees o change their working

routine and environment

Texts referred to incorrect data of the system

Texts referred to wrong reports generated by the system

Texts referred to insufficient decision making from incorrect reporting

Texts referred to project delays

Texts referred to ill-defined plan and strategy for BPR

Texts referred to bad communication within a company

Texts referred to low value added to BP after BPR

Texts referred to additional efforts from staff

Texts referred to conflicts and undefined crosscutting between BP

Texts referred to the wrong BP decided to be reengineered

Texts referred to inadequate BP analysis and assessment

Texts referred to costs that were not expected

Texts referred to wrong project team formation

Texts referred to new staff hired to support the new BP or staff fired as

unnecessary to support the new BP

Texts referred to customer dissatisfaction

Texts referred to the inefficient support given by external consultants

Texts referred to the inadequate staff involvement during the project

Texts referred to the inappropriate monitoring and evaluation of the project

progress

Texts referred to the case of cancelation of the project

Texts referred to inefficient training and education

Texts referred to gap in philosophy and culture of organization and

philosophy needed by ERP system

Texts referred to the gap between system functionality and required

functionality

Texts referred to insufficient project fund

Texts referred to inappropriate use of IT as enabler for BPR

Texts about strong leadership that was given by top managers during the

whole project.

Texts about support given by key users inside the company to the other

staff in order to help them

97

Appendix A3: Final Coding Scheme with Themes

Theme ID Code of CSF Definition Link with Code (Consequence)

Motivations to

BPR in ERP

project

Change

Management

CSFs

Process CSFs

M1

M2

M3

M4

M5

M6

M7

M8

M9

CM1

CM2

CM3

CM4

CM5

PC1

PC2

PC3

PC4

PC5

PC6

Facilitate business and ERP project

Improve operational efficiency

Accurate information across departments (stock, job

costing)

Integration between systems and departments

Streamline business processes

Cost reduction

Reduce response time

Increase staff productivity and performance

Improve management reporting – decision making

Competent reward and motivation systems

Sufficient stimulation of staff receptiveness

Create a new effective culture

Sufficient customer focus

Clear vision and scope – explicit BPR plan

Define the inefficient business processes which must

change

Adequate staff involvement based on processes

(suggestions and feedback from them)

Appropriate allocation of roles and responsibilities

(key users)

Continuous Monitoring and evaluation

Adequate integration between BP and jobs

Efficient Business Process seminars-workshops

across divisions

Texts describe the need to make the ERP project become

successful

Texts describe the need to improve the operational efficiency

Texts describe the need of accuracy of data across departments

Texts describe the need of integration between systems and

departments

Texts describe the need of streamlining the business processes

within the company

Texts describe the need of cost reduction

Texts describe the need of time response reduction

Texts describe the need to increase the performance of the staff

Texts describe the need to improve the management reporting

and decision making

Texts describe the way EKA tried to motivate and reward staff

Texts about stimulation of receptiveness of staff

Texts about the new culture of the company

Texts about the customer focus given during the project

Texts about the vision and scope of the project

Texts about defining the business processes that must change

Texts about staff involvement based on business processes they

work in

Texts about the allocation of roles and responsibilities

Texts about the evaluation and monitoring during the

Texts about integration of jobs and BP for the best allocation of

roles in the organization

Texts about the workshops took place across divisions

C3; C19; C25

C3; C7; C25

C3; C14; C17; C18

C10; C15; C18; C20

C7; C12; C18; C20;

C22

C2; C8; C10;

C20;C21

C2; C10; C11;C20

C8; C13; C14; C16;

C19; C22; C25

C7; C18; C20

C2; C8; C9; C14;

C25

C3; C9; C11; C16

98

Product CSFs

People CSFs

Consequences

PC7

PC8

PD1

PD2

PD3

PD4

PD5

PL1

PL2

PL3

PL4

PL5

PL6

PL7

PL8

PL9

PL10

PL11

C1

C2

C3

Proper implementation sequence between BPR and

ERP

Proper implementation strategy (step by step)

Suitable ERP package selection

Suitable ERP Implementation vendor selection

Effective IT infrastructure

Adequate ERP customization

Adequate information systems integration

Effective communication (continuous and

comprehensive) between stakeholders inside the

company

Effective communication with the stakeholders who

are outside the company

Appropriate project team formation

Efficient supervision by external Project Manager

(third party)

Sufficient education and training

Efficient Risk management

Sufficient Top management support and commitment

(especially at the pre-implementation)

Efficient sponsorship and project fund

Strong top management leadership

Continuous and sufficient support by people inside

the company – key users (post mostly)

Continuous and sufficient support by the vendor

consultants (post implementation mostly)

Low integration between BP and ERP package

(modules)

Low integration of BP between departments

Staff reluctance and resistance to change

Texts about implementation sequence (BPR and ERP)

Texts about the implementation strategy (Smooth and gradual

change to the new business processes – pace of change)

Texts about ERP package in general (modules and

compatibility)

Texts about the ERP implementation vendor selection

Texts about the effective use of IT infrastructure within the

company

Texts about customization done on ERP system to follow BP

Texts about integration of BP with the rest IS within the

company

Texts about the communication of people inside the company

Texts about the communication of stakeholders inside and

people outside the company (staff/managers with vendors staff)

Texts describe the team formation of the project

Texts about the supervision done by the external Project

manager

Texts about training and education given to staff and managers

Texts about risk management practises used from the managers

Texts about top management support given throughout the

project lifecycle

Texts about BPR-ERP fund and sponsorship used.

Texts about strong leadership that was given by top managers

during the whole project.

Texts about support given by key users inside the company to

the other staff in order to help them

Texts about support given by the vendor consultants

Texts referred to low integration between ERP and BP

Texts referred to low integration of BP between departments

Texts referred to the resistance of employees o change their

working routine and environment

C1;C12; C20; C21;

C23

C1; C2; C7; C8;

C20;C21

C1; C2; C4; C5; C6;

C10; C17; C21; C22

C7; C12; C19; C24

C12; C18; C22; C23

C1; C2; C8; C21

C2; C5; C6;C8; C15;

C21

C3; C7; C8; C11

C7; C8; C11; C16;

C24

C7; C14; C16

C7; C26

C3; C8; C16

C3; C7; C12

C7; C12; C22; C10;

C11

C13; C27

C3; C7; C22

C3; C8; C16

C3; C16 C19

99

C4

C5

C6

C7

C8

C9

C10

C11

C12

C13

C14

C15

C16

C17

C18

C19

C20

C21

C22

C23

C24

C25

C26

C27

Incorrect data to the system – low data quality

Managers get incorrect reporting – information

Inefficient decision making

Project delays

Additional effort from employees

Conflicts between BP

Wrong selection of BP to be reengineered

Inadequate analysis and BP assessment

Higher cost than expected

Wrong team formation

Hire unnecessary staff (to support the new BP) / loss

qualified staff (seemed unnecessary for the new BP)

Low level of customer services – customer

dissatisfaction

Inefficient training and education – low skilled staff

The selected ERP system cannot support the new

philosophy and culture of the company

Reengineering plan and strategy is ill-defined

Insufficient/bad communication between staff and

vendor’s consultants

Low value-added to BP

Gap between functionality supported and required

functionality

Project fund and resources are insufficient

Inappropriate use of IT as enabler for BPR

Inefficient support by vendors consultants

Inadequate staff involvement

Inappropriate monitoring and evaluation

Cancelation of the project

Texts referred to incorrect data of the system

Texts referred to wrong reports generated by the system

Texts referred to insufficient decision making from incorrect

reporting

Texts referred to project delays

Texts referred to additional efforts from staff

Texts referred to conflicts and undefined crosscutting between

BP

Texts referred to the wrong BP decided to be reengineered

Texts referred to inadequate BP analysis and assessment

Texts referred to costs that were not expected

Texts referred to wrong project team formation

Texts referred to new staff hired to support the new BP or staff

fired as unnecessary to support the new BP

Texts referred to customer dissatisfaction

Texts referred to inefficient training and education

Texts referred to gap in philosophy and culture of organization

and philosophy needed by ERP system

Texts referred to ill-defined plan and strategy for BPR

Texts referred to bad communication within a company

Texts referred to low value added to BP after BPR

Texts referred to the gap between system functionality and

required functionality

Texts referred to insufficient project fund

Texts referred to inappropriate use of IT as enabler for BPR

Texts referred to the inefficient support given by external

consultants

Texts referred to the inadequate staff involvement during the

project

Texts referred to the inappropriate monitoring and evaluation of

the project progress

Texts referred to the case of cancelation of the project

100

Appendix B: Ethics and other student forms

UUnniivveerrssiittyy RReesseeaarrcchh EEtthhiiccss AApppplliiccaattiioonn FFoorrmm

for Undergraduate & Postgraduate-Taught Students

This form has been approved by the University Research Ethics Committee (UREC) Complete this form if you are an undergraduate or a postgraduate-taught student who plans to undertake a research project which requires ethics approval via the University Ethics Review Procedure. Your Supervisor decides if ethics approval is required and, if required, which ethics review procedure (e.g. University, NHS, Alternative) applies. If the University’s procedure applies, your Supervisor decides if your proposed project should be classed as ‘low risk’ or potentially ‘high risk’. *PLEASE NOTE THAT YOUR DEPARTMENT MAY USE A VARIATION OF THIS FORM: PLEASE CHECK WITH THE ETHICS ADMINISTRATOR IN YOUR DEPARTMENT*

This form should be accompanied, where appropriate, by all Information Sheets / Covering Letters / Written Scripts which you propose to use to inform the prospective participants about the proposed research, and/or by a Consent Form where you need to use one.

Further guidance on how to apply is at: www.sheffield.ac.uk/ris/other/gov-ethics/ethicspolicy/approval-procedure/review-procedure Guidance on the possible routes for obtaining ethics approval (i.e. on the University Ethics Review Procedure, the NHS procedure and the Social Care Research Ethics Committee,

and the Alternative procedure) is at: www.sheffield.ac.uk/ris/other/gov-ethics/ethicspolicy/approval-procedure/ethics-approval Once you have completed this research ethics application form in full, and other documents where appropriate, check that your name, the title of your research project and the date is contained in the footer of each page. If your Supervisor has classed the project as ‘low risk’:

Email this form, together with other documents where applicable, to your Supervisor; and

Sign and date Annex 1 of this form and provide a paper copy to your Supervisor.

Important Note for Supervisors:

FFoolllloowwiinngg tthhee eetthhiiccss rreevviieeww tthhee SSuuppeerrvviissoorr mmuusstt pprroovviiddee tthhee aaccaaddeemmiicc ddeeppaarrttmmeenntt’’ss EEtthhiiccss

AAddmmiinniissttrraattoorr wwiitthh aa ccooppyy ooff tthhee ‘‘llooww rriisskk’’ rreesseeaarrcchh eetthhiiccss aapppplliiccaattiioonn tthhaatt ss//hhee rreevviieewweedd aanndd

aa ccoommpplleetteedd EEtthhiiccss RReevviieewweerr’’ss CCoommmmeennttss FFoorrmm iinnddiiccaattiinngg tthhee eetthhiiccss ddeecciissiioonn tthhaatt ss//hhee ttooookk

iinn rreellaattiioonn ttoo iitt.. TThhee EEtthhiiccss RReevviieewweerr’’ss CCoommmmeennttss FFoorrmm ccaann bbee ddoowwnnllooaaddeedd hheerree::

wwwwww..sshheeffffiieelldd..aacc..uukk//rriiss//ootthheerr//ggoovv--eetthhiiccss//eetthhiiccssppoolliiccyy//ffuurrtthheerr--

gguuiiddaannccee//uunniivveerrssiittyypprroocceedduurree22//rreevviieewweerrsscc TThhee EEtthhiiccss AAddmmiinniissttrraattoorr rreesseerrvveess tthhee rriigghhtt ttoo

ccoonnssuulltt tthhee CChhaaiirr ooff tthhee aaccaaddeemmiicc ddeeppaarrttmmeenntt’’ss EEtthhiiccss RReevviieeww PPaanneell ((oorr eeqquuiivvaalleenntt)) ooff ss//hhee

hhaass ccoonncceerrnnss tthhaatt pprroojjeeccttss ccllaasssseedd aass llooww rriisskk sshhoouulldd iinn ffaacctt hhaavvee bbeeeenn ccllaasssseedd aass ppootteennttiiaallllyy

hhiigghh rriisskk..

If your Supervisor has classed the project as potentially ‘high risk’:

Email this form, together with other documents where applicable, to your department’s Ethics Administrator; and

Ask your Supervisor to sign and date Annex 2 of this form and provide a paper copy of it to your department’s Ethics Administrator.

101

UUnniivveerrssiittyy RReesseeaarrcchh EEtthhiiccss AApppplliiccaattiioonn FFoorrmm for Undergraduate & Postgraduate-Taught Students

I confirm that I have read the current version of the University of Sheffield

‘Ethics Policy Governing Research Involving Human Participants, Personal

Data and Human Tissue’, as shown on the University’s research ethics website

at: www.sheffield.ac.uk/ris/other/gov-ethics/ethicspolicy

A1. Title of research project: “What are the Critical Successful Factors (CSFs) for

Business Process Reengineering (BPR) during the Enterprise Resource Planning (ERP)

implementation life-cycle”

A2. Name of Student: Georgios Michail

Department: Information School Email: [email protected] Tel.: 07936 275 123

Name of Supervisor: Dr. Alex Peng A3. Proposed Project Duration: 4 months

Start date: May 2012 End date: September 2012

A4. Mark ‘X’ in one or more of the following boxes if your research:

involves adults with mental incapacity or mental illness

involves prisoners or others in custodial care (e.g. young offenders)

involves children or young people aged under 18 years

involves using samples of human biological material collected before for another purpose

involves taking new samples of human biological material (e.g. blood, tissue) *

involves testing a medicinal product *

involves taking new samples of human biological material (e.g. blood, tissue) *

involves additional radiation above that required for clinical care *

involves investigating a medical device *

* If you have marked boxes marked * then you also need to obtain confirmation that

appropriate University insurance is in place. To do this email [email protected] and request a copy of the ‘Clinical Trial Insurance Application Form’.

It is recommended that you familiarise yourself with the University’s Ethics Policy Governing Research Involving Human Participants, Personal Data and Human Tissue before completing the following questions. Please note that if you provide sufficient information about the research (what you intend to do, how it will be carried out and how you intend to minimise any risks), this will help the ethics reviewers to make an informed judgement quickly without having to ask for further details.

X

102

A5. Briefly summarise:

i. The project’s aims and objectives:

Aim: The study aims to investigate the critical successful factors (CSFs) of business

process reengineering (BPR) related to the stages of an enterprise resource planning

(ERP) implementation projects. Objectives:

e. A general literature review on BPR and its relationship with ERP implementation

project will be carried out

f. Identify a set of the general areas-categories of CSFs for BPR in ERP context

g. Identify more specifically the CSFs within these general areas-categories

h. Identify the consequences for the organization for not meeting and satisfy the CSFs

that have been found

ii. The project’s methodology:

A variety of methods are going to be used following the inductive research

approach. The main aspects related to BPR and ERP of the most relevant literature

and the most influential authors will be carried out concluding to a general

literature review. The single case study strategy will be used. the collection of data

and information will be achieved by using the qualitative research method of in

depth face to face interviews. After the collection of the qualitative data the

approach of inductive thematic analysis will be performed

A6. What is the potential for physical and/or psychological harm / distress to participants?

There no physical or psychological harm/distress to the participants. A7. Does your research raise any issues of personal safety for you or other

researchers involved in the project? (especially if taking place outside working hours or off University premises)

NO

If yes, explain how these issues will be managed.

103

A8. How will the potential participants in the project be:

i. Identified? Searching in the Internet using the step by step approach. Vendors to Companies who implemented ERP and contact that company

ii. Approached? An initial contact via telephone will be done. After that a meeting with them will be arranged and discussed the potential of participating to the project.

iii. Recruited? By explaining in detail the research aim and objectives, the potential benefits for them And their company and explaining to them any potential risks and disadvantages

A9. Will informed consent be obtained from the participants?

YES X NO

If informed consent or consent is NOT to be obtained please explain why.

Further guidance is at: www.sheffield.ac.uk/ris/other/gov-ethics/ethicspolicy/policy-notes/consent

A9.1. This question is only applicable if you are planning to obtain informed consent:

How do you plan to obtain informed consent? (i.e. the proposed process?): I will give to them an information sheet explaining in full details the whole process of

the research study and any potential benefits, risks or disadvantages for them and their company. Then if the agree they will sign the consent form.

104

A10. What measures will be put in place to ensure confidentiality of personal data,

where appropriate? The personal data of the participants will be kept strictly confidential by using the

University departmental regulations. Of course a consent form will be signed by the researcher ensuring the participants and their personal information.

A11. Will financial / in kind payments (other than reasonable expenses and

compensation for time) be offered to participants? (Indicate how much and on what basis this has been decided)

NO expenses and compensation. A12. Will the research involve the production of recorded media such as audio

and/or video recordings?

YES X NO

A12.1. This question is only applicable if you are planning to produce recorded media:

How will you ensure that there is a clear agreement with participants as to how these recorded media may be stored, used and (if appropriate) destroyed? Firstly a transcription of the interviews will be given to them asking them to confirm what is written. After the analysis of the data the result will be published to them as is. For any additional research for other purposes an extra consent form should be asked and signed by them.

Guidance on a range of ethical issues, including safety and well-being, consent and anonymity, confidentiality and data protection’ are available at: www.sheffield.ac.uk/ris/other/gov-ethics/ethicspolicy/policy-notes

105

For Undergraduate & Postgraduate-Taught Students

Student Declaration

((TThhee ssttuuddeenntt ccoommpplleetteess AAnnnneexx 11 iiff tthhee SSuuppeerrvviissoorr hhaass ccllaasssseedd tthhee

ssttuuddeenntt’’ss pprrooppoosseedd rreesseeaarrcchh pprroojjeecctt aass ‘‘llooww rriisskk’’))

TThhee SSuuppeerrvviissoorr nneeeeddss ttoo rreecceeiivvee aann eelleeccttrroonniicc ccooppyy ooff tthhee ffoorrmm,, aanndd ootthheerr ddooccuummeennttss

wwhheerree aapppprroopprriiaattee,, pplluuss aa ssiiggnneedd,, ddaatteedd ppaappeerr ccooppyy ooff tthhiiss AAnnnneexx 11 ‘‘tthhee SSttuuddeenntt

DDeeccllaarraattiioonn’’..

Full Research Project Title:

“What are the Critical Successful Factors (CSFs) for Business Process

Reengineering (BPR) during the Enterprise Resource Planning (ERP)

implementation life-cycle in SMEs? A case of a Cypriot company”.

In signing this Student Declaration I am confirming that: The research ethics application form for the above-named project is accurate to the best

of my knowledge and belief.

The above-named project will abide by the University’s ‘Good Research Practice Standards’: www.sheffield.ac.uk/ris/other/gov-ethics/good

The above-named project will abide by the University’s ‘Ethics Policy Governing Research Involving Human Participants, Personal Data and Human Tissue’: www.sheffield.ac.uk/ris/other/gov-ethics/ethicspolicy

Subject to the above-named project being ethically approved I undertake to adhere to any ethics conditions that may be set.

I will inform my Supervisor of significant changes to the above-named project that have ethical consequences.

I will inform my Supervisor if prospective participants make a complaint about the above-named project.

I understand that personal data about me as a researcher on the research ethics application form will be held by those involved in the ethics review process (e.g. my Supervisor and the Ethics Administrator) and that this will be managed according to Data Protection Act principles.

I understand that this project cannot be submitted for ethics approval in more than one department, and that if I wish to appeal against the decision made, this must be done through the original department.

106

Name of Supervisor: Alex GC Peng Name of student: Georgios Michail Signature of student: Georgios Michail Date: 18/05/2012

107

For Undergraduate & Postgraduate-Taught Students

Supervisor Declaration

((TThhee SSuuppeerrvviissoorr ccoommpplleetteess AAnnnneexx 22 iiff ss//hhee hhaass ccllaasssseedd tthhee ssttuuddeenntt’’ss

pprrooppoosseedd rreesseeaarrcchh pprroojjeecctt aass ppootteennttiiaallllyy ‘‘hhiigghh rriisskk’’))

TThhee EEtthhiiccss AAddmmiinniissttrraattoorr nneeeeddss ttoo rreecceeiivvee aann eelleeccttrroonniicc ccooppyy ooff tthhee ffoorrmm,, aanndd ootthheerr

ddooccuummeennttss wwhheerree aapppprroopprriiaattee,, pplluuss aa ssiiggnneedd,, ddaatteedd ppaappeerr ccooppyy ooff tthhiiss AAnnnneexx 22 ‘‘tthhee

SSuuppeerrvviissoorr DDeeccllaarraattiioonn’’..

Full Research Project Title: insert name

In signing this Supervisor Declaration I am confirming that:

The research ethics application form for the above-named project is accurate to the best of my knowledge and belief.

The above-named project will abide by the University’s ‘Good Research Practice Standards’: www.sheffield.ac.uk/ris/other/gov-ethics/good

The above-named project will abide by the University’s ‘Ethics Policy for Research Involving Human Participants, Data and Tissue’: www.sheffield.ac.uk/ris/other/gov-ethics/ethicspolicy

Subject to the above-named project being ethically approved I will undertake to ensure that the student adheres to any ethics conditions that may be set.

The student or the Supervisor will undertake to inform the Ethics Administrator of significant changes to the above-named project that have ethical consequences.

The student or the Supervisor will undertake to inform the Ethics Administrator if prospective participants make a complaint about the above-named project.

I understand that personal data about the student and/or myself on the research ethics application form will be held by those involved in the ethics review process (e.g. the Ethics Administrator and/or reviewers) and that this will be managed according to Data Protection Act principles.

I understand that this project cannot be submitted for ethics approval in more than one department, and that if I and/or the student wish to appeal against the decision made, this must be done through the original department.

Name of Supervisor: insert name

Name of student: insert name

SSiiggnnaattuurree ooff SSuuppeerrvviissoorr:: ssiiggnn hheerree

Date: insert date

108

Information Sheet

1. Research Project Title:

“What are the Critical Successful Factors (CSFs) of Business Process Reengineering (BPR)

in the context of Enterprise Resource Planning (ERP) project in SMEs?”

2. Invitation paragraph

You are being invited to take part in a research project. Before you decide it is important for

you to understand why the research is being done and what it will involve. Please take time to

read the following information carefully and discuss it with others if you wish. Ask us if there

is anything that is not clear or if you would like more information. Take time to decide

whether or not you wish to take part. Thank you for reading this.

3. What is the project’s purpose?

The study aims to investigate the critical successful factors (CSFs) of business process

reengineering (BPR) related to the stages of an enterprise resource planning (ERP)

implementation projects. In order to accomplish the above aim the following research

objectives should be established:

i. A general literature review on BPR and its relationship with ERP implementation

project will be carried out

j. Identify a set of the general areas-categories of CSFs for BPR in ERP context

k. Identify more specifically the CSFs within these general areas-categories

l. Identify the consequences for the organization for not meeting and satisfy the CSFs

that have been found.

4. Why have I been chosen?

You have been chosen as the case company due to two main reasons. Firstly, you have

recently implemented an ERP system from a gold partner of SAP which is considered as one

of the best ERP packages in the market. Secondly the implementation of the system is

considered as a successful case and therefore the outcomes are more likely to be valid.

5. Do I have to take part?

It is up to you to decide whether or not to take part. If you do decide to take part you will be

given this information sheet to keep and be asked to sign a consent form. If you decide to take

part you are still free to withdraw at any time and without giving a reason. A decision to

109

withdraw at any time, or a decision not to take part, will not affect the standard of care you

receive.

6. What will happen to me if I take part?

The research will last approximately three months. However the collection of data will last

about 6-8 days. Moreover an interview is estimated to last about 20-30 minutes. Nevertheless

in some cases it may need to last more and that depends on interviewee and his/her role in the

company. A plan of the interviews will be produced for the participants in order to give them

the opportunity to be well prepared. Interviews will be recorded with a professional recorder

and an interview script is going to be produced for them.

7. What do I have to do?

The participant will just answer some open-ended question with no time limit. There are no

lifestyle restrictions.

8. What are the possible disadvantages and risks of taking part?

There are not any possible disadvantages or risks.

9. What are the possible benefits of taking part?

‘Whilst there are no immediate benefits for those people participating in the project, it is

hoped that this work will be good enough in order to be published and therefore the name of

the participants’ organization will be heard as a successful story which helped researchers

and academics. However, this cannot be guaranteed.

10. What happens if the research study stops earlier than expected?

All the appropriate procedures are undertaken to ensure that the study will go as it was

designed.

11. What if something goes wrong?

if you wish to complain, or have any concerns about any aspect of the way you have been

approached during the course of this study, the interviewer should be available to you to

rearrange and solve the issue-problem.

12. Will my taking part in this project be kept confidential?

‘All the information that we collect about you during the course of the research will be kept

strictly confidential. You will not be able to be identified in any reports or publications’.

13. What type of information will be sought from me and why is the collection of this

information relevant for achieving the research project’s objectives?

Questions relevant to the main two aspects (ERP and BPR) of the research study will be

asked. For example questions regarding the scope of the implementation and objectives of its

110

implementation. The information will be analyzed following the thematic analysis with

inductive approach.

14. What will happen to the results of the research project?

The results of the research will be given to the participant organization just after the end of

the study. The results estimated to be published early in September of 2012. The researcher is

responsible to give o copy to the company involved. The data collected are not going to be

used for additional or subsequent research.

15. Who is organising and funding the research?

The study is self-sponsored and is conducted by Mr. Georgios Michail for the purpose of his

MSc Information Systems in the University of Sheffield.

16. Who has ethically reviewed the project?

This project has been ethically approved via Information School department’s ethics review

procedure. The University’s Research Ethics Committee monitors the application and

delivery of the University’s Ethics Review Procedure across the University.

17. Contact for further information

Researcher:

Name: Mr. Georgios Michail

Address: 12, St George Close, Opal2, S3 7HD, Sheffield, UK

Tel: 0044 7936 275 123

Supervisor:

Name: Dr. Alex Peng, Lecturer at the University of Sheffield

Tel: 0114 222 2658

Finally, as a participant you will be given a copy of that information sheet and a consent form

for you to keep. Many thanks for taking part in the project.

Question to insert into an information sheet if the research

involves producing recorded media:

Will I be recorded, and how will the recorded media be used?

‘The audio and/or video recordings of your activities made during this research will be used

only for analysis and for illustration in conference presentations and lectures. No other use

will be made of them without your written permission, and no one outside the project will be

allowed access to the original recordings.’

.

111

Participant Consent Form

Title of Research Project:

“What are the Critical Successful Factors (CSFs) for Business Process

Reengineering (BPR) in the context of Enterprise Resource Planning (ERP)

project in SMEs? The case of a Cypriot company”.

Name of Researcher: Georgios Michail

Participant Identification Number for this project: Please initial

box

1. I confirm that I have read and understand the information sheet

dated [18.05.2012] explaining the above research project

and I have had the opportunity to ask questions about the project.

2. I understand that my participation is voluntary and that I am free to withdraw

at any time without giving any reason and without there being any negative

consequences. In addition, should I not wish to answer any particular

question or questions, I am free to decline.

3. I understand that my responses will be kept strictly confidential and

I give permission for members of the research team to have access to my

anonymised responses. I understand that my name will not be linked with

the research materials, and I will not be identified or identifiable in the

report or reports that result from the research.

4. I agree for the data collected from me to be used in future research

5. I agree to take part in the above research project.

112

________________________ ________________ ____________________

Name of Participant Date Signature

(or legal representative)

_________________________ ________________ ____________________

Name of person taking consent Date Signature

(if different from lead researcher)

To be signed and dated in presence of the participant

_________________________ ________________ ____________________

Lead Researcher Date Signature

To be signed and dated in presence of the participant

Copies:

Once this has been signed by all parties the participant should receive a copy of the

signed and dated participant consent form, the letter/pre-written script/information

sheet and any other written information provided to the participants. A copy of the

signed and dated consent form should be placed in the project’s main record (e.g. a

site file), which must be kept in a secure location.