invest in
© 2016 by Indonesian Investment Coordinating Board. All rights reserved
Industrial Project Investment
Kuala Tanjung, North Sumatera
INVESTMENT-PRO
(Investment Project-Ready- to-Offer)
Business Schemes Offerings:Main processingDownstream productsPower PlantMaterial SupplyDistribution/Business ServicesJoin VentureEPC/Turn-key projects
Deputy of Investment PlanningDirectorate of Manufacturing Industry Planning
PROJECT BACKGROUND
invest in
As first step of aluminum industrial cluster development, some project planning have been initiated and furthermore some potential partners have been as well consolidated. For some projects, join venture agreements (JVAs) have been reached and signed with certain
partners/shareholders. Currently, some feasibility studies (FSs) are on-
going , certain has finalized and some are still in conceptual study stages.
In the mean of improving efficiencies by logistically simplifying and managing supply-chain and also by diversifying to more value-added (downstream)
products , a globally competitive, cheaper energy and environmental friendly aluminum production base industrial cluster are to be established.
PROJECT DESCRIPTION
invest inThe project will have strong competitiveness where such production base will
be integrated with ports (planned logistic port and international hub
ports/IHP nearby), material supplies and utility systems. High purity molten aluminum will give high efficiency where no such metal re-melting is
needed. This will also ensure the high quality of downstream products.
With current (relatively low) Indonesian Aluminum Consumption per capita of
2 kg/capita,tremendous increase of demand is projected. By 2025, even at least consumption is tripled to
6 kg/capita, the
total capacity of 1 million T/yr is still lag behind forecasted domestic demand of 3 million T/yr
PROJECT LOCATION
invest in
Kuala Tanjung aluminum industrial cluster development area (386.9 Ha) is
strategically located on the northern east shore of Sumatera, which is in Selat Malaka, one of world’s busiest strait (100 million TEUS are crossing each year). In 2017, this
zone will be connected with Medan-Tebing Tinggi Toll Road (1.5 hours trip from
Medan), logistic/passenger railroads from Medan (1.5 hour) and Sei-
Mangkei SEZ (1 hour). With port capacity of 500.000 TEUS/year (by 2018), and
IHP up to 60 million TEUS/year (2020), this region is ready to compete with any other port cities.
Kualanamu
International Airport
Hydro Power Plant
(PLTA) in Asahan
286 MW + 317 MW
Coal Power Plant
3x350 MW
Medan/Kualanamu-
Tebing Tinggi Toll Road
Logistic/passanger
railroad SEZ Sei
Mangkei-Medan-Kuala
Tanjung
Kuala Tanjung Port
Western Indonesia
International Hub Port
(IHP)
Supporting Infrastructures:
PROJECT PROFILES
invest in
Current status of main aluminum smelting plant would be 100% ownership by
PT. Inalum ,anyhow some supporting business schemes are still widely open for partnerships or potential investors. Within the 1st phase, i.e. upgrading of current smelting plant and new smelter , feasibility studies have been conducted. For the 2nd phase, i.e. 500.000 t/yr smelting plant, any schemes of business ownerships
and partnerships are widely offered.
Western Indonesia InternationalKualanamu International Airport Port Hub (IPH)
Hydro Power Plant (PLTA) Kuala Tanjung Port in Asahan (286 MW +
Coal Power Plant Logistic/Passenger Rail Road3 x 350 MW Sei Mangke SEZ – Medan – Kuala
Tanjung
Medan – Kualanamu –Tebing Tinggi Toll Road
PROJECT PROFILES
invest in
A. SMELTING PLANT EXPANSION
New Aluminum Smelter
Project Name: Aluminum Smelting Plant Expansion
Capacity: 500.000 T/yr - 300.000 T/yr (upgrading of current plant) - 200.000 T/yr (new smelter)
Product: Aluminum (hot metal or ingot)
Technical Specification: PBCF Hall –Heroult, Current ≥ 400kACurrent Eff. > 95%,DC < 13.000 kWH/Ton
Area : 200 Ha (include current smelter)
On-stream schedule:Q4 2019
Offered Business Schemes/Partnerships:Materials/machinery/technology suppliers, material handling, distribution, business services.
Current status of main aluminum smelting plant would be 100% ownership by
PT. Inalum ,anyhow some supporting business schemes are still widely open for partnerships or potential investors. Within the 1st phase, i.e. upgrading of current smelting plant and new smelter , feasibility studies have been conducted. For the 2nd phase, i.e. 500.000 t/yr smelting plant, any schemes of business ownerships
and partnerships are widely offered.
PROJECT PROFILES
invest in
B. COAL POWER PLANTProject Name: Coal Power Plant
Capacity: 2 x 350 MW (Stage 1) 1 x 350 MW (Stage 2)
Product: electricity
Technical Specification: Fluidized Bed Combustion
Area : 90 Ha
On-stream schedule:Q4 2019
Offered Business /Financial Schemes/Partnerships:Loan/IPO/Obligation, coal supply, sub-contractors, material handling and transportation
For ownership of first 2x350 MW coal power plant, a join venture agreement (JVA) has been reached. This entity are then proposing further
financial schemes (loan/IPO/obligation), while conducting feasibility study for their
project. For the 1st and 2nd stages coal supplier (inc. material handling and
transportation) are at strong need. Another join venture scheme offering for the 2nd
stage are being proposed to private/state-owned local/foreign enterprises.
PROJECT PROFILES
invest in
C. PORT EXPANSION
Project Name: Port Expansion
Capacity: 2 x 60.000 DWT 1 x 25.000 DWT
Services: Aluminum products /coal/smelter raw materials -loading/unloading.
On operation :Q3 2019
Offered Business Schemes:Engineering, procurement and construction (EPC)
Aluminum Smelter
Power Plant
PROJECT PROFILES
invest in
D. ALUMINUM INDUSTRIAL CLUSTER
Project Name:Aluminum Industrial Cluster
Total Area: 58,8 Ha
Products: Aluminium downstream products (Billet, Alloy,Slab-Sheet, Ekstrusi, Wire rod, Auto part)
Business schemes offerings Infrastructures/utilities provider:transportation system, water, waste management, drainage, electricity, telecommunication
PROJECT PROFILES
invest in
E. R&D CENTER/POLYTECHNIC & RESIDENTIAL AREA
Project Name:R&D Center /Polytechnic & Residential Area
Total Area: 38.06 Ha
Business schemes offerings Infrastructures/utilities provider:transportation system, water, waste management, drainage, electricity, telecommunication
PROJECT PROFILES
invest in
F. COKE CALCINATION PLANT
Project Name:Coke Calcination Plant
Area: 7 Ha
Capacity:2 x 100.000 T/yr
Product:Calcined Petroleum Coke (CPC)
Business schemes offerings: Infrastructures/utilities provider, distribution/material handling,.
On-Stream Schedule:Q4 2018
Currently, CPC as one of main raw materials for anode bars in the
reduction pots for aluminum production are still imported or purchased from
production base in Surabaya, East Java. By building the CPC plant inside the complex, which is also approaching the source of petroleum coke in Dumai, Riau, high cut-off of transportation cost will be achieved. Careful material handling, transportation and environmental protection will be at top priority.
PROJECT SCHEDULING
invest in
MAIN ACTIVITY PLANNING of 1st STAGE (2015-2020)
PROJECT NAME ACTIVITY
Smelting Plant Expansion
• FS & DED• Permits• Construction & COD
Coal Power Plant • FS & DED• Permits• Construction & COD
Port Expansion • FS & DED• Permits• Construction & COD
Aluminum Industrial Cluster
• FS & DED• Permits• Construction & COD
R&D Center/Polytechnic & Residential Area
• FS & DED• Permits• Construction & COD
Coke Calcination Plant • FS & DED• Permits• Construction & COD
FS : Feasibility StudyDED : Detailed Engineering DesignCOD : Commercial Operation Date
GOVERNMENT SUPPORT
invest in
Form of Supports Note
Land Utilization Rights (HPL) State Capital Support/Penyertaan Modal Negara (PMN)
Coal Supply As main energy and raw material sources will be secured along project lifetime.
Permits and Licensing Accelerated, simple and transparent: 3 Hour Investment Permits (II3J)Direct Construction Permits (KLIK)
Fiscal Incentives • Tax holiday/tax allowance• Customs/import facilities for machinery or materials
Inner zone infrastructures • Roads• Rail tracks: passengers/containers/hot metal • Power Plants: PPP Initiatives
CONTACT US
invest in
Deputy of Investment Planning
Directorate of Manufacturing Industry Planning
Jl. Gatot Subroto No. 44
Suhartoyo Building, 8th Floor
Jakarta 12190
Phone/Fax: (021) 520.7022
Contact Person : [email protected]
Planning Manager
Strategic Planning Department
PO. Box 1 Kuala Tanjung 21257
Kab. Batu Bara, North Sumatera
Phone/Fax: (0622) 31311 ext 4301 / 31001