Introduction to specifications refresher

21
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404. Introduction to specifications refresher Ofelia Capatina on behalf of the CERN specification team LHC-CC13, 6th Crab Cavity Workshop OC, 10/December/2013 1

description

Introduction to specifications refresher. Ofelia Capatina on behalf of the CERN specification team. Functional specification. https ://espace.cern.ch/HiLumi/WP4/Lists/Team%20Discussion/AllItems.aspx. General. SM18 area - PowerPoint PPT Presentation

Transcript of Introduction to specifications refresher

Page 1: Introduction to specifications refresher

The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404.

Introduction to specificationsrefresher

Ofelia Capatinaon behalf of the CERN specification team

LHC-CC13, 6th Crab Cavity WorkshopOC, 10/December/2013 1

Page 2: Introduction to specifications refresher

Functional specification

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 2

https://espace.cern.ch/HiLumi/WP4/Lists/Team%20Discussion/AllItems.aspx

Page 3: Introduction to specifications refresher

General

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 3

LHC Point 1 (vertical crabbing)4 cavities / IP side/ beamto be installed during LS3 LHC Point 5 (horizontal

crabbing)4 cavities / IP side/ beamto be installed during LS3

SPS BA4 (vertical or horizontal crabbing)One or two cryomodules with 2 identical cavities to be tested before LS2

SM18 areaCold tests and clean room facilities – cold test of cryomodules prior tunnel installation

Page 4: Introduction to specifications refresher

• LHC environmentGeneral

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 4Paolo Fessia

4 cavities / IP side / beam between D2 and Q4=>Total 32 cavities in LHC

Page 5: Introduction to specifications refresher

• LHC environment

General

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 5

Page 6: Introduction to specifications refresher

• SPS environment

General

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 6Alick Macpherson talk

Page 7: Introduction to specifications refresher

• SPS environment

General

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 7

Page 8: Introduction to specifications refresher

Cryomodule

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 8

LHC configuration SPS configuration

Page 9: Introduction to specifications refresher

• SPS :• 2 (identical) cavities in a cryomodule• 3 different cryomodules

Cryomodule

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 9Shrikant Pattalwar talk

Page 10: Introduction to specifications refresher

• SPS :• 2 (identical) cavities in a cryomodule• 3 different cryomodules

Cryomodule

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 10

Shrikant Pattalwar talk

Page 11: Introduction to specifications refresher

• SPS :• 2 (identical) cavities in a cryomodule• 3 different cryomodules

Cryomodule

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 11

Thomas Nicol talk

Page 12: Introduction to specifications refresher

• SPS :• 2 (identical) cavities in a cryomodule• 3 different cryomodules

Cryomodule

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 12Thomas Nicol talk

Page 13: Introduction to specifications refresher

• SPS :• 2 (identical) cavities in a cryomodule• 3 different cryomodules

Cryomodule

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 13Luis Alberty talk

Page 14: Introduction to specifications refresher

• SPS :• 2 (identical) cavities in a cryomodule• 3 different cryomodules

Cryomodule

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 14Luis Alberty talk

Page 15: Introduction to specifications refresher

• Design principle, dimensions and interfaces (RF, cryo) to be standardized as much as possible

• Metric system !

Cryomodule

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 15

Page 16: Introduction to specifications refresher

• SPS:• Two circuits: 2 K and 80 K• Operated at 2 K saturated helium bath -> ~30 mbar• Strong requirement to reduce static heat losses at 2K• Screening at 80 K provided with LN2• Main interface from the top

Cryogenics

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 16

helium tank

crab cavity

common pumping collector

thermal screen at ~80 Kcryostat interface

CWT

Power coupler intercept

CWT

Krzysztof Brodzinski and Federico Carra talks

Page 17: Introduction to specifications refresher

• LHC - Alignment requirements (position accuracy and position stability) – based on general beam dynamics considerations:• Transverse rotation per cavity should be less than 5 mrad• Transverse misalignment per cavity (in both planes) should

be less than 0.7 mm• Cavity tilt with respect to the longitudinal axis should be

less than 1 mrad• Cavity longitudinal misalignment should be less than 10

mm

Alignment

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 17

Page 18: Introduction to specifications refresher

• SPS • Alignment required for operation less than LHC

• To limit SPS crymodule complexity (win time and limit risk)• No active alignment needed for SPS tests • Foresee a system for monitoring the cavity

positions instead

Alignment

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 18

Page 19: Introduction to specifications refresher

• Integration into cryostat at CERN - most likely location SM18

• Cold tests of full cryomodules in SM18 prior tunnel installation

Cryostating

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 19

Vittorio Parma talk

Mathieu Therasse talk

Page 20: Introduction to specifications refresher

• Fundamental Power Couplers• Talk by Eric Montesinos today

• Impedance budget and HOM power & couplers• Talk by Benoit Salvant today

OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 20

Couplers

Page 21: Introduction to specifications refresher

• Bare cavities for SPS designed to be the same as for the LHC• Dressed cavity for SPS tests design as much as possible

compatible with LHC • Conceptual design of SPS cryomodule for the 3 cavities • 2 identical cavities in 3 different cryomodule• Effort to standardize interfaces, basic choices in-

between the 3 cryomodules• The 3 SPS cryomodules could be tested in SM18 (if no

down-selection since then)• 1 or 2 cryomodules to be tested in SPS, after test in SM18• SPS cryomodule design as much as possible compatible

with the LHC OC, 10/December/2013 LHC-CC13, 6th Crab Cavity Workshop 21

Summary