Introduction to Risk Based Inspection

download Introduction to Risk Based Inspection

of 9

Transcript of Introduction to Risk Based Inspection

  • 8/18/2019 Introduction to Risk Based Inspection

    1/9

  • 8/18/2019 Introduction to Risk Based Inspection

    2/9

    The consequence of failure is calculated as the combined values of the consequences for

    damage to the failed equipment, damage to the surrounding equipment, loss of production,

    the cost due to personnel injury and the damage to the environment. The consequence of

    failure can include both a financial consequence (FC) and an area (safety) consequence

    (CA).

    FC = FCcmd  + FCaffa + FC prod  + FCinj + FCenviron 

    CA = max (CAequip, CA personnel ) 

      FCcmd  is the financial consequence to failed equipment.

      FCaffa is the financial consequence to surrounding equipment.

      FC prod  is the financial consequence due to production downtime.

      FCinj is the financial consequence due to personnel injury.

      FCenviron is the financial consequence due to environmental damage/cleanup.

      CAequip is the area consequence to surrounding equipment.

      CA personnel is the area consequence to nearby personnel.

    For further detail on calculating probability of failure and/or consequence of failure, please

    consult API RP 581. [1] 

    Introduction to the RBI Software

    ReliaSoft’s new RBI software tool has all of the functionality of  RCM++ and facilitates risk

    based inspection (RBI) analysis for oil & gas, chemical and power plants in adherence to the

    principles and guidelines presented in the American Petroleum Institute's recommendationsin the API RP 580 and RP 581 publications, as well as the American Society of Mechanical

    Engineers’ recommendations in the ASME PCC-3-2007 publication. RBI also includes all of the

    standard features available in RCM++, such as being able to perform a functional failure

    analysis on an item and/or create a DFR planner.

    The RBI interface is identical to RCM++, with the addition of RBI specific options on the

    System Hierarchy tab.

    The equipment and component types that are available for RBI analysis are currently limited

    to those addressed API RP 581. The available equipment types are shown below.

    http://www.weibull.com/hotwire/issue151/hottopics151.htm#1http://www.weibull.com/hotwire/issue151/hottopics151.htm#1http://www.weibull.com/hotwire/issue151/hottopics151.htm#1http://rcm.reliasoft.com/http://rcm.reliasoft.com/http://rcm.reliasoft.com/http://rcm.reliasoft.com/http://www.weibull.com/hotwire/issue151/hottopics151.htm#1

  • 8/18/2019 Introduction to Risk Based Inspection

    3/9

     

    Each equipment type also has associated components. For example, the Vessel-FinFan

    equipment has the specific components shown below available for analysis.

    While the system hierarchy can contain items that are not RBI-related, those items will be

    ignored when performing an RBI analysis. For example, in the following picture the system is

    the hydrogen generation unit, which has several items that receive RBI analysis and several

    that do not.

  • 8/18/2019 Introduction to Risk Based Inspection

    4/9

     

    Once you create the assets, you must answer questions and fill out the relevant properties

    for the asset to be analyzed. All of these inputs are used to create a failure model that

    determines the probability of failure, and calculates the consequences of failure. The

    results also include the recommended inspections, if any, that should be performed to keep

    the asset under the maximum allowable risk.

    Example

    A small town wants to do a risk analysis on a proposed high pressure 24-inch pipe carrying

    crude oil for which the oil transportation company is willing to pay a rent of $500,000 inadvance for the next 20 years. The company will also perform an inspection on the pipe

    halfway through the rental period. Since the city is self-insured and is not willing to take any

    financial chances, the city council would like to know if the $500,000 offsets the possible

    risk associated with the pipe. The city has requested the required information from the oil

    transportation company to conduct its own RBI analysis of the pipe.

    http://www.weibull.com/hotwire/issue151/ht151fig4.htmhttp://www.weibull.com/hotwire/issue151/ht151fig4.htmhttp://www.weibull.com/hotwire/issue151/ht151fig4.htmhttp://www.weibull.com/hotwire/issue151/ht151fig4.htm

  • 8/18/2019 Introduction to Risk Based Inspection

    5/9

     

    24-Inch Pipe Specifications

    The pipe is composed of carbon steel. The heavy crude, which contains 100ppm H2S, is being

    pumped through at an operating temperature of 25 Celsius with a pressure of 4.5 MPa.

    The only two damage mechanisms expected are general thinning and external corrosion.

  • 8/18/2019 Introduction to Risk Based Inspection

    6/9

     

    For their analysis, the city assumed that the effectiveness of the performed inspections was

    average. All other property values were estimated based on other similar pipes used

    elsewhere.

  • 8/18/2019 Introduction to Risk Based Inspection

    7/9

     

    The city based the financial portion of the consequences on the current population density

    and the property values around the proposed pipe area. For the initial estimate, the city did

    not take into account inflation or any possible losses associated with property value

    changes, nor possible resident dislike of the pipeline across city land.

  • 8/18/2019 Introduction to Risk Based Inspection

    8/9

     

    Results

    The analyzed results show that in case of a containment failure of the pipe, the expected

    cost associated with a failure would be almost $4.9 million. This far exceeds the $500,000

    payment to be received. However, the probability that a failure will occur within 20 years

    under normal circumstances is estimated to be only 0.7%. Therefore, the expected financial

  • 8/18/2019 Introduction to Risk Based Inspection

    9/9

    risk is the product of the two, or a little over $36,000. This is well under the $500,000

    payment to be received.

    In terms of a cost analysis of the risk, and not including the potential loss in property value

    by having the pipe run across city property, the city council recommended that thecommunity accept the proposed pipeline as an additional revenue source with minimal risk.

    References

    [1] American Petroleum Institute, API RP 581 Risk-Based Inspection Technology 2nd ed.,

    Washington, D.C.: American Petroleum Institute, 2008.