Introduction to Construction Contracts

download Introduction to Construction Contracts

of 17

Transcript of Introduction to Construction Contracts

  • 8/20/2019 Introduction to Construction Contracts

    1/44

    Introduction to

    Construction Contracts

    By

    Eng. Ahmed Moustafa B.Sc

    Email: [email protected] 

    Telephone Number: 00201003437028

    mailto:[email protected]:[email protected]:[email protected]:[email protected]

  • 8/20/2019 Introduction to Construction Contracts

    2/44

    Introduction

     

    Name: Ahmed Moustafa Mohammed 

    • Title: Contract Adminstator

    • Department: Structure Engineering & Construction Management

    • University: Zagazig University

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • 8/20/2019 Introduction to Construction Contracts

    3/44

    Main Topics

    Introduction to Construction Contracts: 

    1. Introduction to Construction Projects 

    2. What is Project Delivery System

    3. What are Tenders

    4. What are Contracts

    5. What are Construction Contracts

    6. What is FIDIC 

  • 8/20/2019 Introduction to Construction Contracts

    4/44

    Construction

    It is the process of producing a structure, it is simply “the  buildingprocess” 

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    5/44

    Construction Industry

    It is the industry  that is related to the construction field.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    6/44

    Properties of Construction Industry

    • Service based industry, not product base

    • Uniqueness of each project

    • Higher level of risk  

    • Temporary

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    7/44

    Importance of Construction Industry

    • Good indicator of the country’s economy

    • Contributes to the development  of the country

    • Linked with other industrial sectors 

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    8/44

    Construction Project Parties 

    • This is the traditional  (most commonly used) relation

    between project different parties.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    9/44

    Owner

    (Client/Employer) 

    Contractor Engineer

    (Consultant/Architect /Designer) 

    Construction Project Parties 

    The person/organization has the idea/concept  &

    money for a project.

    The person/organization with the level

    of experience capable of interpreting the

    owner’s  idea  into project documents(drawings, specs, … )

    The person/organization with the required

    resources  and experience  capable of

    converting the project document   into aphysical construction work .

    Owners Role:

    1. Feasibility study

    2. Product Specification/Design Requirements

    3. Financing methods

    4. Contract type selection

    5. Contractor selection method

    Consultant Role:

    1. Project Design

    2. Project Specification

    3. Engineering Estimate

    4. Construction Supervision

    Contractor Role:

    1. Design Review

    2. Construction method

    3. Project Construction

  • 8/20/2019 Introduction to Construction Contracts

    10/44

    Construction Project Resources 

    1. Labor

    2. Material

    3. Equipment

    4. Subcontractor

    5M 

    Manpower 

    Material 

    Machine 

    Money 

    Method 

     Another way to look at

    Project  Resources 

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    11/44

    Different types of Construction Projects 

    • Residential Projects:

    Example; Residential houses/ compounds, etc ….

    • Non - Residential Projects:

    Example; hospitals, schools, etc … 

    • Infrastructure/Engineer Projects:

    Example; highways, bridges, water/waste treatment plants, etc … 

    • Industrial Projects:

    Example; industrial factories 

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    12/44

    Different types of Construction Projects 

    PercentageResourcesFinancingContractorEngineerOwnerProject Types

    40 – 45%

    No special

    resource needed,

    mainly labor

    LowGeneral

    ContractorMostly Archt.

    Mostly

    Private Residential

    25 – 30%

    May require

    some special

    resource, mainly

    labor

    Low -

    Intermediate

    General

    Contractor

    Mostly Archt.

    & Civil

    Mostly

    PrivateNon-Residential

    20 – 25%

    Requires a high

    level of

    resources, mainly

    equipment 

    High (may require

    special financing)

    Large Scale

    ContractorMostly Civil

    Mostly

    PublicInfrastructure

    5 – 10%

    Requires a high

    level of specific

    resources, mainly

    equipment 

    Intermediate -

    High

    Specialized

    Contractor

    Mostly Specific

    Civil

    Mostly

    PrivateIndustrial

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    13/44

    Construction Project Stages

    Feasibility &Strategy Stage 

    Design Stage

    Tendering &

    ContractingStage

    ConstructionStage

    Testing, Primary

    Taking Over andGrantee (Intial)Stage

    Final Taking

    Over andGrantee (Final)Stage

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    14/44

    Project Delivery System (PDS) 

    • It is the system  used by the owner for organizing, financing design,

    construction, operation and maintenance for a project .

    • It identifies  different project parties  assigning each party specific

    responsibilities and authorities  and it also defines how different

    parties interact  with one another.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    15/44

    Project Delivery System (PDS) 

    1. Force Account

    2. Traditional – Design/Bid/Build ( DBB)3. Design Build (DB)

    4. Multiple Prime Contractor (MPC)

    5. Construction Management (CM)

    6. Turnkey (BOT)

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    16/44

    PDS: Force Account  

    Owner performs the construction work using own

    resources, suitable for small maintance project.

     Advantages:

    1. Cheap (No Engineer, No Contractor)

    2. Time effective

    3. No conflict as there is only 1 party

    4. Change orders are easily performed

    Disadvantages:

    1. Not suitable for large projects (owner isn’t  experience enough)

    S di i l i / id/ ild ( )

  • 8/20/2019 Introduction to Construction Contracts

    17/44

    PDS: Traditional – Design/Bid/Build (DBB) 

    Owner assigns an Engineer to design project and a

    Contractor to construct the project.

     Advantages:

    1. Project documents are completed before bid start

    2. Owner has a great idea of the full project details

    3. Decrease change order made during execution

    4. Chance to use open tender to get lowest cost

    Disadvantages:

    1. Conflict may occur between different parties

    2. No co-ordination between Engineer & Contractor

    3. Contractor is not part of design (decrease constructability)

    4. Time consuming

    Benefit to Owner:

    1. Owner deals with 1 Contractor only

    2. Traditional, well known & recognized approach3. Design is impartial

    Risk to Owner:

    1. Failure to co-ordinate between different parties

    2. Conflict may occur during project execution

    PDS D i /B ild (DB)

  • 8/20/2019 Introduction to Construction Contracts

    18/44

    PDS: Design/Build (DB) 

    Owner assigns an design –  build company which designs and constructs project, here

    construction could overlap with design, suitable for major project (heavy construction)

     Advantages:

    1. Time effective (as construction may begin before design is finished).

    2. Coordination between designer & contractor assures higher

    constructability.3. Decreases headache on owner as project responsibility is carried by

    firm.

    Disadvantages:

    1. No bidding, no competition i.e. higher price.

    2. Owner is not as involved in project as other PDS

    Benefit to Owner:

    1. Saves time

    2. Less conflict between parties

    Risk to Owner:

    1. Integration of design is eliminated (no complete vision)

    2. Owner has less control on project

    PDS M lti l P i C t t (MPC)

  • 8/20/2019 Introduction to Construction Contracts

    19/44

    PDS: Multiple Prime Contractor (MPC) 

    Owner assigns multiple contractors each for a specific part of the project, suitable for

    large multidiscipline projects like water structures, ….

     Advantages:

    1. Cheaper as there is not subcontracting.

    2. Utilizes different expertise and vast amount of resources.

    Disadvantages:

    1. Very high chance of conflict between contractors

    2. Extremely difficulty to coordinate between parties

    PDS C t ti M t

  • 8/20/2019 Introduction to Construction Contracts

    20/44

    PDS: Construction Management  

    Owner assigns a CM with high managerial skills/experience to assist him in coordination

    and construction project management.

     Advantages:

    1. Cheaper as there is not subcontracting.

    2. Utilizes different expertise and vast amount of resources.

    3. Decreases conflict and increases coordination between parties4. Decease Owner’s responsibility for managing and coordinating

    Disadvantages:

    1. Expensive but may be proven efficient

    PDS T k

  • 8/20/2019 Introduction to Construction Contracts

    21/44

    PDS: Turnkey 

    Owner (usually government) assigns a company to do all design, construction, financing

    and operating tasks ex. BOT (Build/Operate/Transfer)

     Advantages:

    1. Time effective as 1 party does all the work

    2. Owner relieved from construction problems

    3. Owner doesn’t  have to worry about project financing

    Disadvantages:

    1. Very high benefit costs

    2. Project may be handed over in a bad condition

  • 8/20/2019 Introduction to Construction Contracts

    22/44

    Factors affecting PDS selection 

    Factors related to market Factor related to ownerFactors related to project 

    Availability of PDS in market Owner past practices and

    experienceTime Constraints

    Package size compared to market Owner resource capabilityFinancial Constraints

    Restriction on method for certain

    owners

    Pre-construction Services

    Distribution of risk Design Process Involvement 

    Construction SophisticationShareholder interests

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    23/44

    Tender 

    The tender process  is the process of choosing a contractor to execute the design works; it is of different

    types, some of which are:

    • Direct order: owner directly chooses a contractor to perform the services;

    Suitable for:

    Projects  of a special nature  (where only a small number of contractor are able to

    perform)

     Advantages:

    Not time consuming

    Disadvantages:

    May cost more than other tender types 

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    24/44

    Tender 

    The tender process  is the process of choosing a contractor to execute the design works; it is of different

    types, some of which are:

    • Open/General tender: owner announces project in public and any contractor can submit;

    Suitable for:

    Generally all project, specially government projects  (because of administrative

    restrictions)

     Advantages:

    Ensures high competition thus lower cost

    Disadvantages:

    Time consuming

    Unqualified tenderers may be choosen 

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    25/44

    Tender 

    The tender process  is the process of choosing a contractor to execute the design works; it is of different

    types, some of which are:

    • Selected/Limited tender: owner announces project to the previously pre- qualified short listed 

    contractors;

    Suitable for:

    Generally all project, specially large projects 

     Advantages:

    Ensures high quality a contractor is pre-qualified

    Disadvantages:

    Time consuming  (but less than Open/General tender, due to the lower number of

    tenderers)

    Less competition, higher cost  

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    26/44

    Tender 

    The tender process  is the process of choosing a contractor to execute the design works; it is of different

    types, some of which are:

    • Open/General practice: similar to open/general tender expect that the owner negotiates publicly to get lowest

    price “reverse auction” while standardizing all other criteria.

    • Selective/Limited practice: similar to open/general practice expect that the owner negotiates with selected

    contractors to get lowest price.

    • Note that:

    1. The negotiations are made either in a negotiation meeting  (with all the tenderers present) or via

    correspondents .

    2. The owner  informs the tenderers with their competitors offers’  so that each tenderer (if he wishes)

    would lower his offer, in order to be choosen by the owner.

    3. The problem with practices is that it may cause tenders to submit initially higher offers (as they know

    that these offers will be lowered in the negotiation process).

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    27/44

     

    • A Contract  is an agreement  made in good faith between 2 or more capable parties to perform an

    act for a certain specific purpose.

    • In construction  field the contract is usually between owner  and contractor  to perform

    construction services.

    • The Contract  is a legally bidding document that defines exactly the rights and obligations of each

    party in the contract.

    Steps to contract:

    1. Invitation to bid/tender (Tender Process) from Owner “party A” to Contractor “party B" to

    perform a certain task or a service with certain conditions.

    2. Offer  (tender/bid) from the Contractor  (B) is made to the Owner  (A) to perform the task

    (complying with all or some of the conditions)

    3. Acceptance where the Owner (A) has the right to accept or refuse the Contractor (B) offer, if

    accepted then a contract is born (legally bidding for both parties).

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

    Contracts 

  • 8/20/2019 Introduction to Construction Contracts

    28/44

    Types of Contracts

    Contract  can be categorized according to the payment method, such categories include: 

    • Fixed price contracts 

    Lump sum: a pre-determined fixed priced is set for all project/items; price includes overhead, profit

    and all other necessary costs, this price can be paid:

    Once the project is delivered

    According to work progress (time progress or quantity progress or percent progress)

    In this type of contract:

    The scope should be fully detailed

    No or minimal changes should be allowed during execution

    Fair mechanisms for long – term risk allocation should be placed in the contract (ex. Escalation

    Formula).

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    29/44

    Types of Contracts

    Contract  can be categorized according to the payment method, such categories include: 

    • Remeasure contracts 

    Unit price: (most common contracts) where a fixed unit price (price/quantity “unit”)  is pre-

    determined for each work item which includes all necessary costs; here the contract is remeasured i.e.

    exact contract cost  depends on the actual quantities executed, the price can be paid:

    According to a BOQ containing estimate quantities (most common)

    Rate Only (suitable for small works, maintenance works or rehabilitation works), rates may be

    over priced as there is no quantities to place rates on.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    30/44

    Types of Contracts

    Contract  can be categorized according to the payment method, such categories include: 

    • Cost reimbursement contracts 

    Where the contractor agrees to perform the work for certain price which includes:

    1. Direct cost  of the item plus,

    2. A certain pre-defined fee which covers the profit & overhead.

    The different types of the cost reimbursement are:

    Cost plus percentage fee

    Cost plus fixed fee

    • Target cost contracts 

    Where a target cost is set , whatever the final cost   turns out to be, the saves/losses  are divided 

    between the owner and the contractor.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

    Construction Contracts Types & Risk

  • 8/20/2019 Introduction to Construction Contracts

    31/44

    Construction Contracts Types & Risk  

    Max. 

    Min. 

    Max. 

    Max. 

    Max. 

    Min. 

    Max. 

    Min. 

    Min. 

    Min. 

    Little 

     Alot  

    Little 

     Alot  

    Owner Risk  

    Contractor Risk  

    Owner Control 

    Control Effort  

    Design Changes 

    Info.

    required

    for tender 

    Info.

    required

    for control 

    Lump Sum 

    Unit Price 

    Target Cost  

    Cost + Fixed Fee 

    Cost + % Fee 

    Risk Distribution & Contract Types Price/Contract

  • 8/20/2019 Introduction to Construction Contracts

    32/44

    Risk Distribution & Contract TypesCost Plus

    Contracts 

    Remeasure

    Contracts

    (Red Book ) 

    Target

    Cost

    Contracts 

    Design – Build

    (Yellow Book ) 

    Contractor

    Risk Increase 

    Employer

    Risk Increase 

    Contract Financing Risks are carried by Employer 

    Site, Work Quality & Contractor’s Crew Risks are carried by Contractor 

    Force Majeure Risks are carried by Employer Insurable FM 

    Un - Insurable FM 

    Traditional

    Contracts 

    EPC/ TurnkeyContracts 

    EPC/Turnkey

    (Silver Book ) 

    Contractor

    carries all

    the risks

    with

    limited

    chances of

    claiming

    extension oftime or

    additional

    costs 

    Turnkey,

    BOT, BOOT,

    etc….      R    i   s    k    A    l    l   o   c   a   t    i   o   n

    Price/Contract

    Type Relation 

  • 8/20/2019 Introduction to Construction Contracts

    33/44

    FIDIC

    • FIDIC  (Fédération Internationale des Ingénieurs –  Conseils or International

    Federation of Consulting Engineers) is an international federation ofassociations of consulting engineers representing the profession in their

    respective countries.

    • FIDIC's Contracts Committee is responsible for producing the most commonly

    used standard forms of contract for international construction projects.

    • FIDIC contracts are generally known by the color of their cover: the Red Book ,

    Yellow Book , Silver Book , Green Book , Pink Book , Gold Book , Blue Book   and

    White Book .

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    34/44

    FIDIC Forms of Contracts

    • Main Forms of Contract before 1995 included:

    1. From1913

     (establishment ofFIDIC

    ) till1957

    ,FIDIC

     didn’t 

     produce any form of contracts.

    2. In 1957, the 1st   edition  of “Conditions of Contract for Works of Civil Engineering

    Construction” was published and its cover was red.

    3. In 1962, the 1st  edition of “Conditions of Contract for Electrical and Mechanical Works – 

    Including Erection on Site” was published and its cover was yellow.

    4. In 1969, the 2nd  edition  of “Conditions of Contract for Works of Civil Engineering

    Construction” was published and its cover was also red.

    5. In 1977, the 3rd  edition  of “Conditions of Contract for Works of Civil Engineering

    Construction” was published and its cover was also red.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    35/44

    FIDIC Forms of Contracts

    • Main Forms of Contract before 1995 included:

    7. In 1980, the 2nd edition of “Conditions of Contract for Electrical and Mechanical Works – 

    Including Erection on Site” was published and its cover was also yellow.

    8. In 1987, the 3rd edition of “Conditions of Contract for Electrical and Mechanical Works – 

    Including Erection on Site” was published and its cover was also yellow and the 4th edition 

    of “Conditions of Contract for Works of Civil Engineering Construction” was published and

    its cover was also red, the covers were internationally recognized and the contracts were

    known as Red Book  and Yellow Book .

    9. In 1995, the FIDIC published of 1st  edition of “Conditions of Contract for Design-Build and

    turnkey” and its cover was orange.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    36/44

    FIDIC Forms of Contracts

    • Other Forms of Contract included:A. Client/Consultant Model Service Agreement

    1. In 1990, the 1st  edition of “Client/Consultant Model Service Agreement ” was published and its

    cover was White.

    2. In 1991, the 2nd edition of “Client/Consultant Model Service Agreement ” was published and

    its cover was also White.

    3. In 1998, the 3rd edition of “Client/Consultant Model Service Agreement ” was published and

    its cover was also White.

    4. In 2006, the 4th edition  of “Client/Consultant Model Service Agreement ”  was published and

    its cover was also White.

    B. Sub-Consultant Agreement & Joint Venture Agreement

    1. In 1992, the 1st  edition of “Sub-Consultant Agreement ” was published and 1st  edition of “Joint

    Venture (Consortium) Agreement ”.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    37/44

    FIDIC Forms of Contracts

    • Other Forms of Contract included:

    C. Sub-Contract Agreement

    1. In 1994, the 1st  edition of “Sub-Contract Agreement ”  was published and its cover was

    red in relation with the “Conditions of Contract for Works of Civil Engineering

    Construction”.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    38/44

    FIDIC Forms of Contracts

    • Main Forms of Contract after 1995 :

    After publishing the Orange Book  in 1995, FIDIC formed a committee to update theRed  and Yellow  Books (Red  Yellow  Update Committee) which took into

    consideration the following:

    1. Simplifying the language that is used in the forms

    2. Unifying the numbering & language formats in all the forms

    3. Re-drafting the contracts not based on work but based on the risk allocation

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    39/44

    FIDIC Forms of Contracts

    • Main Forms of Contract after 1995 :

    In conclusion the following were produced:

    1. New Red Book : Conditions of Contract for Construction for Building and Engineering

    Works Designed by the Employer, where the Employer (his representative, Engineer, …)

    supplies design of the Works (which could include: civil, electrical, …) (some designs may

    be presented by the contractor, for which he carries their liability)

    2. New Yellow Book : Conditions of Contract for Plant and Design-Build, where the

    Contractor designs and builds the Works (which could include: civil, electric, …),recommended for plant (where major work is electrical or mechanical). 

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    40/44

    FIDIC Forms of Contracts

    • Other Forms of Contract published after 1995 included:

    1. Silver Book ”Conditions of Contract for EPC/Turnkey Projects”: recommended for turnkey

    mega projects (infra structure, mega project, …) here contractor carries total responsibility for

    design and execution (with little involvement of the Employer) to produce a fully equipped

    facility for operation.

    2. Green Book  ”Conditions of Short Form of Contract ”: due to the negative criticisms on the Red

    book   for not being fit for use for small projects (low capital, short duration, low risk) or

    repetitive projects.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    41/44

    FIDIC Forms of Contracts

    • By September 1999 the FIDIC published four new suits: 

    New Red Book : Conditions of Contract for Construction for Building andEngineering Works Designed by the Employer.

    New Yellow Book : Conditions of Contract for Plant and Design-Build.

    Silver Book : Conditions of Contract for EPC/Turnkey Projects.

    Green Book : Conditions of Short Form of Contract .

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    42/44

    FIDIC Forms of Contracts• Now FIDIC package includes: 

    Red Book : Conditions of Contract for Construction for Building and Engineering

    Works Designed by the Employer 1st  Ed. 1999.

    Construction Subcontract 1st  Ed. 2011.

    Yellow Book : Conditions of Contract for Plant and Design-Build 1st  Ed. 1999.

    Silver Book : Conditions of Contract for EPC/Turnkey Projects 1st  Ed. 1999.

    Green Book : Conditions of Short Form of Contract 1st  Ed. 1999.

    Pink Book : FIDIC conditions incorporated in the standard bidding documents of

    multilateral development banks June 2010 Ed. Gold Book : FIDIC Design, Build and Operate Projects 1st  Ed. 2008.

    Blue Book : Contract for Dredging and Reclamation Works 1st  Ed. 2006

    White Book : Client/Consultant Model Services Agreement 4th Ed. 2006.

    Sub-Consultancy Agreement 1st  Ed. 1992.

    Joint Venture (Consortium) Agreement 1st  Ed.1992.

    Model Representative Agreement 1st  Ed. 2013.

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    43/44

    FIDIC Forms of Contracts 

    Construction

    Projects 

    ProjectDeliverySystem

    Tenders ContractsConstruction

    ContractsFIDIC

  • 8/20/2019 Introduction to Construction Contracts

    44/44

     

    The End

    By Eng. Ahmed Moustafa Mohammed

    • Email: [email protected] 

    • Facebook account: http://www.facebook.com/eng.ahmed.moustafa.mohammed 

    mailto:[email protected]://www.facebook.com/eng.ahmed.moustafa.mohammedmailto:[email protected]:[email protected]://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedmailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]