Introduction to Construction Contracts
-
Upload
ahmed-moustafa-aboelela -
Category
Documents
-
view
249 -
download
1
Transcript of Introduction to Construction Contracts
-
8/20/2019 Introduction to Construction Contracts
1/44
Introduction to
Construction Contracts
By
Eng. Ahmed Moustafa B.Sc
Email: [email protected]
Telephone Number: 00201003437028
mailto:[email protected]:[email protected]:[email protected]:[email protected]
-
8/20/2019 Introduction to Construction Contracts
2/44
Introduction
Name: Ahmed Moustafa Mohammed
• Title: Contract Adminstator
• Department: Structure Engineering & Construction Management
• University: Zagazig University
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
-
8/20/2019 Introduction to Construction Contracts
3/44
Main Topics
Introduction to Construction Contracts:
1. Introduction to Construction Projects
2. What is Project Delivery System
3. What are Tenders
4. What are Contracts
5. What are Construction Contracts
6. What is FIDIC
-
8/20/2019 Introduction to Construction Contracts
4/44
Construction
•
It is the process of producing a structure, it is simply “the buildingprocess”
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
5/44
Construction Industry
•
It is the industry that is related to the construction field.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
6/44
Properties of Construction Industry
• Service based industry, not product base
• Uniqueness of each project
• Higher level of risk
• Temporary
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
7/44
Importance of Construction Industry
• Good indicator of the country’s economy
• Contributes to the development of the country
• Linked with other industrial sectors
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
8/44
Construction Project Parties
• This is the traditional (most commonly used) relation
between project different parties.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
9/44
Owner
(Client/Employer)
Contractor Engineer
(Consultant/Architect /Designer)
Construction Project Parties
The person/organization has the idea/concept &
money for a project.
The person/organization with the level
of experience capable of interpreting the
owner’s idea into project documents(drawings, specs, … )
The person/organization with the required
resources and experience capable of
converting the project document into aphysical construction work .
Owners Role:
1. Feasibility study
2. Product Specification/Design Requirements
3. Financing methods
4. Contract type selection
5. Contractor selection method
Consultant Role:
1. Project Design
2. Project Specification
3. Engineering Estimate
4. Construction Supervision
Contractor Role:
1. Design Review
2. Construction method
3. Project Construction
-
8/20/2019 Introduction to Construction Contracts
10/44
Construction Project Resources
1. Labor
2. Material
3. Equipment
4. Subcontractor
5M
Manpower
Material
Machine
Money
Method
Another way to look at
Project Resources
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
11/44
Different types of Construction Projects
• Residential Projects:
Example; Residential houses/ compounds, etc ….
• Non - Residential Projects:
Example; hospitals, schools, etc …
• Infrastructure/Engineer Projects:
Example; highways, bridges, water/waste treatment plants, etc …
• Industrial Projects:
Example; industrial factories
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
12/44
Different types of Construction Projects
PercentageResourcesFinancingContractorEngineerOwnerProject Types
40 – 45%
No special
resource needed,
mainly labor
LowGeneral
ContractorMostly Archt.
Mostly
Private Residential
25 – 30%
May require
some special
resource, mainly
labor
Low -
Intermediate
General
Contractor
Mostly Archt.
& Civil
Mostly
PrivateNon-Residential
20 – 25%
Requires a high
level of
resources, mainly
equipment
High (may require
special financing)
Large Scale
ContractorMostly Civil
Mostly
PublicInfrastructure
5 – 10%
Requires a high
level of specific
resources, mainly
equipment
Intermediate -
High
Specialized
Contractor
Mostly Specific
Civil
Mostly
PrivateIndustrial
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
13/44
Construction Project Stages
Feasibility &Strategy Stage
Design Stage
Tendering &
ContractingStage
ConstructionStage
Testing, Primary
Taking Over andGrantee (Intial)Stage
Final Taking
Over andGrantee (Final)Stage
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
14/44
Project Delivery System (PDS)
• It is the system used by the owner for organizing, financing design,
construction, operation and maintenance for a project .
• It identifies different project parties assigning each party specific
responsibilities and authorities and it also defines how different
parties interact with one another.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
15/44
Project Delivery System (PDS)
1. Force Account
2. Traditional – Design/Bid/Build ( DBB)3. Design Build (DB)
4. Multiple Prime Contractor (MPC)
5. Construction Management (CM)
6. Turnkey (BOT)
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
16/44
PDS: Force Account
Owner performs the construction work using own
resources, suitable for small maintance project.
Advantages:
1. Cheap (No Engineer, No Contractor)
2. Time effective
3. No conflict as there is only 1 party
4. Change orders are easily performed
Disadvantages:
1. Not suitable for large projects (owner isn’t experience enough)
S di i l i / id/ ild ( )
-
8/20/2019 Introduction to Construction Contracts
17/44
PDS: Traditional – Design/Bid/Build (DBB)
Owner assigns an Engineer to design project and a
Contractor to construct the project.
Advantages:
1. Project documents are completed before bid start
2. Owner has a great idea of the full project details
3. Decrease change order made during execution
4. Chance to use open tender to get lowest cost
Disadvantages:
1. Conflict may occur between different parties
2. No co-ordination between Engineer & Contractor
3. Contractor is not part of design (decrease constructability)
4. Time consuming
Benefit to Owner:
1. Owner deals with 1 Contractor only
2. Traditional, well known & recognized approach3. Design is impartial
Risk to Owner:
1. Failure to co-ordinate between different parties
2. Conflict may occur during project execution
PDS D i /B ild (DB)
-
8/20/2019 Introduction to Construction Contracts
18/44
PDS: Design/Build (DB)
Owner assigns an design – build company which designs and constructs project, here
construction could overlap with design, suitable for major project (heavy construction)
Advantages:
1. Time effective (as construction may begin before design is finished).
2. Coordination between designer & contractor assures higher
constructability.3. Decreases headache on owner as project responsibility is carried by
firm.
Disadvantages:
1. No bidding, no competition i.e. higher price.
2. Owner is not as involved in project as other PDS
Benefit to Owner:
1. Saves time
2. Less conflict between parties
Risk to Owner:
1. Integration of design is eliminated (no complete vision)
2. Owner has less control on project
PDS M lti l P i C t t (MPC)
-
8/20/2019 Introduction to Construction Contracts
19/44
PDS: Multiple Prime Contractor (MPC)
Owner assigns multiple contractors each for a specific part of the project, suitable for
large multidiscipline projects like water structures, ….
Advantages:
1. Cheaper as there is not subcontracting.
2. Utilizes different expertise and vast amount of resources.
Disadvantages:
1. Very high chance of conflict between contractors
2. Extremely difficulty to coordinate between parties
PDS C t ti M t
-
8/20/2019 Introduction to Construction Contracts
20/44
PDS: Construction Management
Owner assigns a CM with high managerial skills/experience to assist him in coordination
and construction project management.
Advantages:
1. Cheaper as there is not subcontracting.
2. Utilizes different expertise and vast amount of resources.
3. Decreases conflict and increases coordination between parties4. Decease Owner’s responsibility for managing and coordinating
Disadvantages:
1. Expensive but may be proven efficient
PDS T k
-
8/20/2019 Introduction to Construction Contracts
21/44
PDS: Turnkey
Owner (usually government) assigns a company to do all design, construction, financing
and operating tasks ex. BOT (Build/Operate/Transfer)
Advantages:
1. Time effective as 1 party does all the work
2. Owner relieved from construction problems
3. Owner doesn’t have to worry about project financing
Disadvantages:
1. Very high benefit costs
2. Project may be handed over in a bad condition
-
8/20/2019 Introduction to Construction Contracts
22/44
Factors affecting PDS selection
Factors related to market Factor related to ownerFactors related to project
Availability of PDS in market Owner past practices and
experienceTime Constraints
Package size compared to market Owner resource capabilityFinancial Constraints
Restriction on method for certain
owners
Pre-construction Services
Distribution of risk Design Process Involvement
Construction SophisticationShareholder interests
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
23/44
Tender
The tender process is the process of choosing a contractor to execute the design works; it is of different
types, some of which are:
• Direct order: owner directly chooses a contractor to perform the services;
Suitable for:
Projects of a special nature (where only a small number of contractor are able to
perform)
Advantages:
Not time consuming
Disadvantages:
May cost more than other tender types
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
24/44
Tender
The tender process is the process of choosing a contractor to execute the design works; it is of different
types, some of which are:
• Open/General tender: owner announces project in public and any contractor can submit;
Suitable for:
Generally all project, specially government projects (because of administrative
restrictions)
Advantages:
Ensures high competition thus lower cost
Disadvantages:
Time consuming
Unqualified tenderers may be choosen
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
25/44
Tender
The tender process is the process of choosing a contractor to execute the design works; it is of different
types, some of which are:
• Selected/Limited tender: owner announces project to the previously pre- qualified short listed
contractors;
Suitable for:
Generally all project, specially large projects
Advantages:
Ensures high quality a contractor is pre-qualified
Disadvantages:
Time consuming (but less than Open/General tender, due to the lower number of
tenderers)
Less competition, higher cost
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
26/44
Tender
The tender process is the process of choosing a contractor to execute the design works; it is of different
types, some of which are:
• Open/General practice: similar to open/general tender expect that the owner negotiates publicly to get lowest
price “reverse auction” while standardizing all other criteria.
• Selective/Limited practice: similar to open/general practice expect that the owner negotiates with selected
contractors to get lowest price.
• Note that:
1. The negotiations are made either in a negotiation meeting (with all the tenderers present) or via
correspondents .
2. The owner informs the tenderers with their competitors offers’ so that each tenderer (if he wishes)
would lower his offer, in order to be choosen by the owner.
3. The problem with practices is that it may cause tenders to submit initially higher offers (as they know
that these offers will be lowered in the negotiation process).
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
27/44
• A Contract is an agreement made in good faith between 2 or more capable parties to perform an
act for a certain specific purpose.
• In construction field the contract is usually between owner and contractor to perform
construction services.
• The Contract is a legally bidding document that defines exactly the rights and obligations of each
party in the contract.
Steps to contract:
1. Invitation to bid/tender (Tender Process) from Owner “party A” to Contractor “party B" to
perform a certain task or a service with certain conditions.
2. Offer (tender/bid) from the Contractor (B) is made to the Owner (A) to perform the task
(complying with all or some of the conditions)
3. Acceptance where the Owner (A) has the right to accept or refuse the Contractor (B) offer, if
accepted then a contract is born (legally bidding for both parties).
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
Contracts
-
8/20/2019 Introduction to Construction Contracts
28/44
Types of Contracts
Contract can be categorized according to the payment method, such categories include:
• Fixed price contracts
Lump sum: a pre-determined fixed priced is set for all project/items; price includes overhead, profit
and all other necessary costs, this price can be paid:
Once the project is delivered
According to work progress (time progress or quantity progress or percent progress)
In this type of contract:
The scope should be fully detailed
No or minimal changes should be allowed during execution
Fair mechanisms for long – term risk allocation should be placed in the contract (ex. Escalation
Formula).
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
29/44
Types of Contracts
Contract can be categorized according to the payment method, such categories include:
• Remeasure contracts
Unit price: (most common contracts) where a fixed unit price (price/quantity “unit”) is pre-
determined for each work item which includes all necessary costs; here the contract is remeasured i.e.
exact contract cost depends on the actual quantities executed, the price can be paid:
According to a BOQ containing estimate quantities (most common)
Rate Only (suitable for small works, maintenance works or rehabilitation works), rates may be
over priced as there is no quantities to place rates on.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
30/44
Types of Contracts
Contract can be categorized according to the payment method, such categories include:
• Cost reimbursement contracts
Where the contractor agrees to perform the work for certain price which includes:
1. Direct cost of the item plus,
2. A certain pre-defined fee which covers the profit & overhead.
The different types of the cost reimbursement are:
Cost plus percentage fee
Cost plus fixed fee
• Target cost contracts
Where a target cost is set , whatever the final cost turns out to be, the saves/losses are divided
between the owner and the contractor.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
Construction Contracts Types & Risk
-
8/20/2019 Introduction to Construction Contracts
31/44
Construction Contracts Types & Risk
Max.
Min.
Max.
Max.
Max.
Min.
Max.
Min.
Min.
Min.
Little
Alot
Little
Alot
Owner Risk
Contractor Risk
Owner Control
Control Effort
Design Changes
Info.
required
for tender
Info.
required
for control
Lump Sum
Unit Price
Target Cost
Cost + Fixed Fee
Cost + % Fee
Risk Distribution & Contract Types Price/Contract
-
8/20/2019 Introduction to Construction Contracts
32/44
Risk Distribution & Contract TypesCost Plus
Contracts
Remeasure
Contracts
(Red Book )
Target
Cost
Contracts
Design – Build
(Yellow Book )
Contractor
Risk Increase
Employer
Risk Increase
Contract Financing Risks are carried by Employer
Site, Work Quality & Contractor’s Crew Risks are carried by Contractor
Force Majeure Risks are carried by Employer Insurable FM
Un - Insurable FM
Traditional
Contracts
EPC/ TurnkeyContracts
EPC/Turnkey
(Silver Book )
Contractor
carries all
the risks
with
limited
chances of
claiming
extension oftime or
additional
costs
Turnkey,
BOT, BOOT,
etc…. R i s k A l l o c a t i o n
Price/Contract
Type Relation
-
8/20/2019 Introduction to Construction Contracts
33/44
FIDIC
• FIDIC (Fédération Internationale des Ingénieurs – Conseils or International
Federation of Consulting Engineers) is an international federation ofassociations of consulting engineers representing the profession in their
respective countries.
• FIDIC's Contracts Committee is responsible for producing the most commonly
used standard forms of contract for international construction projects.
• FIDIC contracts are generally known by the color of their cover: the Red Book ,
Yellow Book , Silver Book , Green Book , Pink Book , Gold Book , Blue Book and
White Book .
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
34/44
FIDIC Forms of Contracts
• Main Forms of Contract before 1995 included:
1. From1913
(establishment ofFIDIC
) till1957
,FIDIC
didn’t
produce any form of contracts.
2. In 1957, the 1st edition of “Conditions of Contract for Works of Civil Engineering
Construction” was published and its cover was red.
3. In 1962, the 1st edition of “Conditions of Contract for Electrical and Mechanical Works –
Including Erection on Site” was published and its cover was yellow.
4. In 1969, the 2nd edition of “Conditions of Contract for Works of Civil Engineering
Construction” was published and its cover was also red.
5. In 1977, the 3rd edition of “Conditions of Contract for Works of Civil Engineering
Construction” was published and its cover was also red.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
35/44
FIDIC Forms of Contracts
• Main Forms of Contract before 1995 included:
7. In 1980, the 2nd edition of “Conditions of Contract for Electrical and Mechanical Works –
Including Erection on Site” was published and its cover was also yellow.
8. In 1987, the 3rd edition of “Conditions of Contract for Electrical and Mechanical Works –
Including Erection on Site” was published and its cover was also yellow and the 4th edition
of “Conditions of Contract for Works of Civil Engineering Construction” was published and
its cover was also red, the covers were internationally recognized and the contracts were
known as Red Book and Yellow Book .
9. In 1995, the FIDIC published of 1st edition of “Conditions of Contract for Design-Build and
turnkey” and its cover was orange.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
36/44
FIDIC Forms of Contracts
• Other Forms of Contract included:A. Client/Consultant Model Service Agreement
1. In 1990, the 1st edition of “Client/Consultant Model Service Agreement ” was published and its
cover was White.
2. In 1991, the 2nd edition of “Client/Consultant Model Service Agreement ” was published and
its cover was also White.
3. In 1998, the 3rd edition of “Client/Consultant Model Service Agreement ” was published and
its cover was also White.
4. In 2006, the 4th edition of “Client/Consultant Model Service Agreement ” was published and
its cover was also White.
B. Sub-Consultant Agreement & Joint Venture Agreement
1. In 1992, the 1st edition of “Sub-Consultant Agreement ” was published and 1st edition of “Joint
Venture (Consortium) Agreement ”.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
37/44
FIDIC Forms of Contracts
• Other Forms of Contract included:
C. Sub-Contract Agreement
1. In 1994, the 1st edition of “Sub-Contract Agreement ” was published and its cover was
red in relation with the “Conditions of Contract for Works of Civil Engineering
Construction”.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
38/44
FIDIC Forms of Contracts
• Main Forms of Contract after 1995 :
After publishing the Orange Book in 1995, FIDIC formed a committee to update theRed and Yellow Books (Red Yellow Update Committee) which took into
consideration the following:
1. Simplifying the language that is used in the forms
2. Unifying the numbering & language formats in all the forms
3. Re-drafting the contracts not based on work but based on the risk allocation
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
39/44
FIDIC Forms of Contracts
• Main Forms of Contract after 1995 :
In conclusion the following were produced:
1. New Red Book : Conditions of Contract for Construction for Building and Engineering
Works Designed by the Employer, where the Employer (his representative, Engineer, …)
supplies design of the Works (which could include: civil, electrical, …) (some designs may
be presented by the contractor, for which he carries their liability)
2. New Yellow Book : Conditions of Contract for Plant and Design-Build, where the
Contractor designs and builds the Works (which could include: civil, electric, …),recommended for plant (where major work is electrical or mechanical).
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
40/44
FIDIC Forms of Contracts
• Other Forms of Contract published after 1995 included:
1. Silver Book ”Conditions of Contract for EPC/Turnkey Projects”: recommended for turnkey
mega projects (infra structure, mega project, …) here contractor carries total responsibility for
design and execution (with little involvement of the Employer) to produce a fully equipped
facility for operation.
2. Green Book ”Conditions of Short Form of Contract ”: due to the negative criticisms on the Red
book for not being fit for use for small projects (low capital, short duration, low risk) or
repetitive projects.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
41/44
FIDIC Forms of Contracts
• By September 1999 the FIDIC published four new suits:
New Red Book : Conditions of Contract for Construction for Building andEngineering Works Designed by the Employer.
New Yellow Book : Conditions of Contract for Plant and Design-Build.
Silver Book : Conditions of Contract for EPC/Turnkey Projects.
Green Book : Conditions of Short Form of Contract .
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
42/44
FIDIC Forms of Contracts• Now FIDIC package includes:
Red Book : Conditions of Contract for Construction for Building and Engineering
Works Designed by the Employer 1st Ed. 1999.
Construction Subcontract 1st Ed. 2011.
Yellow Book : Conditions of Contract for Plant and Design-Build 1st Ed. 1999.
Silver Book : Conditions of Contract for EPC/Turnkey Projects 1st Ed. 1999.
Green Book : Conditions of Short Form of Contract 1st Ed. 1999.
Pink Book : FIDIC conditions incorporated in the standard bidding documents of
multilateral development banks June 2010 Ed. Gold Book : FIDIC Design, Build and Operate Projects 1st Ed. 2008.
Blue Book : Contract for Dredging and Reclamation Works 1st Ed. 2006
White Book : Client/Consultant Model Services Agreement 4th Ed. 2006.
Sub-Consultancy Agreement 1st Ed. 1992.
Joint Venture (Consortium) Agreement 1st Ed.1992.
Model Representative Agreement 1st Ed. 2013.
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
43/44
FIDIC Forms of Contracts
Construction
Projects
ProjectDeliverySystem
Tenders ContractsConstruction
ContractsFIDIC
-
8/20/2019 Introduction to Construction Contracts
44/44
The End
By Eng. Ahmed Moustafa Mohammed
• Email: [email protected]
• Facebook account: http://www.facebook.com/eng.ahmed.moustafa.mohammed
•
mailto:[email protected]://www.facebook.com/eng.ahmed.moustafa.mohammedmailto:[email protected]:[email protected]://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedhttp://www.facebook.com/eng.ahmed.moustafa.mohammedmailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]