    PERANCANGAN PABRIK

    Dr.rer.nat. Ir. Yuswan Muharam, MT

    Ir. Dijan Supramono, MSc.

  • 8/12/2019 Introduction Pabrik

    2/9

    Buku Ajar Introduction

    Feasibility Study

    Preliminary Design Conceptualization and Analysis of Chemical

    Processes: Input Information, Input-outputStucture of the Flowsheet, Recycle Structure

    of the Flowsheet, Separation System, HeatExchanger Networks

    Contract Writing and Forms of Contract,Execution of the Project, Computer Support,

    Quality Assurance

  • 8/12/2019 Introduction Pabrik

    3/9

    Buku Ajar Lorenz T. Biegler dkk., Systematic

    Methods of Chemical Engineering

    Design,

    JM Douglas, Conceptual Design ofChemical Process,

    Robin Smith, Chemical Process Design.

  • 8/12/2019 Introduction Pabrik

    4/9

    Evaluasi PR (30%)

    UTS (30%)

    Tugas proyek (40%)

  • 8/12/2019 Introduction Pabrik

    5/9

    IntroductionSince the 1930s, the design and construction of chemical plants have become

    increasingly specialized.

    Chemistsand engineerscollaborate to develop process and engineering

    concepts, which engineersand designersthen transform into detailed plans

    and specifications for all the components of a chemical plant.

    Purchasing agentsprocure equipment from specialist manufacturers.

    Construction and installation firmsare put under contract to build the plant.

  • 8/12/2019 Introduction Pabrik

    6/9

    IntroductionPlant design and construction starts as an idea of the potential owner.

    Increasingly complex markets and the interrelations of the world economic and

    political systems require critical examination of every project for feasibility,

    economic relevance, and environmental impact.

    As a rule, this is done with the aid of a feasibility studythat includes preliminary

    design work.

    Market analysesare carried out to determine potential sales, future demand

    dynamics, availability of raw materials, and the competitive situation.The plant capacityand locationare specified.

    Particular attention must be paid to environmental protection.

    Studies are supplemented by sufficiently accurate estimates of capital

    requirements and profitability.

  • 8/12/2019 Introduction Pabrik

    7/9

    IntroductionOnce the decision has been made to go ahead with the construction project,

    whereby the owner may have opted not to carry it out himself, the owner will

    prepare an accurate, comprehensive definition of the plant which is used as

    the basis for inviting bids from competent engineering contractors.

    This approach is increasingly employed, especially for large projects.

    If the owner has an adequate pool of experienced design engineers, construction

    specialists, and procurement staff, he may plan and construct the plant himself.

    The conceptual phase of the project ends when an appropriate engineeringfirm is chosen and the contract signed.

  • 8/12/2019 Introduction Pabrik

    8/9

    IntroductionThe implementation phaseconsists of the engineering of the chemical plant,

    procurement of plant equipment and material, construction, and commissioning.

    The engineering contractor either performs all of these tasks or brings in

    subcontractors or personnelemployed by the owner to carry out a portion of

    the work.

    Plant equipment is fabricated by specialized manufacturers.

    Only in rare cases does the engineering contractor or the plant owner have

    production facilities.

  • 8/12/2019 Introduction Pabrik

    9/9

    IntroductionFig. 1: a schematic diagram of the development of a chemical plant project.