    INTRODU TION TO

    MI ROSOFT PROJE T

  • 8/10/2019 Introduction on Microsoft Project

    2/20

    Opening Software

    To start, click Start program, then All Program, thenMicrosoft officeand then click Microsoft Project 2003 icon.

  • 8/10/2019 Introduction on Microsoft Project

    3/20

    MS Project Interface

    MENU

    SIDE

    PANEGANTT

    CHART

    TASK

    INFORMATION

    Microsoft Project 2003 default windows

  • 8/10/2019 Introduction on Microsoft Project

    4/20

    Create a New Project

    Click New

    The New button or you could choose to go File -> New

  • 8/10/2019 Introduction on Microsoft Project

    5/20

    Project InformationClick Project Informationon the Project menu. Type orselect a start date or a finish date for your project, andthen click OK. You will have to select Schedule from.

  • 8/10/2019 Introduction on Microsoft Project

    6/20

    Cont..

    The date will appearautomatically when you finishentering the Task Name

  • 8/10/2019 Introduction on Microsoft Project

    7/20

    Save the File

    File -> Save or Save As

    In the File name box, type a name for your project, andthen click Save

  • 8/10/2019 Introduction on Microsoft Project

    8/20

    Properties On the Menu, click Properties, and then click the Summary

    Tab.

    Key in the Title of your project and Company Name andother information.

  • 8/10/2019 Introduction on Microsoft Project

    9/20

    Enter and Organize a Task List

    On the ViewMenu, click Gantt Chart.

    In the Task Name field, type a task name, and then pressTAB. Microsoft Project enters an estimates duration of oneday for the task followed by a question mark.

  • 8/10/2019 Introduction on Microsoft Project

    10/20

    Duration

    The next step is to define the duration of all the tasks.

    Again, you will draw upon the experience and knowledge ofthe Project Managerand the participants.

    You want to obtain a value that is as possible for theduration of each tasks.

    That may have to be negotiated.

    Duration:Click in the duration column and key in theduration of the project ordouble click the field of duration,fill in Generalof Task Information.

  • 8/10/2019 Introduction on Microsoft Project

    11/20

    Cont..

    Key in the durationin 2 ways

    a. Manually

    b. Table of Task

    Information

  • 8/10/2019 Introduction on Microsoft Project

    12/20

    Task Dependencies

    One of the most reliable methods for scheduling tasks is toestablish relationships between them, that is, taskdependencies.

    Task dependencies reflect how later tasks, or successors,depend on the finish or start of earlier tasks, orpredecessors.

  • 8/10/2019 Introduction on Microsoft Project

    13/20

    Cont Finish to Start means that predecessors finishes before the

    next task begins.

    Lag time creates delay.(ex : you want a gap of 1d afterfinishing task 3)

    Lead time creates an overlap. (..the last 2 days of task 6and the first 2d of task 7 overlap)

  • 8/10/2019 Introduction on Microsoft Project

    14/20

    Cont

    Enter all task, duration, start date, relationship betweentask.

  • 8/10/2019 Introduction on Microsoft Project

    15/20

    Indent

    Select task then use Indent button to show that they aregrouped under the heading.

    A group barwill begenerated

  • 8/10/2019 Introduction on Microsoft Project

    16/20

    TimescaleDouble click at column timescale, Timescalebox willappear.

    Choose formatting of Middle Tier& Bottom Tier

    example :Year & Month / Month & Week

  • 8/10/2019 Introduction on Microsoft Project

    17/20

    Gantt Chart Wizard

    On the FormatMenu, click Gantt Chart Wizard. Select what kind of information do you want to display in

    your Gantt Chart.

  • 8/10/2019 Introduction on Microsoft Project

    18/20

    PDM/PERT Chart

    On the ViewMenu, click Network Diagram.

    Precedence Diagram will produce automatically.

  • 8/10/2019 Introduction on Microsoft Project

    19/20

    Page Set Up & Printing

    On the File Menu, click Page Set Up.

    Click Page, choose Landscapeand adjust scaling paper byclicking Fit to..

    Click Lagend, Add Project Title.

  • 8/10/2019 Introduction on Microsoft Project

    20/20

    Printing

    Click button Print Preview to see overall view