Intro to Ship Production
-
Upload
wawan-nur-cahyo -
Category
Documents
-
view
226 -
download
1
Transcript of Intro to Ship Production
-
8/12/2019 Intro to Ship Production
1/37
IntroductionIntroduction
Week 1Week 1
.T..T.. Faculty of Naval Architecture and Ocean Engineering. Faculty of Naval Architecture and Ocean EngineeringMethods of Ship ProductionMethods of Ship Production GEM314EGEM314E
-
8/12/2019 Intro to Ship Production
2/37
Objectives of the CourseObjectives of the Course
The main aim of this module is to equip students with methods and tools for
production of marine vessels. The objectives of the class are as follows: A good knowledge of methods and tools for production of marine vessels
An appreciation and good understanding of various issues in shipyard production operations.
An ability to analyse system requirements before choosing appropriate production methods andtools
Students will: Be given an understanding through practice of ship production
Observe a shipyard in action through the site visits
Be given instruction
Experience the process of technical report writing
On completing this course students should: Be familiar with the concepts of ship production system design
Recognise the main hardware elements of shipyards
Appreciate the relative merits of differing systems
Understand the technical, and economic issues
-
8/12/2019 Intro to Ship Production
3/37
Cou
rseOutlin
e
Cou
rseOutlin
e
EXAMD311
Mid-Term examination
(Multiple choice / Books open)EXAM
Week 9
12 April
AYO
General outfitting,
Subcontractors work,
Installation priorities, shafting, propellers,
piping, electrical installations
Outfitting and Machinary
installation
Week 8
5 April
Yldz TersanesiBaki Gkbayrak
Tel. 0216 395 4075
Fax. 0216 395 1290
Handling and storage,
forming, weldingAluminum construction
Week 7
29 March
Sedef TersanesiCumhur Kurtel
Sedef Gemi naatA..Tuzla/stanbulTel.0216 395 4741
Fax. 0216 395 4740
Shipyard facilities, process lanes
Material handling systems
Steel cutting and forming,
Steel fabrication
Shipyard Layout and Facility
Planing
Steel Prefabrication (Site visit)
Week 6
22 March
JOTUNMehmet Ali KamacoluJotun Boya Sanayi ve
Tic.A..Tuzla/stanbulTel. 0216 423 5170
Fax. 0216 423 5174
Abrasive blasting and priming, finish
coatingsSurface preparation and Painting
Week 5
15 March
AYOWelding in Shipbuilding (Theory)Welding BasicsWeek 4
8 March
AYO
Building methods, ship structures,
Product Work Breakdown Structure
(PWBS),
Group TechnologyPlanning and scheduing
Costing and value engineering
Shipbuilding Process and Project
Network Analysis
Week 3
1 March
IHHStatistical principles, overview,
Applications
Statitics, accuracy control and
tolerances
Week 2
22
February
AYO
Introduction to class.
Introduction to ship production.
A system view of the ship building.
Rules of the game
Introduction
Week 1
15
February
LecturersSubjectsTitle(Tuesdays-
1400-1700)
COURSE OUTLINE Spring 2005
-
8/12/2019 Intro to Ship Production
4/37
Cou
rseOutlin
e
Cou
rseOutlin
e(cont.)
(cont.)
YONTECHEkber Onuk
Yonca Teknik Tersanesi
Tuzla/stanbul
Tel.0216 392 9970Fax. 0216 392 9969
Materials, methods of productionFRP ConstructionWeek 12
3 May
Trk LoyduHasan HabiboluTrk Loydu VakfTuzla/stanbulTel.0216 446 22 40
Fax.0216 446 22 46
Welding procedures,Inspection of hull welding
Activities of classification societies
WeldingWeek 1126 April
OerlikonHac DolutaOerlikon Kaynak
Elektrotlar ve San.A..Sefaky/stanbulTel.0212 411 1400
Fax.0212 579 3053
Welding and cutting methods, structural
steels, non-ferrous alloys, non-metallic
materials, non-destructive testing,
Hull Materials and WeldingWeek 10
19 April
-
8/12/2019 Intro to Ship Production
5/37
Other ConditionsOther Conditions
TERM-TIME ASSESSMENTS
Quantity Weight (@ points)
Mid-Term Examination 1 %20Quiz 4 %20
Assignment 2 %20
Attendance Compulsory
Contribution of term work on achievemet scores : % 60Contribution of final exam scores on achievement scores : % 40
Prerequisites for attending final exam :
1) 70% attendance to class meetings.
2) Submission of reports in full and on given deadlines
-
8/12/2019 Intro to Ship Production
6/37
Forces in competitionForces in competition -- The BallThe Ball--GameGame
NEWSHIPYARDS
(e.g. FAR EAST)
NEWSHIPYARDS
(e.g. FAR EAST)
SHIP OWNERS(BUYERS)
SHIP OWNERS(BUYERS)
GOVERNMENTPOLICY
GOVERNMENTPOLICY
CHANGING FORCESCHANGING FORCES
SUBSIDY FORCESSUBSIDY FORCES
INTERNATIONALRULES AND
CONVENTIONS
INTERNATIONALRULES ANDCONVENTIONS
SUBCONTRACTORSAND SUPPLIERS
SUBCONTRACTORSAND SUPPLIERS
SUBSTITUTEPRODUCTS
SUBSTITUTEPRODUCTS
BARGAINING FORCESBARGAINING FORCES
COMPETINGSHIPYARDS
COMPETINGCOMPETINGSHIPYARDSSHIPYARDS
-
8/12/2019 Intro to Ship Production
7/37
Competition and Turkish Shipbuilding IndustryCompetition and Turkish Shipbuilding Industry
?
Direction .
Direction 2
Direction 1 ?
FUTUR% 40
TURKISHSHIPBUILDING
INDUSTRY
Environment
JAPAN
?
?
?
?< % 1
USA
%
17
% 21
% 20
RUSSIA
POLONDUKRAINE
CHINAVETNAM
NORWAY
EU
SOUTHKORE
-
8/12/2019 Intro to Ship Production
8/37
Marketing TechniquesMarketing Techniques
Right product
Right market
Right price and payment terms
Right marketing tools
Customer relations
-
8/12/2019 Intro to Ship Production
9/37
Order Winning CriteriaOrder Winning Criteria -- Ship OwnerShip Owners Point of Views Point of View
Price and payment conditions
Quality
Delivery Time
Shipyard reliability
Customer relations
-
8/12/2019 Intro to Ship Production
10/37
ShipbuildingShipbuildingDefinition and Key IssuesDefinition and Key Issues
Ship production is a manufacturing operation whereby procured material, machinery and equipment
is converted into a defined functional product (i.e. Ship, offshore platform, etc) through organized
use of knowledge purchased material, labor and shipyard facilities.
Knowledge manifests itself in design (especially through adopted design standards and production-kindly practices), production methodology, process engineering (methods, jigs & tools), production
and procurement planning and programming and quality management. Information flow is a key
issue in productivity management and improvement.
Shipyard facilities dictate what is not possible. As such in the development of a productionmethodology available facilities play a significant role.
Management of labor is both a technical and management issue. On the technical side topics such as
information of construction logic, methods, labor skills and the design and use of appropriate jigs and
tools play on important role. The management side involves the operational effectiveness of labormix and their control.
Flows Coordination of information, material and work flow are indispensable contribution in
successful ship production.
-
8/12/2019 Intro to Ship Production
11/37
CONCEPT DESIGNCONCEPT DESIGN
The objective of the conceptual design stage can be stated to be: To establish overall features of a design to meet owner or missionrequirements.The content of the stage can be defined as a series of inputs and outputs. Inputsmay be presented in the form of an outline specification, or one may be developed
as a basis for the conceptual design. Inputs and outputs are listed below:Inputs - Service requirements
- Routes- Market forecasts
- Technical change in ship components and equipmentOutputs - Preliminary general arrangement, midship section- Preliminary specification- Preliminary calculations (dimensions, capacities, etc)- Preliminary body plan
If at this stage a shipbuilder has been identified, the following production inputsand outputs are essential:Production Inputs - Shipbuilding policy
- Type plan- Facility dimensions
- Interim product typesProduction Outputs - Preliminary block breakdown
- Zone identification
-
8/12/2019 Intro to Ship Production
12/37
-
8/12/2019 Intro to Ship Production
13/37
-
8/12/2019 Intro to Ship Production
14/37
CONTRACTCONTRACT DESIGNDESIGN (2/2)(2/2)
Outputs - General arrangement, midship section- Specification- Body plan- Ship calculations- Propulsion calculations
- Accommodation arrangements- Machinery arrangements- Piping Diagrams- Electrical load analysis- Plan list
Production Outputs - Preliminary build strategy:planning units
- Equipment identification.long lead items
- Material requirements:quantitieslong lead
-
8/12/2019 Intro to Ship Production
15/37
Contract DesignContract Design -- OutputsOutputs
-
8/12/2019 Intro to Ship Production
16/37
FUNCTIONALFUNCTIONAL DESIGNDESIGN
Functional design follows contract signing and is intended to establish features ofa design for the purposes of classification and other approval and materialspecification, The various inputs and outputs are listed below:Inputs - Contract design
- Functional requirements
Production Inputs - Preliminary build strategy- Standards- Production Processes- Facilities
Outputs - Ship design: hull form, capacities, etc- Structural design: approval drawings, scantling plans- Machinery installation: arrangements, piping diagrams
electrical fittings, etc.- Accommodation design
- Ship systems design- Hull outfitProduction Outputs - Contract build strategy
- Schedules:erection/installation, assembly,manufacture
- Production information- Purchasing information
-
8/12/2019 Intro to Ship Production
17/37
Functional DesignFunctional Design -- OutputsOutputs
-
8/12/2019 Intro to Ship Production
18/37
TTRANSITIONRANSITION DESIGNDESIGN
Transition design is considered here as a distinct stage, although in some aspectsit runs parallel to the functional design process through all the stages.
The objective of transition design is to translate the features of the design from thesystem orientation, necessary to establish functional performance, to a planning
unit orientation, necessary to establish production requirements.
Transition design develops elements of systems into steel and outfit zonecomposites. It should be based on the spatial analysis of earlier design stages.
However, for effective design for production to take place, production needs andcapacities should be highlighted from the earliest stage:Inputs - Conceptual design
- Contract design
- Functional designOutputs - Process analysis- Interim products- Work package information- Work station drawing information
-
8/12/2019 Intro to Ship Production
19/37
Transition DesignTransition Design -- OutputsOutputs
-
8/12/2019 Intro to Ship Production
20/37
DETAILDETAIL DESIGNDESIGN
The objective of detail design is to establish the features of the design necessary toallow local purchasing, part manufacturing and subsequent assembly to be carriedout.
Detail design is carried out by planning unit, on those elements of the ship which
have been developed to the stage where all functional and approval requirementshave been satisfied.
It can be defined in terms of inputs and outputs:Inputs - Functional design
- Transition design- Build strategy- Standards- Work station capacities
- Process analysisOutputs - Work instructions- Work station drawings- Material lists- Dimensional requirements
-
8/12/2019 Intro to Ship Production
21/37
Detail DesignDetail Design -- OutputsOutputs
-
8/12/2019 Intro to Ship Production
22/37
DESIGN FOR PRODUCTIONDESIGN FOR PRODUCTION && PRODUCIBILITYPRODUCIBILITY
Preparing design with full cognition of production facilities anddifficulties in fabrication and erection is known as design for production.
The main issues of design for production are:o Reduction of variety and use of standard detailso Use of standard componentso Employment of modularity and cellularity concepts for
distributed systemso Full knowledge of shipyard production facilities and
capabilities
The main elements of design for production are establishment of
shipyard standards and continuing dialogue between designers, planners,procurement and production personnel.
.
P d ibilit i H ll F
-
8/12/2019 Intro to Ship Production
23/37
ProducibilityProducibility in Hull Formin Hull Form
P d ibilitP d ibilit i St t l D ii St t l D i
-
8/12/2019 Intro to Ship Production
24/37
ProducibilityProducibility in Structural Designin Structural Design
Rationalisation of Bulkhead arrangement
Appropriate choice of panel & grillage
configuration
Use of standard for plates & stiffeners
Use of standard 2-D element
Straight line brackets Reduction of lugs
Asymmetric face flats
Thin panel deflection avoidance
Tolerance selection
Co-ordination with HM & E design groups
A)
Gross weight higher
More difficult scrap
arrangement
Subject to buckling failure,
failure often seen at early
stage of hydrostatic test
before ship leaves yard
More difficult erection butt
and face plate welding - use
of alternative erection joints,
e.g. laps
B)
Net weight higher
Lower production hours du
to straight lines and machin
application
Subject to fatigue failure,
failure seen after a number
of years in service
Good for fast erection,
although accurate alignment
should be maintained
Lends itself to future morefundamental approach, e.g.
plastic design or bracketless
P d ibilitP d ibilit i D t il D i d F b i tii D t il D i d F b i ti
-
8/12/2019 Intro to Ship Production
25/37
ProducibilityProducibility in Detail Design and Fabricationin Detail Design and Fabrication
Method used by Shipyard A Method used by Shipyard B
Complete double bottom assembly
P d ibilitProducibility i E i i S tin Engineering System D is Design
-
8/12/2019 Intro to Ship Production
26/37
ProducibilityProducibility in Engineering Systemin Engineering Systems Designs Design
Requirement verification by functional system
evaluation techniques
Adoption of design standards ( A restrictedsubset)
Use of modular component
Clash avoidance by design
Design features to encourage pre-fabrication
(e.g. use of common supports for pipe & cable
highways)
Coordination with structural and other
engineering design groups
Space allocation for cable support structures
(Clash avoidance & Modularisation)
Product Life CycleProduct Life Cycle
-
8/12/2019 Intro to Ship Production
27/37
Product Life CycleProduct Life Cycle
equirements &
pecifications
Contract
Design
Detail Design
& Planning
Component
Production
Product
Integration
Installation &
Acceptance
Maintenance
Progression
Correction
DEFINITIONDEFINITION
-
8/12/2019 Intro to Ship Production
28/37
DEFINITIONDEFINITION
STANDARD
A standard is that which has been selected as a model to which objects or
actions may be compared.In every case, a standard provides a criterion for Judgement and its form thusdepends on what is to be Judged and how it is to be Judged.(From Encyclopedia Britanica)
STANDARDIZATION
The process of developing and bringing about the utilization of standards.While standardization of some kind or degree is part of almost every humanactivity planned and systematic industrial standardization is meant in normalusage of the term.(From Encyclopedia Britanica)
.
TYPE OF STANDARDSTYPE OF STANDARDS
-
8/12/2019 Intro to Ship Production
29/37
TYPE OF STANDARDSTYPE OF STANDARDS
INTERNATIONAL STANDARDS
ISO (International Organization for Standardization)IEC (International Electrotechnical Committee)
REGIONAL STANDARDS
ASAC (Asian Standards Advisory Committee)CEN (European Committee for Standardization)
NATIONAL STANDARDS
JIS (Japanese Industrial Standards)
BS (British Standards)DIN (Deutche Normen)ANSI (American National Standards)NF (Norm Franaise)Others
INDUSTRIAL ORGANIZATION STANDARDSASTM (American Society of Testing and Materials)ASME (American Society of Mechanical Engineers)SAE (Society of Automotive Engineers)Others
COMPANY INTERNAL STANDARDS
CATEGORIZATION OF COMPANY INCATEGORIZATION OF COMPANY IN--HOUSE STANDARDSHOUSE STANDARDS
-
8/12/2019 Intro to Ship Production
30/37
CATEGORIZATION OF COMPANY INCATEGORIZATION OF COMPANY IN--HOUSE STANDARDSHOUSE STANDARDS
1 Part and Product Standards (Hard)
2 Design Engineering Standards (Soft)
3 Production Process Standards (Soft)
4 Testing and Inspection Standards (Soft)
5 Accuracy and Tolerance Standards (Soft)
STANDARDIZATION GOALS (1/2)STANDARDIZATION GOALS (1/2)
-
8/12/2019 Intro to Ship Production
31/37
STANDARDIZATION GOALS (1/2)STANDARDIZATION GOALS (1/2)
Standardization goals should be planned and developed to provide full benefits to the entire company
including ship owners, vendors, regulatory bodies, etc. The following items indicate the goals whichshould be pursued:
1. Design and Engineering Simplification and improvement of communications between related parties Reduction of design/engineering manhours
Enhance reliability of design/engineering plans Simplify approval procedures and reduce approval time Minimize design changes Improve product quality and reliability Avoid over design due to multiple requirements
2. Purchasing Improve communications with vendors/suppliers Shorten delivery time Minimize custom made products Simplify purchasing procedures
3. Vendors/Suppliers Stabilize technical level and improve product quality Improve production methods Simplify or eliminate approval procedures Improve, product reliability
STANDARDIZATION GOALS (2/2)STANDARDIZATION GOALS (2/2)
-
8/12/2019 Intro to Ship Production
32/37
STANDARDIZATION GOALS (2/2)STANDARDIZATION GOALS (2/2)
4. Inspection Minimize repetitious inspection Eliminate overlapping and duplication of inspection by regulatory agencies Reduce inspection time/cost
5. Product Accuracy Unify product accuracy Improve product reliability and safety
6. Production Methods Improve producibility, productivity and safety Improve production methods
7. Shipowner / Operator Improve communications with shipyard Improve operation efficiency by applying products with proven reliability, performance and
safety Improve interchangeability of components Improve ability to obtain spare parts from other than the original equipment manufacturer
8. Regulator Bodies/Classification Societies Simplify approval procedures and reduce workload Reduce testing/inspection workload Improve communication with shipyards vendors
Management of Technology in Successful OperationsManagement of Technology in Successful Operations
-
8/12/2019 Intro to Ship Production
33/37
Management of Technology in Successful OperationsManagement of Technology in Successful Operations
THEME FACTORS INFLUENCING ITS DEVELOPMENT
Technological development is
evolutionary; progress occurs in steadyand successive steps.
A close and intimate interaction
between technology development work
and potential problems (in plant or
market) is essential.
Product and process innovation are
intimately related.
Progress occurs through organised
effort; team-work and collaboration
across functional boundaries and critical.
Industrial labs and R&D organisations
regarded as an aid to practical problemsolving; dependent on the training and
experience of supervisors and middle
managers.
Long and Short Term needs determine
the research agenda; orientation of R&D
personnel to practical affairs.
Origins in chemical and electricalindustries; existing equipment and
methods considered always improvable.
Complexity of products; systematic and
integrative nature of innovation.
Technical and Economic Success in Technology ImprovementTechnical and Economic Success in Technology Improvement
-
8/12/2019 Intro to Ship Production
34/37
Technical and Economic Success in Technology Improvementgy p
ECHNICAL SUCCESS : Technical success refers to the successful implementation of a neoperating technology which provides reductions in errors and effor
requirements due to the elimination of paper driven steps, growth i
enabling capability and functionality and improved change
management.
CONOMIC SUCCESS : Economic success refers to the realisation of productivity increase,non-productivity benefits (e.g. reduced lead time, quality
improvements, increased flexibility etc.) and translation of thesebenefits into cost reduction and competitive gain.
DESIGN AND DATA INTEGRATION CONTRIBUTE MAINLY TODESIGN AND DATA INTEGRATION CONTRIBUTE MAINLY TOTECHNICAL SUCCESS WITH TANGIBLE ECONOMIC GAINSTECHNICAL SUCCESS WITH TANGIBLE ECONOMIC GAINS
REAL ECONOMIC SUCCESS IS ACHIEVED THROUGHREAL ECONOMIC SUCCESS IS ACHIEVED THROUGH
DECISION AND ORGANISATION INTEGRATIONDECISION AND ORGANISATION INTEGRATION
The Manufacturing CycleThe Manufacturing Cycle
-
8/12/2019 Intro to Ship Production
35/37
g yg y
Management
Forecasting &
customer orders
Master production
schedule
Requirement plannin
Capacity planning
Purchasing
Dispatching
Expediting
Job recording
Shop floor
Engineering design
Engineering drawing
Process planning
Methods, time and
motion study
Routing
Inventory control
Auxiliary services
NEXT WEEK :NEXT WEEK : DEFINITIONS...DEFINITIONS...
-
8/12/2019 Intro to Ship Production
36/37
Task : to search, find and present the definitions of the following words in the
context of GEM314E course
effectiveness
efficiency
productivity
utilisationperformance
capacity
End of Week 1End of Week 1
-
8/12/2019 Intro to Ship Production
37/37
Questions ?Questions ?