Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design...

35
Internal information 2010-10-13 / Carl Jonsson 09:00-11:00 Industrialisation through design 2010-10-13 Solna [email protected] e Skanska Teknik

Transcript of Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design...

Page 1: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

09:00-11:00 Industrialisation through design2010-10-13 Solna

[email protected]

Skanska Teknik

Page 2: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Industrialisation through designHow the principles of industrialisation works in our projects

− Projects using in-house developed production systems

− Other projects

OWOW

Non defined client

Architect competitionOne off

Conglomerate of previously used

solutions

Exchange

IPComponents

Platform

Integrated activities

Coding systemDefined client

Rules

Page 3: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Main topics

Setup of a production system

Important elements in the design process

Examples

Page 4: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Main topics

Setup of a production system

Important elements in the design process

Examples

• Requirement handling• Platform• Process• Compliance verification• Cooperation agreements• Supply chain• Manual

Page 5: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

M2-1

M2-2

M2-3

Current M2 harmonizedFinalized products implemented

Nordic

Nordic

Setup of platform for multi family housing

Nordic

Raised floor

New platform based on req from other values

• Three platforms that can be used on a Nordic level• Each platform optimized for specific values• Skanska’s production system for multi less sensitive to

market situation (suppliers, factories, internal resources)

• The three platforms can be used to control and benchmark both the suppliers’ and our own efficiency

• Increased focus to continuously improve production system, initially phases 2 and 3 of IP.

• Measures taken to establish processes with prioritized suppliers (IPN, Skanska Installation)

?M2-1

M2-2

M2-3

Page 6: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Requirement handling

• Efficiency (cost, speed, labor)• Aesthetics• Industrialization• Universal design & Geometry• Robustness, rigidity, durability• Acoustics• Fire• Hygiene, health, environment• Energy efficiency• Safety in use• Sustainability

2. Express each requirement or group of requirements to one or more properties

1. Collect requirements

• RDN requirements• CS requirements• Building codes

• Platform• Components

• IP

3. Transpose property requirements to appropriate parts of production system

6. Create Project Plan

Development deliverables

• Orientation• Scope• Prerequisits• Goals• …

7. Develop (process detailed separately)

4. Express production system attributes

Do the attributes fulfil the requirements?

• Platform• Components

• IP

No Yes

5. Check

Intermittent flow of new requirements

Page 7: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Requirements Attributes

Requirement handling based on consumer insight

Page 8: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

M2-1− Same as version 1.0 except what is brought up in this presentation

− Slab equals current Finnish solution with some modifications to it in order to work in Sweden and Norway

− Close to the current platform regarding interfaces, performance, assembly order etc. Issues that needs to be checked have been identified.

– Modifications concern both RDN requirement and production methods;

– Room heights 2.60m with 2.40m in hallway– Lack of equipment at suppliers in SE and NO– Electricity in the vicinity of electrical cupboard

220 Massive, HCS 27 or Compressed HCS 37

HCS 37

20 Levelling screed

Page 9: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

M2-1

− Platform Manual− Balcony connection details− Partition walls− Reference building− Building specification− Schedule of room finishes and external colour

scheme− Bathrooms and saunas− Roofs and terraces− Façade details− Slab details− Build up of terraced apartment floor− Soft joints in facade

− Doors− Railings for balconies, terraces and stairs− Substructure, garage, foundations− MEP specification: electricity,

communication and automation systems− MEP specification: air treatment system− MEP specification: plumbing and heating

system− Plant rooms− Fan rooms− Plumbing shaft− Ventilation distribution system in building

and in apartment− Electrical subcentral

Things that will be updated in version 2.0;

Page 10: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

M2-2− Raised floor

− General platform properties;− build up of floor with measurements− ventilation distribution system incl kitchen− air inlets, interior partitions and apartment partitions− electrical distribution− bathroom, balcony and stairway interfaces etc.

− The raised floor height is 200mm (185mm from HCS to top of particle board).

− The interior partitions will be put on top of the raised floor.

− Apartment partition walls shall be in concrete as a general rule. Deviations may occur in special cases like ground floor.

− A load-bearing “gable wall” will be proposed as a new platform solution (valid for both M2-1 and M2-2).

Page 11: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Supporting documents:SXCR Compliance Checklist updated by the project at each tollgate.Contains instructions for technical solutions and processes

SXCR Industrialised Process

2.1

Page 12: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Cooperation agreements

12

Page 13: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

1. Land acquisition and

zoning

2. Premarketing and design

3. Reservations, detailed design

and preconstruction

4. Sales and construction

5. Customer service

SXCR Compliance Checklist.xls follows the project

Commercial launch

approval

Investmentapproval

Supporting document:SXCR Compliance Checklist (Excel-file)

uppdateras av projektet inför varje tollgate.

SXCR Compliance Checklist innehåller alla regler för tekniska lösningar och processer

Conceptapproval

Projectapproval

Platform compliance

Page 14: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

SXC supply chain

• Site configuration• Substructures• Superstructures • Bathrooms• Prefab services• Sanitary and heating• Ventilation• Electricity, comm and automation• Elevators• White goods• Kitchens• Windows• Internal surfaces and detailing• Site surfaces and detailing • Painting• Tiles• Floors• Facades• Sheet metal

• Which subcontractors shall be procured?• Which works do we do ourselves?• Which contract types do we use for the different subcontracts?• Frame agreements vs local agreements?• How do we make it Nordic?

Interface list based on:

Page 15: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Performance and requirement description

1. Site configuration 2. Superstructure 3. Envelope 4. Services 5. Spatial division structures

6. Internal surfaces and detailing

7. Site surfaces and detailing

Platfom description + Platform compliance

checklist

3. Supporting documentsDrawings, BIM objects, specifications, technical information, based on SXC codes

2. Performance and requirement description Platform performace requirements etc. E.g. Fire, Aucoustics, Indoore climate, safety

1. Platform description + Platform compliance checklist

Manuals

- Rules, guidelines and examples- Technical specification templates- Type details- BIM objects

http://navigator.sxc.skanska.com

Page 16: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Page 17: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Main topics

Setup of a production system

Important elements in the design process

Examples

Page 18: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Buildingpermit

3.1Detailed Design

Concept Approval

Commercial Launch Approval

Design setup Multi 2.1 2.2 3.1 3.2 4.11.1Project phase 1.2 4.2 5

Construction documents

DesignStart-up

3.2Preconstruction

2.1Concept Development

2.2Design

CAD

Costing

Planning

1.450 EUR/m2

18 months

Create Improve VerifyDefine

SXC code

Page 19: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Phase 4;Preparation of As Built BIMs and documentation

Phase 3.2;Submittal of building and services documentation

Phase 3.1;Production cost estimate as basis for sales start (Commercial launch approval)

Phase 2.2;Tender estimate prior to building permit application. First time design integration.

Phase 2.1;Early estimate as basis for concept approval and comparison to target cost (Concept Approval)

Phase 1;Early estimate as basis for land purchase (Investment approval)

Design delivery schedules

Model and quantity deliveries at the following occassions;

In connection with:

3.1Detailed

design

3.2Pre-

construction

2.1Concept

development

2.2Design

4Sales &

Construction

5Customer

services

1.2Project

requirements

1.1Land screening &

analysis

All components and elements that shall be assembled in a project shall be illustrated and quantified.

Page 20: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Main topics

Setup of a production system

Important elements in the design process

Examples

Page 21: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Type details

• Roofs and roof terraces

• Facades

• Floors

• Balconies

• Stairs and railings

• Internal doors

• Soft joints for external walls

• Self compacting concrete

• Air handling unit

• Ventilation distribution system

• District heating central

• Plumbing shaft elements

• Electrical distribution system

Page 22: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Specification templates3.1

Detailed design

3.2Pre-

construction

2.1Concept

development

2.2Design

1.2Project

requirements

1.1Land screening &

analysis

General rules for contracts

EnergyEnergyAcousticsAcousticsGeoGeo MoistureMoisture

Communi-cation &

Automation

Interiorfinishes

Exterior finishes

Functional program

Tolerances and surfaces

Ventilation

Building specifi-cations

Electrical

Plumbing & Heating

Assortment database

Contract

FireFire

Admini-strative

directions

InterfaceLists Delivery

schedule

Project program

RDNSXCR

Page 23: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Building specification template

Instructions for project:

• Update document with project specific information

• Remove the instruction pages when the document is ready for send out

• Adapt or remove the red text in the template when the document is ready for send out

Page 24: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

MEP specification templates

Instructions for project:

• Update documents with project specific information

• Remove the instruction pages when the document is ready for send out

• Adapt or remove the yellow text in the templates when the document is ready for send out

Enclosures:• Template for control functions for AHU• Template for operating card for DHC• Template for reporting energy use• Standard for energy monitoring in apartments

Page 25: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Nordic Wetroom Elements

Page 26: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Contents of wetroom elements material

• Technical specification and requirements

• Overview of the 10 main apartment bathrooms, 3 secondary bathrooms/WCs and 10 bathrooms with sauna, scale 1:50

• Each wetroom type in scale 1:20

• Complementary drawings showing ceilings, slopes, elevations and technical information

• Assortment for wetrooms

Page 27: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Principles and layout examples for

• Car parking, storage, plant room etc• Terraces, courtyards and interfaces to superstructure• Dimensions and measurements

Solution principles for:

• In-situ and precast concrete• Services• Fire safety• Radon density• Waterproofing• Dewatering• Ramps

Garage, foundations, substructure

Page 28: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Reference Building

− Currently a Revit model showing a possible configuration for multi projects for IP phases 2 and 3.

Page 29: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Reference Building

− Intentions for having a Reference Building;− To use it to show the contents of the multi platform, good examples of placing bathrooms,

kitchen, shafts, layout of structure etc− To use it to show what we expect is carried out in the Revit model in phases 2 and 3

respectively− To show CAD drawing techniques like grid system, conventions, areas, measurements and

similar− To use it in estimates and production simulations− To use it in energy simulations− To use it in training, e.g. technical / BIM / procurement

and similar workshops

Page 30: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Content of IP phases- IP phase 2

- Quantified objects- Basic measurements- Locked layout

Page 31: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Content of IP phases- IP phase 3

- Increased level of detailing- Correlation to shop drawings

Page 32: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Quantity take-offs- From Revit Architecture

SXC codes in the estimation recipe

Page 33: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Quantity take-offs- From Revit Architecture

- Method shown below

ESTIMATE

Page 34: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Skanska Xchange Center Residential

Standardization and limiting assortmentModernaHus balcony

Type B1

Type C1

Type C2

Add-on: Glazing

SXC balcony

This is the case for most components

Max area: 12sqmMax weight: 10tonsThickness: 150 – 300mm

Design rulesBalconies shall be designed in accordnace with

”Construction principles” in the manual.

Design recommendations- Rectangular shape- Max 5 types per building- Do not use different detailing of balconies

in the same project

Recommended solution

Page 35: Internal information 2010-10-13 / Carl Jonsson 09:00-11:00Industrialisation through design 2010-10-13 Solna carl.jonsson@skanska.se Skanska Teknik.

Internal information2010-10-13 / Carl Jonsson

Stability

Quality

Delivery capability

Efficiency

Flexibility

Where is Skanska Sweden today?

Industrialisation & competitiveness

Time