    AUDIT CHECKLIST ISO 9001:2008

    Page : _____ of _____

    Dept. / Section : Audit Date : / /

    No

    ISO

    9001

    Clause

    Check ItemOK( )

    No ( X )Evidences

    1 4.1 The processes needed for the

    quality management

    system had been established and

    understood by all staffs

    All the requirements of the clause4.1 understood and adhered.

    2 4.2 All the documents required had

    been followed

    3 5.1 Top management fully committed

    4 5.2 Sales/Marketing highly customer

    focus

    5. 5.3 Staff knows the company policy

    and followed it their daily work

    6 5. 4.1 Quality objectives monitored and

    reported

    7. 5.5.1 Every staff knows their

    responsibilities

    8 5.5.2 Management Rep. played his roles

    effectively.

    9 5.5.3 Internal communication done

    effectively

    10 5.6 Management reviewed carriedeffectively.

    mailto:[email protected]:[email protected]
  • 7/27/2019 Internal Audit ISO 9001(2008) Checklists (EJJV)

    2/4

    Auditor

    :

    Name :

    Auditor

    Name :

    EJJV SDN BHD

    AUDIT CHECKLIST ISO 9001:2008

    Page : _____ of _____ Dept. / Section : Audit Date : / /

    No

    ISO

    9001

    Clause

    Check ItemOK( )

    No ( X )Evidences

    1 6.1 Company has sufficient resources;

    manpower, and materials.

    2 6.2.2 - Competence of staff identified

    - Staffs are trained

    - Ever staffs are given awareness

    on quality

    3 6.3 Infrastructures needed for the

    company sufficient

    4 6.4 Work environment found suitable

    Auditor

    :

    Name :

    Auditor

    Name :

    Rev. : 0

  • 7/27/2019 Internal Audit ISO 9001(2008) Checklists (EJJV)

    3/4

    EJJV SDN BHD

    AUDIT CHECKLIST ISO 9001:2008

    Page : _____ of _____

    Dept. / Section : Audit Date : / /

    No

    ISO

    9001

    Clause

    Check ItemOK( )

    No ( X )Evidences

    1 7.1 Planning of product realization

    effectively carried out

    2 7.2.1 Customer requirements are

    identified

    7.3 Control of design excluded &

    justified

    Ref. QM Sec.

    3 7.4.1 Processing processes were adhered

    4 7.4.2 Purchasing information clearly

    written and understood

    5 7.4.3 Purchased products received are

    verified prior to storage and used.

    6 7.5.1 Production is controlled

    effectively.

    7 7.5.3 Product identification and

    traceability carried out effectively.

    8 7.5.4 Customer property properly kept.

    9 7.5.5 Finished products were stored

    securely I the stores.

    10 7.6 All equipments used had been

    calibrated and maintained.

    Auditor

    :

    Name :

    Auditor

    Name :

  • 7/27/2019 Internal Audit ISO 9001(2008) Checklists (EJJV)

    4/4

    Rev. : 0

    EJJV SDN BHD

    AUDIT CHECKLIST ISO 9001:2008Page : _____ of _____

    Dept. / Section : Audit Date : / /

    NoISO9001

    Clause

    Check ItemOK( )

    No ( X )Evidences

    1 8.2.1 Customer satisfaction carried out.

    2 8.2.2 Internal audit carried out as required

    3 8.2.3 Processes are monitored and measured

    4 8.2.4 Products are monitored and measured

    5 8.3 Non conformance products are controlled effectively.

    6 8.4 Data collected hand been analysed.

    7 8.5.2 Root cause of the defective products identified and

    corrected.

    8 8.5.3 Potential problems identified and corrected.