Interim Facilities Report Quincy Public School District #172 September 25, 2013.
Interim Facilities Report
description
Transcript of Interim Facilities Report
Interim Facilities Report
Quincy Public School District #172September 25, 2013
Data Gathering
Data GatheringO Demographic InfoO Enrollment ProjectionsO Capacity AnalysisO Building Data RecordO Operating CostsO Renewal & Replacement ScheduleO Research on Facilities Condition & Student
Performance
2010 2011 2012 2013 2014 2015 2016 2017 2018 20190
5001,0001,5002,0002,5003,0003,5004,0004,5005,0005,5006,0006,5007,0007,5008,0008,5009,0009,500
10,000Quincy Public School District #172
Projected Enrollment Thru 2018-19
Defining CapacityO Building Planning Capacity
O student enrollment that a school can best serve while fully utilizing its physical facilities.
O combination of factors: O the number of teaching stations available, O the area of auxiliary spaces, and O the adopted program for a school of that level.
O Capacity number is used for planning proposes, O enrollment boundaries O building utilization levels.
O Each individually facility may be capable of handling physically many more students than its planning capacity,
O The Planning Capacity is a practical capacity that provides for an easily understood and comparable number between facilities, as well as, providing an optimal operating size.
Defining Capacity - Elementary
O Defined simply as 25 students per classroom multiplied by the number of classrooms
O Classroom Size Factor O Reduced by 2 students with an average classroom
size below 750 square feet O Reduced another 1 student if the average classroom
size is below 650 square feet. O For example, building has 15 classrooms; the
Planning Capacity would be 375, (25 x 15). If the room sizes were 725 sq. ft, the capacity would be 345, (23 x 15).
Defining Capacity – Junior High School
O The Junior High capacity is defined utilizing 150 students for every four classrooms and one science lab.
O Additionally, there is a minimum of one Art and Life Skills labs for every 750 students.
O Each Junior High will have a band room, general music/vocal room,
O Three rooms for special service programs
Defining Capacity – High School
O High School capacity is defined as 175 Students for every four classrooms and one science lab.
O One Art, Life Skills and Tech Arts Areas/Labs per 800 students.
O Other areas are required and are determined by the curriculum and extra-curricular activities. O band and vocal music facilitiesO performing arts areas O athletic facilities. O Six classrooms for special service programs.
Capacity AnalysisPlanning Capacity Capacity by Sq Ft
BUILDING NAMEGrades Served Gross Sq. Ft.
# of general purpose classrms Enrollment
Planning Class Size
FactorPlanning Capacity
Sq Ft per Student*
Sudent Capacity
ADAMS ELEMENTARY SCHOOL K- 3 46,145 21 406 25 525 114.6 403 BERRIAN ELEMENTARY SCHOOL K- 3 36,969 15 205 23 345 114.6 323 DEWEY ELEMENTARY SCHOOL K- 3 38,630 15 247 23 345 114.6 337 ELLINGTON ELEMENTARY SCHOOL K- 3 33,588 16 322 25 400 114.6 293 MADISON ELEMENTARY SCHOOL K- 3 44,392 17 416 23 391 114.6 387 MONROE ELEMENTARY SCHOOL K- 3 32,385 16 257 25 400 114.6 283 WASHINGTON ELEMENTARY SCHOOL K- 3 33,720 16 307 23 368 114.6 294
TOTAL K-3 265,829 116 2160 2774 2,320
BALDWIN INTERMEDIATE SCHOOL 4- 6 211,537 68 1476 23 1564 120.6 1,754
QUINCY J R HIGH SCHOOL 7- 9 303,504 76 1431 1583 127.4 2,382
QUINCY SR HIGH SCHOOL & VOC CTR 10- 12 260,509 75 1334 1,562.5 140.3 1,857
Building InformationO Building Data Record
O Building Age & Square FootageO Construction TimelineO Demographic Information
O EnrollmentO Free and Reduced Lunch
O Information on Program SpacesO Information on Building SystemsO TechnologyO Major Projects
O Floor PlansO Aerial Site PlanO Attendance Map
Operating CostsOPERATING COSTS
ADA BER DEW ELL IRV MAD MON WASH QJHS BALD QHS ECFC DIST. WIDE
TOTALS $69,095 $29,748 $28,485 $24,803 $13,497 $36,842 $40,233 $46,907 $177,353 $184,458 $196,659 $36,248 $195,965 1,080,294$
Square Footage 46,145 36,969 38,630 33,588 40,524 44,392 32,385 33,720 303,504 211,537 260,509 60,000 1,141,903 1,141,903 Costs per Square Foot 1.50$ 0.80$ 0.74$ 0.74$ 0.33$ 0.83$ 1.24$ 1.39$ 0.58$ 0.87$ 0.75$ 0.60$ 0.17$ 0.95$
UTILITY COSTSADA BER DEW ELL IRV MAD MON WASH QJHS BALD QHS ECFC DIST. WIDE
Total 56,033$ 37,195$ 34,406$ 32,108$ 16,045$ 41,634$ 28,270$ 40,630$ 232,042$ 178,364$ 372,697$ 71,771$ 1,141,197$
Square Footage 46,145 36,969 38,630 33,588 40,524 44,392 32,385 33,720 303,504 211,537 260,509 60,000 1,141,903 1,141,903 Costs per Square Foot 1.21$ 1.01$ 0.89$ 0.96$ 0.40$ 0.94$ 0.87$ 1.20$ 0.76$ 0.84$ 1.43$ 1.20$ -$ 1.00$
Labor CostsADA BER DEW ELL IRV MAD MON WASH QJHS BALD QHS ECFC DIST. WIDE
TOTAL 114,854$ 101,893$ 96,988$ 116,467$ -$ 106,456$ 93,135$ 98,488$ 372,233$ 532,648$ 434,975$ 136,006$ 975,746$ 3,179,889$
Square Footage 46,145 36,969 38,630 33,588 40,524 44,392 32,385 33,720 303,504 211,537 260,509 60,000 1,141,903 1,141,903 Costs per Square Foot 2.49$ 2.76$ 2.51$ 3.47$ -$ 2.40$ 2.88$ 2.92$ 1.23$ 2.52$ 1.67$ 2.27$ 0.85$ 2.78$
Building Square FootagesADA BER DEW ELL IRV MAD MON WASH QJHS BALD QHS ECFC DIST. WIDE
Square Footage 46,145 36,969 38,630 33,588 40,524 44,392 32,385 33,720 303,504 211,537 260,509 60,000 1,141,903 1,141,903 4.04% 3.24% 3.38% 2.94% 3.55% 3.89% 2.84% 2.95% 26.58% 18.52% 22.81% 5.25% 100.00% 100.00%
Total Costs 239,982$ 168,836$ 159,880$ 173,378$ 29,543$ 184,933$ 161,637$ 186,026$ 781,628$ 895,471$ 1,004,331$ 244,025$ 1,171,711$ 5,401,380$
Costs per Square Foot 5.20$ 4.57$ 4.14$ 5.16$ 0.73$ 4.17$ 4.99$ 5.52$ 2.58$ 4.23$ 3.86$ 4.07$ 1.03$ 4.73$
FY 2013
SystemYear
Installed
Remain-ing Life Span
Year work req'd
Year 1
Year 2
Year 3
Year 4
Year 5
Year 6
Site ImprovementsEED # xxxxxxxx Site UtilitiesDist. # xxxx-xxx Foundation/Substruct. 11,060 - - 393 - - X 11,453$
Superstructure 29,518 - - 1,126 - - X 30,644$ Exterior Wall System 17,553 - - - - - X 17,553$ Exterior Windows 2,076 - - - - - X 2,076$ Exterior Doors 894 - 29 - 93 39 X 1,055$ Roof Systems 6,297 - 4,077 297 733 - X 11,404$ Interior Partitions 9,534 - - - - - X 9,534$ Interior Doors 3,861 - - - - - X 3,861$ Interior Floor Finishes 6,180 4,566 - - 2,224 - X 12,971$ Interior Wall Finishes 4,860 - - - - - X 4,860$ Interior Ceiling Finishes 4,739 - - - - - X 4,739$ Specialties - - - - - - -$ Conveying Systems 330 - - - - - X 330$ Plumbing piping 4,576 - - - - - X 4,576$ Plumbing Fixtures 1,005 - - - - - X 1,005$ Fire Protect./Suppres. - - - - - - -$ HVAC Distribution 289 - - - - - X 289$ HVAC Equipment 7,894 - - - - - X 7,894$ HVAC Controls 2,101 - 163 1,660 377 325 X 4,625$ Electrical Serv./Gen. - - - - - - -$ Electrical Distribution - - - - - - -$ Electrical Lighting 4,442 - - - - - X 4,442$ Special Electrical 2,798 - 1,818 364 - - X 4,979$ Equip and FurnishingsTotals 120,008 4,566 6,088 3,839 3,426 364 Six Year Total
Building or Facility Use
Atta
ch S
urve
y if
incl
uded
in C
IP
Facility or Building
Name and/or Number
Replacement Value
NOTES
Number of Stories
Facility Cost Index
Gross Square Footage
Total Costs by System (in
dollars)
Current Dollar Value of Systems/Components that require Renewal or Replacement during Year
(in thousands of dollars)Building System Appraisal
138,292,188$
Renewal & Replacement Schedule
Quincy Public School District #172Technology by Building - 2012 - 2013
25-Sep-13
ADA BER DEW ELL IRV MAD MON WASH QJHS BALD QHS QAVTC ECFC Totals
Number of Classrooms 20 13 13 13 0 17 13 16 66 64 52 15 19 321
Number of Computers 42 14 31 13 0 30 30 19 95 84 83 79 0 520
Interactive Board, Projection, Doc Camera & Computer setup
14 13 13 10 0 9 10 14 6 29 13 0 0 131
Classrooms w/o Interactive Board Setup 6 0 0 3 0 8 3 2 60 35 39 15 19 190
Age of Computers 4 - 6 yrs 4 - 5 yrs 4 - 5 yrs 4 - 5 yrs 0 4 - 7 yrs 4 - 5 yrs 4-5 yrs 4-7 yrs 4-5 yrs 2-7 yrs 6m - 7 yrs ?
LabsNumber of Labs 0 0 1 1 0 0 0 0 3 2 4 3 1 15
Number of Computers 0 0 8 24 0 0 0 0 80 39 86 84 7 328
Age of Computers 0 0 6 to 7 yrs 8 to 10 yrs 0 0 0 0 1 yr 4 yrs ? 1 - 2 yrs 4-7 yrs
Office/Administration
Number of Computers 14 14 11 12 0 16 10 12 41 51 47 6 24 258
Age of Computers 6 - 7 yrs 4 - 5 yrs 4 - 6 yrs 4 -5 yrs 0 4-7 yrs 1-5 yrs 4-5 yrs 1-6 yrs 4-5 yrs 2-6 yrs 3 - 6 yrs 3-7 yrs
Facilities Conditions and Student Performance
OStudies support educators common sense - Students do better when they:
OHear wellOSee wellOAre not packed into small spacesONoise is not distractingOLighting is goodOAir Quality is goodOHeat and cooling are balanced
Facilities Conditions and Student Performance
O Educational DeliveryO Milwaukee study suggest facility
conditions have stronger affect on performance than other factors, such as family background, socio-economic status, attendance and behavior
O Indoor Air QualityO About 40% of schools report
unsatisfactory environmental conditions
Facilities Conditions and Student Performance
O Temperature & VentilationO Good ventilation systems are effective in
keeping toxic and nuisance materials out of the air.
O AcousticsO Studies have linked student hearing
problems with being held back a gradeO Lighting
O The visual environment is one of the most important factors in learning, affecting mental attitude, class attendance, and performance
Facility Appraisal
Appraisal InstrumentO An Appraisal Guide for Older & Historic
School FacilitiesO Developed by The Council of
Educational Facility Planners International
O A tool to evaluate the physical condition and educational adequacy of older and historic school facilities, and is designed to engage a broad audience in the appraisal process.
Appraisal CriteriaOEducational AdequacyOEducational EnvironmentOThe School SiteOBuilding Safety and SecurityOStructural Condition and
Electrical & Mechanical Systems OPlant Maintainability
Appraisal TeamO Team Members
O Bill Sanders – QHSO Mike Carter – Klinger & Assoc.O Todd Moore – Architechnics, Inc.O Dave Schlembach - Poepping, Stone, Bach &
Associates, Inc.O Dan Nutt – QPS Maint DeptO Dane Barnes – QPS Maint DeptO Dennis Peters – QPS Maint DeptO Rick Selsor – QPS Maint DeptO Rick Owsley – QJHSO Joel Murphy, Facilitator – QPS
Initial Findings
Initial FindingsO “Great Schools”, not so Great Facilities
O “A good teacher can teach anywhere”O Physical Structure is limiting the
learning experienceO No Facility Rated higher than
SatisfactoryO Only one Elementary was rated
SatisfactoryO 7 out of 12 of our active facilities were
rated BorderlineO Grade Alignment out of sync with
current practices
Initial FindingsO Smaller Elementary Schools generate some operational
inefficienciesO Large Intermediate School causes logistical and
operational issuesO Small Elementary & Intermediate Classrooms – Avg 750 Sq
FtO Undersized Gym & Cafeterias
O Multiple Lunch PeriodsO Limited PE Activities
O Relationship between spaces limitingO Restrooms located only on one floorO Movement restricted by Multi-Leveled buildingsO Old and outdated Building designs limiting programs
O Lack of Specialized Learning AreasO No Art RoomsO Music taught in converted classrooms or other spaces
Initial FindingsOLibrary well undersizedOTechnology Access Limited
O Computer Labs small or lackingO Low computer to student ratios
OSpace for teacher resource areas limited
OAdministrative Spaces very limited
Initial FindingsO Most Elementary sites too small, lack
adequate open space and parkingO Most Elementary sites too small to allow for
expansion of buildingO Vehicular & Pedestrian Traffic patterns not
separatedO Site Ingress/Egress Issue at Elementary sites
O Bus Drop Off AreasO Parent Drop Off AreasO Staff/Visitor Parking
Initial FindingsO Inability to meet ADA Requirements w/o extensive
workO Deterioration due to ages of facilitiesO HVAC Inadequate
O Fresh air exchangeO Individual AC UnitsO Efficiency of older equipment
O Poor Energy efficiencyO Electrical system is unable to accommodate
additional technology in classroomsO Trying to maintain 100+ year old buildingsO Maintaining “temporary” facilitiesO Building systems “tired”, needed major upgrades
Initial FindingsO Inability to meet ADA Requirements w/o extensive
workO Deterioration due to ages of facilitiesO HVAC Inadequate
O Fresh air exchangeO Individual AC UnitsO Efficiency of older equipment
O Poor Energy efficiencyO Electrical system is unable to accommodate
additional technology in classroomsO Trying to maintain 100+ year old buildingsO Maintaining “temporary” facilitiesO Building systems “tired”, needed major upgrades
Building Condition
Category Poss
ible
Poin
ts
Ave
rage
Rat
ing
Ave
rage
Pe
rcen
tage
Rat
ing
by
Cond
itio
n
1.0 Educational Adequacy 200 142 99 106 93 139 118 104 100 93 134 143 133 158 120 60% Borderline
2.0 Environment for Education 200 156 106 118 119 131 143 126 92 138 149 162 150 164 135 67% Borderline
3.0 School Site 100 82 53 64 58 60 77 64 53 75 77 82 76 75 69 69% Borderline
4.0 Building Safety & Security 200 145 123 118 123 129 138 113 88 136 141 150 158 164 133 66% Borderline
5.0Structural Condition and Electrical/ Mechanical Systems
200 149 129 101 116 130 111 125 75 108 148 163 168 167 130 65% Borderline
6.0 Plant Maintainability 100 75 62 50 56 72 58 55 44 56 64 78 77 81 64 64% Borderline
TOTAL 1000 749 573 556 564 661 646 587 452 605 713 777 763 808 650 65.0% Borderline
Educational Adequacy
O District Average – 60% - BorderlineO Elementary & Intermediate - 56% -
BorderlineO Berrian, Ellington & Baldwin –Poor
O Quincy Jr High School - 67% - Borderline
O Quincy High School - 64% - Borderline
O ACRSS & ABC Academy - 67%Borderline
O ECFC - 80% - Satisfactory
Educational Environment
O District Average – 67% - BorderlineO Elementary & Intermediate - 65% -
BorderlineO Quincy Jr High School – 75% -
SatisfactoryO Quincy High School – 81% -
SatisfactoryO ACRSS & ABC Academy – 75% -
SatisfactoryO ECFC - 79% - Satisfactory
The School SiteO District Average – 69% - BorderlineO Elementary & Intermediate - 67% -
BorderlineO Quincy Jr High School - 77% -
SatisfactoryO Quincy High School - 82% -
SatisfactoryO ACRSS & ABC Academy - 76% -
SatisfactoryO ECFC – 75% - Satisfactory
Building Safety & Safety
O District Average – 66% - BorderlineO Elementary & Intermediate – 64% -
BorderlineO Quincy Jr High School – 70% -
SatisfactoryO Quincy High School – 75% -
SatisfactoryO ACRSS & ABC Academy – 79% -
SatisfactoryO ECFC – 82% - Satisfactory
Structural Condition and Electrical & Mechanical Systems
O District Average – 65% - BorderlineO Elementary & Intermediate - 61% -
BorderlineO Quincy Jr High School – 74% -
SatisfactoryO Quincy High School - 81% -
SatisfactoryO ACRSS & ABC Academy - 84%
SatisfactoryO ECFC - 83% - Satisfactory
Plant Maintainability
O District Average – 64% - BorderlineO Elementary & Intermediate - 61% -
BorderlineO Dewey - Poor
O Quincy Jr High School - 64% - Borderline
O Quincy High School - 78% - Satisfactory
O ACRSS & ABC Academy - 80% Satisfactory
O ECFC - 81% - Satisfactory
Next StepsPlanning Parameters/Guidance Needed to Develop Recommendations
Options to Address FindsCommunity InputRefining Options
Develop Recommendations
Planning ParametersO Limiting Transitions/Grade Level
ConfigurationsO Current, 3 Transitions: K-3, 4-6, 7-9, 10-12 O Other Models
O K-5, 6-8, 9-12 – 3 TransitionsO K-8, 9-12 – 2 Transitions
O Historical Preservation
Planning ParametersO Site Ingress/Egress
O Bus Drop Off AreasO Parent Drop Off AreasO Staff/Visitor Parking
O ADA ComplianceO Need for Specialized Spaces
O CafeteriaO GymO LibraryO MusicO ArtO Other
Planning ParametersO Technology
O InfrastructureO Devices
O Size of SchoolO Small schools – More BuildingsO Larger Schools – Less Buildings
O Neighborhood SchoolsO Sustainability/Energy Efficiency – “Green Bldgs”O Alternate Use for Buildings
Options to Correct FindingsO New ConstructionO AdditionsO RenovationsO Building ReplacementsO Cost Estimates?O Tax Impact?
Next StepsO Community Dialog 1
O School SizeO Grade ConfigurationO Neighborhood schoolsO Historic Preservation
O Refine Facility OptionsO Community Dialog 2
O Rate/Rank Facility OptionsO Gauge Support
O Final Report & Recommendation to Board
Questions