Interim and Long-term Approaches for Assessing Wind’s Contribution to Capacity Adequacy PNW...
-
Upload
matthew-wilson -
Category
Documents
-
view
215 -
download
1
Transcript of Interim and Long-term Approaches for Assessing Wind’s Contribution to Capacity Adequacy PNW...
Interim and Long-term Approaches for Assessing
Wind’s Contribution to Capacity Adequacy
PNW Resource Adequacy PNW Resource Adequacy Steering Committee MeetingSteering Committee Meeting
July 21, 2008July 21, 2008
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 2
WIAP Action 1 - Wind Capacity Value
Phase I: By July 2007, the Northwest Resource Adequacy Forum should reassess its 15 percent pilot sustained wind capacity value using currently available data on wind plant operation during periods of peak load.
Phase II: In 2008, the NWRA Forum should further refine the sustained peaking capacity value of wind power using the improved wind resource data set of Action 3 and other available data.
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 3
PHASE I: Interim Wind Capacity Value
• Council 2011 and 2013 Resource Adequacy Assessments– Wind Capacity Contribution to Resource
Adequacy equated to 5% installed capacity– Placeholder value– Supported by BPA’s wind capacity
analyses in the BPA control area
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 4
PHASE II: Long-term Plan to develop Wind Capacity Value
• Need sufficient years of hourly wind generation by wind site for GENESYS to perform Monte Carlo picks
• Ideally would like backcast wind generation simulation to ascertain performance of wind over historical cold snaps/heat waves
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 5
LONG-TERM OPTIONSSynthetic Data
• Assumes recent years of wind generation are representative of long-term history
• Use statistics from actual data to create synthetic wind
data • Advantage = this data set
can be created now
Backcast Simulation• Need clean Anemometer
Data for several decades– Stable location, altitude, or
way to adjust data
– On-site data preferable
• Need good Correlations between anemometer data and actual wind generation– Consider wind speed,
direction, lag time
• Allows analyses of historical cold snaps/heat waves
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 6
OPTION 1: Synthetic Data• Investigate long-term anemometer data
to test whether recent record of actual wind generation is typical of long-term record
• If so, use Synthetic Data
• If not, may still need to use Synthetic Data until credible Backcast Simulation is complete
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 7
OPTION 2: Backcast Simulation
• Results from BorisMetrics Contract provide starting point for more detailed analyses
• BorisMetrics Contract Purpose:− Evaluate Wind Generation that would have
been available to meet peak loads during historical cold snaps/heat waves
− Develop Backcast simulation of Hourly Wind Generation as input to the GENESYS Loss of Load Probability model
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 8
Borismetrics Work Identified Issues
0.0
0.1
0.2
0.3
0.4
0.5
Pro
bab
ilit
y o
f O
ccu
ran
ce
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
Capacity Midpoint
Simulated Backcast East Gorge% NameplateHourly Data From 1/44 - 1/06
• Most frequent capacity factor is 15% of nameplate rather than 0%, as shown by the BPA Wind Capacity Analyses
• Was Gorge windier in the past, or is there a problem with the simulation?• Case of the missing zeros:
− "dummy" or surrogate variables to allow for generation facilities to be shut down for maintenance or other reasons.
− Problem identified: 40% of time when wind was blowing, there was zero wind generation.
Distribution of All Generation Data East Gorge Synthetic DataActual Boris Data
0.0%
0.5%
1.0%
1.5%
2.0%
2.5%
3.0%
3.5%
4.0%
4.5%
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 97 101
% of 100
% o
f to
tal
Mode is Zero, Over 4% is at zero
1/
1/ Probability of occurrence should be divided by 10
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 9
Borismetrics Work Identified Issues• Case of missing zeros
– Example: East Gorge Generation Dec 2006– Why is there so little generation when the wind is blowing?
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 10
Borismetrics Work Identified Issues• Can a unique function calculating generation based
on wind speed be determined?
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 11
Borismetrics Work Identified Issues• Pendleton Anemometer Data not Clean
Pendleton Ave Annual Anemometer DataHeight, reading method, and meter location are noted
5
6
7
8
9
10
11
12
1944
1946
1948
1950
1952
1954
1956
1958
1960
1962
1964
1966
1968
1970
1972
1974
1976
1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
Year
Ave
An
nu
al W
ind
Sp
eed
(m
ph
)
37' manualT-107 bldg
53' manterminal bldg
20' manualterminal bldg
20' automaticterminal bldg
30' automaticterminal bldg
July 21, 2008 PNW Resource Adequacy Steering Committee Meeting 12
Next Steps• Form Technical Wind Assessment Team to:
– Investigate seasonal/annual variability of wind to determine if Synthetic Data Option is workable
– Investigate whether better Correlations are achievable using on-site wind anemometer data
• Check whether anemometer data is clean and of sufficient length
• If height of anemometer readings has varied; can adjustments be made to data?
• Is there sufficient anemometer and generation data to create credible backcast simulations?