Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by: Dick Stottler [email protected] 650-931-2714

Transcript of Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick...

Page 1: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Intelligent Space Surveillance Network (SSN) Scheduling

AIAA@Infotech 2012

Presented by: Dick [email protected]

Page 2: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Space Surveillance Network Scheduling

• Resources: ground & space-based radar & E/O sensors• Dedicated, Collateral, Contributing

• Plan/schedule observations (metric/SOI) of known objects, & surveillance

• Currently tracking tens of thousands of objects• Automatic capability needed for DCS/SSA scenarios• Inputs: tracked object observation opportunities and

desired tracking/metrics/SOI/objectives, surveys and time constraints

• Output assignment of resources to tasks for time periods, if possible

• During potential attacks/problems, rapidly adjust (replan)

Page 3: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

SSN Scheduling Challenges

• Antiquated/unique computer HW/software/scheduler at sensor• Prevents Automated Real-Time Response (Human responds)• Prevents (or at least hinders) globally optimized scheduling

• Non-dedicated sensors, sharing with other missions

• Non-Taskable sensors (e.g. space fences)

• Balancing need: complementary metric info & SOI & surveys

• Probabilistic results (calculated probability of successful track)• Includes both prob. of attempting & prob. of detecting given attempt

• Heterogeneous/complementary sensors (radar: accurate range/range rate; EO accurate angles & angle rate • Complementary signature info. (RCSs vs. spectral intensities)

• Orbit accuracy needs different sensors, different parts of orbit

Page 4: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Sensing Error => Covariances• Orbiting object described by 6 orbital parameters:

• Eccentricity, Semimajor Axis, Inclination, Longitude of ascending node, Argument of periapsis, and Mean anomaly at epoch

• Or by 3-D position and 3-D velocity vectors • Radar systems provide

• accurate range and range rate measurements (2 #s)• Less accurate angle & angular rate (4 #s w/ relatively high error)

• Optical sensors provide • good angle (2 parameters) and angular rate (2 parameters) • but no range or range rate (2 parameters missing).

• For each sensing opportunity of an object from a sensor: • based on geometry & sensor accuracies: 6 x 6 covariance matrix• the variances and covariances of the errors in measurement • describes the probable volume of space

Page 5: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Combining Measurements/Covs

• C1 & C2 are covariances (volumes) from 2 measurements

• C3 is result of • combining them

• C3 = C1*(C1 + C2)-1*C2

Page 6: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

2 Examples, Complementary & Not

• Volumes intersect near• orthogonally

• Volumes intersect with narrow angle

Page 7: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Current SSN Scheduling Problems

• Summary: Current Tasker implements policies dictated for it

• Local scheduling done with no global info.• Must be suboptimal (can’t consider bottlenecks or other

sensor data being collected)• Priority based local scheduling (IS suboptimal)• Executing all scheduled tasks likely implies undertasked• Possible to get sensor’s other mission’s detailed tasking?

• No automated real-time response• Human response required – no automated feedback loop

• Number of objects increasing (new sensors / smaller object resolution)

Page 8: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Scheduling 101: 1 Slide!• Scheduling with resource assignment is NP Complete (next slide)

• Takes exponential time to guarantee an optimal solution• (4 options per each choice)1000 Decisions

• 41000 = 22000 = 10200 >> 1080 = # particles in the universe

• Much scheduling research is in Job Shop Domain• Choice of resource doesn't effect start time: not applicable for satellites

• Constraint Satisfaction Problem: Search for Solution• Search Problem: Genetic Algorithms, Simulated Annealing, A*,

Heuristic Search, Iterative Repair• Operations Research: Linear Programming, Branch and Bound, Hill-

Climbing, Usually these must oversimplify the problem• Use multiple algorithms and pick the best schedule• Common Bad Algorithm: Priority Order, Greedily Pick Resource

• Other ways to guarantee high priority tasks, e.g. swap out lower Priority

• Nearly Linear Algorithms (Global Info.) vs Search

Page 9: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

VERY Simple NP Completeness eg

• 3 Remaining Tracks: Track 1, Track 2, Track 3• Track 1 highest priority, Track 3 lowest• 2 Sensors: A (1 track capacity left), B (2 tracks left)• A best for Track 1, also applicable to Track 3• B Applicable to Tracks 1 & 2• Priority-based allocation poor:• Track 1 <- A, Track 2 <-B, Track 3 <- ?• # of solutions: 2 (Track 1) x 1 (T2) x 1 (T3) = 2• But, 30 tracks, 4 choices each:

• 4x4x4x…x4 = 430 >million trillion solutions• Avoid simple linear & systematic (exponential) algs• Avoid “greedy” decisions made without global

context• NP Problems: solutions hard to find, easy to verify

Page 10: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Schedule Issue:• Resource Contention (Bottlenecks):

• Scheduling flexible, high priority activity on a specific resource at a specific time, when other (probably less desirable) options are available when a lower priority activity absolutely needed it.

• Both could have been scheduled but only one is

• Need to consider resource side (not just task)• Need global (schedule difficulty, resource contention)

information when making local decisions• Precalculate most contended-for resources (Global Info.)• Process most constrained requests first• Swap out lower priority tracks, if necessary

• Global Info also includes complementary data needs for most accurate orbit metrics

Page 11: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

SSN Track and Search Scheduling

• Simple priority-based schemes will significantly underutilize resources (including information-gain-based schemes)

• LEO objects – highly constrained to specific sensors at very specific times (10 – 15 minute windows)

• GEO objects – specific sensors, any time• MEO & non-GEO DS objects – loosely constrained in both• Highly Elliptical Orbit (HEO) – A mix of all 3• Complex requests:

• Min/Preferred tracks/day• Min/Max time or orbits between tracks• Mix of resources (e.g. 2 optical, 3 radar /day)

• Precalculate most contended-for resources

• Process most constrained requests first

• Swap out lower priority tracks, if necessary

Page 12: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

LEO Frequent Revisit Scheduler

• Current Problem• Currently LEO FR: all-pass codes (“Every sensor, every pass”)

• Duplicative and wasteful– Multiple sensors engaged over continental US, very little time separation/benefit – Small debris sensors (SDS) (SHY, EGL, CAV) waste time/energy on these

• Need to reduce drain on SDSs & improve overall efficiency– For each object, apply all-pass code tasking only to those sensors needed to

meet a certain stated revisit time, but not assigning every sensor to every object

• Solution: AI-based scheduler to meet revisit times & schedule small debris tracking

Page 13: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

DS Frequent Revisit Scheduler

• Different situation from LEO• No fixed definition of “pass”• More interest in frequent revisit for this regime• Sensor set more flexible• Ground vs space-based optimization needed

• More elaborate and potentially satisfactory solutions possible

• Solution: AI-based scheduler to revisit appropriately• Need to use predicted tracks from surveillance tasks• Consider sunlight on sensors and objects• Allocate tracks appropriately to ground radar & ground and space-

based optical sensors

Page 14: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

GIG-Enabled Global Optimizing Scheduler

• Schedule all objects’ tracking (LEO and DS)

• Use all sensors (new, surveillance/untasked, collateral, contributing)

• Quality Metric for DS: Covariance statistics

• Quality Metric for LEO: number of tracks per object per day(empirically linked to accuracy)

• Other Metrics: meeting revisit times, tracks lost, missed detections, redundant tracks, searches conducted, sensor utilization, SOI data gathered, etc.

• Solution: AI-based scheduler, Bottleneck avoidance, FOV scheduling

• Combination of 4 subschedulers (DS/NE, FR/not)

Page 15: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Family of 4 SSN Schedulers• Global, optimizing scheduler composed of 4 subschedulers

• Deep Space Frequent Revisit Scheduler• Low Earth Orbit Frequent Revisit Scheduler• Deep Space Non-FR Scheduler• Low Earth Non-FR Scheduler

• All have in Common:• Use of AI Architecture• LOS constraint between satellite and sensor• Optimize a Metric (Covariance, # of tracks, time between tracks)• Large # of satellites (100s to 1000s)• Bottleneck Avoidance (massive overlapping version)• Set of satellites / “free” tracks / set of resources

Page 16: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Multiple Subschedulers

• Generating a schedule much more difficult than grading one

• Architecture makes development of different algorithms quick

• Need different algorithms for different problem spaces• Different amounts of time available• Call best scheduler for problem space & time available• Call multiple subschedulers, grade results, return best

Page 17: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

High Level Scheduling Architecture

Page 18: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

AI ArchitectureHuman

Directives

Human Override & Influence Allowed

Track/Search Requests, Visabilities

Sensor Status

Task Queue

Task Conversion Knowledge

Task Ordering: Pick a Task

Select/Assign Resources

Task, & Time Window

Propagate Constraints

Handle Problems

Fix Problems & Optimize Schedule

Criteria & Instructions

Methods & Knowledge Guidance

Problem Resolution Knowledge

Schedule objects

Preprocessor

Knowledge Editors

Process Task

Task Conversion

Page 19: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Conclusions• SSN Scheduling is difficult, complex, and hampered by

antiquated hardware

• Essentially 4 different problems need 4 different but integrated solutions• DS FR Scheduler: intelligently use of sun/EO/radar/space-based-EO• DS NonFR Scheduler should utilize complementary observations to

minimize orbit covariances• NE FR Scheduler; “shield” SDSs, and more efficiently use other

sensors while meeting FR reqs• NE non-FR scheduler: maximize # of observations for each object• All need to use predicted tracks from non-taskable sensors• Use general AI architecture to rapidly create needed subschedulers

• Can set priorities/observation #s to “schedule” unschedulable sensors to nearest 90 minute period

Page 20: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

FOV Scheduling• With sensors that can track more than one

object and move their field of FOV, need to schedule the sensor’s aimpoint

• To maximize the number of tracks• Very hard problem: FOV pointing adds 2

continuous dimensions• Calculate and consider sets of aimpoints

that can track multiple objects each

Page 21: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Object Track & Visibility Squares

Page 22: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Intersecting Visibility Sets

Page 23: Intelligent Space Surveillance Network (SSN) Scheduling AIAA@Infotech 2012 Presented by:Dick Stottler stottler@StottlerHenke.com 650-931-2714.

Intersection Set ClustersCandidate & Selected Aim Points