Inspection management, integrity & corrosion prevention
2
Agenda
1. Approach2. findings 2008 &20093. Integrity4. Fort Eben Emael5. Seek for weak spots and threads 6. Improvement7. Inspection results8. Recommendations9. New threads10. AOB
Staatstoezicht op de MijnenMinisterie van Economische Zaken
3
Approach• Joined inspections with HSE UK for external corrosion project.• Step Change In Safety asset integrity toolkit as guideline.• 9 Dutyholders and 20 visits.• Incident analyses.• Database SodM gas leakages, general leakages and spills.• PDCA cycle central in project.
Staatstoezicht op de MijnenMinisterie van Economische Zaken
4
Findings in 2008 & 2009?
Positive; Dutyholders are improving on integrty. Organizations are adjusted to new insights ( based on the ‘Baker Panel report’). Information from inspections, audits and maintenance reports is frequently linked and analyzed holistic to get a total view on integrity
Still all duty holders have incidents.Analyzing gas leaks and spills points to good management on systems and disciplines but a failing integral management system.
17% instrumentation failures 50% technical failures16% hoses / couplings / flanges 34% during operat./maint. activities10% overflowing diesel / skimmer tanks
Staatstoezicht op de MijnenMinisterie van Economische Zaken
5
Integral auditing on integrity
Only few duty holders have a structured audit system on the technical integrity to know the status of the complete offshore installation. Audits are made on systems like pressurized equipment, maintenance system and organisation (ISO 901).
Staatstoezicht op de MijnenMinisterie van Economische Zaken
good
Verry good
improvement needed failing system
maintenance
pressurized-
equipment
organisation
6
What is integrity?ASSET INTEGRITY OF A FACILITY IS ACHIEVED WHEN THE RISK OF FAILURE ENDANGERING THE SAFETY OF PERSONNEL, THE ASSET VALUE OR THE ENVIRONMENT IS AS LOW AS REASONABLE PRACTICABLE.
ASSET INTEGRITY is a continuous process of knowledge and experience applied throughout the lifecycle to manage the risk of failures and events in design, construction, and during operation of facilities to ensure optimal production without compromising safety, health and environmental requirements
What is the integrity core idea?
Staatstoezicht op de MijnenMinisterie van Economische Zaken
7
Intermezzo
Know your weak spots!
Staatstoezicht op de MijnenMinisterie van Economische Zaken
8
Fort Eben EmaelBelgium 1939. Eben Emael is a giant fortress. 17 bunkers from various types. Total fire power: 2100 kg. a minute. An impressive piece of Belgium defense. Inside this fortress, 60meter under the top, underground barracks for 1.200 soldiers. Military experts from various countries agreed that this fortress was one of the strongest in Europe. To concur this fortress was impossible!
Staatstoezicht op de MijnenMinisterie van Economische Zaken
9
The fall.
Guess how much time the Germans needed to get control on the fortress?
Answer: 15 minutes and a 71 crew!
Staatstoezicht op de MijnenMinisterie van Economische Zaken
10
New threats; Para's, gliders and the hollow charge
Staatstoezicht op de MijnenMinisterie van Economische Zaken
11
The fortress strength was its weakness! To convinced of their own strength.Design based on WO I.No studies or analyzes on new threads.Operational, no plan B.Artillerists not trained on man to man battle.Low moral.
The bottom line was that the fortress failed on organization, technology and human skills
The fortress was NOT sound!
DesignIntegrity
TechnicalIntegrity
(maintenance / inspection)
OperationalIntegrity
AssetIntegrity
Staatstoezicht op de MijnenMinisterie van Economische Zaken
12
Know your weak spots!
Integrity is not about your strength but about to know your weak spots!
Staatstoezicht op de MijnenMinisterie van Economische Zaken
13
Seek for weak spots and threads
Active investigation to weak spots in
technology and organization.
HAZOP's, audits, etc.
Involve your workforce in
integrity. Create ownership!
Use independent verification and
reports.
Weak spots are no threads if you
Staatstoezicht op de MijnenMinisterie van Economische Zaken
14
Gaslekkages totaal Nogepa gas leak data base
2003 2004 2005 2006 2007 2008
0
10
20
30
40
50
60
70
80
90
aan
tal
Overige lekkages totaal uit MIS (exclusief gaslekkages)
2003 2004 2005 2006 2007 2008
0
10
20
30
40
50
60
70
80
90
100
aa
nta
l
Improvement possible
Staatstoezicht op de MijnenMinisterie van Economische Zaken
15
Inspection results
Positive:
• Audits • A lot focus on maintenance and inspection.• External corrosion a lot better than in the UK.• TCVT certification scheme for offshore cranes improves safety.
Staatstoezicht op de MijnenMinisterie van Economische Zaken
16
Recommendations
Secure technical integrity.
Use reports and independent verification to improve.
Involve your workforce in integrity. Create ownership to improve.
Staatstoezicht op de MijnenMinisterie van Economische Zaken
17
New threads
Aging workforce. Ownership and experience can get lost. Life time extension installations. Is everything covered?Credit crisis, cut cost.Organization, information management.New design philosophies.Verification by NoBo' s???????????????????
Staatstoezicht op de MijnenMinisterie van Economische Zaken
18
Questions / AOB
Real strength is to know your weak spots.
Be open minded and seek for threads.
A planned audit system is one way to improve integrity.