Integration Between PP Module and PM

21
Generated by Jive on 2014-07-16+02:00 1 Integration between PP module and PM module Hi, This document explains integration between PP module and Plant Maintenance (PM) module.... Overview: Integration between PP and PM modules happens during following scenarios... A) During Capacity Planning for work centers B) For tracking the usage value of PRT's Process flow of integration during Capacity Planning for work centers: When the production work center is overloaded with capacity, if we try to do capacity leveling and want to shift the capacity to other dates, where already some preventive maintenance activity is planned for the same work center ( equipment) during that period, then system will not allow to reschedule the production order to those days. PP Work center is Equipment in PM. In the concerned equipment's master data you can mention the PP work centers name. This links the PP work center and PM equipment. Process flow... Create work center :

description

PP PM

Transcript of Integration Between PP Module and PM

Page 1: Integration Between PP Module and PM

Generated by Jive on 2014-07-16+02:001

Integration between PP module and PMmodule

Hi,

This document explains integration between PP module and Plant Maintenance (PM) module....

Overview: Integration between PP and PM modules happens during following scenarios...

A) During Capacity Planning for work centers

B) For tracking the usage value of PRT's

Process flow of integration during Capacity Planning for work centers:

When the production work center is overloaded with capacity, if we try to do capacity leveling and want to shift

the capacity to other dates, where already some preventive maintenance activity is planned for the same work

center ( equipment) during that period, then system will not allow to reschedule the production order to those

days. PP Work center is Equipment in PM. In the concerned equipment's master data you can mention the PP

work centers name. This links the PP work center and PM equipment.

Process flow...

Create work center :

Page 2: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:002

in the capacities header tab maintain the data as per the requirement....

Page 3: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:003

Now save the work center....

Create Routing : Create the routing for material and assign the work center for operation as shown in the below

screen shots...

Page 4: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:004

Now save the Routing..

Create BOM : Create the BOM for the material through CS01 for creation of Production orders...

Page 5: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:005

this completes the master data from Production planning module side....

Create Equipment : Create equipment in Plant maintenance module through IE01 and assign the work center

( created in PP module ) in the location tab as shown below. and assign the planning plant as same the work

center plant...

Page 6: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:006

Page 7: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:007

Page 8: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:008

Save the equipment.....

Now create Preventive Maintenance order for the above equipment through IW31...

Page 9: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:009

Now give the order start date as 26.05.2014 and end date as 30.05.2014 as shown below...

Page 10: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0010

maintain system condition as not in operation as shown below....

Page 11: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0011

Finally save the Preventive Maintenance order...

Now create production order for material 2570 through CO01...

Page 12: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0012

Now give the start date as 22.05.2014 and end date as 27.05.2014 as shown below..and release the order and

save the production order...

Page 13: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0013

Now create one more production order for the same material with same start and end dates as shown below...

this is for creating the capacity overload for the period....

Page 14: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0014

then save the order...

Now check the capacity situation of the work center in the CM50 transaction...

Page 15: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0015

Page 16: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0016

above you can observe that there is a capacity overload on dates 23.05.2014, 26.05.2014 and

27.05.2014....now as there is a overload we will try reschedule the one of the production order to other dates

on the capacity planning table with function capacity leveling...

Page 17: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0017

in the next selection screen give work center, plant, capacity category and Capacity planner grp

Now execute

Page 18: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0018

Now take the second production order ( 60004673) and try dispatch it on the dates 28.05.2014 to 30.05.2014

where already preventive maintenance order is present which is shown in black color..

Page 19: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0019

Now when you try to dispatch the second production order system will not allow you to do on the dates of

preventive maintenance dates and it will rescheduled (dispatched) to subsequent dates as shown below...

Page 20: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0020

Now save the planning table and observe the change in dates in second production order..

Page 21: Integration Between PP Module and PM

Integration between PP module and PM module

Generated by Jive on 2014-07-16+02:0021

Process flow of integration for tracking the usage value of PRT's :

Tracking of usage of a tool in production, every time a tool is used there should be a count of that usage...This

requires PP-PM integration. A production resource tool as equipment is created with the measuring points. The

PRT will then be assigned to the operation that requires usage. During confirmation of the production order, the

system will automatically record the usage as measuring documents. In this way, the count of the tool usage is

monitored...

Thanks

Kumar