Integration Between PP Module and PM
description
Transcript of Integration Between PP Module and PM
Generated by Jive on 2014-07-16+02:001
Integration between PP module and PMmodule
Hi,
This document explains integration between PP module and Plant Maintenance (PM) module....
Overview: Integration between PP and PM modules happens during following scenarios...
A) During Capacity Planning for work centers
B) For tracking the usage value of PRT's
Process flow of integration during Capacity Planning for work centers:
When the production work center is overloaded with capacity, if we try to do capacity leveling and want to shift
the capacity to other dates, where already some preventive maintenance activity is planned for the same work
center ( equipment) during that period, then system will not allow to reschedule the production order to those
days. PP Work center is Equipment in PM. In the concerned equipment's master data you can mention the PP
work centers name. This links the PP work center and PM equipment.
Process flow...
Create work center :
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:002
in the capacities header tab maintain the data as per the requirement....
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:003
Now save the work center....
Create Routing : Create the routing for material and assign the work center for operation as shown in the below
screen shots...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:004
Now save the Routing..
Create BOM : Create the BOM for the material through CS01 for creation of Production orders...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:005
this completes the master data from Production planning module side....
Create Equipment : Create equipment in Plant maintenance module through IE01 and assign the work center
( created in PP module ) in the location tab as shown below. and assign the planning plant as same the work
center plant...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:006
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:007
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:008
Save the equipment.....
Now create Preventive Maintenance order for the above equipment through IW31...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:009
Now give the order start date as 26.05.2014 and end date as 30.05.2014 as shown below...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0010
maintain system condition as not in operation as shown below....
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0011
Finally save the Preventive Maintenance order...
Now create production order for material 2570 through CO01...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0012
Now give the start date as 22.05.2014 and end date as 27.05.2014 as shown below..and release the order and
save the production order...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0013
Now create one more production order for the same material with same start and end dates as shown below...
this is for creating the capacity overload for the period....
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0014
then save the order...
Now check the capacity situation of the work center in the CM50 transaction...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0015
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0016
above you can observe that there is a capacity overload on dates 23.05.2014, 26.05.2014 and
27.05.2014....now as there is a overload we will try reschedule the one of the production order to other dates
on the capacity planning table with function capacity leveling...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0017
in the next selection screen give work center, plant, capacity category and Capacity planner grp
Now execute
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0018
Now take the second production order ( 60004673) and try dispatch it on the dates 28.05.2014 to 30.05.2014
where already preventive maintenance order is present which is shown in black color..
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0019
Now when you try to dispatch the second production order system will not allow you to do on the dates of
preventive maintenance dates and it will rescheduled (dispatched) to subsequent dates as shown below...
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0020
Now save the planning table and observe the change in dates in second production order..
Integration between PP module and PM module
Generated by Jive on 2014-07-16+02:0021
Process flow of integration for tracking the usage value of PRT's :
Tracking of usage of a tool in production, every time a tool is used there should be a count of that usage...This
requires PP-PM integration. A production resource tool as equipment is created with the measuring points. The
PRT will then be assigned to the operation that requires usage. During confirmation of the production order, the
system will automatically record the usage as measuring documents. In this way, the count of the tool usage is
monitored...
Thanks
Kumar