Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at...

27
Renewable energy and the National Electricity Market: Issues & Challenges © CEEM, 23 November 2005 Integrating renewable energy in the NEM: Economic issues

Transcript of Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at...

Page 1: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

Renewable energy and the National Electricity Market: Issues & Challenges© CEEM, 23 November 2005

Integrating renewable energy in the NEM: Economic issues

Page 2: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

2Integrating renewable energy in the NEM: Economic issues © CEEM 2005

OutlineGeneration mix conceptsCost estimates for electricity generation optionsWind energy cost & benefit issuesPV energy cost & benefit issuesCommercial viability of renewable energy in the NEM

Page 3: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

3Integrating renewable energy in the NEM: Economic issues © CEEM 2005

EnergyAustralia - Summer 2000/01 Profiles - Peak and Average Days

0

1000

2000

3000

4000

5000

2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00

MW

23 Jan 2001

Avg Workday

Avg NonWorkday

Air conditioning usage

0

2000

4000

6000

8000

10000

12000

14000

Sunday Monday Tuesday Wednesday Thursday Friday Saturday

07 to 13 March 2004 27 to 02 August 2003NSW summer & winter peak demand

Page 4: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

4Integrating renewable energy in the NEM: Economic issues © CEEM 2005

2003 Load duration curves for NEM states(NEMMCO SOO documents, 2004)

0

10

20

30

40

50

60

70

80

90

100

0 10 20 30 40 50 60 70 80 90Percentage of time

New South Wales Victoria Queensland South Australia Tasmania

Page 5: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

5Integrating renewable energy in the NEM: Economic issues © CEEM 2005

‘Optimal’ resource mix (generation & demand)‘peak duty’ option

‘base duty’ option

‘intermediate duty’ option(voluntary)

demandreduction

envelope of cheapest available options

breakevenpoints

C1 C2 C3

$/kW/yr

Capacityfactor

10

Page 6: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

6Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Capacityfactor0 1

MW

Load duration curve & resource mix(ideal case: no uncertainty in demand or unit availability & no load growth)

base duty resources

C3C2

intermediate duty resources

C1

peak duty resourcesdemand reduction

load duration curve

Page 7: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

7Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Direct costs for some renewable energy & fossil fuel power stations

012345678

Bio Hydro SolarHW

Wind Fossil

RangeMin

C/kWh

(network location & controllability also matter)

Source: Australian Greenhouse Office 2001

Page 8: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

8Integrating renewable energy in the NEM: Economic issues © CEEM 2005

PMSEIC cost estimatesPMSEIC Beyond Kyoto Report, 2002

(PMSEIC, 2002b)

0.00

20.00

40.00

60.00

80.00

100.00

120.00

140.00

160.00

Conventional Coal Gas combined cycle Zero emissions coal Renewables

$/M

Wh

(Source: Roam Consulting – unpublished data 2002)

0.00

20.00

40.00

60.00

80.00

100.00

120.00

140.00

160.00

Conventional Coal Gas combined cycle Zero emissions coal Renewables

$/M

Wh

0.00

20.00

40.00

60.00

80.00

100.00

120.00

140.00

160.00

Conventional Coal Gas combined cycle Zero emissions coal Renewables

$/M

Wh

(Source: Roam Consulting – unpublished data 2002)

Wind

Photovoltaics

Hot Dry Rocks

Biomass

Not available in large scalefor ~20 years &

may prove to be optimistic

Page 9: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

9Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Wind farm indicative connection costs to 330kV (Transgrid, 2002)

15028.32004

18017.71002

65012.9201

2,50012.751

Conn.cost$/kW

Conn. cost $MTotal wind MW

Wind farm number

Important to capture economies of scale of grid connection

Page 10: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

10Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Wind resource & network issues in South Australia

Map: ESIPC, 2002

Good wind resources along entire coastline including:

• Eyre Peninsula• Yorke Peninsula• Fleurieu Peninsula• Kangaroo Island• South-East

Sites available for up to 2000MW

Page 11: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

11Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Eyre Peninsula Backbone network upgrade to support 500MW wind

(Meritec, 2002)

Estimated cost of 275kV backbone upgrade: $140M or $280/MW assuming equally shared by 500MW of wind.

Wind may not have to pay full cost of backbone upgrade.

Page 12: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

12Integrating renewable energy in the NEM: Economic issues © CEEM 2005

NEMMCO concerns about wind energy (NEMMCO, 2003)

Frequency control in normal operation:– Frequency regulating service costs ~5 $/MWH

Security control - largest single contingency– Will wind farms ride-through disturbances?– Are wind farm dynamic models adequate?

Interconnection flow fluctuations:– Exceeding flow limit may cause high spot price

Forecast errors due to wind resource uncertainty:– Five minute dispatch forecast (spot price)– Pre-dispatch & longer term (PASA & SOO) forecasts

Page 13: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

13Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Wind farms in the NEM spot marketWind farms will operate as “price takers”:– Generate whenever wind is blowing

NEM spot market prices are volatile with a “rectangular” price distribution:– Prices are usually low, sometimes high– Timing of high prices not easily predicted

Value of wind energy in the spot market:– Will depend on how regularly wind farms are producing

when spot prices are highWind farms may have to pay ancillary service costs

Page 14: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

14Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Western Power’s proposed wind penalty charge (c/kWh) (Western Power, 2002)

Page 15: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

15Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Indicative impact of wind on SA NEM spot price duration curve (www.esipc.sa.gov.au)

Page 16: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

16Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Price-demand plots for NEMregionsNSW (top) & SA (bottom)Jan-Mar 2004

($/MWH vs MW)(NECA, 04Q1 Stats, 2004)

Page 17: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

17Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Smoothed NEM Regional Ref Prices (RRPs) since market inception (AER, 05Q2 Stats, 2005)

Page 18: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

18Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Annual average RRP flat contract prices (AER, 05Q2 Stats, 2005)

Page 19: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

19Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Premium at50 $/MWH strike price (above) & installed peaking capacity(below)by NEM region(AER, 05Q2 Stats, 2005)

Page 20: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

20Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Wind farms marginal at $70/MWH(PWC, 2002)

Page 21: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

21Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Forward prices for wind energyWind farms may have to accept a lower price than “flat contract” due to uncertainty in production: – Daily– Seasonal, – Annual

(Giebel (2000) Riso National Lab, Denmark)

Page 22: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

22Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Prediction of REC Prices (A$/MWH) (ORER, 2003)

0

510

15

2025

30

3540

45

5055

60

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Year

RE

C p

rice

average price

Page 23: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

23Integrating renewable energy in the NEM: Economic issues © CEEM 2005

REC requirement to 2020 is almost metThe Federal Govt. has rejected key review finding of a higher target to 2020BCSE estimates only approx. 700-800MW of new (post Jan04) projects required to meet existing target, and……project commitments > 500MW in 2004 leaves < 300MW new projects required

(BCSE, 2005)

Page 24: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

24Integrating renewable energy in the NEM: Economic issues © CEEM 2005

PV solar energy

PV can be installed at point of end-useOffers potential to:– Displace investment in remote generation,

transmission & distribution– Provide local network voltage & reliability support

However, value will depend strongly on relationship between PV output & demand:– Storage may improve correlation but at additional cost

Page 25: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

25Integrating renewable energy in the NEM: Economic issues © CEEM 2005

Relationship between PV output & commercial load in NSW (Watt et al, 2005)

Page 26: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

26Integrating renewable energy in the NEM: Economic issues © CEEM 2005

PV output & NEMprices in NSW & SA(Watt et al, 2005)

Page 27: Integrating renewable energy in the NEM: Economic issues · PV solar energy PV can be installed at point of end-use Offers potential to: – Displace investment in remote generation,

27Integrating renewable energy in the NEM: Economic issues © CEEM 2005

ConclusionsStochastic renewable energy:– Brings new challenges for electricity industry

restructuring (technical, market design, regulation)Wind energy:– The first significant form of “intermittent generation”– Not yet cost-competitive on electricity price alone

PV solar energy:– Technically sound– May not correlate well enough with peak demand to

defer network investment– Not cost-effective at this time