Integrating Multiple Microgrids into an Active Network Management System

23
Integrating Multiple Microgrids into an Active Network Management System Presented By: Colin Gault, Smarter Grid Solutions Co-Authors: Joe Schatz, Southern Company George Gao, Southern Company George Simard, SIMARD SG Bob Currie, Smarter Grid Solutions February 3 rd 2015

Transcript of Integrating Multiple Microgrids into an Active Network Management System

Integrating Multiple Microgrids into an Active Network Management System

Presented By: Colin Gault, Smarter Grid SolutionsCo-Authors: Joe Schatz, Southern Company

George Gao, Southern CompanyGeorge Simard, SIMARD SGBob Currie, Smarter Grid Solutions

February 3rd 2015

The “Project”

• Regional Microgrid Control: Research and Development

• Multi-year project between Southern Company and Smarter Grid Solutions

• Develop microgrid control platform using Active Network Management technology

• Phased Approach

– Phase 1: Use Case Definition and Simulation of Active Network Management (Complete February 2015)

– Phase 2: Trial deployment of Active Network Management at test site (Summer 2015)

– Future Phases: Phased implementation of microgrid functionality (2016)

2

Active Network Management

• End-to-end autonomous control solutions • Real-time operating system providing deterministic control

over distributed energy resources• Safe, secure and reliable method to increase hosting

capacity of electricity grid• Complements existing SCADA and Protection systems

3

Generator

DMS

Energy Storage System

GeneratorEnergy Storage System

DERMS

Data Historian

Active Network ManagementReliable - Deterministic - Repeatable

Scalable - Open Standards

4

Active Network Management

• Applied active network management to the following use cases in live deployments– Management of power flow constraints– Management of voltage constraints– Management of distributed generation contributing to transmission system

constraints– Smart electric vehicle charging– Demand Response (domestic / commercial)– Day ahead scheduling of controllable demand to coincide with renewable

energy production to support frequency stability

• Interfacing with range of Distributed Energy Resources– Wind | Solar | CHP |Building Management System | Electrical Energy Storage

Thermal Energy Storage | Electric Vehicle Charging Equipment

• Future development could include interoperability with automatic restoration and volt-var control solutions leveraging DER control

5

Generator

Energy Storage System

Circuit Microgrid

Generator

Facility Microgrid

Energy Storage System

Substation Microgrid

Microgrid Controller

Microgrid Controller

Microgrid Controller

DMS

ANM Application

DERMS

Data Historian

Adaptation to Incorporate MicrogridsNew layer of control: Microgrid Controller

6

Layers of Microgrid Control

7

Use Case Definition

• Create use cases across three modes of operation

– Interconnected• Microgrids interconnected

with area power system

– Transition Management• Microgrid transitioning into

and out of islanded operation

– Islanded• Microgrid operating as an

island

8

Interconnected

Regional Constraint

Management

Microgrid Constraint

Management

Ancillary Services

Energy Management

DER Controller

9

Transition Management

Planned Islanding

Regional Microgrid

Unplanned Islanding

Regional Microgrid

Reconnection

Regional Microgrid

10

Islanded

Frequency / Voltage Control

Energy Management

Black StartDER

Controller

11

1 MW Solar PV

1MW, 2MWh ESS

Modelling and Simulation

• Model of 12.47 kV Feeder with existing Solar PV: Peak demand 8MW

• Large proportion of feeder load is a single industrial customer

• Battery Energy Storage System to be installed later this year

• Steady State Load Flow simulations using CYMDIST

• Interconnected and Islanded Microgrid Use Cases Explored

12

1 MW Solar PV

1MW, 2MWh ESS

Feeder Demand

Measured at Substation

• Interconnected

– Use of the Energy Storage to minimize total feeder maximum demand

– Use of the energy Storage to minimize ratio between total feeder maximum and minimum demand

13

1 MW Solar PV

1MW, 2MWh ESS

Microgrid Isolation

Points

Microgrid

Loads

25 kVA500 kVA

25 kVA

14

• Islanded

– Use ESS profile generated during simulation of interconnected use case

– Maintain balance between load and generation on section of feeder

– Loads chosen are non-industrial customers

1 MW Solar PV

1MW, 2MWh ESS

Microgrid Isolation

Points

Microgrid

Loads

25 kVA500 kVA

25 kVA

1500 kVA

15

• Extended Island

– Extend microgrid boundary

– Include additional load to stretch capability of microgrid resources

• Input Data– One year (2014) of hourly data for feeder

measured at substation

• Calculate “average day” profile for feeder

• Generate a 24 hour schedule for battery to reduce peaks and troughs and apply to 365 days

• Apply upper and lower thresholds that trigger unscheduled charge/discharge of battery

Method: Interconnected

16

• Starting position uses results from interconnected study

• For every hour in the year calculate the maximum duration that an island could be sustained if an “event” was to occur– Match Battery and PV to load on section of feeder

– Excess energy from PV charges battery

– Shortfall in PV discharges battery

• Assumes battery inverter has capability to maintain frequency and voltage stability

Method: Islanded

17

• Interconnected– Yearly peak demand reduced by 200 kW

– Yearly minimum demand increased by 150 kW

• Islanded: Peak load 500 kW– Islanding achievable 6888 hours out of 8760

– Average duration: 30 hours

• Extended Island: Peak load 2,000 kW– Islanding achievable 1584 hours out of 8760

– Average duration : 7.6 hours

Results

18

19

4

4.5

5

5.5

6

6.5

7

0 2 4 6 8 10 12 14 16 18 20 22 24

Typical Day

Original Profle (MW) With Battery (MW)

-2

-1.5

-1

-0.5

0

0.5

1

1.5

2

-0.3

-0.2

-0.1

0

0.1

0.2

0.3

0 2 4 6 8 10 12 14 16 18 20 22 24

Battery Profile

Final SOC (MWh) Final Power Profile (MW)

• Shape of profile with long peaks and deep troughs makes it difficult for battery to reduce peak and increase trough significantly during interconnected mode when following a daily schedule

• May be more appropriate to use battery during instantaneous events using triggers as opposed to implementing daily schedule

• Islanding results show promise in being able to sustain a microgrid for significant period of time to reduce interruptions to non-industrial customers on feeder

Conclusions

20

Project Next Steps

• Deploy Active Network Management solution to perform field trial of use cases and compare results

• Phased roll-out of microgrid functionality at pilot site and/or other appropriate sites and development of inter microgrid control philosophies

21

1 MW Solar PV

1MW, 2MWh ESS

MP

MP

MPPower Flow

Measurement Point22

Proposed architecture for trial deployment

Presented by: Colin Gault, Principal Consultant, Smarter Grid Solutions

E-mail: [email protected]: +1 (718) 260 3603

23