INTEGRATED RESOURCE PLANNING REPORT TO …aep.com...integrated resource planning report . to the ....

1504
INTEGRATED RESOURCE PLANNING REPORT TO THE KENTUCKY PUBLIC SERVICE COMMISSION CASE NO. 2016-00413 VOLUME A – PUBLIC VERSION December 20, 2016 KPSC Case No. 2016-00413 2016 Integrated Resource Plan Of Kentucky Power Company Volume A - Public Version Page 1 of 1497

Transcript of INTEGRATED RESOURCE PLANNING REPORT TO …aep.com...integrated resource planning report . to the ....

  • INTEGRATED RESOURCE PLANNING REPORT

    TO THE

    KENTUCKY PUBLIC SERVICE COMMISSION

    CASE NO. 2016-00413

    VOLUME A PUBLIC VERSION

    December 20, 2016

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 1 of 1497

  • INTEGRATED RESOURCE PLANNING REPORT

    TO THE

    KENTUCKY PUBLIC SERVICE COMMISSION

    CASE NO. 2016-00413

    VOLUME A PUBLIC VERSION

    PAGES 2-199 of 1497

    December 20, 2016

  • KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 2 of 1497

  • Table of Contents

    LIST OF FIGURES .................................................................................................................... VI

    LIST OF TABLES ................................................................................................................... VIII

    EXECUTIVE SUMMARY .......................................................................................................... 1

    INTRODUCTION ................................................................................................................ 1 1.0

    1.1 Overview .................................................................................................................................................. 1

    1.2 Integrated Resource Plan (IRP) Process .................................................................................................... 1

    1.3 Introduction to Kentucky Power .............................................................................................................. 2

    1.4 Power Coordination Agreement (PCA) ..................................................................................................... 3

    1.5 The Impact of Coal Mining on KPCo Service Territory ............................................................................... 4

    1.6 Significant Changes from the 2013 IRP ..................................................................................................... 5

    LOAD FORECAST AND FORECASTING METHODOLOGY .................................... 8 2.0

    2.1 Summary of KPCo Load Forecast .............................................................................................................. 8

    2.2 Forecast Assumptions .............................................................................................................................. 8 2.2.1 Economic Assumptions ................................................................................................................................ 8 2.2.2 Price Assumptions ....................................................................................................................................... 9 2.2.3 Specific Large Customer Assumptions ......................................................................................................... 9 2.2.4 Weather Assumptions ................................................................................................................................. 9 2.2.5 Demand Side Management (DSM) Assumptions ......................................................................................... 9

    2.3 Overview of Forecast Methodology ....................................................................................................... 10

    2.4 Detailed Explanation of Load Forecast ................................................................................................... 12 2.4.1 General ...................................................................................................................................................... 12 2.4.2 Customer Forecast Models ........................................................................................................................ 13 2.4.3 Short-term Forecasting Models ................................................................................................................. 13 2.4.4 Long-term Forecasting Models .................................................................................................................. 14 2.4.4.1 Supporting Models ................................................................................................................................. 15

    2.4.4.1.1 Consumed Natural Gas Pricing Model ................................................................................................ 15 2.4.4.1.2 Regional Coal Production Model ........................................................................................................ 15

    2.4.4.2 Residential Energy Sales ......................................................................................................................... 16

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 3 of 1497

  • 2.4.4.3 Commercial Energy Sales ....................................................................................................................... 18 2.4.4.4 Industrial Energy Sales ........................................................................................................................... 18

    2.4.4.4.1 Manufacturing Energy Sales ............................................................................................................... 18 2.4.4.4.2 Mine Power Energy Sales ................................................................................................................... 18

    2.4.4.5 All Other Energy Sales ............................................................................................................................ 19 2.4.5 Internal Energy Forecast ............................................................................................................................ 19 2.4.5.1 Blending Short and Long-Term Sales...................................................................................................... 19 2.4.5.2 Losses and Unaccounted-For Energy ..................................................................................................... 19

    2.4.6 Forecast Methodology for Seasonal Peak Internal Demand ..................................................................... 20

    2.5 Load Forecast Results and Issues ............................................................................................................ 20 2.5.1 Load Forecast ............................................................................................................................................. 21 2.5.2 Peak Demand and Load Factor .................................................................................................................. 21 2.5.3 Weather Normalization ............................................................................................................................. 21

    2.6 Load Forecast Trends & Issues ............................................................................................................... 21 2.6.1 Changing Usage Patterns ........................................................................................................................... 21 2.6.2 Demand-Side Management (DSM) Impacts on the Load Forecast ............................................................ 24 2.6.3 Interruptible Load ...................................................................................................................................... 24 2.6.4 Blended Load Forecast............................................................................................................................... 25 2.6.5 Large Customer Changes ........................................................................................................................... 26 2.6.6 Wholesale Customer Contracts ................................................................................................................. 26

    2.7 Load Forecast Scenarios ......................................................................................................................... 26

    2.8 Energy-Price Relationships ..................................................................................................................... 27

    2.9 Significant Changes from Previous Forecast ........................................................................................... 29 2.9.1 Energy Forecast ......................................................................................................................................... 29 2.9.2 Peak Internal Demand Forecast ................................................................................................................. 30 2.9.3 Forecasting Methodology .......................................................................................................................... 30

    2.10 Additional Load Information .................................................................................................................. 30

    2.11 Data-Base Sources.................................................................................................................................. 31

    2.12 Other Topics ........................................................................................................................................... 31 2.12.1 Residential Energy Sales Forecast Performance ........................................................................................ 31 2.12.2 Peak Demand Forecast Performance ........................................................................................................ 32 2.12.3 Forecast Data and Model Results .............................................................................................................. 32 2.12.4 Forecast Updates ....................................................................................................................................... 32 2.12.5 KPSC Staff Recommendations Addressed .................................................................................................. 33

    RESOURCE EVALUATION ............................................................................................ 34 3.0

    3.1 Current Supply-Side Resources............................................................................................................... 34

    3.2 Environmental Issues and Implications .................................................................................................. 37

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 4 of 1497

  • 3.2.1 Mercury and Air Toxics Standards (MATS) ................................................................................................ 37 3.2.2 Cross-State Air Pollution Rule (CSAPR) ...................................................................................................... 39 3.2.3 National Ambient Air Quality Standards (NAAQS) ..................................................................................... 40 3.2.4 Coal Combustion Residuals (CCR) Rule ...................................................................................................... 40 3.2.5 Effluent Limitations Guidelines .................................................................................................................. 41 3.2.6 Clean Water Act 316(b) Rule ..................................................................................................................... 41 3.2.7 New Source Review Consent Decree ......................................................................................................... 42 3.2.8 Carbon Dioxide (CO2) Regulations, Including the Clean Power Plan (CPP) ................................................ 44

    3.3 Current Demand-Side Programs ............................................................................................................. 47 3.3.1 Impacts of Existing and Future Codes and Standards ................................................................................ 47 3.3.2 Demand Response (DR) ............................................................................................................................. 49 3.3.2.1 Existing Levels of Active Demand Response (DR) ................................................................................... 51

    3.3.3 Energy Efficiency (EE) ................................................................................................................................. 51 3.3.3.1 Existing Levels of Energy Efficiency (EE) ................................................................................................. 53

    3.3.4 Distributed Generation (DG) ...................................................................................................................... 53 3.3.4.1 Existing Levels of Distributed Generation (DG) ...................................................................................... 57 3.3.4.2 Cogeneration / Combined Heat and Power (CHP) ................................................................................. 57

    3.3.5 Volt VAR Optimization (VVO) ..................................................................................................................... 58 3.3.6 KPSC Staff DSM Recommendations Addressed ......................................................................................... 59

    3.4 AEP-PJM & Kentucky Power Transmission ............................................................................................. 63 3.4.1 General Description ................................................................................................................................... 63 3.4.2 Transmission Planning Process .................................................................................................................. 65 3.4.3 System-Wide Reliability Measure .............................................................................................................. 66 3.4.4 Evaluation of Adequacy for Load Growth .................................................................................................. 66 3.4.5 Evaluation of Other Factors ....................................................................................................................... 67 3.4.6 Transmission Expansion Plans ................................................................................................................... 67 3.4.7 FERC Form 715 Information ....................................................................................................................... 67 3.4.8 Kentucky Transmission Projects ................................................................................................................ 69

    3.5 Distribution ............................................................................................................................................ 70

    MODELING PARAMETERS .......................................................................................... 72 4.0

    4.1 Modeling and Planning Process An Overview ...................................................................................... 72

    4.2 Methodology ......................................................................................................................................... 73

    4.3 Fundamental Modeling Input Parameters .............................................................................................. 73 4.3.1 Commodity Pricing Scenarios .................................................................................................................... 75 4.3.1.1 Emission Reduction Credit (ERC) Pricing ................................................................................................ 75 4.3.1.2 Mid Scenario .......................................................................................................................................... 76 4.3.1.3 Low Band Scenario ................................................................................................................................. 76 4.3.1.4 High Band Scenario ................................................................................................................................ 77 4.3.1.5 No Carbon Scenario ................................................................................................................................ 77 4.3.1.6 Forecasted Fundamental Parameters .................................................................................................... 77

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 5 of 1497

  • 4.4 PJM Capacity Performance Rule Impacts ............................................................................................... 81

    4.5 Demand-Side Management (DSM) Program Screening & Evaluation Process ........................................ 82 4.5.1 Overview .................................................................................................................................................... 82 4.5.2 Levels of Energy Efficiency (EE) Potential .................................................................................................. 82 4.5.3 Evaluating Incremental Demand-Side Resources ...................................................................................... 83 4.5.3.1 Incremental Energy Efficiency (EE) Modeled ......................................................................................... 83 4.5.3.2 Volt VAR Optimization (VVO) Modeled .................................................................................................. 86 4.5.3.3 Demand Response (DR) Modeled .......................................................................................................... 87 4.5.3.4 Distributed Generation (DG) .................................................................................................................. 88 4.5.3.5 Combined Heat and Power (CHP) .......................................................................................................... 89

    4.6 Identify and Screen Supply-side Resource Options ................................................................................. 89 4.6.1 Capacity Resource Options ........................................................................................................................ 89 4.6.2 New Supply-side Capacity Options ............................................................................................................ 90 4.6.3 Base/Intermediate Options ....................................................................................................................... 91 4.6.3.1 Natural Gas Combined Cycle (NGCC) ..................................................................................................... 92

    4.6.4 Peaking Options ......................................................................................................................................... 92 4.6.4.1 Simple Cycle Combustion Turbines (NGCT)............................................................................................ 93 4.6.4.2 Aeroderivatives (AD) .............................................................................................................................. 93 4.6.4.3 Reciprocating Engines (RE) ..................................................................................................................... 94 4.6.4.4 Battery Storage ...................................................................................................................................... 95

    4.6.5 Renewable Options .................................................................................................................................... 96 4.6.5.1 Solar ....................................................................................................................................................... 96

    4.6.5.1.1 Large-Scale Solar ................................................................................................................................. 96 4.6.5.1.2 Trends in Solar Energy Pricing ............................................................................................................ 98

    4.6.5.2 Wind ....................................................................................................................................................... 99 4.6.5.3 Hydro .................................................................................................................................................... 102 4.6.5.4 Biomass ................................................................................................................................................ 102

    4.7 Integration of Supply-Side and Demand-Side Options within Plexos Modeling ................................... 102 4.7.1 Optimization of Other Demand-Side Resources ...................................................................................... 103

    RESOURCE PORTFOLIO MODELING ..................................................................... 104 5.0

    5.1 The Plexos Model - An Overview ......................................................................................................... 104 5.1.1 Key Input Parameters .............................................................................................................................. 105

    5.2 Plexos Optimization ............................................................................................................................ 106 5.2.1 Modeling Options and Constraints .......................................................................................................... 106 5.2.2 Optimization Scenarios ............................................................................................................................ 108 5.2.2.1 Optimized Portfolios of Commodity Pricing Scenarios ........................................................................ 109 5.2.2.2 Optimized Portfolios of Load Scenarios ............................................................................................... 110

    5.3 Preferred Plan ...................................................................................................................................... 111 5.3.1 Demand-Side Program Levels .................................................................................................................. 112 5.3.2 Comparing the Cost of the Preferred Plan ............................................................................................... 113 5.3.3 Rate Impacts of the Preferred Plan ......................................................................................................... 115

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 6 of 1497

  • 5.3.4 Comparing Costs of Clean Power Plan Compliance ................................................................................. 117 5.3.5 Risk Analysis ............................................................................................................................................. 118 5.3.5.1 Stochastic Modeling Process and Results ............................................................................................ 119

    SUMMARY AND CONCLUSIONS ............................................................................... 122 6.0

    6.1 Conclusion ........................................................................................................................................... 128

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 7 of 1497

  • List of Figures

    Figure 1. Kentucky Power Service Territory ...................................................................................3

    Figure 2. Economic Impact of Lost Mining Load on KPCo Regional Economy ............................4

    Figure 3. KPCo Internal Energy Requirements and Peak Demand Forecasting Method ..............11

    Figure 4. Eastern Kentucky Coal Production (Millions of Tons) 2000-2015................................16

    Figure 5. KPCo Normalized Use per Customer (kWh) .................................................................22

    Figure 6. Projected Changes in Cooling Efficiencies, 2010-2030 .................................................23

    Figure 7. Projected Changes in Lighting and Clothes Washer Efficiencies, 2010-2030 ...............23

    Figure 8. Load Forecast Blending Illustration ...............................................................................25

    Figure 9. KPCo "Going-In" Capacity Position throughout Planning Period (2017-2031) ............36

    Figure 10. Total Energy Efficiency (GWh) Compared with Total Residential and

    Commercial Load (GWh) ............................................................................................49

    Figure 11. Residential and Commercial Forecasted Solar Installed Costs (Nominal $/WAC)

    for Kentucky ................................................................................................................54

    Figure 12. Breakeven Cost vs. Forecasted Installation Costs for Residential Rooftop Solar

    System; Discount Rate = 10%; Capacity Factor = 19.7% ...........................................55

    Figure 13. Breakeven Cost vs. Forecasted Installation Costs for Residential Rooftop Solar

    System; Discount Rate = 10%; Capacity Factor = 16% ..............................................56

    Figure 14. Range of Residential Distributed Solar Breakeven Values Based on Discount

    Rate; Capacity Factor = 19.7% ....................................................................................57

    Figure 15. Volt VAR Optimization Schematic ..............................................................................58

    Figure 16. Long-term Power Price Forecast Process Flow ............................................................74

    Figure 17. Dominion South Natural Gas Prices (Nominal $/mmBTU) .........................................78

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 8 of 1497

  • Figure 18. Dominion South Natural Gas Prices (2015 Real $/mmBTU) ......................................78

    Figure 19. NAPP High Sulfur Coal Prices (Nominal $/ton, FOB origin) .....................................79

    Figure 20. CO2 Prices (Nominal $/short ton).................................................................................79

    Figure 21. PJM On-Peak Energy Prices (Nominal $/MWh) .........................................................80

    Figure 22. PJM Off-Peak Energy Prices (Nominal $/MWh) .........................................................80

    Figure 23. PJM Capacity Prices (Nominal $/MW-Day) ................................................................81

    Figure 24. Energy Efficiency Bundle Levelized Cost vs. Potential Energy Savings for 2019......86

    Figure 25. KPCo Forecasted Rooftop Solar Installations ..............................................................88

    Figure 26. Large-Scale Solar Pricing Tiers with Investment Tax Credits .....................................98

    Figure 27. U.S. Average Solar Photovoltaic (PV) Installation Cost (Nominal $/WAC) Trends,

    excluding Investment Tax Credit Benefits ..................................................................99

    Figure 28. Levelized Cost of Electricity (LCOE) of Wind Resources (Nominal $/MWh) .........101

    Figure 29. KPCo Energy Efficiency Savings According to Preferred Plan ................................113

    Figure 30. Bill Impacts ($/Month) of Preferred Plan Compared to Do Nothing Plan .................115

    Figure 31. Range of Variable Inputs for Stochastic Analysis ......................................................119

    Figure 32. Revenue Requirement at Risk (RRaR) ($000) for Preferred Plan and Do Nothing

    Plan ............................................................................................................................120

    Figure 33. 2017 KPCo Nameplate Capacity Mix ........................................................................123

    Figure 34. 2031 KPCo Nameplate Capacity Mix ........................................................................123

    Figure 35. 2017 KPCo Energy Mix .............................................................................................124

    Figure 36. 2031 KPCo Energy Mix .............................................................................................124

    Figure 37. KPCo Annual PJM Capacity Position (MW) According to Preferred Plan ...............126

    Figure 38. KPCo Annual Energy Position (GWh) According to Preferred Plan.........................126

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 9 of 1497

  • List of Tables

    Table 1. PJM Energy and Capacity Prices in 2013 IRP and 2016 IRP, in 2011 $ ..........................6

    Table 2. Natural Gas and Coal Prices in 2013 IRP and 2016 IRP, in 2011 $ ..................................6

    Table 3. KPCo Existing Supply-Side Resources ...........................................................................35

    Table 4. Consent Decree Annual NOx Cap for AEP-East.............................................................43

    Table 5. Modified Consent Decree Annual SO2 Cap for AEP-East .............................................44

    Table 6. Modified Consent Decree Annual SO2 Cap for Rockport Plant .....................................44

    Table 7. KPCo State Mass-Based Clean Power Plan Goals ..........................................................46

    Table 8. KPCo State Rate-Based Clean Power Plan Goals ...........................................................46

    Table 9. Forecasted View of Relevant Residential Energy Efficiency Code Improvements ........48

    Table 10. Forecasted View of Relevant Non-Residential Energy Efficiency Code

    Improvements ..............................................................................................................48

    Table 11. Energy Efficiency Market Barriers ................................................................................52

    Table 12. Efficiency Potential for Industrial Sector, as Provided by AEG in the 2015 KPCO

    Market Potential Study ................................................................................................62

    Table 13. Incremental Residential Energy Efficiency (EE) Bundle Summary .............................84

    Table 14. Incremental Commercial Energy Efficiency (EE) Bundle Summary ............................85

    Table 15. Volt VAR Optimization (VVO) Tranche Profiles .........................................................87

    Table 16. Incremental Demand Response (DR) Resource Blocks ................................................87

    Table 17. New Generation Technology Options with Key Assumptions ......................................91

    Table 18. Optimization Scenarios ................................................................................................109

    Table 19. Cumulative PJM Capacity Additions (MW) and Energy Positions (GWh) for Mid,

    Low Band, High Band, and No Carbon Scenarios ....................................................110

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 10 of 1497

  • Table 20. Cumulative PJM Capacity Additions (MW) and Energy Positions (GWh) for Low

    and High Load Scenarios ...........................................................................................111

    Table 21. Cumulative PJM Capacity Additions (MW) and Energy Positions (GWh) for

    Preferred Plan.............................................................................................................112

    Table 22. Approximate Rate Impacts of Preferred Plan ..............................................................116

    Table 23. Estimated Costs of Mass-Based and Rate-Based Compliance with Clean Power

    Plan (CPP) ..................................................................................................................118

    Table 24. Risk Analysis Factors and Relationships .....................................................................119

    Table 25. Preferred Plan Capacity Additions throughout Planning Period (2017-2031) ............127

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 11 of 1497

  • Executive Summary

    This Integrated Resource Plan (IRP, Plan, or Report) is submitted by Kentucky Power

    Company (KPCo or Company) based upon the best information available at the time of its

    preparation. However, changes that impact this Plan can occur without notice. Therefore, as with

    any planning document, this Plan is not a commitment by the Company to specific resource

    additions or other courses of action, since the future is highly uncertain, particularly in light of

    current economic and political conditions, the movement towards increasing use of renewable

    generation and end-use efficiency, as well as current and future environmental regulations,

    including the U.S. Environmental Protection Agencys (EPA) Final Clean Power Plan (CPP).

    An IRP explains how a utility company plans to meet the projected capacity (i.e., peak

    demand) and energy requirements of its customers. KPCo is required to provide an IRP that

    encompasses a 15-year forecast period (in this filing, 2017-2031). KPCo plans to aggressively

    pursue economic development throughout its service territory, however, this IRP does not

    include any assumptions for economic development opportunities, but rather, has been

    developed using the Companys current long-term assumptions for:

    customer load requirements peak demand and energy;

    commodity prices coal, natural gas, on-peak and off-peak power prices, capacity

    and emission prices;

    supply-side alternative costs including fossil fuel and renewable resources; and

    demand-side program costs and impacts.

    In addition, KPCo considered the effect of environmental rules and guidelines, such as

    the CPP, which could add significant costs and present significant challenges to operations. The

    CPP is still being reviewed by the courts, and individual state plans to implement it may not be

    finalizedlet alone approvedfor a number of years. In preparing this Report, KPCo has analyzed

    multiple scenarios, with differing commodity pricing conditions, as well as multiple internal load

    conditions. KPCo has also conducted analyses which specifically address certain aspects of

    compliance with the CPP.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 12 of 1497

  • Summary of KPCo Resource Plan

    KPCos customers consist of both retail and wholesale customers located in the Eastern

    portion of the Commonwealth of Kentucky. Currently, KPCo serves approximately 168,000

    retail customers. The peak load requirement of KPCos total retail and wholesale customers is

    seasonal in nature, with distinctive peaks occurring in the summer and winter seasons. KPCos

    all-time highest recorded peak demand was 1,685 MW, which occurred in January 2005; and the

    highest recorded summer peak was 1,358 MW, which occurred in July 2005.

    Over the next 15 year period (2017-2031)1, KPCos service territory is expected to see

    population and non-farm employment decline 0.1% per year. KPCo is projected to see its

    customer count decline at a similar rate of 0.2% per year. Over the same forecast period, KPCos

    retail sales are projected to decline at 0.2% per year with growth expected from the industrial

    class (+0.1% per year) while the residential class experiences a decline (0.5% per year) over the

    forecast period. Finally, KPCos internal energy and peak demand are expected to decline at an

    average rate of 0.2% and 0.3% per year, respectively, through 2031.

    KPCos IRP provides adequate supply and demand resources to meet its peak load and

    energy obligations for the next fifteen years. The key intial assumptions in developing this plan

    are for Kentucky Power to:

    continue operation of the Mitchell Plant (KPCo share 780 MW);

    continue operation through 2030 of Big Sandy Unit 1 (285 MW) which was

    converted to burn natural gas instead of coal;

    continue to receive power under the Unit Power Agreement (UPA) from the

    Rockport Units (393 MW);

    add cost-effective wind and large-scale solar as needed to continue to

    diversify its mix of supply-side resources;

    incorporate demand-side resources, including but not limited to additional

    1 15 year forecast periods begin with the first full forecast year, 2017.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 13 of 1497

  • Energy Efficiency (EE) programs and Volt VAR Optimization (VVO)

    installations; and

    Residential and commercial customers will add distributed resources,

    primarily in the form of residential and commercial rooftop solar.

    Additionally, KPCo evaluated other supply- and demand-side measures and, as a result,

    expects that there will be opportunities for utility-scale storage (i.e. batteries) and Combined

    Heat and Power (CHP) resources in the KPCo service territiory within the next 10 years. KPCo

    also expects that customer-owned solar generation will continue to expand, further reducing the

    requirements for new utility-owned generation.

    The Rockport Plant UPA for 393 MW expires at the end of 2022. While KPCo is

    assuming, for purposes of this IRP, that the UPA will be renewed and continue through the

    planning period, the actual decision to extend the UPA will be made in the future. KPCo is

    currently committed to this purchase through 2022, and there remains much uncertainty with

    regard to load growth, carbon regulations, commodity pricing, and the future UPA cost.

    KPCo can meet its customers requirements with existing resources and modest

    investments in renewable resources and energy efficiency. Figure ES-1 below present KPCos

    Going-In capacity position. The Going-In position represents how KPCos existing and

    planned capacity resources would compare with the capacity requirements absent any

    incremental changes in capacity.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 14 of 1497

  • Figure ES-1. KPCo "Going-In" PJM Capacity Position (MW)

    To determine the appropriate level and mix of incremental supply-side and demand-side

    resources to include in its portfolio, KPCo utilized the Plexos Linear Program optimization

    model to develop least cost resource portfolios under a variety of pricing and load scenarios.

    Although the IRP planning period is limited to 15 years (through 2031), the Plexos modeling

    was performed through the year 2035, so as to properly consider various cost-based end-

    effects for the resource alternatives being considered.

    KPCo used the results of the modeling to develop a Preferred Plan. To arrive at the

    Preferred Plan composition, KPCo developed six Plexos-derived, optimum portfolios under

    four long-term commodity price forecasts, and two load sensitivity forecasts. The Preferred

    Plan is presented as an option that attempts to balance cost and other factors while meeting

    KPCos peak load obligations. In addition, this IRP considers existing and future environmental

    requirements, including those that may result from the CPP, and the practical limitations of

    customer self-generation.

    In summary, the Preferred Plan:

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 15 of 1497

  • invests $6 million/year in demand-side management through 2024;

    adds 75 MW (nameplate capacity)/year of wind resources beginning in 2018 for

    a total of 300 MW through 2021;

    adds utility scale solar, beginning with 10 MW in 2019, for a total of 130 MW

    by 2031.

    implements customer and grid EE programs, including VVO, reducing energy

    requirements by over 90 GWh and 70 MW of capacity by 2031;

    assumes KPCos customers add Distributed Generation (DG) (i.e. rooftop solar)

    capacity totaling 1.1 MW (nameplate) by 20312;

    adds 10MW (nameplate) of battery storage resources in 2025;

    assumes a host facility is identified such that a CHP project can be implemented

    by 2022;

    continues operation of KPCos existing generation facilities including Big

    Sandy 1 through 2030, and the KPCo share of the Mitchell Units (West

    Virginia), and

    continues the UPA for a 15% share of the energy and capacity from the

    Rockport Plant (Indiana)..

    Specific KPCo capacity changes over the 15-year planning period associated with the

    Preferred Plan are shown in Figure ES-2 and Figure ES-3, and their relative impacts on KPCos

    annual energy position are shown in Figure ES-4 and Figure ES-5 .

    2 KPCo does not have control over the amount, location or timing of these additions

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 16 of 1497

  • Figure ES-2. 2017 KPCo Nameplate Capacity Mix

    Figure ES-3. 2031 KPCo Nameplate Capacity Mix

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 17 of 1497

  • Figure ES-4. 2017 KPCo Energy Mix

    Figure ES-5. 2031 KPCo Energy Mix

    Figure ES-2 through Figure ES-5 indicate that this Preferred Plan would reduce KPCos

    reliance on coal-based generation and increase reliance on demand-side (EE, CHP, VVO) and

    renewable resources, further diversifying the portfolio. Specifically, over the 15-year planning

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 18 of 1497

  • horizon the Companys nameplate capacity mix attributable to coal-fired assets would decline

    from 80% to 71.3%. Natural Gas capacity would be 0% by 2031. Wind and solar assets climb

    from 0% to 26%, and demand-side resources (including EE, VVO, DG, Demand Response [DR],

    and CHP) increase from 0.5% to 2.5% over the planning period.

    KPCos energy output attributable to coal-fired generation shows a decrease from 94.9%

    to 82% over the period. The Preferred Plan shows a significant increase in renewable energy

    (wind and solar), from 0% to 14.9%. Energy from these renewable resources, combined with EE

    and VVO energy savings reduce KPCos exposure to energy, fuel and potential carbon prices.

    Figure ES-6 and Figure ES - 7 show annual changes in capacity and energy mix,

    respectively, that result from the Preferred Plan. The capacity contribution from renewable

    resources is fairly modest due to their intermittent performance, as well as the implications of

    PJMs Capacity Performance rule; however, those resources (particularly wind) provide a

    significant volume of energy. KPCos model selected those wind resources because they were

    lower cost than alternative resources. When comparing the capacity values in Figure ES-6 with

    those in Figure ES-2 and Figure ES-3, it is important to note that Figure ES-6 provides an

    analysis of PJM-recognized capacity, while Figure ES-2 and Figure ES-3 depict nameplate

    capacity.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 19 of 1497

  • Figure ES-6. KPCo Annual PJM Capacity Position (MW) According to Preferred Plan

    Figure ES - 7. KPCo Annual Energy Position (GWh) According to Preferred Plan

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 20 of 1497

  • Table ES-1 below provides a summary of the Preferred Plan.

    Table ES-1. Preferred Plan Capacity Additions throughout Planning Period (2017-2031)

    (1)

    (2)

    (3)

    (4)

    (5)

    (6)

    (7)

    (8)

    (9)

    (10)

    (11)

    (12)

    (13)

    (14)

    =(1)

    to(1

    3) e

    xcl(5

    )(1

    5)(1

    6)(1

    7)(1

    8)(1

    9)(2

    0)

    (Cum

    ulat

    ive)

    (Cum

    ulat

    ive)

    Exis

    ting

    Flee

    tEx

    istin

    g Fl

    eet

    (Cum

    ul.)

    VVO

    DRW

    ind

    (D)

    Batt

    ery(

    F)N

    ETW

    ind(

    D)Ba

    tter

    y(F)

    IRP

    Perio

    d

    PJM

    Pl

    anni

    ng

    Year

    (A)

    Unit

    Upra

    tes &

    De

    rate

    s

    PJM

    Cap

    acity

    Pe

    rfor

    man

    ce

    Impa

    ct (U

    CAP

    Redu

    ctio

    n)N

    G CH

    PN

    G C

    C

    Embe

    dded

    Fe

    dera

    l EE

    Regu

    latio

    ns

    (Non

    -DSM

    EE)

    (B

    )

    Curr

    ent

    DSM

    Pr

    ogra

    ms(C

    ) N

    ewN

    ew

    Pre-

    Exist

    ing

    DR

    Prog

    ram

    s(C)

    Larg

    e Sc

    ale

    Dis-

    trib

    uted

    'RES

    OUR

    CE'

    CHAN

    GE(K

    )

    PJM

    M

    inim

    um

    Rqrm

    nt(L

    )

    PJM

    Re

    serv

    e M

    argi

    nLa

    rge

    Scal

    eDi

    s-tr

    ibut

    ed

    Yr.

    MW

    MW

    MW

    MW

    MW

    MW

    MW

    MW

    MW

    MW

    MW

    MW

    MW

    MW

    MW

    %M

    WM

    WM

    WM

    W

    120

    175

    (G

    )-

    -

    -

    66

    9

    -

    -

    2

    -

    -

    0.

    1

    -

    16

    136

    12.4

    %-

    -

    0.2

    -

    220

    185

    -

    -

    -

    69

    16

    -

    -

    2

    4

    -

    0.1

    -

    2713

    512

    .2%

    75

    -

    0.2

    -

    320

    195

    -

    -

    -

    73

    19

    8

    -

    2

    8

    4

    0.1

    -

    4513

    612

    .2%

    150

    10

    0.2

    -

    420

    2011

    (H)

    -

    -

    -

    77

    19

    16

    -

    2

    11

    4

    0.

    1

    -

    62

    291

    29.3

    %22

    5

    10

    0.

    2

    -

    5

    2021

    11-

    -

    -

    80

    19

    25

    -

    2

    15

    8

    0.1

    -

    7930

    630

    .9%

    300

    20

    0.3

    -

    620

    2211

    -

    14

    -

    84

    19

    32

    -

    2

    15

    8

    0.

    1

    -

    10

    032

    733

    .0%

    300

    20

    0.3

    -

    720

    2311

    -

    14

    -

    87

    19

    40

    -

    2

    15

    11

    0.1

    -

    112

    338

    34.3

    %30

    0

    30

    0.

    3

    -

    8

    2024

    11-

    14

    -

    89

    19

    47

    -

    2

    15

    11

    0.

    2

    -

    11

    934

    334

    .9%

    300

    30

    0.4

    -

    920

    2511

    -

    14

    -

    92

    19

    50

    -

    2

    15

    15

    0.2

    5

    12

    534

    134

    .5%

    300

    40

    0.5

    10

    1020

    268

    (I)-

    14

    -

    94

    19

    53

    -

    2

    15

    15

    0.

    2

    5

    125

    335

    33.8

    %30

    0

    40

    0.

    5

    10

    11

    2027

    8-

    14

    -

    96

    19

    56

    -

    2

    15

    19

    0.

    2

    5

    132

    335

    33.8

    %30

    0

    50

    0.

    6

    10

    12

    2028

    8-

    14

    -

    97

    19

    58

    -

    2

    15

    19

    0.

    3

    5

    135

    328

    33.2

    %30

    0

    50

    0.

    7

    10

    13

    2029

    5(J)

    -

    14

    -

    99

    19

    58

    -

    2

    15

    27

    0.3

    5

    14

    032

    432

    .5%

    300

    70

    0.8

    10

    1420

    305

    -

    14

    -

    10

    1

    19

    61

    -

    2

    15

    34

    0.

    4

    5

    150

    331

    33.2

    %30

    0

    90

    0.

    9

    10

    15

    2031

    (280

    )(M

    )-

    14

    -

    103

    19

    66

    4

    2

    15

    49

    0.

    5

    5

    (111

    )93

    9.3%

    300

    13

    0

    1.

    1

    10

    (A) P

    JM P

    lann

    ing

    Year

    is e

    ffect

    ive

    6/1/

    XXXX

    .

    (C) R

    epre

    sent

    s est

    imat

    ed co

    ntrib

    utio

    n fr

    om cu

    rren

    t/kn

    own

    KPCo

    DSM

    -EE

    and

    Dem

    and

    Resp

    onse

    (Int

    erru

    ptib

    le, D

    LC/E

    LM) p

    rogr

    am a

    ctiv

    ity th

    roug

    h 20

    18; v

    alue

    s are

    bas

    elin

    ed fr

    om 2

    016

    (D) D

    ue to

    the

    inte

    rmitt

    ency

    of w

    ind

    reso

    urce

    s, K

    PCo

    assu

    mes

    5%

    of n

    amep

    late

    ' MW

    ratin

    g ar

    e in

    clude

    d fo

    r cap

    acity

    reso

    urce

    det

    erm

    inat

    ion

    purp

    oses

    bey

    ond

    2020

    .(E

    ) Due

    to th

    e in

    term

    itten

    cy o

    f sol

    ar re

    sour

    ces,

    Util

    ity a

    nd D

    istrib

    uted

    Sol

    ar re

    ceiv

    e 38

    % o

    f nam

    epla

    te M

    W ra

    ting

    for c

    apac

    ity re

    sour

    ce d

    eter

    min

    atio

    n pu

    rpos

    es.

    (F) D

    ue to

    the

    inte

    rmitt

    ency

    of b

    atte

    ry/s

    tora

    ge re

    sour

    ces,

    KPC

    o as

    sum

    es 5

    0% o

    f nam

    epla

    te M

    W ra

    ting

    for c

    apac

    ity re

    sour

    ce d

    eter

    min

    atio

    n pu

    rpos

    es.

    Chan

    ges t

    o ex

    istin

    g re

    sour

    ces P

    ost-J

    une

    1, 2

    017:

    (G) R

    ockp

    ort 1

    turb

    ine

    upgr

    ade.

    (H) R

    ockp

    ort 2

    turb

    ine

    upgr

    ade.

    (I) R

    ockp

    ort 1

    FGD

    par

    asiti

    c loa

    d in

    crea

    se.

    (J) R

    ockp

    ort 2

    FGD

    par

    asiti

    c loa

    d in

    crea

    se.

    (K)

    Inclu

    des c

    hang

    es in

    exis

    ting

    reso

    urce

    s plu

    s pla

    n ad

    ditio

    ns, e

    xclu

    ding

    colu

    mn

    5 "e

    mbe

    dded

    " EE

    and

    exist

    ing

    DR p

    rogr

    ams.

    (L)

    PJM

    min

    imum

    crite

    rion

    @16

    .5%

    as a

    func

    tion

    of p

    eak

    dem

    and

    effe

    ctiv

    e w

    ith th

    e 20

    19/2

    0 PY

    (pre

    viou

    sly @

    15.

    7%).

    (M) B

    ig S

    andy

    1 G

    as C

    onve

    rsio

    n un

    it re

    tirem

    ent

    Kent

    ucky

    Pow

    er C

    ompa

    ny

    131

    (Cum

    ulat

    ive)

    'N

    AMEP

    LATE

    ' ADD

    ITIO

    NS

    New

    -Bui

    ldEn

    ergy

    Eff

    icie

    ncy

    (EE)

    Sola

    r(E)

    Abov

    eSo

    lar(E

    )

    Pref

    erre

    d Pl

    an

    2016

    Inte

    grat

    ed R

    esou

    rce

    Plan

    Cum

    ulat

    ive

    Reso

    urce

    Cha

    nges

    - (M

    W)

    (Cum

    ulat

    ive)

    Firm

    Cap

    acity

    Res

    ourc

    e AD

    DITI

    ON

    SRe

    sulti

    ngKP

    Co R

    eser

    ves

    (B) R

    epre

    sent

    s est

    imat

    ed (p

    ost-2

    005)

    ene

    rgy

    effic

    ienc

    y le

    vels

    alre

    ady

    'em

    bedd

    ed' in

    to K

    PCo'

    s lon

    g-te

    rm lo

    ad &

    pea

    k de

    man

    d fo

    reca

    st b

    ased

    on

    emer

    genc

    e of

    prio

    r-es

    tabl

    ished

    Fed

    eral

    effi

    cienc

    y st

    anda

    reds

    (EPA

    ct

    2005

    ; 200

    7 EI

    SA, 2

    009

    ARRA

    ).

    Tota

    l Sol

    ar

    89To

    tal I

    ncre

    m. E

    nerg

    y Ef

    ficie

    ncy

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 21 of 1497

  • The Clean Power Plan (CPP) and KPCos Preliminary Modeling Assessment

    On October 23, 2015, EPA published a final rule the CPP - in the Federal Register

    establishing carbon dioxide (CO2) emission guidelines for existing fossil fueled electric

    generating units under Section 111(d) of the Clean Air Act. The CPP established interim and

    final uniform national emission standards for two subcategories of generating units: (1) fossil-

    fueled electric steam generating units; and (2) natural gas-fired combined-cycle units. EPA also

    determined equivalent state-specific CO2 emission rate-based goals and mass-based goals. The

    interim goals decline over the period from 2022-2029, with final goals effective in 2030 and

    beyond.

    Twenty-seven states, many utilities, coal producers, unions, national business

    associations and other interested parties challenged the final rule, and sought to stay its

    implementation pending judicial review. Although the D.C. Circuit denied these motions for

    stay, on February 9, 2016, the U.S. Supreme Court granted the applications, staying

    implementation of the CPP during review by the D.C. Circuit and any subsequent petitions for

    review by the Supreme Court.

    To account for potential incremental costs associated with the CPP or any future CO2

    regulations, KPCos commodity price forecast assumes costs associated with CO2 emissions will

    begin in 2024, escalating through 2030.

    Conclusion

    This IRP, based upon various assumptions, identifies adequate capacity resources at

    reasonable cost, through a combination of supply-side resources (including renewable supply-

    side resources) and demand-side programs throughout the forecast period.

    Moreover, this IRP also identifies a means to enhance KPCos energy position. The

    Preferred Plan offers incremental resources that will providein addition to PJM installed

    capacity to achieve mandatory PJM (summer) peak demand requirementsadditional energy to

    reduce the long-term exposure of the Companys customers to PJM energy markets.

    The portfolios discussed in this Report attribute limited capacity value for solar and wind

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 22 of 1497

  • resources, in part due to PJMs Capacity Performance rule. It is possible that intermittent

    resources can be combined, or coupled, and offered into the PJM market as Capacity

    Performance resources. Now that the final PJM Capacity Performance tariffs have been

    accepted, the Company will investigate methods to maximize the utilization of future

    intermittent resources within that construct. An example could be the additional coupling of wind

    and solar resources in a manner that would mitigate potentially costly non-performance risk.

    This IRP also addresses the Commission Staffs 2013 IRP recommendations. A table

    showing the location of KPCos responses to the staffs recommendations is included at the end

    of this executive summary, as well as in Exhibit A of the appendix to this report.

    The IRP process is a continuous activity; assumptions and plans are reviewed as new

    information becomes available and modified as appropriate. Indeed, the capacity and energy

    resource portfolios reported herein reflect, to a large extent, assumptions that are subject to

    change; an IRP is simply a snapshot of the future at a given time. As noted previously, this IRP

    is not a commitment to specific resource additions or other courses of action, as the future is

    highly uncertain. The resource planning process is becoming increasingly complex when

    considering pending regulatory restrictions, technology advancement, changing energy supply

    pricing fundamentals, uncertainty of demand and end-use efficiency improvements. These

    complexities exacerbate the need for flexibility and adaptability in any ongoing planning activity

    and resource planning process.

    To that end, KPCo intends to pursue the following three-year action plan:

    1. Pursue economic development opportunities to increase and diversify our industrial and commercial load. This includes looking at green power tariff alternatives for the growing number of customers who seek green power in the upcoming years.

    2. Continue the planning and regulatory actions necessary to implement cost-effective Demand-Side Management (DSM)/EE programs.

    3. Monitor renewable resource costs, particularly wind and solar, and based on consumer demand for green energy or other economic/strategic factors,

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 23 of 1497

  • determine the appropriate schedule to pursue cost-effective solicitations that would include self-build or acquisition options.

    4. Monitor the status of, and if necessary, participate in formulating plans for Kentucky (as well as West Virginia and Indiana) pertaining to the CPP. Once plans are established, perform specific assessments as to the implications of the CPP on KPCos resource profile. And

    5. Monitor this action plan and future IRPs to address changing circumstances.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 24 of 1497

  • Cross Reference Table of Staff Comments from 2013 Final IRP Report

    Topic Staff Comment Section Load Forecast

    Provide a comparison of forecasted winter and summer peak demands with actual results for the period following the 2013 IRP, along with a discussion of the reasons for the differences between forecasted and actual peak demands (update of one of the recommendations in the previous IRP Staff Report)

    2.12.5, 2.12.2

    Provide a comparison of the annual forecast of residential energy sales, using the current econometric models, with actual results for the period following the 2013 IRP. Include a discussion of the reasons for the differences between forecasted and actual results

    2.12.5, 2.12.1

    Depending on the timing of its next IRP filing, Kentucky Power should, as needed, update the information relied upon in developing its forecast in order to reflect a greater amount of actual data for the year in the forecast is prepared

    2.12.5

    DSM/EE Include all environmental costs, as they become known, in future benefit/cost analyses

    3.3.6

    Research and report on best practices for DSM/EE program promotion, educational programs, and innovative marketing opportunities;

    3.3.6

    Research and report on possible partnering with adjoining AEP operating companies in order to enhance marketing and reduce advertising costs by using common program titles and offerings

    3.3.6

    Report on work undertaken to enhance evaluation, measurement, and verification procedures to ensure DSM/EE programs are achieving expected goals

    3.3.6

    Report on the results of the market potential study and, specifically, on industrial sector potential for implementing DSM/EE measures

    3.3.6

    Monitor the PJM capacity markets for economic opportunities related to demand response and DSM/EE and include an update on the potential for bidding peak savings from demand response and DSM/EE in the PJM capacity markets

    3.3.6

    General Include a discussion of and any changes or modifications that are under consideration for the PCA, and potential impacts to Kentucky Power

    1.3

    Provide current specific discussions of pending renewable generation sought by Kentucky Power in its system, or by coordination with other utilities

    3.1

    Discuss the status of cogeneration and CHP opportunities in its 3.3.4.2

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 25 of 1497

  • service territory and the consideration given to cogeneration and CHP in the resource plan Identify and describe currently installed net metering systems 3.3.4.1 Provide a detailed discussion of the ways in which net metering systems are encouraged and considered in the IRP, along with customer specific statistics

    3.3.4.1

    Provide detailed discussions of the consideration, suitability, and evaluation given to distributed generation

    3.3.4

    Provide additional specific discussions of the improvements and more efficient utilization of generation, transmission and distribution facilities as required by 807 KAR 5:058, Section 8(2a). The discussion should cover all modifications since the filing of the 2013 IRP and should address Kentucky Power's plans for the three years immediately following the filing of its next IRP.

    3.1, 3.4.8, 3.5

    Discuss system reliability and the criteria used to determine appropriate summer and winter reserve margins. Identify the capacity margin required by PJM and how it correlates to the reserve margin the Company used prior to its RTO membership.

    3.1

    In addition to describing how Kentucky Power is addressing current and pending environmental regulations and anticipated new regulations and legislation, the next IRP should address the expected impact and changes on the costs and operations

    3.2, 5.3.3, 5.3.4

    Discuss how Kentucky Power has addressed uncertainty in modeling future load and the resources to meet that load.

    5.2.2

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 26 of 1497

  • Introduction 1.0

    1.1 Overview

    This Report presents the 2016 Integrated Resource Plan (IRP, Plan, or Report) for Kentucky

    Power Company (KPCo or Company) including descriptions of assumptions, study parameters,

    and methodologies. The results integrate supply- and demand-side resources.

    The goal of the IRP process is to identify the amount, timing and type of resources required to

    ensure a reliable supply of power and energy to customers at the least reasonable cost.

    In addition to developing a long-term plan for achieving reliability/reserve margin

    requirements as set forth by PJM, resource planning is critical to KPCo due to its impact on:

    Capital budgeting; rate case planning; and environmental compliance and other planning processes.

    1.2 Integrated Resource Plan (IRP) Process

    This Report covers the processes and assumptions used to develop the IRP for the

    Company. The IRP process for KPCo includes the following components/steps:

    Description of the Company, the resource planning process in general, and the

    implications of current issues as they relate to resource planning;

    provide projected growth in demand and energy which serves as the

    underpinning of the Plan;

    identify and evaluate demand-side options such as Energy Efficiency (EE)

    measures, Demand Response (DR) and Distributed Generation (DG);

    identify current supply-side resources, including projected changes to those

    resources (e.g., de-rates or retirements), and transmission system integration

    issues;

    identify and evaluate supply-side resource options; and

    perform resource modeling and use the results to develop various portfolios.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 27 of 1497

  • Figure 1. Kentucky Power Service Territory

    1.4 Power Coordination Agreement (PCA)

    Prior to 2014, the AEP-East utilities operated as part of the AEP integrated public utility

    holding company system under the now-repealed Public Utility Holding Company Act of 1935.

    As part of that arrangement, those companies coordinated the planning and operations of their

    respective generating resources pursuant to the AEP Interconnection Agreement (Pool or Pool

    Agreement). The Pool Agreement was terminated on January 1, 2014.

    As of January 1, 2014 KPCo has been responsible for maintaining an adequate level of

    power supply resources to meet its own load requirements for capacity, including any required

    reserve margin. KPCo is also a party to the Power Coordination Agreement (PCA)3. The most

    recent change to the PCA was the addition of Wheeling Power Company (WPCo) effective June

    1, 2015. This addition was the result of WPCo acquiring a 50% undivided interest in the Mitchell

    3 The Power Coordination Agreement currently provides Appalachian Power Company (APCo), Indiana Michigan Power (I&M), KPCo and Wheeling Power Company (WPCo) the opportunity to participate collectively (a) under a common Fixed Resource Requirement (FRR) capacity plan in PJM, and (b) in specified collective off-system sales and purchase activities. Under the Power Coordination Agreement, generation is not planned on a single-system basis as it was under the previous Pool Agreement. Rather, APCo, I&M, KPCo and WPCo individually are required to own or contract for sufficient generation to meet their respective load and reserve obligations. Additional information regarding the PCA as it pertains to Kentucky Power can be found in FERC Docket No. ER13-234.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 29 of 1497

  • Plant. This change had no impact on KPCos obligations under the PCA. No further changes to

    the PCA are under consideration at this time.

    1.5 The Impact of Coal Mining on KPCo Service Territory

    For decades, coal mining has been a significant portion of KPCos industrial load.

    Approximately 85% of KPCos customers live in counties that are part of the Appalachian coal

    basin. As market conditions and environmental regulations have evolved and gas prices have

    declined over the past decade, the demand for Appalachian coal produced in KPCos service

    territory has declined.

    While the direct impact of the lost mining loads within KPCos service territory has been

    severe, an indirect impact on other industries located within the area has also been felt. Since the

    2008 recession, mining employment within KPCos coal counties is down 68% (approximately

    7,900 jobs), while total employment is down 13%. KPCos residential customer counts have

    also dropped by 6% (approximately 8,000 customers) since the 2008 recession. The population

    within the coal counties has also declined by over 15,000 people since the recession. Figure 2

    below illustrates the overall impact the lost mining loads have had on the regional economy

    within KPCos service territory.

    Figure 2. Economic Impact of Lost Mining Load on KPCo Regional Economy

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 30 of 1497

  • 1.6 Significant Changes from the 2013 IRP

    KPCo generally updates its load forecast and commodity price forecasts on an annual

    basis. KPCo also monitors the cost of supply and demand side resources and incorporates the

    latest forecasts and trends into its analysis when preparing its IRP. The changes to the load

    forecast since the 2013 IRP filing are described in Section 2.9, Exhibit C-11 and Exhibit C-12 of

    this report. Pricing trends for renewable resources are generally discussed in Section 4.6.5,

    although the most significant change is related to wind and solar pricing, which now include the

    benefits of the production tax credit and investment tax credit, respectively, in their pricing

    assumptions. In the 2013 IRP, the Production Tax Credit (PTC) for wind was assumed to expire

    for projects not in service before 2017. In the 2016 IRP the PTC is now available on a

    diminishing scale for projects that begin construction prior to the end of 2019. For solar projects,

    in addition to extending the Investment Tax Credit (ITC) benefit, a lower priced tier of solar

    projects were also made available for modeling purposes.

    Changes to the fundamental pricing forecast reflect the impact lower natural gas prices

    have had on the energy market and demand for coal. Table 1 and Table 2 below show, in

    constant 2011 dollars, the difference in the base commodity price forecast for energy, capacity

    and fuels. Note that the current forecasts for all these commodities, with the exception of Powder

    River Basin coal, are now lower than previously forecasted.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 31 of 1497

  • Table 1. PJM Energy and Capacity Prices in 2013 IRP and 2016 IRP, in 2011 $

    Table 2. Natural Gas and Coal Prices in 2013 IRP and 2016 IRP, in 2011 $

    Finally, the assumptions regarding Carbon Dioxide (CO2) pricing have also been revised.

    In the 2013 IRP, a $15/ton cost, in nominal dollars, associated with emitting CO2 would take

    effect in 2022, and this cost would remain flat through the forecast period. The 2016 forecast

    2013 IRP 2016 IRP 2013 IRP 2016 IRP 2013 IRP 2016 IRP2017 $50.35 $24.12 $32.26 $19.16 $113.52 $114.592018 $49.80 $30.87 $32.38 $22.26 $167.62 $123.402019 $49.24 $33.18 $32.37 $24.54 $176.81 $96.042020 $49.59 $33.87 $32.87 $25.70 $185.83 $41.552021 $50.52 $34.17 $33.33 $25.87 $194.93 $17.952022 $56.10 $34.53 $41.56 $26.11 $204.01 $17.562023 $56.09 $34.88 $41.40 $26.05 $213.09 $17.182024 $56.01 $36.87 $41.49 $28.37 $222.27 $16.822025 $55.99 $38.56 $41.35 $30.30 $231.22 $16.472026 $55.75 $40.15 $41.11 $32.06 $240.15 $16.132027 $55.75 $41.88 $40.84 $33.92 $249.07 $22.912028 $55.54 $43.46 $40.78 $35.59 $258.10 $31.072029 $55.50 $45.46 $40.77 $37.48 $260.33 $40.402030 $54.86 $48.26 $40.74 $39.33 $260.33 $50.902031 $54.76 $50.43 $40.86 $41.72 $260.33 $62.57

    On-Peak Energy Prices Off-Peak Energy Prices Capacity Prices

    2013 IRP 2016 IRP 2013 IRP 2016 IRP 2013 IRP 2016 IRP2017 $5.48 $2.74 $46.57 $32.92 $11.60 $11.542018 $5.45 $4.04 $48.02 $33.80 $11.54 $10.802019 $5.39 $4.18 $50.02 $35.43 $11.89 $14.702020 $5.47 $4.18 $51.13 $36.99 $12.49 $16.282021 $5.61 $4.18 $50.15 $36.10 $12.18 $17.022022 $5.82 $4.22 $50.13 $35.25 $12.62 $17.122023 $5.78 $4.23 $51.19 $34.43 $12.80 $15.412024 $5.82 $4.31 $50.24 $36.62 $12.35 $15.712025 $5.87 $4.38 $49.32 $37.25 $12.05 $16.482026 $5.82 $4.45 $48.33 $35.97 $11.93 $18.082027 $5.82 $4.55 $47.36 $36.45 $11.85 $16.952028 $5.83 $4.64 $46.11 $35.33 $11.77 $17.122029 $5.83 $4.73 $45.50 $34.01 $11.87 $19.532030 $5.79 $4.85 $45.21 $34.81 $13.06 $18.592031 $5.81 $4.94 $44.41 $35.45 $14.31 $20.52

    (A) TCO = Columbia Gas Transmission Corporation(B) Powder River Basin (PRB) Coal, 8,800 Btu/lb.

    Nat. Gas TCO(A)-Delivered Illinois Basin Coal PRB - 8800 Coal(B)

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 32 of 1497

  • assumes costs associated with CO2 would not begin until 2024, and those costs would start at

    $3/ton, but escalate to $20/ton by 2030.

    Changes in the load forecast, commodity price forecast, and resource pricing assumptions

    have resulted in a resource plan recommendation that is different than the one proposed in 2013.

    The 2016 Preferred Plan includes 300 MW of wind, compared to the 2013 plan which added 100

    MW. The utility scale solar profile is very similar with the 2016 plan adding 130 MW of utility

    scale solar by 2031 compared to the 2013 plan adding 90 MW by 2028. The 2013 plan included

    an aggressive 41 MW of DG by 2028, while the 2016 plan has only 1 MW, based on current

    trends. The 2016 plan replaced the 59 MW biomass project with a 15 MW Combined Heat and

    Power (CHP) installation, and adds a 10 MW battery. Demand side programs, including Volt

    VAR Optimization (VVO) have more than doubled in the 2016 plan compared to the 2013 plan,

    from 44 MW to 89 MW.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 33 of 1497

  • Load Forecast and Forecasting Methodology 2.0

    2.1 Summary of KPCo Load Forecast

    The KPCo load forecast was developed by the American Electric Power Service

    Corporation (AEPSC) Economic Forecasting organization and completed in June 2016.4 The

    final load forecast is the culmination of a series of underlying forecasts that build upon each

    other. In other words, the economic forecast provided by Moodys Analytics is used to develop

    the customer forecast, which is then used to develop the sales forecast, which is ultimately used

    to develop the peak load and internal energy requirements forecast.

    Over the next 15-year period (2017-2031)5, KPCos service territory is expected to see

    population and non-farm employment decline of 0.1% per year. KPCo is projected to see

    customer count decline at a similar rate of 0.2% per year. Over the same forecast period, KPCos

    retail sales are projected to decline at 0.2% per year with growth expected from the industrial

    class (+0.1% per year) while the residential class experiences a decline (0.5% per year) over the

    forecast horizon. Finally, KPCos internal energy and peak demand are expected to decline at an

    average rate of 0.2% and 0.3% per year, respectively, through 2031.

    2.2 Forecast Assumptions

    2.2.1 Economic Assumptions

    The load forecasts for KPCo and the other operating companies in the AEP System

    incorporate a forecast of U.S. and regional economic growth provided by Moodys Analytics.

    The load forecasts utilized Moodys Analytics economic forecast issued in December 2015.

    4 The load forecasts (as well as the historical loads) presented in this Report reflect the traditional concept of internal load, i.e., the load that is directly connected to the utilitys transmission and distribution system and that is provided with bundled generation and transmission service by the utility. Such load serves as the starting point for the load forecasts used for generation planning. Internal load is a subset of connected load, which also includes directly connected load for which the utility serves only as a transmission provider. Connected load serves as the starting point for the load forecasts used for transmission planning. 5 Fifteen year forecast period begins with the first full forecast year of 2017.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 34 of 1497

  • Moodys Analytics projects moderate growth in the U.S. economy during the 2017-2031 forecast

    period, characterized by a 2.0% annual rise in real Gross Domestic Product (GDP), and moderate

    inflation, with the implicit GDP price deflator expected to rise by 2.0% per year. Industrial

    output, as measured by the Federal Reserve Board's (FRB) index of industrial production, is

    expected to grow at 1.5% per year during the same period. Moodys projects employment growth

    of -0.1% per year during the forecast period and real regional income per-capita annual growth

    of 2.1% for the KPCo service area.

    2.2.2 Price Assumptions

    The Company utilizes an internally developed service area electricity price forecast. This

    forecast incorporates information from the Companys financial plan for the near term and the

    U.S. Department of Energy (DOE) Energy Information Administration (EIA) outlook for the

    East North Central Census Region for the longer term. These price forecasts are incorporated

    into the Companys energy sales models, where appropriate.

    2.2.3 Specific Large Customer Assumptions

    KPCos customer service engineers are in frequent touch with industrial and commercial

    customers about their needs and activities. From these discussions, expected load additions or

    deletions are relayed to the Company.

    2.2.4 Weather Assumptions

    Where appropriate, the Company includes weather as an explanatory variable in its

    energy sales models. These models reflect historical weather for the model estimation period and

    normal weather for the forecast period.

    2.2.5 Demand Side Management (DSM) Assumptions

    The Companys long term load forecast models account for trends in EE both in the

    historical data as well as the forecasted trends in appliance saturations as the result of various

    legislated appliance efficiency standards (Energy Policy Act of 2005 [EPAct], Energy

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 35 of 1497

  • Independence and Security Act [EISA] of 2007, etc.) modeled by the EIA. In addition to general

    trends in appliance efficiencies, the Company also administers multiple Demand-Side

    Management (DSM) programs that the Commission approved as part of its DSM portfolio. The

    load forecast utilizes the most current Commission-approved programs at the time the load

    forecast is created to adjust the forecast for the impact of these programs.

    2.3 Overview of Forecast Methodology

    KPCo's load forecasts are based mostly on econometric, statistically adjusted end-use and

    analyses of time-series data. This is helpful when analyzing future scenarios and developing

    confidence bands in addition to objective model verification by using standard statistical criteria.

    KPCo utilizes two sets of econometric models: 1) a set of monthly short-term models

    which extends for approximately 24 months and 2) a set of monthly long-term models which

    extends for approximately 30 years. The forecast methodology leverages the relative analytical

    strengths of both the short- and long-term methods to produce a reasonable and reliable forecast

    that is used for various planning purposes.

    For the first full year of the forecast, the forecast values are generally governed by the

    short-term models. The short-term models are regression models with time series errors which

    analyze the latest sales and weather data to better capture the monthly variation in energy sales

    for short-term applications like capital budgeting and resource allocation. While these models

    produce extremely accurate forecasts in the short run, without logical ties to economic factors,

    they are less capable of capturing structural trends in electricity consumption that are more

    important for longer-term resource planning applications.

    The long-term models are econometric, and statistically adjusted end-use models which

    are specifically equipped to account for structural changes in the economy as well as changes in

    customer consumption due to increased energy efficiency. The long-term forecast models

    incorporate regional economic forecast data for income, employment, households, output, and

    population.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 36 of 1497

  • The short-term and long-term forecasts are then blended to ensure a smooth transition

    from the short-term to the long-term forecast horizon for each major revenue class. There are

    some instances when the short-term and long-term forecasts diverge, especially when the long-

    term models are incorporating a structural shift in the underlying economy that is expected to

    occur within the first 24 months of the forecast horizon. In these instances, professional

    judgment is used to ensure that the final forecast that will be used in the peak models is

    reasonable. The class level sales are then summed and adjusted for losses to produce monthly net

    internal energy sales for the system. The demand forecast model utilizes a series of algorithms to

    allocate the monthly net internal energy to hourly demand. The inputs into forecasting hourly

    demand are internal energy, weather, 24-hour load profiles and calendar information.

    A flow chart depicting the sequence of models used in projecting KPCos electric load

    requirements as well as the major inputs and assumptions that are used in the development of the

    load forecast is shown in Figure 3, below.

    Figure 3. KPCo Internal Energy Requirements and Peak Demand Forecasting Method

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 37 of 1497

  • 2.4 Detailed Explanation of Load Forecast

    2.4.1 General

    This section provides a more detailed description of the short-term and long-term models

    employed in producing the forecasts of KPCos energy consumption, by customer class.

    Conceptually, the difference between short- and long-term energy consumption relates to

    changes in the stock of electricity-using equipment and economic influences, rather than the

    passage of time. In the short term, electric energy consumption is considered to be a function of

    an essentially fixed stock of equipment. For residential and commercial customers, the most

    significant factor influencing the short term is weather. For industrial customers, economic

    forces that determine inventory levels and factory orders also influence short-term utilization

    rates. The short-term models recognize these relationships and use weather and recent load

    growth trends as the primary variables in forecasting monthly energy sales.

    Over time, demographic and economic factors such as population, employment, income,

    and technology influence the nature of the stock of electricity-using equipment, both in size and

    composition. Long-term forecasting models recognize the importance of these variables and

    include all or most of them in the formulation of long-term energy forecasts.

    Relative energy prices also have an impact on electricity consumption. One important

    difference between the short-term and long-term forecasting models is their treatment of energy

    prices, which are only included in long-term forecasts. This approach makes sense because

    although consumers may suffer sticker shock from energy price fluctuations, there is little they

    can do to impact them in the short-term. They already own a refrigerator, furnace or industrial

    equipment that may not be the most energy-efficient model available. In the long term, however,

    these constraints are lessened as durable equipment is replaced and as price expectations come to

    fully reflect price changes.

    KPSC Case No. 2016-00413 2016 Integrated Resource Plan

    Of Kentucky Power Company Volume A - Public Version

    Page 38 of 1497

  • 2.4.2 Customer Forecast Models

    The Company also utilizes both short-term and long-term models to develop the final

    customer count forecast. The short-term customer forecast models are time series models with

    intervention (when needed) using Autoregressive Integrated Moving Average (ARIMA) methods

    of estimation. These models typically extend for 24 months into the forecast horizon.

    The long-term residential customer forecasting models are also monthly but extend for 30

    years. The explanatory jurisdictional economic and demographic variables include gross regional

    product, employment, mortgage rate, population, real personal income and households are used

    in various combinations. In addition to the economic explanatory variables, the long-term

    customer models employ a lagged dependent variable to capture the adjustment of customer

    growth to changes in the economy. There are also binary variables to capture monthly variations

    in customers, unusual data points and special occurrences.

    The short-term and long-term customer forecasts are blended as was de