Integrated Cost Schedule Risk Analysis3885
-
Upload
gerry-triaz -
Category
Documents
-
view
59 -
download
0
description
Transcript of Integrated Cost Schedule Risk Analysis3885
Integrated Cost / Schedule Risk Analysis
© 2004 Hulett & Associates, LLC. 1
A presentation to the NASA Project Management Conference
March 30 and 31, 2004
David T. Hulett, Ph.D.Hulett & Associates, LLC
Los Angeles, CA(310) 476-7699 / [email protected]
www.projectrisk.com
Cost and Schedule Risk Integration
© 2004 Hulett & Associates, LLC. 2
“Burn Rate” Time Independent Costs
Variable Costs
Project Schedule Risk
Cost Risk
Risk
Time
Project Cost Risk
We do not deal with Time Independent
costs here
Cost Estimating Basics
© 2004 Hulett & Associates, LLC. 3
• Cost estimates can be constructed by multiplying:– People assigned – Daily Rate– Duration
• Uncertainty in any of these variables leads to uncertainty in project cost estimates
• Cost risk estimating can be more accurate and the reasons for risk better illuminated when time and cost factors are addressed individually rather than as one cost uncertainty distribution
Simple Equation for Cost of an Activity
© 2004 Hulett & Associates, LLC. 4
Base Cost Estimate
Duration 40
People average 5Daily Rate average 800
Total Cost 160,000
How Likely are We to
Overrun the Estimate of
$160,000 for this Task?
Uncertainty in Time and in Cost Elements
© 2004 Hulett & Associates, LLC. 5
Low ML High
Duration 40 30 40 60
People 5 3 5 8
Daily Rate 800 750 800 875
Total Cost 160,000
Compare Cost and Time Uncertainty Results
© 2004 Hulett & Associates, LLC. 6
Cost Risk
Percentile Vary Only Cost Elements
Vary only Task Time
Cost and Time Vary
(000)0% 98.0 121.6 81.6
10% 128.5 141.9 132.620% 142.7 150.9 147.630% 152.4 157.9 159.140% 160.9 164.0 171.050% 170.8 170.7 182.760% 178.8 178.0 193.870% 190.1 186.3 206.380% 202.3 196.0 223.790% 219.5 209.0 248.0
100% 262.4 238.0 350.1
$160,000 is 31%(vs. 33%-39% with cost
or time separately)
80th Percentile is NOW $223.7 thousand
(vs. $202-209 thousand)
© 2004 Hulett & Associates, LLC. 7
Varying both Cost and Time Elements Provides a More Accurate Picture of Cost Risk
Cost Uncertainty Varying only Cost Elements, Only Task Druation and Both Duration and Cost Elements
0%
20%
40%
60%
80%
100%
80,000 130,000 180,000 230,000 280,000 330,000
Cost
Perc
entil
e
CostRiskOnly
TimeRiskOnlyCost &TimeRisk
© 2004 Hulett & Associates, LLC. 8
Time / Cost Pairs for 1,000 Iterations, Compared with the Target Values
Date Cost Scatter And Analysis
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
400,000
9/26 10/1 10/6 10/11 10/16 10/21 10/26 10/31
Overrun cost and time is 54% likely
Overrun Cost is 70% likely
Overrun time (10/10 = 40 days)
is 67% likely
Meeting both cost and time is
17% likely
© 2004 Hulett & Associates, LLC. 9
Cost / Schedule Risk using a Schedule with Detail and Summary Activities
ID Task Name Duration Start Finish0 Integrated Cost-Schedule 163 d 9/1 2/101 Start 0 d 9/1 9/12 Component 1 98 d 9/1 12/73 Design 1 28 d 9/1 9/284 Build 1 45 d 9/29 11/125 Test 1 25 d 11/13 12/76 Component 2 95 d 9/1 12/47 Design 2 32 d 9/1 10/28 Build 2 38 d 10/3 11/99 Test 2 25 d 11/10 12/410 Integration and Test 65 d 12/8 2/1011 Integrate 40 d 12/8 1/1612 System Test 25 d 1/17 2/1013 Finish 0 d 2/10 2/10
Designers[5]Builders[10]
Testers[8]
Designers[7]Builders[8]
Testers[5]
Integrators[12]Testers[9]
3rd Quarter 4th Quarter 1st Quarter 2nd Qua
Schedule is defined and statused at detail level, whereas cost is often estimated and collected at summary level
© 2004 Hulett & Associates, LLC. 10
Computing Schedule Risk when Cost and Schedule are in Separate Programs: Example
• Using Risk+®, simulate the MS Project schedule, collecting duration results for the summary activity
• Inputs– 3-point estimates for duration of tasks– Distribution shape for each task
• Outputs– Duration results for the summary tasks– Summary activity duration for each iteration
Inputs to Schedule Risk Analysis
© 2004 Hulett & Associates, LLC. 11
Schedule Risk InputsReport ID Min Rdur ML Rdur Max Rdur Curve
Component 1 1Design 1 0 20 d 28 d 45 d 2
Build 1 0 35 d 45 d 55 d 2
Test 1 0 20 d 25 d 50 d 2
Component 2 1Design 2 0 24 d 32 d 43 d 2
Build 2 0 35 d 38 d 47 d 2
Test 2 0 20 d 25 d 45 d 2
Integration and Test 1Integrate 0 35 d 40 d 55 d 2
System Test 0 20 d 25 d 60 d 2
Schedule Risk Analysis for Integration and Test
© 2004 Hulett & Associates, LLC. 12
Date: 9/1/2003 4:05:56 PMSamples: 1000Unique ID: 18Name: Integration and Test
Completion Std Deviation: 12.72 d95% Confidence Interval: 0.79 dEach bar represents 4 d
Completion Date
Freq
uenc
y
Cum
ulat
ive
Prob
abilit
y3/72/8 4/15
0.1
0.2
0.30.4
0.5
0.60.7
0.8
0.91.0
0.02
0.04
0.06
0.08
0.10
0.12
0.14 Completion Probability Table
Prob ProbDate Date0.05 2/170.10 2/210.15 2/230.20 2/250.25 2/270.30 2/290.35 3/10.40 3/30.45 3/40.50 3/6
0.55 3/80.60 3/90.65 3/110.70 3/130.75 3/160.80 3/180.85 3/210.90 3/250.95 3/311.00 4/15
Dates do not equate to durations for this activity because of uncertainty in the predecessor activities
Duration Results for Summary Tasks
© 2004 Hulett & Associates, LLC. 13
Schedule Measure Scheduled Mean Standard Deviation
(days)
Total Project 163 176.6 9.2
Component 1 98 101.0 8.0
Component 2 95 101.3 7.8
Integration and Test 65 71.0 6.3
For the cost risk we use simulation results for durations of summary tasks or phases. This is a table summarizing
duration results.
© 2004 Hulett & Associates, LLC. 14
Computing Schedule Risk when Cost and Schedule are in Separate Programs (continued)
• Input the duration risk results into the MS Excel spreadsheet that contains the cost model– Fit the available Crystal Ball® functions to the 1,000
iteration results for phase durations– Input the fit distributions as assumptions to the cost risk
model– Add interview results for the burn rate uncertainty in the
cost model
© 2004 Hulett & Associates, LLC. 15
Estimate the Best-Fitting Distribution Available in Crystal Ball for Summary Task DurationsComponent 1:
Lognormal
Component 2: Lognormal Integration and
Test: Gamma
© 2004 Hulett & Associates, LLC. 16
Baseline Cost Estimate from the Resource Loaded and Priced Schedule
Activity Estimated Cost
(000)Integrated Cost-Schedule Project $1,629 Component 1 $557
Design 1 $101 Build 1 $288 Test 1 $168
Component 2 $461 Design 2 $161 Build 2 $195 Test 2 $105
Integration and Test $611 Integrate $422 System Test $189
Cost is $1,629,000 if everything goes “according to plan”
© 2004 Hulett & Associates, LLC. 17
Combine Duration Burn Rate Risks: Component 1 Example
Component 1 Baseline Estimate Cost (000) Low Most
Likely High
Avg. Workers per day 8.1 6 8 12
Avg. Rate / Hour 88.1 80 88 91
Duration from Schedule 98.0 Est. Lognormal distribution
Component 1 Cost 557
The Lognormal distribution was estimated from the 1,000 duration results for Component 1
© 2004 Hulett & Associates, LLC. 18
Cost Risk With Cost Elements’, Schedule Elements’ and All Elements’ Risk Included
Build-Up of Total Project Cost Risk
0%
20%
40%
60%
80%
100%
1,200 1,500 1,800 2,100 2,400
Cost (000)
TimeRiskOnly
CostRiskOnly
Time &CostRisks
Including both Cost and Schedule risk elements provides a more complete estimate of cost risk
Components of Total Project Cost Risk
© 2004 Hulett & Associates, LLC. 19
Components of Total Project Cost Risk
0%
20%
40%
60%
80%
100%
300 600 900 1,200 1,500 1,800 2,100 2,400
Cost (000)
Comp. 1Comp. 2Integ. & TestTotal Project
Picture of a Troubled Project
© 2004 Hulett & Associates, LLC. 20
Cost / Schedule "Football" All Risks
1,000
1,2001,400
1,6001,800
2,000
2,2002,400
2,600
1/24/04 2/3/04 2/13/04 2/23/04 3/4/04 3/14/04 3/24/04
Date
Cos
t (00
0)
Cost /Schedule
Target
3%
78%
Joint scatter plot of cost and schedule compared to the baseline estimates without risk. For this plot we have to schedule in Excel, a risky business
© 2004 Hulett & Associates, LLC. 21
Computing Schedule Risk when Cost and Schedule are in the Scheduling Program
• Resources are identified and their hourly or daily cost are input into the scheduling software
• Resources are assigned to tasks and costs of those tasks and the total project are computed
• Uncertainty can be added by:– Probability distribution of the duration– Probability distribution of the burn rate
• Jointly simulate the cost and schedule in the program
Cost and Cost Risk in Scheduling Software
© 2004 Hulett & Associates, LLC. 22
Examples of Component 1 resource loading included in scheduling software – Pertmaster®
Add Duration and Burn Rate Uncertainty
© 2004 Hulett & Associates, LLC. 23
Examples of Component 1 duration and burn rate uncertainty included in scheduling software – Pertmaster®
Cost and Cost Risk in Scheduling Software
© 2004 Hulett & Associates, LLC. 24
Examples of Component 1 resources, costs, and time and burn rateuncertainty included in scheduling software – Monte Carlo®
Integrated Cost and Schedule Risk Results
© 2004 Hulett & Associates, LLC. 25
27/Jan/04 08/Feb/04 21/Feb/04 05/Mar/04 18/Mar/04
Entire Plan Finish
$1,424,930
$1,507,017
$1,589,103
$1,671,190
$1,753,276
$1,835,363
$1,917,449
$1,999,536
$2,081,622
$2,163,709
Entir
e Pl
an C
ost
Integrated Cost-ScheduleScatter Plot
Date and Cost Scatter plot from Pertmaster® schedule risk software
Integrated Cost and Schedule Risk Results
© 2004 Hulett & Associates, LLC. 26Date and Cost Scatter plot from Monte Carlo® schedule risk software
Summary of Main Principles
© 2004 Hulett & Associates, LLC. 27
• Cost risk depends on elements of schedule uncertainty
• The cost estimate is not secure if the schedule is slipping
• Distinguishing the schedule risk elements and their impact on the cost estimate risk provides a more accurate picture of cost risk
• Data gathering on burn rate demands new thinking
Technical Summary
© 2004 Hulett & Associates, LLC. 28
• Cost estimation is often conducted at a level more summary than scheduling
• If the resources and cost are not included in the schedule– Estimating duration uncertainty of a summary task using a
schedule risk analysis program– Use fitted probability distribution of duration as an input to the
cost risk model– Add burn rate uncertainty
• There are other costs that are not sensitive to time. We have not analyzed those in this paper
Technical Summary (continued)
© 2004 Hulett & Associates, LLC. 29
• If the resources are loaded and priced in the schedule software, at least two schedule risk packages can perform the integrated cost / schedule risk analysis
• Simultaneous simulation ensures that the concepts and the results are consistent
• Not many schedules have fully-loaded and priced out the resources, however
Integrated Cost / Schedule Risk Analysis
© 2004 Hulett & Associates, LLC. 30
A presentation to the NASA Project Management Conference
March 30 and 31, 2004
David T. Hulett, Ph.D.Hulett & Associates, LLC
Los Angeles, CA(310) 476-7699 / [email protected]
www.projectrisk.com