Instrumentation Construction Activity

download Instrumentation Construction Activity

of 22

Transcript of Instrumentation Construction Activity

  • 7/28/2019 Instrumentation Construction Activity

    1/22

    Instrument Field documents andCommissioning Activities

  • 7/28/2019 Instrumentation Construction Activity

    2/22

    Page 2 of 22

    Table of Contents

    1. Symbols and abbreviations .................................................................................................... 3

    2. General .................................................................................................................................. 3

    3. Instrumentation receiving and storage ................................................................................... 4

    3.1. General ....................................................................................................................... 4

    3.2. Electronic instruments................................................................................................. 4

    3.3. Pneumatic instruments ............................................................................................... 4

    3.4. Local control panels .................................................................................................... 5

    3.5. Dial thermometers, pressure gauges, and gauge glasses ........................................... 5

    4. Documentation....................................................................................................................... 54.1. General ....................................................................................................................... 5

    4.2. Records ...................................................................................................................... 6

    5. Installation inspection............................................................................................................. 6

    5.1. Prerequisites ............................................................................................................... 6

    5.2. General ....................................................................................................................... 6

    5.3. Instrument inspection checks ...................................................................................... 7

    5.4. Piping, conduit, cable, and tubing ............................................................................... 8

    5.5. Control valves inspection checks ................................................................................ 9

    5.6. Temperature instruments inspection checks ............................................................... 9

    5.7. Flow instruments....................................................................................................... 105.8. Level instruments ...................................................................................................... 11

    6. Loop check and system checkout ........................................................................................ 11

    6.1. Prerequisites ............................................................................................................. 11

    6.2. General ..................................................................................................................... 12

    6.3. Instrument calibration and checkout ........................................................................ 122

    6.4. Systems checkout ................................................................................................... 200

    6.5. Alarm system components ...................................................................................... 211

    6.6. Logic system components....................................................................................... 211

    7. Commissioning completion 22

  • 7/28/2019 Instrumentation Construction Activity

    3/22

    Page 3 of 22

    1. Symbols and abbreviations

    a.c. Alternating current.

    DCS Distributed control system.

    d/p Differential pressure.

    I/E Instrument/Electrical.

    I/P Current-to-pressure.

    IS Intrinsic safety.

    LRV Lower range value.

    P&ID Piping and instrument diagram.

    PAS Process automation system.

    PLC Programmable logic controller.

    RTD Resistance temperature detector.

    SIS Safety instrumented system.

    URV Upper range value.

    2. General

    a. For all checkout and commissioning activities, safety shall be the primary concern and

    responsibility of all involved personnel. It is required that all commissioning personnel bequalified to perform their assigned activities.

    b. Personnel involved in calibration and commissioning of instrument systems shall have

    experience and verifiable training to included but not limited to the following:

    1. Calibration of instruments being installed.

    2. Use of compression fittings.

    3. Installation/inspection of electrical equipment in hazardous areas.

    c. Commissioning personnel shall review, be familiar with, and adhere to all relevant

    portions of Health, Safety and Environmental (HSE) documents and procedures.

    d. Prior to commencing any work, a Job Safety Analysis (JSA) or other equivalent, site

    specific, procedure shall be conducted to confirm that persons involved are trained andcompetent, ensure that appropriate Personal Protection Equipment (PPE) is worn, reviewemergency response plans, and emphasize that each person is empowered to stop the work

    if it is perceived to be unsafe.

    e. If hazardous materials (chemicals, fluids, etc.) are part of the commissioning procedure,

    Material Safety Data Sheets (MSDS) shall be reviewed by all involved personnel prior toproceeding with any related commissioning activity.

    f. The safe and efficient commissioning of any facility requires associated instrumentation to

    be installed completely, checked for integrity and commissioned for use. The stepsinvolved in achieving this process should be clearly understood and followed.

  • 7/28/2019 Instrumentation Construction Activity

    4/22

    Page 4 of 22

    g. Refer to Annex A for examples of checkout and pre-commissioning of instrument and

    control systems.

    h. Prior to initiating any checkout and/or commissioning activities, mechanical completion

    checklists and other appropriate documents shall be reviewed and confirmed as complete

    and all components are acceptable for subsequent commissioning efforts.

    i. Defective instruments shall be replaced or repaired.

    3. Instrumentation receiving and storage

    3.1. General

    a. Upon receipt, instruments shall be checked for:

    1. Compliance with purchase specifications.

    2. Correct tagging.

    3. Shipping damage.

    4. Relevant documentation (installation and handling instructions).

    b. After inspection, instruments shall be:

    1. Replaced in their original factory boxes.

    2. Correctly tagged.

    3. Stored on shelves in a dry, enclosed area.

    c. Pneumatic and electrical openings should be closed with proper plugs and screw capsshould be securely in place if storing instruments prior to installation.

    d. Integrity of sealed protective covers shall be maintained during storage.

    e. For instruments or control panels that have been pre-mounted on the machinery package

    and cannot be stored in a dry, enclosed area, special arrangements should be made.

    f. Removal and indoor storage of pre-mounted instruments and control panels may be

    required if such devices cannot be protected from rain, humidity, temperature, or dusty

    conditions.

    3.2. Electronic instruments

    a. Electronic instruments shall be stored in a dust-free room between 8C and 45C (45F

    and 110F).

    b. If humidity is excessive, instruments shall be sealed and stored in plastic wrap, placed in a

    box with desiccant outside the plastic wrapping, and stored indoors.

    c. Manufacturer recommendations shall be reviewed to determine if climate-controlledstorage facilities are required.

    d. Electronic instruments that cannot be stored in a protective environment, shall be protected

    as follows:

    1. Desiccant should be placed in instrument enclosures.

    2. Instruments should be covered to protect against water entry.

    3. Control valve ports should be protected against contamination by solids (examplestones, soil, etc).

    3.3. Pneumatic instruments

    Pneumatic instruments shall be stored in a dry area, protected from the elements.

  • 7/28/2019 Instrumentation Construction Activity

    5/22

    Page 5 of 22

    3.4. Local control panels

    a. Panel labelling should be visible through packaging to avoid opening.

    b. If labelling is not visible, packaging shall be opened just enough to identify the control

    panel, then resealed and placed in a dry, enclosed or protected area with temperature

    between 8C and 45C (45F and 110F).

    c. In high-humidity areas, desiccant shall be placed inside the packaging before resealing.

    d. Panels with internal heaters shall be energized during storage.

    3.5. Dial thermometers, pressure gauges, and gauge glasses

    a. Dial thermometers, pressure gauges, and gauge glasses shall be protected against physicaldamage from construction activities.

    b. Such protection may require tagging and storage in a dry, enclosed area. In that case,process connections shall be capped or plugged with metal caps/plugs until the instrumentsare installed.

    4. Documentation

    4.1. Generala. Pre-commissioning documentation shall be organized either by system or by area.

    b. Commissioning activities shall be performed using the current edition of the following

    project documents:

    1. Loop diagrams. *

    2. Piping and instrument diagrams (P&IDs). *

    3. Instrument index.

    4. Instrument data sheets and/or specifications. *

    5. Instrument calculation sheets. *

    6. Level transmitter URV and LRV calculations (if applicable). *

    7. Orifice inspection records. *

    8. Instrument design drawings.

    a) Instrument location drawings.

    b) Wiring diagrams.

    c) Junction box drawings.

    d) Cable schedules.

    e) Instrument installation detail drawings.

    f) Relevant motor schematics. *

    g) Marshalling cabinet drawings.

    h) Shutdown schematics (if applicable). *

    i) Specialized documentation unique to specific loop types (for example, trip pointcalculation for current switches, panel drawings, etc.). *

    9. Instrument supplier data.

    10. Factory calibration certification. *

    11. Control Strategy Diagrams (if applicable). *

  • 7/28/2019 Instrumentation Construction Activity

    6/22

    Page 6 of 22

    c. The items indicated above with an asterisk (*) should be the minimum assembled drawings

    in a loop check folder for ready reference:

    4.2. Records

    a. As each instrument is checked, calibrated, and commissioned, a certification record shall

    be completed. These records shall include the following information:

    1. Complete listing of calibration test equipment being used and acceptable tolerances.

    2. Record of test equipment calibration checks that have been performed.

    3. Readout or output values from the calibration.

    4. Commissioning services performed.

    5. Deficiencies noticed.

    6. Concerns identified.

    b. Factory certification shall be included for factory-calibrated instruments. Theseinstruments should be verified, but not recalibrated, in the field.

    c. For each instrument loop, a separate document file shall be maintained. The followingitems shall be included in the file:

    1. As-built status of installation.

    2. Calibration, testing, and final instrument loop certification of control system

    components.

    3. Subsystems provided for the facility.

    d. A complete set of project drawings, marked up to reflect the as-built condition of allinstruments and subsystems, shall be required at the end of the project.

    e. Changes to documents shall be recorded to show the as-built condition of the document.The following colour-coded format should be used:

    1. Additions shall be in red.

    2. Deletions shall be in green

    3. Comments should be in blue or grey.

    5. Installation inspection

    5.1. Prerequisites

    a. Air headers, takeoff lines, and signal tubes shall be cleaned by blowing clean, dry air

    before connecting to instrument components.

    b. Before the installation of inline instrumentation components, process lines, tanks, and

    pressure vessels shall be prepared as follows:

    1. Cleaned.

    2. Flushed.

    3. Pressure-tested.

    4. Blown down, if applicable.

    5. Placed in service, if feasible.

    5.2. General

    a. Some installation inspection activities may be deferred and combined with systemcheckout or loop check.

    b. A mechanical completion documentation (including a punch list) shall be submitted.

  • 7/28/2019 Instrumentation Construction Activity

    7/22

    Page 7 of 22

    c. Inspection of local gauges shall be performed just before commissioning activities are

    started.

    d. Miscellaneous and special instruments shall be checked for correct installation in

    accordance with manufacturer instructions and instrument specifications.

    e. Instruments shall be isolated during initial field inspection as follows:

    1. Signal and process valves shall be closed.

    2. Instruments shall be electrically de-energized.

    5.3. Instrument inspec tion checks

    Installation inspection for instruments and associated components (including junction boxes,control valves, relief valves, and meters) shall include checks for the following, as applicable:

    a. Identification tags shall be checked as follows:

    1. Comply with the instrument Data Sheet.

    2. Properly engraved.

    3. Properly attached.

    4. Identify each device.

    b. Missing or damaged tags shall be replaced.

    c. Engraved nameplates have been provided and correctly installed with stainless steelholders for all field instruments, including:

    1. Transmitters.

    2. Process switches.

    3. Remote mounted indicators.

    4. Control valves.

    d. Consideration should be given to tagging the location of the instrument as well, so that

    when the instrument is removed the location is still identified.

    e. Location, material, and orientation comply with Manufacturer recommendations andinstallation design drawings.

    f. Instrument and system configuration is correct.

    g. Access for observing, adjusting, setting, and calibrating does not require climbing over,

    under, or through equipment and piping.

    h. Piping connections have been made, and piping and valving comply with Manufacturer

    recommendations and installation design drawings.

    i. Capability to rod out instrument piping has been provided, if required.

    j. Sloping of instrument piping and tubing is in the correct direction and at adequate gradient.

    k. Instruments are supported in accordance with specified requirements and no excessive

    strain is placed on connected tubing.

    l. Electrical equipment is certified for the process area in which it is being used, as requiredby the area classification drawing. Manufacturer nameplates or stickers shall indicate that

    the instruments or systems are listed or approved for use in the specified electrical areaclassification.

    m. Case bolts, stem clamps, yoke lockouts, and travel indicators are tight and packing gland

    bolts are torqued in accordance with Manufacturer instructions.

    n. Low-temperature thread sealants have not been used in high temperature applications.

    o. High point vents and drains have been provided, if required, and verified that they havepipe plugs.

  • 7/28/2019 Instrumentation Construction Activity

    8/22

  • 7/28/2019 Instrumentation Construction Activity

    9/22

    Page 9 of 22

    6. Tube bottoms in fitting body.

    7. Ferrule adequately biting the tube and back from the tube end.

    8. Ferrule(s) fitted correct way round.

    5.4.3. Wire and cable

    a. Field wiring shall be inspected according to the following:

    1. Check wiring against drawings.

    2. Confirm wire labelling is correct.

    3. Verify wire size and type.

    4. Check for proper circuit isolation at junction boxes and terminations.

    5. Low voltage signals shall be isolated from power. IS circuits require barriers andisolation.

    6. Verify wiring terminals are the correct type and wiring has been properly dressed-out

    to provide easy access to terminations.

    b. Electrical gland connections shall be tight and electrical tape not added as filler.

    5.5. Control valves ins pection c heck s

    a. Control valves and regulators shall be checked to ensure that installation orientation agreeswith process flow direction.

    b. Lubricators and isolating valves shall be checked for proper installation and loading.

    c. Valve plugs and shaft orientation on rotary valves shall be checked.

    d. Control valves and regulators shall not be inline during piping hydrostatic tests or lineflushing. If left installed, they shall either be blocked-in or slip-blinded.

    e. Control valves, regulators, and accessories shall be checked against nameplate data andinstrument data sheets, and the results recorded.

    f. Pressure regulator nameplate set pressure value shall be checked against Manufacturer

    specification data.

    g. Split range positioners and positioners that require air loadings greater than 0,2-1,0 bar(g)

    (3-15 psig) should be checked to ensure that bypasses are either secured or not included.

    h. Diaphragm and piston-operated control valves shall be bench checked as follows:

    1. Stems shall be inspected for burrs or paint, which shall be removed if present to

    prevent valve packing damage.

    2. If required, valves shall be lubricated in accordance with Manufacturer instructions.

    i. Throttling butterfly valves shall be checked for a mark to indicate vane position.

    j. Valve visual inspection and checks shall include at least the following:

    1. Verify that internal moving parts of valve actuators are correctly lubricated (whereapplicable) to ensure safe operation.

    2. Ensure that required extension stems or other operating devices that are necessary for

    operation but are not indicated by drawings or specification have been installed.

    3. Visually inspect facility piping systems and valve internals for damage and verify the

    correct installation of internals.

    4. Verify that valves are in the correct open or closed operating mode.

    5.6. Temperature ins truments inspection checks

    a. Thermocouple systems shall be checked for:

  • 7/28/2019 Instrumentation Construction Activity

    10/22

    Page 10 of 22

    1. Type.

    2. Polarity.

    3. Double reversals.

    4. Proper point identification.

    5. Proper burnout indication.

    b. For thermocouple elements, the following shall be verified:1. Element type is as specified (for example, E, K, R).

    2. Junction type is correct (earthed/grounded or unearthed/ungrounded).

    c. Thermowells shall be checked to verify that they comply with the Data Sheet. This checkmay include verifying the correctness of:

    1. Material.

    2. Flange rating.

    3. Insertion length.

    d. RTD transmitters and receivers shall be checked to ensure that RTD material matches the

    Data Sheet.

    5.7. Flow instruments

    a. Correct flow direction shall be verified.

    b. For differential pressure type flow instruments, the primary instrument piping connections

    shall be verified that they are properly made up at both the element connection anddifferential pressure instrument connections. The correct orientation of the high side versus

    the low side shall be verified.

    c. Lines containing inline flow elements shall be cleaned and flushed before installation ofthe flow element.

    d. Inline flow elements shall be removed before lines are flushed or hydrostatically pressure

    tested.

    e. Differential pressure type flow instruments, during hydrostatic pressure tests:

    1. Orifice tap shutoff valves shall be closed.

    2. Instrument drain valves shall be opened.

    f. Rotameters shall be checked to ensure:

    1. Installation is plumb.

    2. Shipping stops shall be removed and floats inserted.

    g. The following meters shall be checked for free operation of internal parts:

    1. Rotameters.

    2. Turbine meters.

    3. Positive displacement meters.

    h. Differential flow elements and meter runs shall be checked for compliance withManufacturer and relevant specifications.

    i. The following shall be checked for dimension and material compliance with the Data

    Sheet:

    1. Flow orifice meter runs.

    2. Venturi tubes.

    3. Flow nozzles.

  • 7/28/2019 Instrumentation Construction Activity

    11/22

    Page 11 of 22

    j. For orifice plates, bores shall be callipered before installation as follows:

    1. Bores shall comply with the specification.

    2. Bores shall be within tolerances shown in Table 1.

    Table 1 - Practical tolerances for orifice diameters

    3. Results shall be recorded on certification documentation.

    k. Orifice plates shall be visually checked for an upstream sharp edge.

    l. Orifice plates shall be installed after flushing and cleaning operations are complete.

    m. Orifice plate installation shall be checked to ensure that orifice plate is in the correct line.

    5.8. Level instruments

    a. Installation of the following shall be checked for proper installation:

    1. Gauge glasses.

    2. Gauge cocks.

    3. Illuminators.

    4. Ball checks.

    5. Heat tracing.

    6. Other accessories.

    b. External float and displacer type level instruments shall be checked as follow:

    1. The float chamber shall be blocked, drained, and vented during hydrostatic testing.

    2. The operation shall be field checked mechanically by raising and lowering the

    displacer with water.

    3. The cage shall be checked to ensure it is plumb.

    c. Internal float and displacer type level instruments shall be removed during hydrostatic

    testing.

    6. Loop check and system checkout

    6.1. Prerequisites

    a. The following shall be verified before loop check or system checkout:

    1. All items are mechanically completed.

    2. Installation inspection is completed.

    3. Compliance with local requirements and regulations.

    b. Pressure testing and blowing out of tubing runs shall be completed before initial

    connection to instruments.

    Orifice diameter Practical tolerance (+/-)

    mm in mm in

    6 0,250 0,0075 0,0003

    9,5 0,375 0,01 0,0004

    12 0,500 0,0125 0,0005

    25 1,0 0,0125 0,0005

    25+ 1,0+ 0,0005(per mm ofdiameter)

    0,0005(per inch ofdiameter)

  • 7/28/2019 Instrumentation Construction Activity

    12/22

    Page 12 of 22

    c. All documentation pertaining to the loop should be available as per section sub-clause

    4.1.c

    6.2. General

    a. The following procedure should be followed to ensure all elements in the loop are

    checked:

    1. Check each loop in accordance with the latest revision of the approved for

    construction loop diagram.

    2. As the loop check proceeds and elements are checked, highlight verified portions ofthe loop drawing.

    3. Complete the appropriate loop check documentation.

    4. When a loop check is complete and signed off, place a green dot on all major

    components. If any work that could affect the loop is subsequently performed, notifyinstrument personnel to recheck the loop.

    5. The loop check should include a test label, with testers initial and date for

    traceability.

    b. Discrepancies, errors, or deficiencies shall be corrected and rechecked.

    c. The sequence of loop certification shall be coordinated with area construction schedules.

    d. Loops shall be checked as a complete system, from inputs to outputs.

    e. Loop checks shall involve checking components in all positions and under all scenarios toensure they work correctly, both locally and from the process automation system (PAS).

    f. If an impact to operations may occur, Operations shall be advised of the loop to be

    checked. In such cases, the state of the input shall be verified before proceeding.

    g. A functional loop check shall be made while all loop instruments are energized.

    6.3. Ins trument calibration and checkout

    6.3.1. General

    a. Factory calibrated instruments should be verified by corresponding certification.

    b. Instruments that have been factory calibrated shall not be recalibrated in the field.

    c. Calibrate in the field only if not already factory calibrated. If certified factory calibration isfound to be wrong, the Manufacturer should be notified and the instrument replaced. Do

    not recalibrate onsite.

    d. If the calibration check indicates that the instrument will operate within the manufacturerstated accuracy, additional calibration shall not be required.

    e. Calibration of instruments shall be reserved only for those devices that, upon checking, arenot within their specified operating range.

    f. Calibration checks shall be documented.

    g. Stickers with the following information shall be attached to instruments that have been

    checked and calibrated:

    1. Date and time of calibration verification.

    2. Technician identification.

    h. To verify, calibration checks should be performed as follows:

    1. At a minimum of three calibration points (0%, 50%, and 100% of operating range), or

    otherwise indicated.

    2. For smart transmitters, use electronically simulated outputs.

  • 7/28/2019 Instrumentation Construction Activity

    13/22

    Page 13 of 22

    3. For standard analogue transmitters, use simulated process variable inputs.

    4. Check calibration from each field device through the PAS to each device that uses theselected variable and any combination of devices that use the selected variable and

    other variables.

    i. Check loop components for:

    1. Correct readout or response at each transmitter input level.

    2. Correct action of the controller, positioner, and control valve.

    3. Incorrect response or readout shall be reported for correction.

    j. Instrument covers and enclosures that were removed for calibration shall be replaced.

    k. Loop check personnel shall not change calibration or system ranges without approval.

    l. Conflicting data encountered between calibration ranges of field devices and displayed orconfigured ranges within the PAS shall be brought to attention for resolution.

    m. Signals shall be simulated at the input of the end device as shown in Table 2 (for analogue

    transmitters) and Table 3 (for switches).

    Table 2 - Simulating signals at analogue transmitters

    Table 3 - Simulating signals at swi tches

    n. Digital communications devices may be used to set smart transmitter output to the required

    levels for loop checking.

    o. Smart transmitters shall be operationally tested and digitally ranged.

    p. Input devices should be checked as follows:

    1. Read and confirm correct value(s), as appropriate, on the PAS, at the panel, and at themarshalling cabinet (if the device is a relay input).

    2. For signals that enter multiple locations [for example, surge control points and

    programmable logic controller (PLC) points], values should be checked at all inputlocations.

    3. For PLC inputs, use a voltmeter or check the input card indication light.

    4. For relays, use a voltmeter or visually check the relay state.

    5. Check local indicators or other remote indicator readings.

    q. If feasible, correct outputs should be verified as shown in Table 4.

    Type of transmitter Procedure

    Pressure, orifice meter, and d/p Pump up at 0%, 50%, and 100%.

    Temperature Read the temperature.

    Level (d/p type) Fill column with approved liquid to 0%, 50%, and 100%.

    Analogue transmitters, for which the processparameter cannot be simulated

    Check at zero. Use a calibrator (for example, Altek) to input acurrent at 0%, 50%, and 100%.

    Type of switch Procedure

    Level Fill float chamber with approved liquid to trip the switch.

    Pressure or d/p Pump it up to trip the switch.

    Transmitter current Pump up the transmitter (pressure, d/p, or orifice d/p), use atemperature calibrator (for example, Altek), or fill the columnwith liquid.

  • 7/28/2019 Instrumentation Construction Activity

    14/22

    Page 14 of 22

    Table 4 - Outpu t verifi cation

    r. Using loop drawings or shutdown schematics, input and output interaction should bechecked for action direction as follows:

    1. For control loops, increasing or decreasing transmitter input should open or close the

    control valve, as applicable.

    2. For shutdowns, toggling the inputs should cause solenoid valves or other end devicesto open or close or be on or off, as applicable.

    s. After input wiring has been confirmed to the shutdown panel, subsequent toggling of the

    input may be accomplished by removing the appropriate fuses at the input termination

    strip.

    6.3.2. Cal ibrat ion test equipment

    a. If calibration is required the test equipment shall be according to this section.

    b. Shop test equipment (excluding pressure generating devices, such as manometers and deadweight testers) shall require certification. Certification shall be:

    1. Current within one year of testing activity.

    2. Traceable to a recognized, approved certification agency.

    3. Kept on file.

    c. Calibration test equipment shall be selected to be more accurate than the manufacturer

    advertised accuracy of the equipment being tested. Order of magnitude of 10 if feasible.

    d. Transmitting or receiving signal accuracy of calibration equipment shall be greater than theinstrument to be calibrated.

    e. Pneumatic calibration gauges, electronic test meters and equipment, and digital strain

    gauge instruments shall have an accuracy of at least 0,1% full scale.

    f. Portable field test devices shall be tested for accuracy at least twice a week against shop

    calibration equipment.

    g. Air for the calibration of pneumatic-actuated instruments shall be instrument-quality air. Ifinstrument air is not available onsite at the time of calibration, dry bottled filtered air shallbe used.

    6.3.3. Receiving inst ruments

    a. Controllers, recorders, and indicators shall be checked for alignment in accordance withthe Manufacturer-supplied manual.

    b. Recorder charts and pens shall be prepared for use.

    c. Charts and scales shall be checked for range in accordance with specifications.

    6.3.4. Switches

    a. Instruments that are two-position devices should not be calibrated over their full range.Only the trip point and dead band (reset point) should be checked.

    Type of output Procedure

    Controllers with control valves Put controller in manual and check valve movementcorresponding to 0%, 50%, and 100% output.

    Discrete outputs Confirm that the output state (either DCS, PLC, or relay) at theend device matches the expected output state.

    Automated valves Check the valve at 0% and 100%.

    Valves with a failure position Shut off air supply (typically block and vent) and check forfailure.

  • 7/28/2019 Instrumentation Construction Activity

    15/22

    Page 15 of 22

    b. Switches used in alarms, shutdown, or signal switching service shall be set to specified

    values by applying a rising and falling signal.

    c. Dead bands shall be checked to ensure they are within the Manufacturer published

    tolerance.

    6.3.5. Control valves and pressure regu lators

    a. Valve function tests shall be performed to ensure that valves operate effectively, have no

    damage, and have correct fail functions.

    b. Valve failure position shall be checked to ensure failsafe operation on loss of motive fluid.

    c. Solenoid valves mounted on control valves shall be energized and de-energized to ensure

    that the control valve fails correctly.

    d. Butterfly valves shall be checked to ensure that:

    1. The vane moves freely in upstream and downstream piping.

    2. Mechanical stops are set as specified on the Data Sheet.

    e. Throttling butterfly valves are set for maximum travel restrictions in accordance with

    specifications.

    f. The following shall be completed and recorded:

    1. Check valve failure action.

    2. Set position indicator.

    g. Operation of valve accessories shall be checked, including:

    1. Handwheels.

    2. Solenoid valves.

    3. Limit switches.

    4. Boosters.

    5. Relays.

    h. Handwheels shall be in neutral position before stroking valves.

    i. Diaphragm and piston-operated control valves shall be pneumatically stroked using a

    regulator and test gauge.

    j. The following shall be verified to be in accordance with Manufacturer nameplate data and

    job specifications (if applicable) and recorded:

    1. Valve action.

    2. Mechanical seating.

    3. Spring range or bench setting shown on valve nameplate.

    4. Valve travel (including bench set).

    5. Valve failure position.

    6. Actuator setting (either reverse or direct action) is in accordance with Manufacturer

    specifications.

    7. Limit switches indicate full open and close.

    8. Solenoid valves bleed the actuator when energized or de-energized.

    9. Boosters amplify the pneumatic signal in compliance with Manufacturer

    specifications.

    10. Handwheel, if provided, opens and closes the valve and in neutral position, permits

    automatic control.

    11. Relays, if provided, activate in accordance with Manufacturer specifications.

  • 7/28/2019 Instrumentation Construction Activity

    16/22

    Page 16 of 22

    12. Rotary valve plugs seat properly and are operating in the proper quadrant.

    13. Local valve position indicators are installed properly to match valve position.

    k. If valve includes a volume booster bypass valve, the gain shall be set by backing out the

    adjusting screw 1-1/2 to 2 turns from closed and shall be checked for stable operation.

    l. I/P transducers that output to control valves shall be calibrated to be direct acting, with an

    output range of 0,2-1,0 bar (g) (3-15 psig) or 0,4-2,0 bar (g) (6-30 psig) for a

    corresponding input of 4 to 20 mA.m. Valve positioners and other auxiliary devices (for example, limit switches, position

    transmitters, and trip relays) shall be verified in accordance with nameplate data andManufacturer specifications.

    n. Manually operated valves (including skid mounted valves) shall be manually sequenced

    and spindle rotation and integrity shall be verified.

    6.3.6. Aut omated Valves

    a. Automated valve shall be checked as follows:

    1. Stroke valve from the PAS.

    2. Check limit switch settings, open and closed. Limit switches should be less than

    90 degrees apart from each other (approximately 85 degrees).

    3. Verify that the following all match the valve position:

    a) Valve shaft.

    b) Beacon.

    c) PAS.

    4. Verify the valve fail position as follows:

    a) For fail last, open the valve, turn off power at the field junction housing, andensure the valve holds the open position.

    b) Repeat the same procedure for closed valve position.

    5. If valves are fitted with handwheels, manually stroke the valve with the handwheel.

    6. Check travel stops.

    b. After automated valves are checked, valves shall remain energized.

    6.3.7. Temperature in stru men ts

    a. Temperature indicators shall be checked at ambient conditions, where practical.

    b. Certification of calibration should be provided by equipment Manufacturers that embeddevices in their products (for example, motor winding RTDs).

    c. Thermocouples and RTDs should not require calibration checks if accompanied with

    vendor test certification and/or if they are removable in service.

    d. Thermocouples and RTDs that are wired directly to any type of readout device (forexample, digital control system, multipoint temperature indicator, or recorder) shall be

    field checked to verify operation as follows:

    1. Check for ambient reading.

    2. Remove RTD/thermocouple to verify the correct point is being read.

    3. Check output of RTD and thermocouple elements:

    a) For RTD elements, measure element resistance and compare measurement to theambient temperature.

    b) For thermocouple elements, measure millivolt output and compare measurement

    to the ambient temperature.

  • 7/28/2019 Instrumentation Construction Activity

    17/22

    Page 17 of 22

    4. Verify the signal at the receiving instrument and/or PAS.

    e. For thermocouples or RTDs that are not replaceable while process equipment is running(for example, reactor thermocouples and tube skin thermocouples), checkout of

    temperature elements shall be performed and shall consist of a three-point calibration

    check using a controlled temperature bath before installation, if feasible. After installation,

    the measurement shall be compared to ambient temperature.

    f. Bimetallic dial thermometers shall not be field calibrated. The dial or pointer shall be set to

    the ambient temperature known at the time of installation.

    g. For instruments with suspected calibration and/or calibration is deemed necessary thefollowing guidance should apply:

    1. Thermal-filled system temperature instruments shall be calibrated as follows:

    a) At three calibration points, minimum (0%, 50%, and 100% of operating range).

    b) By immersing the sensing bulb in a precisely controlled and agitated

    temperature bath that is continuously monitored with a precision thermometer.

    2. Non-factory calibrated thermocouple transmitters and receivers shall be calibrated, if

    required, as follows:

    a) Apply upscale and downscale millivolt signals from a precision voltage source.

    b) Verify and adjust upper and lower operating limits.

    c) Recheck the three-point calibration.

    3. Non-factory calibrated RTD transmitters and receivers shall be checked, if required,as follows:

    a) Use a precision decade resistance box.

    b) Verify and adjust upper and lower operating limits.

    c) Recheck the three-point calibration.

    h. Temperature switches shall be checked and set in accordance with procedures in Table 5.

    Table 5 - Checks for different types of temperature switches

    6.3.8. Flow instruments

    a. Flow indicators shall be zeroed.

    b. Transmitting and indicating rotameters in which the float is not visible shall be calibratedas follows:

    1. Manually position the float.

    2. Adjust the indicator or transmitter output to the correct value at 0% and 100%.

    c. Equipment associated with meters, regardless of whether or not they are used for custodytransfer and allocation, calibration should be verified according to Manufacturer standards

    and relevant specifications.

    Sw itc h type Checking procedure

    All types Check dead band to confirm that it is within Manufacturer statedtolerance.

    Filled Check and set to specified trip point by immersion in fluidisedsand bath or controlled temperature bath (depending ontemperature range).

    Thermocouple Check using a precision voltage source.

    RTD Check using a precision decade resistance box.

  • 7/28/2019 Instrumentation Construction Activity

    18/22

    Page 18 of 22

    d. The following meters shall have their zero and span checked in accordance with

    Manufacturer recommended procedure:

    1. Turbine meters.

    2. Positive displacement meters.

    3. Vortex meters.

    4. Ultrasonic meters.

    5. Coriolis meters.

    6. Magnetic meters.

    7. Target meters.

    e. Thru-flow type flow switches shall be mechanically checked only.

    f. Differential pressure type flow switches shall be checked as follows:

    1. Calibration shall be against a standard water column manometer or precision gauge.

    2. Dead band of switches shall be verified against the Data Sheet.

    6.3.9. Level instruments

    a. For cage displacer type instruments, the following shall be checked:

    1. Pneumatic or electronic transmitter with output gauges or meters for smooth and fulloutput change.

    2. Operation of the pneumatic controller and verification that the set action (direct or

    reverse) complies with the Data Sheet.

    b. Level indicators shall be zeroed.

    c. External displacer type level instruments shall be calibrated as follows:

    1. Set specific gravity adjustment to 1,0.

    2. Fill chamber with clean water, while using clear plastic tubing connected at thebottom drain as a gauge glass.

    3. Check calibration at three points (0%, 50%, and 100% of span).

    4. After each calibration adjustment, recheck for zero.

    5. Reset specific gravity adjustment to operating conditions.

    d. Internal displacer type level instruments shall be removed from the vessel and bench

    calibrated as follows:

    1. Set specific gravity adjustment to 1,0.

    2. Check calibration at three points (0%, 50%, and 100% of span).

    3. After each calibration adjustment, recheck for zero.

    4. Reset specific gravity adjustment to operating conditions.

    e. To verify calibration of differential pressure (d/p) level instrument checks should beperformed at three points (0%, 50%, and 100% of span).

    f. Level instrument switches shall be checked and set as follows:

    1. Float operated level switches shall be checked for switch operation by filling the floatchamber with water.

    2. Head, displacer, or differential pressure operated level switches shall be set at the

    required trip points.

    3. Dead band of the switches shall be verified against the Data Sheets.

  • 7/28/2019 Instrumentation Construction Activity

    19/22

    Page 19 of 22

    g. Ultrasonic, radar, capacitance, and other special types of level instruments shall be

    checked in accordance with Manufacturer recommendations.

    6.3.10. Pressure i ns truments

    a. Pressure gauges shall be checked at ambient conditions.

    b. To verify calibration of pressure and differential pressure (d/p) transmitters checks should

    be performed at three points (0%, 50%, and 100% of span).

    c. Switches shall be checked and calibrated as follows:

    1. Calibrate pressure switches using hydraulic tester, dead-weight tester, or precision air

    regulator and an output gauge to set the required alarm and trip point.

    2. Verify dead band of the switches against the Data Sheet.

    d. If pressure gauge reading suspect, the manufacturer should be notified and the instrument

    replaced.

    e. For critical pressure gauges the following may apply:

    1. Bourdon tube type pressure gauges should be checked at 10%, 50%, and 90% of full

    scale. If gauge varies more than 1,0% from true reading at any of the three points,

    gauge should be replaced and/or recalibrated.

    2. Draft type instruments shall be bench calibrated using an inclined-tube manometer or

    precision accuracy strain gauge at 0%, 50%, and 100% of range.

    3. Receiver type pressure gauges should be field checked to verify calibration at threepoints (0%, 50%, and 100% of span).

    4. Diaphragm type draft gauges shall be field checked to verify calibration as follows:

    a) Verify calibration at three points (0%, 50%, and 100% of span).

    b) Use a water column or inclined tube manometer in accordance withManufacturer recommended procedure.

    6.3.11. Analyt ical inst ruments

    a. Sample systems shall not be connected to process piping before commissioning, at whichpoint they should be:

    1. Installed and cleaned to meet analyser system requirements.

    2. Inspected for proper installation, operation, and tightness.

    b. If specification calls for the instrument Manufacturer to furnish the services of a factoryservice engineer for checkout and calibration purposes, this work shall be performed underthe factory service engineers direction.

    c. The following shall be verified:

    1. Necessary standard and calibration samples are available.

    2. Spare parts (including filters. coalescers, and consumables) necessary for initial

    calibration, startup, and testing are available.3. Analyser housing has appropriate approvals for the area classification.

    d. Calibration shall be in accordance with Manufacturer recommended procedure using

    sample gases or liquids provided.

    e. Analytical instruments shall be checked as follows:

    1. Analysers shall be inspected for correct installation of piping and wiring.

    2. A two-point field calibration check shall be performed.

  • 7/28/2019 Instrumentation Construction Activity

    20/22

    Page 20 of 22

    f. Analysers and sampling systems shall be checked as calibrated using standard samples, if

    available, to verify analyser output against laboratory analysis. The following tests andchecks shall be performed, as applicable:

    1. Analyser is recording properly.

    2. All alarms are functional.

    3. Peak picking capability is operating.

    4. Interrupt functions operate correctly.

    5. Automatic shutoff of sample flow is functioning.

    6. Sample flow rate is adequate.

    7. Sample transport time is acceptable.

    g. Analysers shall be protected during hydrostatic testing as follows:

    1. Sample taps shall be isolated.

    2. Analyser tubing shall be disconnected.

    3. After completion of the hydrostatic testing, sample piping shall be dried with dry airand sealed.

    h. If housing is purged, proper operation of the purging system shall be verified, includingalarms when purge pressure is lost. Settings and results shall be recorded on thecertification documentation.

    i. Power connections to the analyser and a.c. circuits to the distribution panel shall beverified.

    j. Process connections shall remain closed until after startup.

    k. Sample system piping shall be flushed with process fluid for several hours before allowingsamples to enter analyser.

    6.3.12. Miscel laneous f ield instruments

    a. Density or specific gravity meters as a minimum shall have their zero and span checked in

    accordance with Manufacturer recommended procedure.

    b. Special instruments not discussed in this document shall be checked and calibrated inaccordance with Manufacturer instructions and relevant specifications.

    6.4. Systems checkout

    6.4.1. General

    a. The complete functions tested during FAT should not be retested onsite.

    b. Retesting or an acceptable subtest should be required only to verify proper installation and

    integration with other systems onsite.

    c. Control systems components shall be checked as follows:

    1. Check dynamic variables on each graphic screen during loop checks and verifyreadings are correct.

    2. Verify commands from operator consoles and screens.

    3. Check printed logs and reports.

    d. Cascade systems shall be checked to ensure proper functioning of:

    1. Primary loop control set points.

    2. Secondary loop.

    3. Control action.

  • 7/28/2019 Instrumentation Construction Activity

    21/22

    Page 21 of 22

    e. Interlock, safety, and sequential control systems shall be checked for continuity and

    verified with a functional test of each circuit.

    f. Control system loop continuity and output action shall be checked as follows:

    1. Verify that control actions are set in accordance with specifications.

    2. Observe control outputs and controller responses.

    3. Check and observe auxiliary functions (for example, alarms, ratioing, etc.).

    g. Loop points shall remain disabled until they are loop checked.

    h. Points that are loop checked shall remain active on the control system.

    6.4.2. Controllers

    a. Ratio controllers shall be checked by feeding a known signal into the station and observingthe output for various set ratios.

    b. Set control modes, set points, and tuning parameters.

    c. After loop checking, controllers shall be left in manual mode.

    6.5. Alarm system components

    a. Annunciators shall be checked through to the final display window or PAS screen asfollows:

    1. Verify operation and point continuity by a functional test of each circuit using the

    primary instrument. This test shall involve actuating all field contacts, as shown on

    the instrument loop diagrams or elementary diagrams, for the following:

    a) Low, high, or deviation alarm operation.

    b) Auxiliary contact operation.

    c) Proper sequence.

    2. Verify correct actuation of each device as described in the specification for theparticular type of instrument.

    b. Alarm windows and nameplates shall be verified for accuracy and correct location.

    c. For alarm and switch sensing elements, the following shall apply:

    1. Abnormal conditions shall be simulated by either of the following methods:

    a) Simulate the process variable.

    b) Manually trip the switch.

    2. The correct operational sequence and actions of related devices shall be checked.

    3. Switch terminals shall not be jumpered to simulate actuation without approval.

    6.6. Logic system components

    a. Electrical devices that are part of an interlock, shutdown, or auto start circuit shall be

    checked as follows using a pre-developed test plan:

    1. Devices shall be thoroughly checked as an integrated system for continuity and

    operation.

    2. Shutdown and interlock responses shall be checked against shutdown and interlocklogic diagrams.

    b. Switching and shutdown systems shall be checked as follows:

    1. Perform check from the originating device to the switching or shutdown function.

    2. Verify the operation of each circuit using the latest issue of the designated

    logic/ladder drawings.

  • 7/28/2019 Instrumentation Construction Activity

    22/22

    3. Record changes to logic/ladder drawings and show on as-built logic/ladder

    drawings.

    4. Check PLC systems using Manufacturer-provided system test procedures.

    c. Process-actuated switches and process transmitters shall be checked as follows:

    1. Activate by simulating the process variable or by manual trip.

    2. Perform functional test, without use of jumpers.

    d. Each shutdown system shall be checked as follows:

    1. Verify failsafe design philosophy.

    2. Verify the correct state of each output on loss of power to the logic system and onloss of power to the field devices.

    7. Commission ing completion

    a. Before commissioning, mechanical completion documentation (including a punch list)shall be submitted.

    b. Pre-commissioning shall consist of preparing instrumentation for plant startup, including

    the following tasks:1. Confirm that installation inspection, calibration and loop check tasks have been

    completed.

    2. Place process control valves and other final elements in the status specified by thestartup requirements.

    3. Open or close instrument block valves as specified by the startup requirements.

    4. Pour electrical seals where conduit is used.

    5. Fill condensate pots and check that legs are filled with the specified seal fluids.

    6. Place controllers in manual mode.

    7. Warm up instruments, such as analysers, as required.

    8. Set airsets at the correct pressure and open instrument air valves to place enclosure airpurges in service.

    9. Make electrical power supplies and pneumatic pressure sources ready for service.

    10. Confirm electrical and pneumatic power systems are operating correctly.

    11. Energize electric heat tracing or cut in steam tracing on instrument tubing and

    instrument enclosures.

    12. Ensure protection devices are in working order and are not bypassed or overridden.

    13. Place instruments in service by opening or closing instrument shutoff valves andequalizing valves in instrument manifolds.

    14. Vent air from instrument sensing lines in liquid service.15. Drain liquids from instrument sensing lines in gas service.

    c. Instruments and loops shall remain powered or pressurized with switches and valves set in

    accordance with the startup requirements.

    d. Control and instrumentation is considered to be commissioned and ready for startup when:

    1. Mechanical completion checklists are signed off as complete.

    2. All loop checks and system checkout are signed off as complete.

    3. All punch lists are signed off as complete.

    4 All commissioning activities are signed off as complete and ready for startup