Inquiry for Package 2. EPC Building Works
-
Upload
donny-b-tampubolon -
Category
Documents
-
view
52 -
download
0
Transcript of Inquiry for Package 2. EPC Building Works
2x60MW MERAK CFPP PROJECT
DOCU. NO. : Rev. No. : A Page No. : 1 of 7 TITLE REQUISITION FOR QUOTATION
TITLE
REQUISITION FOR QUOTATION (EPC work for non-process buildings)
DISCIPLINE : ARCHITECTURE / STRUCTURE PROJECT NAME : 2x60MW MERAK CFPP PROJECT JOB NO. : 090213 OWNER : PT. MERAK ENERGI INDONESIA
REV. NO.
DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
REV. NO. PREPARATION
GROUP. PREPARATION CHECK REVIEW APPROVAL
A Architectural K.H.KIM S.H.KIM
H.M.SUH
I.C.ROH
June. 8, 2010 June. 8, 2010 June. 8, 2010 June. 8, 2010
This Document is the property of Daewoo Engineering Company. Therefore, it shall not be released to any third party without permission of an authorized personnel of the Daewoo Engineering Company
2x60MW MERAK CFPP PROJECT
DOCU. NO. : Rev. No. : A Page No. : 2 of 7 TITLE REQUISITION FOR QUOTATION
TABLE OF CONTENTS
1. GENERAL ··························································································································· 3
2. INSTRUCTION TO BID ······································································································· 3
2.1. Correspondence ······································································································· 3
2.2. Intention to Bid·········································································································· 3
2.3. Clarifications ············································································································· 3
2.4. Submission of Proposal ···························································································· 4
2.5. Validity of Bid ············································································································ 4
2.6. Expenses of Bidders································································································· 4
2.7. Currency ··················································································································· 4
2.8. Bid Price ··················································································································· 4
3. GENERAL DESIGN CONDITION ························································································ 4
3.1. General ····················································································································· 4
3.2. Site Reference Conditions ························································································ 5
3.3. Site Conditions ········································································································· 5
3.4. Environment Condition ····························································································· 5
4. SCOPE OF WORK ·············································································································· 6
5. PROJECT SCHEDULE ······································································································· 7
6. SUBMITTAL LIST ················································································································ 7
7. ATTACHMENT ····················································································································· 7
Appendix #1 : Bid Specification for Architectural Engineering. ············································ 7
Appendix #2 : Division of Work Scope (Architectural) ·························································· 7
Appendix #3 : Reference Basic Drawings ············································································ 7
Appendix #4 : Site Reports and Data ··················································································· 7
2x60MW MERAK CFPP PROJECT
DOCU. NO. : Rev. No. : A Page No. : 3 of 7 TITLE REQUISITION FOR QUOTATION
1. GENERAL
The Power Plant Facilities consist of two Units of 60MW (gross) generation capacity and
associated facilities. The Power Plant Facilities shall provide 55 tons/h of steam with
steam pressure of minimum 25 ata. The Units shall be atmospheric circulation fluidized
bed type, steam electric generating units fueled with Indonesian coal as the primary fuel
and high speed diesel (HSD) oil as the secondary startup fuel. The location of the
Facilities shall be at Mangunreja village in the sub-district of Pulo Ampel, district of
Serang in Banten Province on the western part of the Java island in Indonesia.
2. INSTRUCTION TO BID
2.1. Correspondence
Any correspondence for clarification and other queries that may arise regarding this RFQ
shall be addressed to :
Attention: Mr. Ihn Chul, Roh / Project Manager
E-mail: [email protected]
C.C: Mr. Jong Min Oh / Section Manager
E-mail : [email protected]
Tel. +82-31-738-0423
Mr. Se Yeon, Won/Engineering Coordinator
E-mail : [email protected]
Tel. +82-31-738-0976
Mr. Kang Suk, Oh /Site Manager
E-mail : [email protected]
2.2. Intention to Bid
Within 3 days of receipt of this RFQ, Bidder shall e-mail DEC confirming his intention to
bid.
2.3. Clarifications
2x60MW MERAK CFPP PROJECT
DOCU. NO. : Rev. No. : A Page No. : 4 of 7 TITLE REQUISITION FOR QUOTATION
It shall be responsibility of Bidder to advise DEC of any conflicted requirements or
missing information that are needed to be resolved in order to enable Bidder to have a
clear understanding of the RFQ.
2.4. Submission of Proposal
The proposal of Bidder shall send to aforesaid address mentioned in Section 1.1 not
later than September 6, 2010.
2.5. Validity of Bid
The Proposal shall be valid for sixty (60) days from the Bid Closing Date.
2.6. Expenses of Bidders
DEC shall not be responsible for any cost incurred by Bidder in preparing, submitting
and discussing the bid during any pre-or-post bid negotiations.
2.7. Currency
The quotation will be made in US dollars.
2.8. Bid Price
Bid price shall be included all direct and indirect cost associated with the work.
3. GENERAL DESIGN CONDITION
3.1. General
Project Name : 2×60MW MERAK Coal Fired Power Plant
Owner : PT. MERAK ENERGI INDONESIA
Plant Capacity : 2×60MW (Gross)
Plant Type : Coal Fired Power Plant with steam generation
Plant Configuration : 2STG + 2Boiler + 2ESP
Fuel : Indonesian Coal
Site Location : Serang in Indonesia
Cooling System : Once-through Cooling System with Seawater
2x60MW MERAK CFPP PROJECT
DOCU. NO. : Rev. No. : A Page No. : 5 of 7 TITLE REQUISITION FOR QUOTATION
3.2. Site Reference Conditions
Barometric Pressure : 1.0127 Bar a
Ambient Temperature : 27 C
Relative Humidity : 79 %
3.3. Site Conditions
Altitude : 3.9 m
Barometric Pressure Average : 1.0127 Bar a
Ambient Temperature
1) Mean Daily Temparature : 27 ℃
2) Maximum Range : 11 ℃
3) Minimum Range : 7.5 ℃
Relative Humidity
1) Maximum : 87 %
2) Minimum : 72 %
3) Average : 79 %
Rain Fall
1) Total Annual Precipitation : 1911 mm
Wind Velocity
1) Maximum : 35 m/s, Exposure D
Seismic Load
1) Design Code : UBC 97
2) Soil Profile Type : (Later)
3) Code Zone : Zone 2B
4) Peak Ground Acceleration(Z) : 0.20
3.4. Environment Condition
Air Emission Limits
2x60MW MERAK CFPP PROJECT
DOCU. NO. : Rev. No. : A Page No. : 6 of 7 TITLE REQUISITION FOR QUOTATION
Pollutant Unit Limits Value
Particulate Matter mg/Nm3 50
Sulfur Dioxide mg/Nm3 750
Nitrogen Oxides (NO2) mg/Nm3
Solid Fuel mg/Nm3 750
Liquid Fuel mg/Nm3 460
Noise Emissions Limits (at plant boundary)
Parameter Unit Limits Value
Industrial or Commercial dB(A) Day: 70
Night: 70
4. SCOPE OF WORK
Detailed design and engineering for below buildings including piling design.
- Administration & Amenity Building
- Warehouse
- Security Building
- Mobile Heavy Equipment Garage Shelter
Submission of Bill of Material for above buildings
Review of other building drawings based on local regulations or practices
Building permit for the buildings including other buildings designed by DEC.
Construction Assistance
- Technical Assistance
2x60MW MERAK CFPP PROJECT
DOCU. NO. : Rev. No. : A Page No. : 7 of 7 TITLE REQUISITION FOR QUOTATION
- Dispatch of field engineer during construction period of bidder designed
buildings, if necessary.
Material supply and construction for aforesaid buildings except piling work
As Built Documentation
The engineering subcontractor shall be approved by DEC and/or Owner.
For more details, please refer to Attachment
5. PROJECT SCHEDULE
Contract signing : September 20, 2010.
Detailed design period: 3 months from the date of contract signing
Start of piling work for bidder designed building : middle of October
All design and engineering deliverables shall be submitted agreed schedule to be
fixed during kick-off meeting
6. SUBMITTAL LIST FOR BIDDER’S PROPOSAL
List of engineering deliverables
Estimated manpower for engineering
Permit information
Brief specifications for interior schedule
Estimated construction cost based on estimated Bill of Quantity
Engineering Subcontractor prequalification documents
7. ATTACHMENT
Appendix #1 : Bid Specification for Architectural Engineering. Appendix #2 : Division of Work Scope (Architectural) Appendix #3 : Reference Basic Drawings Appendix #4 : Site Reports and Data
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 1 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
TITLE
BID SPECIFICATION
FOR ARCHITECTURAL ENGINEERING
DISCIPLINE : ARCHITECTURE / STRUCTURE PROJECT NAME : 2x60MW MERAK CFPP PROJECT JOB NO. : 090213 OWNER : PT. MERAK ENERGI INDONESIA
REV. NO. DATE DESCRIPTION PREP'N CHECK REVIEW APPROVAL
REV. NO. PREPARATION
GROUP. PREPARATION CHECK REVIEW APPROVAL
A Architectural K.H.KIM S.H.KIM H.M.SUH I.C.ROH
June. 8, 2010 June. 8, 2010 June. 8, 2010 June. 8, 2010
This Document is the property of Daewoo Engineering Company. Therefore, it shall not be released to any third party without permission of an authorized personnel of the Daewoo Engineering Company
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 2 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
TABLE OF CONTENTS
1. GENERAL ························································································································ 3
2. CODES AND STANDARDS ······························································································ 3
3. SCOPE OF WORKS ········································································································· 4
4. DESIGN LOAD ················································································································· 4
5. STEEL STRUCTURES ····································································································· 6
6. REINFORECED CONCRETE STURUCTURE & FOUNDATION ······································ 8
7. BUILDING DESCRIPTION······························································································ 11
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 3 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
1. GENERAL
This section covers the general requirements and conditions for the design of civil and architecture
works. The civil and architecture works include the design of all the items required for successful
completion of the job described in the scope of work. The civil and architecture shall be designed to
the required service condition in accordance with the clause 2 codes and standards.
2. CODES AND STANDARDS
The structural and civil design will meet the requirements of local authorities.
In principle the following Codes and Standards shall be applied for the design, in their latest edition.
- AASHTO American Association of State Highway and Transportation Officials
- ACI American Concrete Institute
- AISC American Institute of Steel Construction
- AISI American Iron and Steel Institute
- ANSI American National Standard Institute
- API American Petroleum Institute
- ASCE American Society of Civil Engineers
- ASME American Society of Mechanical Engineers
- ASTM American Society of Testing and Materials
- AWS American Welding Society
- BSI British Standards Institution
- CRSI Concrete Reinforcing Steel Institute
- HI Hydraulic Institute
- IBC International Building Code
- ISO International Organization for Standardization
- JIS Japanese Industrial Standards
- KS Korean Industrial Standards
- NFPA National Fire Protection Association
- OSHA Occupational Safety and Health Administration
- SSPC Structural Steel Painting Council
- UBC Uniform Building Code (1997)
- Pedoman Perencanaan Pembebanan untuk Rumah dan Gedung (Indonesian Standard, “Guidance
of Load Planning for House and Building)
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 4 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
3. SCOPE OF WORKS
All architecture works are as follows, but not limited to the follows:
3.1. ARCHITECTURE WORKS - Administration & Amenity Building
- Ware House
- Security Building
- Mobile Equipment Garage Shelter
4. DESIGN LOAD
4.1. GENERAL
Buildings, equipment foundations and support structures and ancillary structures shall be designed
for the worst combinations of dead loads, live loads (imposed loads), impact and dynamic effects
due to operation of plant, crane loads, maintenance loads, earth pressure, wind loads, seismic
loads, etc.
4.2. DEAD LOAD
Dead loads shall include the weight of the structure and equipment of a permanent or semi-
permanent nature including tanks, silos, bins, ceilings, wall panels, partitions, roofing, piping, drains,
electrical tray, bus ducts, and the contents of tanks and bins measured at full capacity. However,
the contents of tanks and bins will not be considered as effective in resisting column uplift. Dead
loads shall be determined using the unit weights from ASCE 7.
4.3. LIVE LOAD
Live load is the load superimposed by the use and occupancy of the building or other structure.
Live load shall be include loads due to traffic and permanency of people, vehicles operation loads,
and gas, liquid or earth pressures which are or may be variable in time while in usual operation. It
does not include the wind load, seismic load, or dead load.
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 5 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
4.4. WIND LOAD
Building and other structures, including the main wind force resisting system and all components
and cladding thereof, shall be designed and constructed to resist wind loads as specified in ASCE
7 and the project specifications
- The exposure category : D
- The importance factor : 1.15
- The basic wind speed at 10[m] above ground level : 35 m/sec
- The gust effect factor(Gf) for rigid structures : 0.85
4.5. SEISMIC LOAD
All structures shall be designed for seismic loads conforming to Zone 2B of the Uniform Building
Code (UBC, 1997). Wind and/or crane live loads are not to be combined with earthquake loads.
- Seismic zone factor(Z) : 0.20
- Importance Factor
· Administration & Amenity Bldg, Security Bldg : 1.0
· Warehouse & Mobile Equipment Garage Shelter : 1.25
4.6. EARTH PRESSURE
Lateral soil pressure shall be in accordance with the recommendations of the geotechnical
engineer. The relative flexibility of the retaining structure shall be considered in establishing the
pressure coefficient.
4.7. GROUND WATER PRESSURE
For structural and buoyancy calculations, the high groundwater table shall be considered with the
basis on the geological investigation report to be performed by contractor after contract award.
4.8. DESIGN LOAD COMBINATION
Proper load combinations shall be used for structural steel and reinforced concrete to comply with
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 6 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
applicable codes, standards and equipment supplier requirement.
All steel and concrete structures or buildings shall be designed to meet the seismic requirements in
ASCE 7.
5. STEEL STRUCTURES
5.1. MATERIAL
All steel members except cold-formed steel members and as noted shall conform to the
requirement of ASTM A 36, ASTM A 572 GR50 having the following minimum characteristics.
- Minimum yield strength ( Normal structural steel )
For ASTM A 36, Fy = 250 MPa
- Minimum yield strength ( High-strength structural steel )
For ASTM A 572 GR50, Fy = 345 MPa
5.2. DESIGN BASIS
Steel structures and connection shall be designed in accordance with the following standards:
- AISC American Institute of Steel Construction : "Specifications for the Design, Fabrication and
Erection of Structural Steel for Buildings", Appendices and Commentaries.
All steel framed structures shall be designed as “rigid frame” (AISC Specification Type 1) or “simple
space frame” (AISC Specification Type 2), utilizing single span beam system, vertical diagonal
bracing at main column lines and horizontal bracing at the roof and major floor levels. The use of
Type 1 rigid frame will prefabricated metal buildings. All other framed structures shall utilized Type
2 design and construction or will utilize a combination of Type 1 and Type 2.
5.3. PAINTING WORKS
Application and testing of the work shall conform to the standard SSPC (Steel Structure Painting
Council, USA).
Preparation methods conform to the standards SSPC-SP1 (for Solvent Cleaning), SSPC-SP2 (for
hand Tool Cleaning), SSPC-SP3 (for Power Tool Cleaning), SSPC-SP6 (Commercial Blast
Cleaning) and SSPC-SP10 (Near-White Blast Cleaning).
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 7 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
5.3.1. Structural steel (indoor condition)
1) Shop coat 1: Inorganic zinc rich primer: 75 microns
2) Shop coat 2 : Polyamide epoxy: 50 microns
3) Shop coat 3 : Polyurethane: 50 microns
4) Touch-up 1: Epoxy mastic aluminum primer : 75 microns
5) Touch-up 2: Epoxy Polyamide epoxy: 50 microns
6) Touch-up 3: Polyurethane: 50 microns
5.3.2. Structural steel (outdoor condition)
1) Shop coat 1: Inorganic zinc rich primer: 75 microns
2) Shop coat 2 : Polyamide epoxy: 100 microns
3) Shop coat 3 : Polyurethane: 50 microns
4) Touch-up 1: Epoxy mastic aluminum primer : 75 microns
5) Touch-up 2: Epoxy Polyamide epoxy: 100 microns
6) Touch-up 3: Polyurethane: 50 microns
5.3.3. Galvanized deck plate (in door)
1) Field coat 1: Wash primer: 10 microns (before erection)
2) Field coat 2: Alkyd enamel: 40 microns (before erection)
3) Field coat 3: Alkyd enamel: 40 microns (after erection)
5.3.4. Galvanized deck plate (acid resistant finish/battery room)
1) Field coat 1: Epoxy primer: 50 microns (before erection)
2) Field coat 2: Epoxy polyamide: 50 microns (after erection)
5.3.5. Miscellaneous steel (indoor, handrail, checkered plate, ladder)
1) Shop coat 1: Epoxy mastic aluminum primer: 75 microns
2) Field coat 1: Polyamide epoxy: 50 microns
5.3.6. Galvanized miscellaneous steel (outdoor ladder, handrail, downspout, gutter, checkered plate,
all indoor and outdoor doors and shutters, etc.)
1) Shop coat 1: Epoxy primer: 75 microns
2) Field coat 1: Polyamide epoxy: 50 microns
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 8 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
5.3.7. Galvanized miscellaneous steel (touch-up coating)
1) Field coat 1: Epoxy mastic aluminum primer: 75 microns
6. REINFORECED CONCRETE STURUCTURE & FOUNDATION
6.1. MATERIAL PROPERTIES
6.1.1. Concrete Concrete
Class Compressive Strength
at 28 days in MPa Type of cement
Lean Concrete 15MPa ASTM C150 Type II or V
for foundation at or bellow ground level.
Type I for above ground level.
Concrete Pavement 21MPa
Building & Structure Heavy Equipment Foundation
28MPa
6.1.2. Fine Aggregate : ASTM Standard C33; C289; C295 or equivalent standard.
Use graded natural sand.
6.1.3. Coarse Aggregate : ASTM Standard C33; C289; C295 or equivalent standard.
Use graded crushed stone
6.1.4. Reinforcing Bars : Codes for design of reinforcing bars are as follows :
ASTM Standard A615 Grade 25 to Grade 60
For all reinforcing, dowels of equipment foundations over grade slab.
6.1.5. Bar Supports : CRSI Manual of Standard Practice Class C
For material foundations on soil or mud use precast concrete blocks
having the same compressive strength as the foundations.
6.1.6. Form Ties : For all other structures, steel snap-ties architectural type without washers.
6.1.7. Welled Steel Wire Fabric : ASTM Standard A185 or equivalent standard
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 9 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
6.1.8. Maximum allowed fly ash content in all structural concrete is 20% cementious.
6.1.9. Formworks : Plywood (for exposed surface, shall be water proof, resin bonded, exterior type).
Lumber-Straight, uniform width and thickness and free of knots offsets, holes, other surface
defects.
6.1.10.Grouting
1) Plastic Grout (Regular sand & cement grout and non-shrink admixture)
- Conduit, piping, etc. through concrete floors or walls
- Bases & supports of mechanical & electrical equipment(except rotating equipment foundation)
2) Non-shrink Grout
- Anchor bolts in drilled holes
- Equipment bases where required by manufacturer
- Anchor bolts including sleeves and column base plates
6.2. PILING
6.2.1. Types of pile : Solid precast pre-stressed concrete spun pile or bored pile.
6.2.2. Materials
Pre-casting piling shall be in accordance with applicable provisions of the “Standard
Specifications for Highway Bridges" of the American Association of State Highway and
Transportation Officials (AASHTO).
Piling shall be spun or bored pile concrete with reinforcing and pre-stressing steel, with no voids
permitted.
Concrete shall have a minimum compressive cylinder strength of 35 MPa at age 28 days.
6.2.3. Pre-stressing
Each pre-stressing strand will have an initial stress not exceeding 70 percent of the breaking
strength. The effective unit pre-stress in the concrete after losses will not be less than 4,900 kPa.
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 10 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
6.2.4. Pre-stressing Material
Strand for pre-stressed concrete shall be of 7 wires complying with ASTM A416 or equivalent
standard. The strands shall be twisted into cables with a pitch not exceeding 20 times the
diameter of a single wire.
Bars for pre-stressed concrete shall be made from open hearth steel with sulphur and
phosphorus contents each below 0.05 percent by a manufacturer specializing in the manufacture
of steel for pre-stressing.
6.2.5. Pile capacity
1) The required allowable pile bearing capacities for vertical and lateral loads shall be determined by
the contractor and shall be confirmed by the static pile load test in accordance with ASTM D1143
Standard.
6.3. DESIGN BASIS
Reinforced concrete shall be designed by Ultimate Strength Method in accordance with "Building
Code Requirements for Reinforced Concrete" of the American Concrete Institute, ACI 318.
6.4. FOUNDATION WORKS
The procedure used for the design of the foundations shall be the most critical loading combination
of the superstructure and/or equipment and other conditions based on sub soil condition, which
produces the maximum stresses in the foundation or the foundation component.
The type of all foundations shall be finally decided by soil investigation results.
Foundation and floor levels to be normally adopted for various plant units are indicated below,
unless otherwise noted.
- Pedestal top from FFL(Floor Finishing Level) :
Min. +200 mm for indoor equipment foundation & building structure
- Pedestal top from GL(Ground Level) :
Min. +300 mm for outdoor equipment foundation & structure
- First Floor Finishing top from GL(Ground Level) :
Min. +200 mm for Bldg & Shelter
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 11 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
7. BUILDING DESCRIPTION
7.1. BUILDING DESCRIPTION
7.1.1. Administration & Amenity Building
1) Type of Structure : RC Moment Frame
2) Type of Foundation : Pile Foundation
3) Exterior Finish
Wall : Latex paint on plastered cavity wall
Roof : Light weight concrete finish on
waterproofing membrane
4) Interior Finish : Refer to interior finishing schedule
7.1.2. Warehouse
1) Type of Structure : Steel Moment & Braced Frame
2) Type of Foundation : Pile Foundation
3) Exterior Finish
Wall : Thermal insulated metal panel(Zincalume)
Roof : Thermal insulated metal panel(Zincalume)
4) Interior Finish : Refer to interior finishing schedule
7.1.3. Security Building
1) Type of Structure : RC Moment Frame
2) Type of Foundation : Pile Foundation
3) Exterior Finish
Wall : Latex paint on plastered reinf concrete block
Roof : Light weight concrete finish on
waterproofing membrane
4) Interior Finish : Refer to interior finishing schedule
7.1.4. Mobile Equipment Garage Shelter
1) Type of Structure : Steel Moment & Braced Frame
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 12 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
2) Type of Foundation : Pile Foundation
3) Exterior Finish
Roof : Single skin metal panel(Zincalume)
4) Interior Finish : Refer to interior finishing schedule
7.2. INTERIOR FINISHING SCHEDULE FOR BUILDING WORK
No Building Name Room
Finishing Re-
Marks Floor Wall Ceiling
1 Administration &
Amenity Building
Office Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Meeting
Room
Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Manager
Room
Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Plant
Manager
Room
Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 13 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
No Building Name Room
Finishing Re-
Marks Floor Wall Ceiling
1 Administration &
Amenity Building
File Room Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Kitchen Unglazed
ceramic tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
PVC Panel
Pantry Unglazed
ceramic tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
PVC Panel
Canteen Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
First Aid
Station
Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Praying
Room
Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 14 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
No Building Name Room
Finishing Re-
Marks Floor Wall Ceiling
1 Administration &
Amenity Building
Shower
Room
Unglazed
ceramic tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
PVC Panel
Locker Room Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Change
Room
Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Toilet Unglazed
ceramic tile
Glazed
ceramic tile
Suspended
ceiling with
PVC Strip
Cleaners
Store
Unglazed
ceramic tile
Glazed
ceramic tile
Suspended
ceiling with
PVC Strip
Vestibule Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 15 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
No Building Name Room
Finishing Re-
Marks Floor Wall Ceiling
1 Administration &
Amenity Building
Storage Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Hall and
Corridor
Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Staircase Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Latex paint
on Exposed
concrete
Machine
Room
Epoxy paint
on Steel
trowel
finish/
Concrete
Slab
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Latex paint
on Exposed
concrete
Alarm Valve
Room
Epoxy paint
on Steel
trowel
finish/
Concrete
Slab
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Latex paint
on Exposed
concrete
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 16 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
No Building Name Room
Finishing Re-
Marks Floor Wall Ceiling
2 Warehouse Warehouse
Epoxy
Paint on
Hardener/
Concrete
Slab
Exposed metal
cladding -
3 Security Building
Guard Room Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Locker
Room/
Tea Room
Composite
vinyl tile
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
Suspended
ceiling with
Acoustical
tile
Toilet Unglazed
ceramic tile
Glazed
ceramic tile
Suspended
ceiling with
PVC Strip
2x60MW MERAK CFPP PROJECT DOCU. NO. :
Rev. No. : A Page No. : 17 of 17 TITLE BID SPECIFICATION FOR
ARCHITECTURAL ENGINEERING
No Building Name Room
Finishing Re-
Marks Floor Wall Ceiling
4 Mobile Equipment
Garage Shelter
Storage,
Tool Room
Epoxy
Paint on
Hardener/
Concrete
Slab
Latex paint on
Cement
plastered
/Reinforced
Concrete Block
-
Garage
Epoxy
Paint on
Hardener/
Concrete
Slab
- -
Appendix #2. Division of Work Scope (Architecture Part)
Project : 2×60MW MERAK COAL POWER PLANT
DEC CONTRACTOR REMARK
A. Basic Design
1. Design Criteria O
2 Specification O O
3 Information for Civil/Architecture/Structure O
4 Standard Drawing O
B. Detail Design
1. Drawings
a. Administration & Amenity Building O
b. Warehouse O
c. Security Building O
d. Mobile(Heavy) Equipment Garage Shelter O
e. Others
1) Rebar Bending Schedule (if required) O Option
2) Building Color Schedule O
3) Materials Check / Review O
4) Vendor and Shop drawing Review O O
2. Calculations O Use STAAD Pro
a. Structural Calculation Sheet
1) Administration & Amenity Building O
2) Warehouse O
3) Security Building O
4) Mobile(Heavy) Equipment Garage Shelter O
3. Bill of Material (3 Times)
a. Administration & Amenity Building O
b. Warehouse O
c. Security Building O
d. Mobile(Heavy) Equipment Garage Shelter O
C. AS-BUILT
1. Drawing
a. Administration & Amenity Building O
b. Warehouse O
c. Security Building O
d. Mobile(Heavy) Equipment Garage Shelter O
2. Structural Calculation Sheet
a. Administration & Amenity Building O
b. Warehouse O
c. Security Building O
ITEM
1 of 2
DEC CONTRACTOR REMARKITEM
d. Mobile(Heavy) Equipment Garage Shelter O
D. Local Regulation Check & Permit
1. Local Regulation Check
a. Administration & Amenity Building O
b. Warehouse O
c. Security Building O
d. Mobile(Heavy) Equipment Garage Shelter O
e. Turbine Building (Including T/G FDN. & Equipment Independent FDN.) O Provide Drawings
f. Main Control Room and Switchgear Building O Provide Drawings
g. Coal Handling Control Building O Provide Drawings
h. Electro-Chlorination & Cooling Water Elec. Building O Provide Drawings
i. #1,2 20kV Switchgear Building O Provide Drawings
j. Water Treatment Building O Provide Drawings
k. Seawater Intake & Cooling Water Pump House O Provide Drawings
l. Ash Handling Equipment & ESP MCC Building O Provide Drawings
m. Bed Material Shelter O Provide Drawings
n. Coal Storage Yard Shelter O Provide Drawings
o. High Speed Oil Pump Station Shelter O Provide Drawings
p. Demi. Water Pump Station Shelter O Provide Drawings
q. Pipe Rack O Provide Drawings
r. Coal Bunker Bay Structure O Provide Drawings
s. Coal Laboratory Building (Option) O Provide Drawings
t. Weight Scale House (Option) O Provide Drawings
u. Jetty House (Option) O Provide Drawings
E. Technical assistance for construction
1. Technical Assistance for Construction O O
2. Field Engineering Work O O
F. Others
1. O
2. O O
3. O O
CONTRACTOR shall provide working space in his office for DECengineers, if requested. (desk, chair, internet, etc. for 1 persons)
Additional design and technical support shall be provided aftercoordination between DEC and CONTRACTOR, If necessary.
CONTRACTOR shall be attended regular or irreqular meeting, Ifrequired.
2 of 2
Appendix #2. Division of Work Scope (VAC & Plumbing Part)
Project : 2×60MW MERAK COAL POWER PLANT
DEC CONTRACTOR REMARK
A. Basic DesignBuildings
1. Administration & Amenity Building O
2. Warehouse O
3. Security Building O
4 Mobile(Heavy) Equipment Garage Shelter O
B. Detail DesignDocuments
1. Design Criteria for VAC & Plumbing System O
2. Technical Specification for VAC & Plumbing System ORequest for QuotationProvide Form
3. Calculation for VAC & Plumbing System O Provide Form
4. System Description for VAC & Plumbing System O
5. Construction Specifications for VAC & Plumbing System O
6. Equipment List O
7. Bill of Material (3 Times) O Provide Form
C. AS-BUILTDrawings
1. Equipment Schedule O Provide Form
2. P & ID O Provide Form
3. Plan (Piping & Duct) O Provide Form
4. VAC Control (Wiring Plan, Diagram, etc.), If necessary. O Provide Form
D. Local Regulation Check & PermitCoordination Work O
E. Technical assistance for construction Vendor Printer Check O
F. OthersTBE (Technical Bid Evaluation) O
G. AS-Built O
H. Local Regulation Check & Permit
1. Local Regulation Check
a. Administration & Amenity Building O
b. Warehouse O
c. Security Building O
d. Mobile(Heavy) Equipment Garage Shelter O
e. Turbine Building (Including T/G FDN. & Equipment Independent FDN.) O Provide Drawings
f. Main Control Room and Switchgear Building O Provide Drawings
g. Coal Handling Control Building O Provide Drawings
h. Electro-Chlorination & Cooling Water Elec. Building O Provide Drawings
i. #1,2 20kV Switchgear Building O Provide Drawings
j. Water Treatment Building O Provide Drawings
k. Seawater Intake & Cooling Water Pump House O Provide Drawings
l. Ash Handling Equipment & ESP MCC Building O Provide Drawings
m. Bed Material Shelter O Provide Drawings
ITEM
1 of 2
DEC CONTRACTOR REMARKITEM
n. Coal Storage Yard Shelter O Provide Drawings
o. High Speed Oil Pump Station Shelter O Provide Drawings
p. Demi. Water Pump Station Shelter O Provide Drawings
q. Coal Bunker Bay Structure O Provide Drawings
r. Coal Laboratory Building (Option) O Provide Drawings
s. Weight Scale House (Option) O Provide Drawings
t. Jetty House (Option) O Provide Drawings
E. Technical assistance for construction
1. Technical Assistance for Construction O O
2. Field Engineering Work O O
F. Others
1. O
2. O O
3. O O
CONTRACTOR shall provide working space in his office for DEC engineers, if requested. (desk, chair, internet, etc. for 1 persons)
Additional design and technical support shall be provided after coordination between DEC and CONTRACTOR, If necessary.
CONTRACTOR shall be attended regular or irreqular meeting, If required.
2 of 2
2 X 60 MW POWER PLANT
PT.MERAK ENERGI INDONESIA
EXHIBIT– C - i
(March 2010)
EXHIBIT C – SITE REPORTS AND DATA
2 X 60 MW POWER PLANT
PT.MERAK ENERGI INDONESIA
EXHIBIT– C - ii
(March 2010)
Table of Contents
1. Definitions . ...................................................................................................................................... 1
2. Project Location ............................................................................................................................... 1
3. Site Description ................................................................................................................................ 1
3.1. Topography…………………………………………………………………….. ................... 1
3.2. Stratigraphy ……………………………………………………………………. ................... 2
3.3. Geology Structure ………………………………………………… ...................................... 2
3.4. Morphology ……………………………………. .................................................................. 2
3.5. Climate …………………………………………… ............................................................... 2
3.6. Seismic Zoning ………………………………………. ......................................................... 3
3.7. Ground Water Level ………………………………………. ................................................. 3
3.8. Design of High and Low Water Levels …………………….. ............................................... 3
3.9. Seawater Supply …………………….. .................................................................................. 4
3.10. Soil Condition ………………………………………………………………. ....................... 4
3.11. Bearing Capacity of Subsoil ……………………………………………… ......................... 4
EXHIBIT– C-1
(March 23, 2010)
SITE REPORTS AND DATA
1 Definitions
Except as otherwise defined in this Exhibit C, capitalized terms used in this Exhibit C shall
have the respective meanings assigned to them in the Engineering, Procurement, and
Construction Contract between Owner and Contractor to which this Exhibit C is annexed (the
“Contract”). Unless otherwise specified, all references to Articles and Sections without other
attribution are references to Articles and Sections of the Contract.
2 Project Location.
The location of the Facilities is in Mangunreja village in the sub-district of Pulo Ampel,
district of Serang in Banten Province on the western part of the Java island in Indonesia. The
benchmark grid coordinates of the Facilities are included in Exhibit A.
3 Site Description.
3.1 Topography.
This project site area is located in the north coastal plain area of Mount Bojonegara (Mount
Gede) Peninsula. The land has a characteristic of coastal hill side where the plain area is
relatively narrow. A distance of coastal line to the foothill ranges from 500 m to 800 m.
The land area is bordered by 530 m of coastal line of the Java Sea in the north, 615 m of
neighboring fence (PT Latexia Indonesia– Chemical Plant) in the east, and 525 m of
neighboring fence in the west. The south part of the land area is bordered by a public road
with a total distance of 674 m.
Based on Tidal Observation Report, the Mean Sea Level (MSL) is 60 cm above the
topographic datum (EL. 0.00), or MSL at EL. 0.600. The Highest Water Spring (HWS) is at
EL. 1.26, while the Lowest Water Spring (LWS) is at EL. -0.04.
The terrain of land is almost flat since this area was formerly a shipyard with a small port
pool facility. Surface elevation ranges from EL. 2.900 (or +2.300 MSL) to EL. 4.700 (or
+4.100 MSL). There is a small area within this land terrain that is at EL. 7.286 (or +6.686
MSL).
The existing port pool, formed by a pair of jetties just east of the coastal line, has a width of
75 m. The left jetty is 89 m long and the right jetty is 84 m long. The deepest pool floor is at
EL. 3.846 (or -4.446 MSL). The rest of the coastal line is shallow sea reef bed.
Total land area excluding the jetties is 68,640 m2 with a land boundary of 1,120 m long.
Owner intends to reclaim the seashore and build a breakwater, which is estimated to increase
the land area by approximately 60,000 m2. The reclamation is estimated to make available
approximately 30,000 m2 of additional land. The remaining reclaimed area of approximately
30,000 ha will be used as a landfill for ash disposal. If the Owner completes the reclamation
work, the Owner may make such additional land available for the Project. However, the
Owner is under no obligation to complete such work or make it available to the Contractor.
The coal unloading jetty is planned to be located at north side of breakwater at the north east
EXHIBIT– C-2
(March 23, 2010)
of the project site.
3.2 Stratigraphy.
The project site is located in a valley at about 15 km north east of the Merak Harbor and
geologically in the Merak region. This rugged valley area was formed by radiating dykes of
Mount Gede. The dykes were formed by extinct and highly eroded Quaternary volcanic
peaks, which were deposited in the valley floors.
3.3 Geology Structure.
The Merak region was formed by Andesitic (basalt) volcanic rocks of Pleistocene age. These
rocks are composed of successive lava flows and tuffaceous material.
The subsoil of this site consists of alluvial deposits, which are influenced by sea bed alluvial
rock like coral limestone, having a thickness ranging from 2 m to 16 m, overlaying
uncemented tuffaceous layers of silt/clayey silt and sand stone on top of volcanic
pyroclastic rock.
3.4 Morphology.
In general, the morphological condition of the project site and its surroundings is closely
related to the physical characteristics of the area. The morphology of the project site can be
grouped into two parts: alluvial plain morphology and hill morphology.
The alluvial plain morphology, which is influenced by coastal characteristics such as sea
water tide, is dominated by silt/clayey silt and sand/sand stone intercalated with coral reef
layer.
The hill morphology, which is in the backyard of the project site, is dominated by volcanic
rock and tuffaceous rock. In recent times, an area of the backyard closest to the project site is
an ex-quarry area. The Andesitic rock and tuffaceous rock were exploited for other site
construction works.
3.5 Climate.
The altitude of the project area is about EL. 4.500 or 3.90 m above MSL. The UTM
coordinate of the project site is 5,325,224 north and 4,409,502 east.
It is obvious that general climate in the region of the project site is influenced by annual
monsoon seasons. The west monsoon is from December through March, while the east
monsoon is from June through August. Beyond these monsoon seasons, are the transition
times. The climate parameters such as wind characteristic, sea circulation, air temperature,
air humidity, precipitation, etc are governed by these monsoon seasons.
3.5.1 Precipitation.
EXHIBIT– C-3
(March 23, 2010)
Dry season is generally from May through October, while the rainy season brings heavy
rainfalls normally from November through April. On the average, the total annual
precipitation is 1,911 mm. The annual rainy days are 135 days of which 97 days (72
percent) occur from November through April. The maximum precipitation occurs in January
when the rain falls for an average of 24 days. The minimum precipitation is in August when
rain falls for less than a day.
In Indonesia the precipitation data base in daily information, contractor shall be evaluated and
adjusted to hourly basis.
3.5.2 Temperature.
The monthly average of mean daily temperature at the project region ranges from 26.0 °C to
27.6 °C. The mean daily temperature is about 27.0 °C. The maximum range of mean daily
temperature is about 11 °C while the minimum range is about 7.5 °C.
3.5.3 Relative Humidity.
The mean daily relative humidity in the region varies from 72 percent (minimum) to 87
percent (maximum). The mean annual daily relative humidity is about 79 percent.
3.5.4 Wind Characteristic.
The wind at sea is consistent with the monsoon pattern, but near the coast where land and sea
breezes can develop, wind can attain a velocity greater than that caused by the general air
circulation during monsoon transitional periods.
In the Serang region, the land and sea breeze effects are seen to be of greater significance
than the monsoon circulation. The average wind velocity is 1.70 m/s, and the maximum
velocity recorded is 35 m/s. The wind generally blows to the west. During the wet season
(November through April), the wind blows from west to east. But during the dry season
(May through October), the wind blows from south east to north west.
The maximum velocity shall be adjusted to some factor as height above ground, shape factor and
others according relation standard for find the wind load.
3.5.5 Sun Radiation.
Based on the average of 10-year data (1983 to 1993), the highest sun radiation occurs in July
(71.2 percent) and the lowest radiation in February (55.0 percent). The average annual
radiation is 63.0 percent.
3.6 Seismic Zoning.
Per the published data from Indonesia Earthquake Regulations, the project site is on the UBC
EXHIBIT– C-4
(March 23, 2010)
Zone 4 boundary. The Contractor shall conform to the requirements of the UBC Zone 2B,
1997, and design the Facilities to withstand a base rock acceleration coefficient of up to 0.2g.
3.7 Ground Water Level.
Based on the soil investigation reported by PT. Surya Jenar Mandhiri, the level of ground
water varies from 2.5 m to 3.00 m below the existing ground surface or at level EL. 2.200 to
EL. 1.700 relative to topographic datum.
3.8 Design of High and Low Water Levels.
Various sea levels and tide characteristics were determined by observations of tidal
activities carried out by PT. Surya Jenar Mandhiri. The tidal observations were done for
15 continuous days using tide pole, which was used as a reference point and positioned in
the port pool during the site observations.
Based on the results of tidal observations were as follow:
Mean Sea Level (MSL) EL. 0.600 m
Highest Water Spring (HWS) EL. 1.260 m
Lowest Water Spring (LWS) EL. Minus 0.040 m
Average Ground Surface (AGS) EL. 4.500 m
Ground Water Level (GWL) EL. 1.900 sloping to EL. 1.400 m
3.9 Seawater Supply.
The Java Sea is a semi enclosed body of water surrounded by Sumatera island on the west,
the island of Kalimantan on the north, and the Java island on the south. The oceanography of
the Java Sea is governed by the yearly monsoon cycles. The west monsoon occurs from
December through March and the east monsoon occurring from June through August. The
monsoon cycles control the circulation, temperature, and salinity structure of the water
column.
The maximum sea surface temperatures are influenced by the transition of the monsoon
cycles. During the monsoon cycle transition, radiant heating and low evaporation rates allow
the sea surface temperature to rise to 29 – 30 °C. With low radiant heating and high
evaporation rates during the transition can lower the surface temperature to 26 - 27.5 °C.
An annual sea surface temperature variation of about 3 °C.
3.10 Soil Condition.
Based on the soil investigation report issued by PT. Surya Jenar Mandhiri, soil strata of the
Site can be classified into 6 soil layers:
Layer Description
1 Silt, clayey silt, medium stiff, gray
2 Silt, clayey silt, hard, gray
EXHIBIT– C-5
(March 23, 2010)
3 Coral reef, mixed sand, loose, brown
4 Sandstone, very dense, black
5 Boulder, dense, black
6 Boulder, very dense, black
In general, the subsurface condition of the Site can be described as set out below:
0.00 – 8.50 m The soil was formed by silt, clayey silt containing sand and coral,
medium to stiff consistency or stiff to hard consistency, gray to
brown in color.
Cone resistance (qc) is about 10 to 25 kg/cm2 for medium
consistency and 50 to 250 kg/cm2 for hard consistency, and the
SPT value is about 4 to 14 blows/ft for medium consistency and
more than 40 blows/ft for hard soil.
8.50 – 14.50 m The soil was formed by sandstone, very dense, and black in color.
This layer has a cone resistance (qc) of more than 250 kg/cm2 and
50 to 60 blows/ft of SPT-value.
14.50 – 20.00 m This soil layer was formed by boulder and coral reef, very dense
and black in color. This layer has a SPT-value of more than 60
blows/ft.
3.11 Bearing Capacity of Subsoil.
Structures with heavy static loadings or dynamic loadings are proposed to use deep
foundations such as bored piles or driven piles. Light structures are proposed to use shallow
foundations like spread footings, raft, etc.
The hard layer, for deep foundations, was found in various depths of 9.00 to 16.00 m. This
layer gives adequate bearing capacity (Dutch Cone Penetration indicators) of more than 250
kg/cm2 and SPT-value of more than 60 blows/ft.
The shallow foundations such as spread footings can be laid at a 1.00 m depth of soil layer.
The soil bearing capacity at 1.00 m depth is 0.50 to 1.00 kg/cm2.
Owner will provide a preliminary soil investigation data and reports, as available, and other
approximate information regarding general climate, sea water, and tide levels, etc. to the
Contractor for reference only. In addition to the soil investigation of PT Surya Jenar
Mandhiri, Owner will also provide the Contractor with the soil investigation report of
Shanghai Electric Engineering Consulting Co. Ltd. (soil investigation work by Sofoco), but
the Owner shall not take any responsibility for the accuracy or adequacy of the information
contained therein and the Contractor shall carry out his own on-site soil investigation to
independently define the soil structure and its engineering properties. The Contractor shall
also undertake an independent topographical survey of the site and shall base his offer on the
information defined from those investigations.
EXHIBIT– C-6
(March 23, 2010)
EXHIBIT– C-7
(March 23, 2010)