Combined Cycle Power Plant

AGENDA

• Introduction - Neil Cass (JKC Australia LNG)

• Welcome to Country

• CH2M HILL-UGL GE - Welcome and Introduction

• Combined Cycle Power Plant (CCPP) Project Structure

• CCPP Project details

• Australian Industry Participation (AIP), Aboriginal & Torres Strait Islander (ATSI) engagement and Industry Capability Network (ICN)

• Project Requirements – Health, Safety, Environment and Quality

• Lower Tier Subcontractor / Supplier packages

• Lower Tier Subcontractor / Supplier selection process

• Open discussions

Page 3: INPEX - ICN Gateway

3

Combined Cycle Power Plant

INTRODUCTION

by

NEIL CASS

AIP Local Content Manager

Ichthys Project

JKC Australia LNG Pty Ltd

Page 4: INPEX - ICN Gateway

4

Combined Cycle Power Plant

JKC Australia LNG Pty Ltd

Welcome to Country

Page 5: INPEX - ICN Gateway

5

Combined Cycle Power Plant

WELCOME

Peter Jones Deputy Project Manager – CH2MHILL-UGL GE

John Mazunik Project Procurement Manager – CH2MHILL-UGL GE

Greg Gowans Director of Logistics – CH2MHILL-UGL GE

Manish Kolhe Sourcing Leader – CH2MHILL-UGL GE

Page 6: INPEX - ICN Gateway

6

Combined Cycle Power Plant

CH2M HILL-UGL GE INTRODUCTION

• Global Firm providing EPC services in multiple market

sectors including power:

• EPC - 630 MW Combined Cycle Power Plant for Origin

Energy at Darling Downs

• EPC- 540 MW Combined Cycle Plant for Xcel Energy

at St Paul, Minnesota

• EPC - 635 MW Combined Cycle Power Plant for Empire

Generation Co LLC at New York

Page 7: INPEX - ICN Gateway

7

Combined Cycle Power Plant

• Global leader in Engineering, Construction. Property, Asset

management

• UGL capabilities in power

• Gas Turbine power stations

• Diesel power stations

• Hydro power stations

• Cogeneration power stations

• Steam turbine power stations

• Current power project : Solomon power station for Fortescue

Metals Group

CH2M HILL-UGL GE INTRODUCTION

Page 8: INPEX - ICN Gateway

8

Combined Cycle Power Plant

CH2M HILL-UGL GE INTRODUCTION

• GE works in all areas of power generation, the energy

industry - including renewable resources such as wind and

solar; biogas and alternative fuels; and coal, oil, natural gas

and nuclear energy

• GE power generation equipment and technology is used to

generate a quarter of the world’s electricity every day

• Recently executed works in Australia:

• Darling Downs 630 MW plant

9E Gas Turbine Generators – 3 units

Steam Turbine Generators – 2 units

Page 9: INPEX - ICN Gateway

9

Combined Cycle Power Plant

JKC Australia LNG Pty Ltd

CH2M Hill & UGL (JV) and GE & GEII

Lower Tier

Subcontractors

COMBINED CYCLE POWER PLANT PROJECT STRUCTURE

CH2M Hill and

UGL JV

Lower Tier

Vendors

GE and GE

International

Page 10: INPEX - ICN Gateway

10

Combined Cycle Power Plant

• Provision of complete engineering, procurement, construction,

commissioning for Combined Cycle Power Plant (CCPP)

• Assistance to start-up of a new and operable CCPP

• CCPP designed to meet approximately 500 megawatts of

electrical power demand

PROJECT SCOPE

Page 11: INPEX - ICN Gateway

11

Combined Cycle Power Plant

• Fabricate and supply 2000 tonnes of structural steel

and approximately 1300 tonnes of piping

• 15,000 m3 structural concrete

• 3000 m3 of stabilised sand formation

• Steam and gas turbine generators

• Heat recovery steam generators (HRSG)

• Air cooled condensers (ACC)

• Utility boilers

• All plant electrical equipment and cables

• Piping

• Tanks

• Full construction and commissioning of all supply

• Temporary construction facilities, and

• related works…..

PROJECT SCOPE - DETAIL

Page 12: INPEX - ICN Gateway

12

Combined Cycle Power Plant

COMBINED CYCLE POWER PLANT– PROJECT SCOPE.

Page 13: INPEX - ICN Gateway

13

Combined Cycle Power Plant

• Register your interest and capability with the Industry

Capability Network (ICN)

Note: Several Long Lead Packages are already in the

Procurement Process

• Register your interest against the specific packages on

ICN Gateway:

www.ch2m_ugl_jv.icn.org.au

www.generalelectric.icn.org.au

PROJECT STATUS : UNDERGOING DESIGN PHASE.

COMMENCING PROCUREMENT PHASE

Page 14: INPEX - ICN Gateway

14

Combined Cycle Power Plant

AUSTRALIAN INDUSTRY PARTICIPATION

• CH2MHILL-UGL GE actively supports Australian

Industry Participation (AIP) as a core principle for the

project

• CH2M HILL-UGL GE is committed to working

constructively with Australian Industry

• CH2MHILL-UGL GE will provide full, fair and

reasonable opportunity to Australian industry

• CH2MHILL-UGL GE will ensure use of ICN Gateway to

communicate subcontracting and supplier opportunities

Page 15: INPEX - ICN Gateway

15

Combined Cycle Power Plant

AUSTRALIAN INDUSTRY PARTICIPATION

• Project Engineering / Design Managers will be responsible

for ensuring the incorporation of applicable AIP

considerations throughout the project design / engineering

activities

• AIP will be considered as part of the commercial bid evaluation. Where bids are assessed as being equal in all other respects and both commercially and technically acceptable, preference will be given to the tenderer with AIP qualifications

• To maximise local industry participation, sourcing will consider:

• Darwin local area • Northern Territory • Interstate • International

Page 16: INPEX - ICN Gateway

16

Combined Cycle Power Plant

ABORGINAL AND TORRES STRAIT ISLANDER (ATSI) ENGAGEMENT

• CH2MHILL-UGL GE will actively implement INPEX and JKC

ATSI policy

• CH2MHILL-UGL GE will have a specific point of contact for

ATSI engagement (to be advised when identified)

• CH2MHILL-UGL GE is using the JKC ATSI business register

and ATSI business assessments as a basis to identify and

review the capability of ATSI businesses to undertake

specific Lower Tier Subcontracting (LTSC) opportunities

• CH2MHILL-UGL GE will engage suitable ATSI businesses and

persons to work through use of the JKC ATSI business

register, liaison with local ATSI groups, such as the Larrakia

Development Corporation and Ironbark.

Page 17: INPEX - ICN Gateway

17

Combined Cycle Power Plant

ABORGINAL AND TORRES STRAIT ISLANDER (ATSI) ENGAGEMENT

• CH2M HILL-UGL GE in consultation with its engineering

and design departments will review procurement strategy,

particularly in regard to package size and scope definitions

to assist ATSI businesses

• CH2M HILL-UGL GE is already in dialogue with Ironbark,

Industry Services Australia and Larrakia Development

Corporation

• Preference will be awarded to ATSI businesses subject to

technical and commercial comparability

• CH2MHILL-UGL GE will ensure that their LTSC are aware

of the obligations with respect to ATSI employment

opportunities on the project

Page 18: INPEX - ICN Gateway

18

Combined Cycle Power Plant

ABORGINAL AND TORRES STRAIT ISLANDER (ATSI) ENGAGEMENT

• CH2MHILL-UGL GE actively supports engagement of

ATSI people into the Lower Tier Subcontractors on

project works, and will:

• Give ATSI people every opportunity to participate,

including aiming to source, train and develop local ATSI

people

• Provide workplace induction and training for ATSI

people

• Provide cultural awareness training for non-ATSI

employees

Page 19: INPEX - ICN Gateway

19

Combined Cycle Power Plant

INDUSTRY CAPABILITY NETWORK (ICN)

• CH2M HILL-UGL GE will utilise ICN Gateway as a tool to

communicate its project needs

• CH2M HILL-UGL GE has started uploading Scope of works

for LTSC and Supply packages seeking Expression Of

Interest (EOI) on the ICN Gateway (It’s Free )

• CH2M HILL-UGL GE will ensure sufficient duration is

available for prospective bidders to register their EOI’s

• Registrations can be for:

• Tier 1: Capability to execute / supply total scope of

package works

• Tier 2: Capability to execute / supply partial scope

of package works

Page 20: INPEX - ICN Gateway

20

Combined Cycle Power Plant

INDUSTRY CAPABILITY NETWORK (ICN).

• Register your interest against the specific packages on ICN Gateway:

www.ch2m_ugl_jv.icn.org.au

www.generalelectric.icn.org.au

Page 21: INPEX - ICN Gateway

21

Combined Cycle Power Plant

• Health Safety Security & Environment (HSSE) is integral to everything CH2MHILL-UGL GE does

• CH2MHILL-UGL GE promotes an injury-free environment and works on the basis that all injury and damage is preventable

• All Safety, Quality and Environmental management systems accredited to ISO certifications

• CH2MHILL-UGL GE will ensure that they and all their Lower Tier Subcontractors are compliant with JKC guidelines on site specific additional Safety, Quality and Environmental requirements

PROJECT REQUIREMENTS: Health, Safety, Environment and Quality

Page 22: INPEX - ICN Gateway

22

Combined Cycle Power Plant

• Safety management plan, Quality management plan, and

Environmental management plan all specifically designed

for the project

• All CH2M HILL-UGL GE Lower Tier Subcontractors will

be required to comply with the Project requirements on

Health, Safety, Environment and Quality

PROJECT REQUIREMENTS: Health, Safety, Environment and Quality

Page 23: INPEX - ICN Gateway

23

Combined Cycle Power Plant

Gas Turbine /

Generator

components

+ +

US GE Contact: Jesse Middelkoop, Thermal Sourcing Operations Leader

+1-518-385-7104, [email protected]

Typical Combined

Cycle Power

Plant

Procurements

• Traditionally longer cycle, engineering intensive, technically

complex scope with very stringent quality requirements

• Seeking suppliers with demonstrated experience for similar

product/component in the oil & gas, power generation, or like

industry with stringent quality requirements

=

Steam Turbine /

Generator

components

Plant

accessories

Page 24: INPEX - ICN Gateway

24

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

ICN Package Status:- Tier 1: Open Tier 2: Open

PACKAGE DESCRIPTION

• Air Inlet Filter House. Inlet and exhaust system, support

and acoustic enclosures

• Air processing unit.

Air processing unit to supply

compressed air to the filter cleaning

system

• Cooling System Off base coolers for cooling of the

gas turbine and generator

• Fire suppression system CO2 LP type for fire protection in

turbine area

Page 25: INPEX - ICN Gateway

25

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

ICN Package Status:- Tier 1: Open Tier 2: Open

PACKAGE DESCRIPTION

• Electrical items Lighting, cable trays, bus ducts

etc.,

• Ventilation system

Centrifugal Blower complete with

motor, heating resistor, pressure

sensor etc.,

• Water injection skid

Skid complete with frame,

trunnions, pumps, electrical and

instrumentation with acoustical

enclosure

Page 26: INPEX - ICN Gateway

26

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

ICN Package Status:- Tier 1: Closed Tier 2: Open

PACKAGE DESCRIPTION

• Gas turbine and steam

turbine castings

Open sand pit or flask type ranging

from 230kg to 13,000 kg in various

grades of iron and steel

• Gas Turbine and Steam

Turbine Engineered

Systems

Gas conditioning systems, oil lube

systems, liquid fuel handling systems

• Electrical kits

Specialised junction box assemblies,

conduits, brackets, sleeves,

switches, relays, O-rings, etc.,

Page 27: INPEX - ICN Gateway

27

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

ICN Package Status:- Tier 1: Closed Tier 2: Open

PACKAGE DESCRIPTION

• Hardware kits

Thermocouple wells, dowels, pipe

plugs, bolts, gussets, gaskets,

flanges and custom fabricated nuts

and studs

• Piping kits Gauge assemblies, specialized

welded pipe assemblies etc.,

• Wrench and tool kits

Heavy duty socket wrenches,

sledging wrenches, spanner

wrenches, electrical bolt heaters,

alignment tools, guides, eyebolts

etc.,

Page 28: INPEX - ICN Gateway

28

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

ICN Package Status:- Tier 1: Open Tier 2 : Open

PACKAGE DESCRIPTION

• Bypass Stack

Design, fabrication and delivery of

5 Bypass stacks of diameter

approximately 3m with 6mm

thickness.

• Diverter Damper

Design, fabrication and delivery of

5 continuous operation Diverter

Damper systems capable of

modulation between simple cycle

and combined cycle operation.

Page 29: INPEX - ICN Gateway

29

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Combustion hardware Precision machined gas turbine

hardware

• Transition pieces Precision machined gas turbine

hardware

• Small machined

fabrications

• 2nd tier HRSG opportunities

Specialized welded/machined

components

Sub components on the heat

recovery steam generators

ICN Package Status: Coming shortly…..

Page 30: INPEX - ICN Gateway

30

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

ICN Package Status:- Tier 1: Closed Tier 2: Open

PACKAGE DESCRIPTION

• International Freight and

Customs.

International freight forwarding

services.

• Heavy Haul Transportation

Darwin to site/ on site Road trucks , trailers, SPMT's etc.

• Inland Transportation

Australia

Inland over the road and air

transportation

• Local Transportation

Passenger cars and vans

• Marine Warranty Surveyor

Cargo inspection

Page 31: INPEX - ICN Gateway

31

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Pumps (as separate

Packages)

Vertical sump pumps, Centrifugal

pumps, Condensate pumps, Boiler

Feedwater (6.6KV) etc.,

• Shop Fabricated Tanks -

Underground

Storage tanks – Fuel and other liquids

- fabricated to engineered drawings

• Transformers Step up transformers

• Heat Exchanger Heat exchanger for fuel gas heating

ICN Package Status:- Tier 1: Closed Tier 2: Open

Page 32: INPEX - ICN Gateway

32

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Structural Steel package

Structural steel and pipe racks

including platforms, staircases,

monorails, walkways etc.,

• Civil and Concrete works Foundations, earthwork, concrete

• Temporary site office facilities Provision of crib rooms, ablution

sheds, etc.,

ICN Package Status:- Tier 1: Closed Tier 2: Open

Page 33: INPEX - ICN Gateway

33

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Maintenance facilities Cleaning and servicing of all

temporary construction facilities

• Water Tankers Supply of water tankers for dust

management

• Early civil works Minor earthworks, Construction of

shelters, fencing etc.,

• Skids Ammonia and Phosphate Skids-

fabricated to engineered drawings

ICN Package Status : Tier 1:Closed Tier 2 :Open

Page 34: INPEX - ICN Gateway

34

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Deareators Design and supply of Deareators as

per specifications

• Miscellaneous structural

steel Fabrication of shelters, panels etc.,

• Precast fire walls Supply of precast fire walls for

transformers

• Construction plant and

equipment

Provision of construction plant and

equipment

ICN Package Status:- Tier 1: Open Tier 2: Open

Page 35: INPEX - ICN Gateway

35

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Pipe bulk fittings Supply of couplings, elbows,

reducers, tees, etc.

• Valves manual &

motorised

Supply of manual and/or motorised

valves

• Valves - general low

pressure

Supply of low pressure motorised

valves

• Electrical cables Supply of high/medium and low

voltage and instrument cables

ICN Package Status:- Tier 1: Open Tier 2: Open

Page 36: INPEX - ICN Gateway

36

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Station service

transformers

Supply of Station service

transformers

• Local Electrical Rooms

and Local Instrument

Rooms (approx 11 rooms)

Local Electrical and Instrument

rooms to house switchgear and

instruments

• Motor Control centre. Manufacture and supply of 440 V

motor control centres

• Switchgear

Low and medium voltage

switchgear

ICN Package Status:- Tier 1: Open Tier 2: Open

Page 37: INPEX - ICN Gateway

37

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Variable Frequency drives Supply of medium voltage variable

frequency drives

• Uninterruptible power

systems

Supply of Uninterruptible power

systems including batteries,

chargers etc.,

• Cathode protection system Design and supply of Cathodic

protection system

• Bus Duct Non Segregated Design and supply of Bus ducts

ICN Package Status:- Tier 1: Open Tier 2: Open

Page 38: INPEX - ICN Gateway

38

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Shop Fabrication - Piping Fabrication of piping works

• Instrumentation

Supply of process instrumentation

(field mounted and in line

instrumentation)

• Pipe supports Piping supports, engineered spring

supports, pipe anchors etc

• Precast pits and sumps Supply of precast pits and sumps,

electrical vaults

• Panels Fabrication of panels for sample

analysis as per engineered drawings

ICN Package Status:- Coming shortly…..

Page 39: INPEX - ICN Gateway

39

Combined Cycle Power Plant

LOWER TIER SUBCONTRACT PACKAGES

PACKAGE DESCRIPTION

• Batteries and chargers Supply of batteries and chargers

• Fire Extinguishers Supply of fire extinguishers – plant

wide

• Safety Showers Supply of safety showers.

• Consumables Safety, Electrical and Mechanical

tools

ICN Package Status:- Coming shortly…..

Page 40: INPEX - ICN Gateway

40

Combined Cycle Power Plant

LOWER TIER SUBCONTRACTOR (LTSC) and

SUPPLIER SELECTION PROCESS

• Brief Scope of work for package listed on ICN Gateway

• Prospective LTSC / Suppliers to register interest for

specific packages

• LTSC / Supplier evaluation by ICN and by CH2M HILL-

UGL GE broadly based on :

• Safety, Environmental and Quality capability

evaluation

• Technical capability evaluation

• Previous similar project experience

• Resource capacity

• Extent of value adding in Australia (not necessary in the same order)

Page 41: INPEX - ICN Gateway

41

Combined Cycle Power Plant

LOWER TIER SUBCONTRACTOR (LTSC) and

SUPPLIER SELECTION PROCESS

• Request for expression of interest (REOI) will be

issued to the shortlisted LTSC/ Suppliers.

• REOI will contain confidentiality agreement,

specifications, drawings, draft terms and conditions

and project specific requirement's

• The responses to REOI will be evaluated for work

specific technical capabilities, resource capabilities,

compliance to site requirements, IR compliance and

reference checks

• A final list of shortlisted LTSC/ suppliers will be

generated to which complete tender package enquiry

will be issued

Page 42: INPEX - ICN Gateway

42

Combined Cycle Power Plant

LOWER TIER SUBCONTRACTOR (LTSC) / SUPPLIER SELECTION

PROCESS – Tender

• Tender packages issued to shortlisted LTSC / Suppliers containing:

• Tender invitation letter • Scope of work • Contract conditions including site specific conditions • Technical specifications • Related drawings, maps, plans as required • Construction schedule

• Pre-Bid meetings, if required • CH2M HILL-UGL GE reviews the tender submission • Post bid meetings, if required • Award of Lower Tier Subcontract / Supplier package

Page 43: INPEX - ICN Gateway

43

Combined Cycle Power Plant

LOWER TIER SUBCONTRACTOR (LTSC) / SUPPLIER SELECTION

PROCESS – Key Considerations

• Ability to meet AIP requirements • Local participation commitment • Ability to meet or better HSES requirements

• Ability to meet programme timeline

• Methodology proposal

• Acceptance of Commercial Terms and Conditions including

project specific requirements

• Ability to meet quality and technical / regulation standards

• Price

Page 44: INPEX - ICN Gateway

44

INPEX

Ichthys Project

Onshore LNG Facilities

OPEN DISCUSSION

Ichthys LNG Project

Page 45: INPEX - ICN Gateway

45

Combined Cycle Power Plant

COMBINED CYCLE POWER PLANT– PROJECT SCOPE.