Injection of Biogas Into the Natural Gas Grid in Laholm, Sweden

download Injection of Biogas Into the Natural Gas Grid in Laholm, Sweden

of 4

Transcript of Injection of Biogas Into the Natural Gas Grid in Laholm, Sweden

  • 8/11/2019 Injection of Biogas Into the Natural Gas Grid in Laholm, Sweden

    1/4

    INJECTION OF BIOGAS INTO THE

    NATURAL GAS GRID IN LAHOLM, SWEDENCO-DIGESTION OF MANURE

    AND INDUSTRIAL WASTE

    BIOGAS IN THE SOCIETYInformation from IEA BIOENERGYTASK 37 Energy from biogas andlandfill gas

    SUMMARY

    The Laholm Biogas plant in Sweden was started in1992 with the purpose of reducing eutrophication inthe area. It is a central co-digestion plant that recei-ves manure and different kinds of organic wastefrom the region and turns this into bio-fertilizer andbiogas. The biogas has since 2001 been injected intothe local natural gas distribution grid and now havereplaced around 25% of the regional natural gasconsumption thereby reducing the CO2-emissions by3700 tons/year.

    Biogas from the Laholm plant is upgraded to natural gasquality in a Selexol plant with a capacity of 500 m 3/h

    FACTS

    Treatment of manure and industrial organicwaste

    Total biogas production correspondingto 2,4 Mm3/year CH4

    Biogas injection into the gas gridreplacing 1,8 Mm3 natural gas annually

    IEA Bioenergy Task 37

  • 8/11/2019 Injection of Biogas Into the Natural Gas Grid in Laholm, Sweden

    2/4

    BACKGROUND

    The Laholm biogas plant was built in 1992 as ameasure to reduce the increasing eutrophication ofthe Laholm bay area on the west coast of Sweden.The goals for the project were also to produce bio-gas for the city of Laholm and to produce a certifiedbio-fertiliser for the farmers in the area.

    Laholm was in the 80s a city with increasing pro-

    blems with nitrogen leakage from the agriculturalsector in the bay area. The first indication of eutro-phication was detected in the 70s and in 1980 thefirst indication of oxygen deficit in the sea bottomflora was detected. In 1984 the water in the bay wasdeclared as not suitable for swimming. Measureslike increased seasonal manure storage capacity,banning of spreading of manure outside the springseason etc were not sufficient to reach the desiredreduction of nitrogen supply to the Laholm bay.Different supplementary measures to reduce thenitrogen leakage into the bay were studied and one

    of the most favourable alternatives, that later waschosen for implementation, was to build the Laholmbiogas plant. The plant not only provides the possi-bility to treat the manure but also supplies an incre-ased storage capacity as well as possibilities todistribute bio-fertilizer from one farmer to another.

    PROJECT

    Laholm Biogas AB is a company owned jointly bythe local power utility company Sdra Hallands KraftAB, the local farmers association (VallbergaLantmn) and the City of Laholm. The plant handles28 000 tonnes/year animal manure and 20 000 ton-

    nes/year of other waste materials, mainly waste

    from 15 different food industries (waste fat, vegeta-ble waste, slaughter-house waste, fish waste etc).

    The biogas plant is a conventional stirred tank reac-tor (2 250 m3, residence time 25 30 days, 38C,7,5% DS) that is fed through a pre-tank, a systemof heat exchangers and a batch type pasteurisationunit (1h, 70C) that has replaced the original conti-nuous pasteurisation unit. The plant capacity was in2002 doubled by the erection of another similarproduction line and the plant now has a total capa-city of around 70 000 tonnes/year.

    The annual production of bio fertilizer is around43 000 tonnes. The plant has 2800 m3 bio-fertilizerstorage capacity. The main part of the bio-fertilizeris recycled to farms in the surrounding area, at pre-sent 17 farms.The digestion process converts organic nitrogen inthe industrial wastes to ammonia thereby compen-sating for the increased amounts of nitrogen thatwill be added to the system from the industrialwastes.The gas production from the plant is approximately20 30 GWh/year with methane content of about

    75%. The biogas was until 2000 used in a district

    Table 1: Laholm biogas plant inputs andoutputs (2004)

    Input tonnes/yearManure for pigs and cattle 28,000

    Abattoir waste 10,000Industrial waste 3,000Household waste 1,000Others 6,000Total 48,000

    OutputBio fertilizer to farming 28,000Other 15,000Total 43,000

    BIOGAS IN THE SOCIETYInformation from IEA BIOENERGY TASK 37 Energy from biogas and landfill gas

    All raw material to the digesters is pasteurisedin two batch type pasteurisation units

  • 8/11/2019 Injection of Biogas Into the Natural Gas Grid in Laholm, Sweden

    3/4

    heating plant (DHP) in the vicinity to produce heat

    for a local district heating system, supplying 300apartments. The gas was distributed to the DHP in aplastic pipe system, built according the nationalrequirements for distribution of natural gas at pres-sures up to 4 bars. The DHP used natural gas in situ-ations when the biogas production was insufficient.The main drawback with this system was that appro-ximately 40% of the biogas had to be flared duringperiods when the heat demand was low in thedistrict heating system. An upgrading plant was erec-ted in 2000. The original upgrading plant was capa-ble of upgrading 250 m3/h biogas with a methanecontent of 60 75% to natural gas quality. The upgra-

    ding is performed in three steps. First sulphur isremoved in a Sulfatreat process. The carbon dioxi-de is then removed in Selexol plant and finally theWobbe number of the gas is adjusted to the same asfor natural gas by adding 5 10% propane to the gas.The gas is then introduced into the same gas linethat earlier was used to distribute the raw biogas tothe DHP.The gas installation in theDHP has been revised and anew pipe has been installed,connecting the biogas pipe

    to the local low-pressurenatural gas grid.During winter conditions, themain part of the gas stillgoes to the boiler but whenthe district heating load goesdown, an increasing share ofthe biogas is injected intothe local gas grid and is

    distributed to the city of Laholm. The interconnection

    of the biogas plant with the natural gas grid hasresulted in an increase of biogas sales and biogasdid in 2004 cover approximately 30% of the total gasdemand in Laholm.

    RESULTS

    The Laholm biogas plant has substantially reducedthe regional eurtrophication and nitrogen leakageinto the Laholm bay area.It has also reduced the CO2-emissions by 3700 ton-nes/year by annually replacing 18 000 MWh naturalgas. The biogas is partly used in the city of Laholmfor heating in industries and houses. A part of thebiogas is also used as vehicle fuel in a filling stationlocated on the outskirts of Laholm, thereby reducingthe local emissions of particulates and hydrocarbons.

    CONCLUSIONS

    Co-digestion of animal manure and organic wastehas contributed to solve a substantial environmentalproblem in the Laholm bay area in Sweden. The bio-

    gas installation has also made it possible to reducethe local emissions of CO2 substantially by replacingfossil fuels for heating and in the transport sector.Upgrading of biogas and injection into the naturalgas grid has made it possible to use 100% of thebiogas, thereby avoiding flaring of gas during thesummer period.

    Table 2: Laholm biogas plant energy statistics (2004)

    MWh/yearTotal biogas production 24,000

    Biogas injection into thenatural gas grid 18,000

    BIOGAS IN THE SOCIETYInformation from IEA BIOENERGY TASK 37 Energy from biogas and landfill gas

    The filling station in Laholmsupplies biogas via the naturalgas grid to a growing number of

    light duty vehicles and lorries

  • 8/11/2019 Injection of Biogas Into the Natural Gas Grid in Laholm, Sweden

    4/4

    CONTACTS

    Plant:

    Contractor:

    Bigadan A/SCarsten Buchhave

    Vroldvej 1688660 SkanderborgTel +45 86 57 90 90Fax +45 86 57 90 93e-mail:[email protected]

    Operator:

    Laholm Biogas ABke AronssonBox 63312 21 LaholmTel +46 430 480 00 or

    +46 70 891 56 87Fax +46 430 133 77

    Biogas upgrading plant:

    Contractor:

    Malmberg WaterRune Simonsson

    296 85 husSwedenTel +46 44 23 18 00e-mail: [email protected]

    Operator:

    E.ON GasStaffan Ivarsson205 09 MalmSwedenTel +46 40 24 47 13e-mail: [email protected]