Initial Environmental Examination...Department of Tourism, GoTN 4 [[[[[EXECUTIVE SUMMARY 1. Palani...
Transcript of Initial Environmental Examination...Department of Tourism, GoTN 4 [[[[[EXECUTIVE SUMMARY 1. Palani...
-
Initial Environmental Examination
This report has been submitted to ADB by the Government of Tamil Nadu, Chennai and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB.
This initial environmental examination report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, of by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 40638-033 September 2016
Loan 2833-IND: Infrastructure Development Investment Program for Tourism – Project 2
Submitted by
Department of Tourism and Culture, Government of Tamil Nadu
-
Project: Tourism-Project Management Unit (ADB-IDIPT-TN) – Loan No.2833-IND - Department of Tourism - Infrastructure Development & Investment Programme for Tourism TN Project 2.
Sub: Tranche II program: Revised IEE (Palani)
Ref: ADB E-mail dt. 01 September, 2016
Dear Saurav Majumder,
We refer to the above.
In respect of the Tranche II program sub-projects comprising of 12 Towns with various categories of works made out through 20 Contract Packages commenced during 2013-2014 and now nearing
completion – 2016, the Initial Environmental Examination (IEE) reports furnished to ADB (by PMU) and accordingly the 20 Contracts Awarded with the PCSS Number assigned to the Contracts on
completion of IEEs and SSDDRs. (Similarly the Social Safeguard Due Diligence Report – SSDDR in respect of all the towns furnished and so also the PCSS number assigned for Contracts Award).
Now, all the works in respect of the above are nearing completion in respect of Tranche II program and the Tranche IV program preparations are underway. (Also brought to kind attention is the fact that as
part of review of IEE by ADB during January 2015, it is indicated that the “IEE’s are generally satisfactory” and this could be read with assignment of PCSS Number for Award of Contracts)
In the above context, it is naturally surprising that the issue of IEE is being discussed at this stage (of the project – Tranche II completion) wherein all the works is poised for completion shortly and no cue on this count could be visualized at this stage.
Further, on verification of the records it is found that the Revised IEE (Palani) has been furnished during the
month of January 2015 (copy of the communication made as above is attached for reference).
However, as desired, the Public Consultation is included and IEE furnished (Chapter 6.0 Public Consultation
and Disclosure).
Regarding the O&M of garbage collection, it is to state that this work – Deep Earth Bins has been dropped from
the Tranche II program.
For kind information and needful,
Regards,
PMU
IDIPT-TN
-
TABLE OF CONTENTS
EXECUTIVE SUMMARY………………………………………………… 04
1.0 INTRODUCTION
1.1 Background……………………………………….………………………. 08
1.2 Project Components……………………………………….……………… 08
1.3 Project Cost - Component Wise…………………………….………….… 08
1.4 Operation & Maintenance Cost………………………………………….. 09
1.5 Purpose of the IEE……………………………………………………….. 09
1.6 Environmental Regulatory Compliance………………………………….. 10
1.7 Report Structure ………………………………………………………….. 15
2.0 DESCRIPTION OF PROJECT COMPONENTS
2.1 Description & Need of the project………………………………………. 16
2.2 Proposed Facilities………………………………………………………... 16
2.3 Components of the Subproject…………………………………………… 17
2.4 Sanitray Complex…………………………………………………………. 18
2.5 Deployment Schedule……………………….……………………………. 18
3.0 DESCRIPTION OF THE EXISTING ENVIRONMENT
3.1 Environmental Profile ………………………………………….………… 19
3.1.1 Physical Characteristics……………………….…………….. 19
3.1.2 Accessibility ………………………………………………… 19
3.1.3 Physical & Geographical features ………………………….. 19
3.1.4 Trade and Commerce……………………………………….. 20
3.1.5 Administration……………………………………………… 20
3.1.6 Tourism……………………………………………………… 20
-
TABLE OF CONTENTS
3.1.7 Tourism Places………………………………………………. 21
3.1.8 Socio-Economic Condition…………………………………. 23
3.1.9 Population Details………………………………………….. 23
3.1.10 Existing Infrastructure Facilities……………………………. 24
3.2 Environmental Profile – Site Specific …………………………………… 27
3.2.1 Description of Project………………………………………. 27
3.2.2 Site Details…………………………………………………. 27
4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
4.1 Location Impacts…………………………………………………………. 28
4.2 Design Impacts and Pre-Construction Impacts ………………………….. 29
4.3 Construction Impacts …………………………………………………….. 29
4.4 Operation and Maintenance Impacts …………………………………….. 30
4.5 Cumulative Impact Assessment………………………………………….. 30
4.6 Environment Management Plan ………………………………………….. 33
5.0 ENVIRONMENTAL MANAGEMENT PLAN
5.1 Institutional Arrangements……………………………………………….. 34
5.2 Program Management …………………………………………………… 34
5.2.1 Safeguards Management…………………………………….. . 37
5.3 Environmental Management Plan ………………………………………... 39
5.4 Envrionmental Monitoring Plan…………………………………………… 54
5.5 Capacity Building …………………………………………………………. 58
5.5.1 Target Audience………………………………………………. 58
-
TABLE OF CONTENTS
5.5.2 Envirionmental Awareness Building…………………………. 63
5.6 Environmental Budget ……………………………………………………. 64
5.7 Environmental Monitoring and Reporting ……………………………….. 64
6.0 PUBLIC CONSULTATION AND INFORMATION DISCLOSURE
6.1 Process for Consultation followed ……………………………………… 66
6.2 Plan for Continued Public Participation ………………………………….. 66
6.3 Grievance Redress Mechanism …………………………………………… 67
7.0 FINDINGS & RECOMMENDATIONS …………………………………… 69
8.0 CONCLUSIONS …………………………………………………………….. 70
List of Tables
Table 1 Applicability of Acts and Ruels………………………………… 10
Table 2 Sanitary complex Location……………………………………… 18
Table 3 Population Details & Tourist Inflow……………………………. 23
Table 4 Environmental Management Plan……………………………….. 40
Table 5 Environmental Monitoring Plan………………………………….. 55
Table 6 Traning Modules For Environmental Managment……………….. 59
Table 7 Envrionmental Budget…………………………………………… 64
List of Figures
Figure No. 1 Palani Regional Settings ……………………………………… 19
Figure No. 2 Murugan Temple ……………………………………………… 21
Figure No. 3 Thiru Avinanakudi Temple …………………………………… 21
Figure No. 4 The Kuthiraiyar Dam Falls ……………………………………. 22
-
TABLE OF CONTENTS
Figure No. 5 Bison Wells……………………………………………………. 22
Figure No. 6 View of Existing Toilets………………………………………. 25
Figure No. 7 Existing Garbage Collection Bins…………………………….. 26
Figure No. 8 Existing Street Lighting……………………………………….. 26
List of Appendix
Appendix 1……Contract Clauses To Be Integrated Into Bid Documents…… 71
1.0 Construction of Sanitary Complex………………………………………. 71
2.0 Provision of Deep Earth Bins…………………………………………. 74
3.0 Installation of Signage’s…………………………………………………. 76
4.0 Provision of Street Furniture’s…………………………………………... 77
5.0 General ………………………………………………………………….. 77
Appendix 2…………Rapid Environmental Assessment (REA) Checklist…… 89
Appendix 3…………Deployment Sequence of Key Experts ……………….. 93
Appendix 4…………Environmental Monitoring Format……………………. 95
Appendix 5…………Sample Grievance Registration Form…………………. 97
-
Initial Environmental Examination Construction of sanitary complexes for the floating population, placement of gravity entailed
deep earth bins for garbage collection (2.5 cubic meters), Placement of tourism friendly
uniform signage‘s for convenience of the tourists and Placement of street furniture such as
litter bins & benches for the comforts of travelling tourists in Palani Town, Dindugal District,
Tamilnadu.
Revised Initial Environmental Examination - Palani
July 2014 IND: Infrastructure Development Investment Program for Tourism (IDIPT) — Project 2: Tamil Nadu ADB Loan: 2833 IND Prepared by the Government of Tamil Nadu for the Asian Development Bank
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 3
[[[[[
ABBREVIATIONS
ADB - Asian Development Bank
CPCB - Central Pollution Control Board
CRZ - Coastal Regulation Zone
CPHEEO – Central Public Health and Environmental Engineering Organization, GoI
DOT - Department of Tourism
DSC- Design and Supervision Consultants
EIA - Environmental Impact Assessment
EMP - Environmental Management Plan
IEE - Initial Environmental Examination
PIU- Project Implementation Unit
PMU - Project Management Unit
RCC - Reinforced cement concrete
ROW - Right-of-way
SPS - Safeguard Policy Statement
TA - Technical Assistance
TNPCB – Tamil Nadu Pollution Control Board
TTDC - Tamil Nadu Tourism Development Corporation
WEIGHTS AND MEASURES
ha – Hectare
km – Kilometer
m – Meter
mm – Millimeter This initial environmental examination is a document of the borrower. The views
expressed herein do not necessarily represent those of ADB's Board of Directors,
Management, or staff and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other
Status of any territory or area.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 4
[[[[[
EXECUTIVE SUMMARY
1. Palani is a city and a municipality in the Dindigul district of the South Indian state
of Tamil Nadu, located about 100 km north-west of Madurai city and 100 km
South-east of Coimbatore City and 60 km west of Dindigul. It is the location of the
far-famed temple of the god Kartikeya, resorted to by more than 7 million
devotees each year. As of 2011, the town had a population of 70,467.
2. Description of the Project: The India Infrastructure Development
Investment Program for Tourism (the Investment Program) envisages
environmentally and culturally sustainable and socially inclusive tourism
development in the project states of Himachal Pradesh and Punjab, Tamil Nadu
and Uttarakhand, delivered through a multi-tranche financing facility (MFF)
modality. Project 2 includes the states of Uttarakhand and Tamil Nadu.
3. Description of the Subproject: (i) Provision of sanitary complexes for the
floating population, (ii) Placement of gravity entailed deep earth bins for garbage
collection, (iii) Placement of tourism friendly uniform signages for convenience of
the tourists and (iv) Placement of street furniture such as litter bins and benches
for the comforts of travelling tourists
4. The IEE was based on a careful review of subproject site plans and reports defined
management plans; field visits, and secondary data to characterize the
environment and identify potential impacts; and consultations/ discussions with
stakeholders. An environmental management plan (EMP) outlining the specific
environmental measures to be adhered to during implementation of the subproject
has been prepared. Subprojects will provide needed environmental and tourist
infrastructure to improve the environmental management and quality of the sites
towards preserving their ecological and cultural integrity. The subproject will
conform to all Government regulations, policies, and standards, as well as Asian
Development Bank‘s Safeguard Policy Statement (2009).
5. Categorization of Projects and Activities:
(i) Under the EIA Notification, 2006 promulgated under Environment
(Protection) Act 1986 of the MOEF, Govt of India, all developmental
projects and activities listed under the schedule of the Notification are
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 5
[[[[[
broadly categorized in to two categories - Category A and Category B, based
on the spatial extent of potential impacts on human health and natural & man
made resources.
(ii) All projects or activities under Category ‗A‘ in the Schedule, including
expansion and modernization of existing projects or activities and change in
product mix, shall require prior environmental clearance from the Central
Government in the Ministry of Environment and Forests (MoEF) on the
recommendations of an Expert Appraisal Committee (EAC) to be constituted
by the Central Government for the purposes of this Notification;
(iii) All projects or activities under Category ‗B‘ in the Schedule, including
expansion and modernization of existing projects or activities as specified in
sub paragraph (ii) of paragraph 2, or change in product mix as specified in
sub paragraph (iii) of paragraph 2, but excluding those which fulfill the
General Conditions (GC) stipulated in the Schedule, will require prior
environmental clearance from the State/Union territory Environment Impact
Assessment Authority (SEIAA). The SEIAA shall base its decision on the
recommendations of a State or Union territory level Expert Appraisal
Committee (SEAC) as to be constituted for in this Notification. In the
absence of a duly constituted SEIAA or SEAC, a Category ‗B‘ project shall
be treated as a Category ‗A‘ project;
6. Considering the likely impacts and subproject location which does not pass
through or is located near any national park, wildlife sanctuary, reserved forests,
or any other ecologically sensitive area, it is concluded that no adverse impacts
will result due to the proposed project. Further, no archaeological/protected
monument is located in the vicinity of the project sites. The subproject is not listed
under the Schedule and hence is exempted from environmental clearance of
MOEF. Hence, the subproject is classified as Category-B in compliance to the
ADB Safeguard Policy Statement (2009).
7. The likely environmental impacts of the project are not significant and at Category
B level, as per ADB's Safeguards Policy Statement. The specific measures stated
in the EMP will address all adverse environmental impacts if any due to the
subproject.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 6
[[[[[
8. The selection of components are consistent with the subproject selection criteria
outlined in the Environmental Assessment and Review Framework (EARF) aimed
at enhancing protection of these sites and enhancing their environmental quality.
Subprojects are consistent with defined management plans designed to protect
environmentally sensitive and cultural locations. Management plans guided
subproject design and location; therefore, all proposed facilities in natural areas
are located outside sensitive areas and sited in designated tourist development
zones.
9. Impacts are readily mitigated through careful sitting, specific selection
criteria for procuring contractors with demonstrated experience; execution of
proven mitigation measures during the design; and adoption of good engineering
practices during construction and implementation. A detailed monitoring plan
prepared as part of this IEE will further mitigate negative environmental impacts
during implementation.
10. Potential induced impacts are addressed through the following: (i)
awareness- building of local management plans at proposed sites specifically
addressing the need to regulate tourism related development and planning in the
area through coordination with related Government Departments and local land
use committees; and (ii) project-supported environmental awareness campaigns in
surrounding communities to encourage participatory sustainable development
consistent with eco-tourism principles and in compliance with the state's tourism
policy ecotourism aspects.
11. The Investment Program includes upfront and on-going supervision and training
assistance for environmental monitoring reporting in project management
structures. The effective implementation of the measures proposed will be ensured
through the building up of capacity towards environmental management within the
project management unit (PMU) supplemented with the technical expertise of a
Safeguards Specialist as part of the Design Supervision Consultants (DSC) and
Project Management Consultants (PMC). Further, the environmental monitoring
plans provide adequate opportunities towards course correction to address any
residual impacts during construction or operation stages.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 7
[[[[[
12. The Project 2 includes additional environmental awareness-building to raise
conservation values consistent with management plans and Tamil Nadu‘s
environmental and tourism policies (which emphasize ecotourism) amongst local
communities and local governments in order to ensure future sustainable
development in and around these locations.
13. Anticipated Impacts and Mitigation Measures: All pre-construction,
construction, and operation activities that are likely to cause environmental
impacts were identified, and evaluated to assess their magnitude, duration, and
potential receptors in consultation with the stakeholders. Consultations were held
with the government representatives (Tamilnadu Tourism Department, Town
Panchayat Office, Palani) and local communities. Accordingly, an EMP has been
prepared to mitigate any adverse impacts that may occur during implementation of
the project.
14. Conclusion: In the light of the foregoing, this initial environmental examination
(IEE) ascertains the temporary impacts likely to arise during various stages of
implementation of the project could be eliminated / mitigated through proper
implementation of EMP as outlined in the report. Hence, the subproject is unlikely
to cause any significant environmental impacts. No need for undertaking detailed
EIA is envisaged.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 8
[[[[[
1.0 INTRODUCTION
1.1 Background
1. The proposed Project 2 (the Project) targets enhanced economic growth and
provision of livelihood opportunities for local communities through tourism
infrastructure development with a focus on preservation and development of natural
and cultural heritage and incidental services. The Project supports the states of
Uttarakhand and Tamil Nadu to develop the tourism sector as a key driver for
economic growth.
2. The Project aims to enhance contribution of the tourism industry to sustainable and
inclusive economic growth for each participating state. Increased visits of domestic
and international tourists to tourist destinations within each participating state would
be the outcome of the Project.
1.2 Project Components - Project activities aims at
(i) Construction of sanitary complexes for the floating population,
(ii) Placement of gravity entailed deep earth bins for garbage collection,
(iii) Placement of tourism friendly uniform signages and
(iv) Placement of street furniture
1.3 Project Cost - Component Wise
Sl. No. Description Amount (Rs.
in lakhs)
1 Standard size sanitary complex (4 nos.) 98.62
2 Gravity Entailed Deep Earth Bins for Garbage Collection (20 Nos)
(Rs.1.23 lakh each) 24.62
3 Retro Reflective Road Signages Details. (28 Nos.) 40.58
4 Street furniture (Litter Bins 24 Nos.), Bus Shelters (2 Nos.),
Benches (5 Nos.) 21.61
Total 185.43
Various Designs / Types of Sanitary Complex (S1, S3, S4, S5, S6, S7 & S8) and Deep Earth
Bins has been enclosed in Annexure – A (Common for all locations)
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 9
[[[[[
1.4 Operation & Maintenance Cost
1.5 Purpose of the IEE
1. This Initial Environmental Examination (IEE) assesses a subproject under Project 2
for the state of Tamil Nadu, ‗Construction of sanitary complexes for the floating
population, placement of gravity entailed deep earth bins for garbage collection (2.5
cubic meters), Placement of tourism friendly uniform signages for convenience of the
tourists and Placement of street furniture such as litter bins, and benches for the
comfortable travelling of the tourists in Palani Town, Dindugal District, Tamilnadu.
The IEE was based on a careful review of subproject site plans, detailed design and
reports defined management plans; field visits, and secondary data to characterize the
environment and identify potential impacts; and consultations/discussions with stake
holders.
2. An environmental management plan (EMP) outlining the specific environmental
measures to be adhered to during implementation of the subproject has been prepared.
These EMPs will be appended to the respective contract documents to enable
integration of environmental provisions in the contract. The IEE goes further and
provides sample contract clauses (Appendix 1) to be added to contract documents.
Subproject will provide needed environmental and tourist infrastructure to improve
the environmental management and quality of the sites towards preserving their
ecological and cultural integrity. The subproject will conform to all Government
regulations, policies, and standards, as well as Asian Development Bank‘s Safeguard
Policy Statement (2009).
3. In accordance with ADB‘s Safeguard Policy Statement (2009), the project
belongs to Category ―B‖ as no significant impacts are anticipated.
Sl. No. Description Amount (Rs. in lakhs)
1 Sanitary Complexes 4.93
2 Gravity Entailed Deep Earth Bins for Garbage
Collection 10.00
3 Retro Reflective Road Signages Details. ( 5 % of
estimate cost) 2.03
4 Street furniture 2.37
Total 19.33
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 10
[[[[[
1.6 Environmental Regulatory Compliance
1. The realm of environmental regulations and mandatory requirements for the
proposed subproject is shown in Table 1.The EIA Notification (2006) by the
Government of India Ministry of Environment and Forests (MOEF) specifies the
mandatory environmental clearance requirements. Accordingly, all projects and
activities are broadly categorized in to two categories1 - Category A and
Category B, based on the spatial extent of potential impacts and potential
impacts on human health and natural and man-made resources.
Various policy guidelines, acts and regulations pertaining to sustenance of
environment those applicable to various developmental projects have been presented
in the following section.
Table: 1 Applicability of Acts and Rules
Sl. No Acts / Rules Year Compliance Criteria
1 Environmental (Protection)
Act 1986
This act is applicable all environmental
notifications, rules and schedules are issued under
this act.
2 Environment Impact
Assessment Notification 2006
As per the notification, Projects categorized as A
& B need prior Environmental clearance from the
Central and State Expert Appraisal Committee
respectively. But, this Sub-project does not come
under the purview of the above categories
hence this notification is not applicable.
3 Forest Conservation Act 1927
1980
This Act will be applicable in case the proposed
project road is passing through the Forest Areas
which requires the diversion of forest land to the
non-forestry purposes.
This is not applicable as there is no forest land
involved for the project development.
Permission and clearance for cutting and
transportation of trees will be required from
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 11
[[[[[
Sl. No Acts / Rules Year Compliance Criteria
Divisional Forest Officers, which is not applicable
for this sub-project.
4 Wild Life (Protection) Act 1972
This act will be applicable in case the project road
traverses through wildlife protected areas for
which permission will be sought from National
Board for wildlife.
This is not applicable as there is no wildlife
protected area is involved for the project
development.
5
Coastal Regulation Zone
Notification
1991
2011
Buildings shall be permitted only on the
landward side of the existing road, or on the
landward side of existing authorized structures;
Buildings permitted on the landward side of the
existing and proposed roads or existing
authorized structures shall be subject to the
existing local town and country planning
regulations including the ‗existing‘ norms of
Floor Space Index or Floor Area Ratio, Provided
that no permission for construction of buildings
shall be given on landward side of any new
roads which are constructed on the seaward side
of an existing road
6 Water (Prevention and
Control of Pollution) Act 1974
The Sub-projects require consent to establish from
the State Pollution Control Board if it involves
discharge waste water from labour camps which is
applicable during construction phase of the
project.
But, it is being ensured that no discharges will
be there to any inland water bodies or
sea/ocean, hence this Act will not be applicable.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 12
[[[[[
Sl. No Acts / Rules Year Compliance Criteria
Moreover, the excreta from the toilets will be
collected in septic tanks/soak pits ensuring no
discharges to water bodies.
7 Air (Prevention and Control
of Pollution) Act 1981
The project requires consent to establish from the
State Pollution Control Board if it involves
operation of Hot Mix Plants and Diesel Generator
Sets. This act will be applicable to the project
during construction phase of projects as use of DG
sets is being envisaged.
8 Noise Pollution Regulation
and Control Act 1990
The project requires consent to establish from the
State Pollution Control Board if the noise level
from the construction machinery and the vehicles
are above the standards. This act will apply to the
project especially during the construction phase if
such machineries will be used which is unlikely.
9 Land Acquisition Act 1894
1989
This act will be applicable in case land is being
acquired for the project road.
This act will not be applicable as no land
acquisition is required for the project
development. The project is being developed on
Town Panchayat owned land.
10
Ancient Monuments and
Archaeological Sites and
Remains Act
1958
This act is applicable is case of any chance finds
during construction phase of the project which
may be remains/ monuments which are deemed to
be protected by ASI or the State Directorate of
Archaeology .
This act will not be applicable as no
archeological sites are affected because of the
project development. However, provision has
been made so that chance found ancient
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 13
[[[[[
Sl. No Acts / Rules Year Compliance Criteria
properties are protected.
11
The Hazardous Wastes
(Management, Handling
&Tran boundary
movement) Rules,
1989
2003
2008
These rules will be applicable if contractors
during construction phase will store and handle
hazardous material such HSD and paints etc. But,
the EMP spells that all such materials will be
procured from licensed depots and consumed
immediately so storage is ruled out.
12 The Explosives Act (&
Rules)
1884
1983
This Act specifies regulations regarding the use of
explosives and precautionary measures while
blasting and quarrying. Provisions of these rules
are not applicable to this project as materials
will be procured from 3 rd party licensed
holders.
Further, for sand, soil and stone quarrying, prior permission is to be obtained from the
state authorities for the purpose. However, considering the project profile, it is
preferred to procure materials from the licensed third party owners.
However, considering the kind and quantum of activities, it is envisaged that no borrow
areas and quarry sites will be established as a part of activity / sub project. Raw
materials will be procured from licensed quarry owners. Similarly, no crusher sites will
be opened by the contractor. Also, No borrow area shall be made available by the
Employer for this work. The arrangement for the source of supply of the material for the
civil works shall be the sole responsibility of the Contractor.
But, the contractor might be using DG sets for which the permission will be required
under Air act 1981.
No fuel storage takes place in this project and for construction purposes, the fuel shall
be procured from the existing petrol bunks
For labour accommodation, no labour camp will be established and for accommodation
of labours nearby construction sites, rented houses will be engaged by the contractor.
2. All projects or activities included as Category A in the Schedule, including
expansion and modernization of existing projects or activities and change in product
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 14
[[[[[
mix, will require prior environmental clearance from the Central Government in the
Ministry of Environment and Forests (MOEF) on the recommendations of an Expert
Appraisal Committee (EAC) to be constituted by the Central Government for the
purposes of this notification.
3. All projects or activities included as Category B in the Schedule, including
expansion and modernization of existing projects or activities as specified in sub
paragraph (ii) of paragraph 2, or change in product mix as specified in sub
paragraph (iii) of paragraph 2, but excluding those which fulfill the General
Conditions (GC) stipulated in the Schedule, will require prior environmental
clearance from the State/Union territory Environment Impact Assessment Authority
(SEIAA). The SEIAA will base its decision on the recommendations of a State or
Union territory level Expert Appraisal Committee (SEAC) as to be constituted for
in this notification. In addition, GC of the notification specifies that any project or
activity specified in Category B will be treated as Category A, if located in whole
or in part within 10 km from the boundary of (i) protected Areas notified under the
Wild Life Protection) Act, 1972, (ii) critically polluted areas as notified by the
Central Pollution Control Board from time to time, (iii) notified eco-sensitive areas,
and (iv) inter-State boundaries and international boundaries.
4. Level of environmental assessment required for each category of Project, as per
ADB‘s Safeguard Policy Statement (2009) is as follows:
Category A. Subproject components with potential for significant adverse
environmental impacts. An environmental impact assessment (EIA) is required
to address significant impacts;
Category B. Subproject components judged to have some adverse
environmental impacts, but of lesser degree and/or significance than those for
Category A projects. An initial environmental examination (IEE) is required
to determine whether significant environmental impacts warranting an EIA are
likely. If an EIA is not needed, the IEE is regarded as the final environmental
assessment report.
Category C. Sub-components unlikely to have adverse environmental impacts.
No EIA or IEE is required, although environmental implications are still
reviewed.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 15
[[[[[
5. The above table indicates that the proposed subproject will comply with necessary
government regulations and ADB's Safeguard Policy Statement (2009). ADB's
Safeguard Policy Statement (2009) stipulates addressing environmental concerns, if
any, of a proposed activity in the initial stages of project preparation. For this, the
ADB guidelines categorize the proposed components into categories (A, B or C) to
determine the level of environmental assessment required to address the potential
impacts. The subproject has been categorized as B.
6. Accordingly this IEE is prepared to address the potential impacts, in line with the
recommended IEE content and structure for Category B projects. The IEE was based
mainly on secondary sources of information and field reconnaissance surveys and
stakeholder consultations. Stakeholder consultation was an integral part of the IEE.
An EMP outlining the specific environmental measures to be adhered to during
implementation of the subproject has been prepared.
1.7 Report Structure
This IEE contains eight sections: (i) Introduction; (ii) Description o f Project
Components; (iii) Description of the Existing Environment; (iv) Environmental
Impacts and Mitigation Measures; (v) Environmental Management Plan; (vi) Public
Consultation and Information Disclosure; (vi) Findings and Recommendations; and
(vii) Conclusions.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 16
[[[[[
2.0 DESCRIPTION OF PROJECT COMPONENTS
2.1 Description & Need of the project.
The existing Infrastructure of the town is inadequate to cater to the needs of the
Tourist as well as the resident population. It is therefore necessary to improve the
basic amenities to the public. The identified key interventions and improvements
have a direct bearing on the tourist wellbeing.
The core tourist areas of the Town need to be provided with improved infrastructure
facilities that would in addition to providing a facelift for the town would bring in a
paradigm shift in the approach to provision of Basic infrastructure facilities. Therefore
modern and state of the art facilities are to be provided, which can be replicated in
other parts of the town, and can trigger better management of assets. Each tourist
location has a unique architectural context.
2.2 Proposed Facilities
The existing Infrastructure under the proposed project – 2 is inadequate to cater the
needs of the tourist as well as the resident population. It becomes imperative to
improve the basic amenities to the public. Some of the key interventions and
improvements that have a direct bearing on the tourist wellbeing are discussed
below.
1 Improved Sanitary Facilities: Sanitation facilities form a key element of tourist
convenience at any destination. The present facilities for public toilets/sanitary
complexes are limited and do not address the needs of the large floating
population of pilgrims / tourists. This has led to unhygienic conditions during the
festival seasons with people resorting to open defecation. Overall, sanitary toilet
complexes help in ensuring social dignity and privacy, and maintaining the health
status of the Urban Local Body (ULB). The key considerations for toilets /
sanitary complexes are that they should be aesthetically appealing for use for all
age group without difficulty easy approach and maintenance eco-friendly,
hygienic and cost effective.
2 Improvements to solid waste collection system: In line with the objective of
‗Cleaner and Greener Tourism‘ in Tamil Nadu, it is proposed to provide the
appropriate garbage bins to reduce the littering of garbage on streets as the
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 17
[[[[[
garbage collection in few places of Tamilnadu State is through open garbage bins.
This exposure system leads to bad odour, over flow, spilling, and attack by
rodents, dogs and cats, besides a site of nuisance and major distraction to tourists.
The key considerations for unique design for bins (say Deep Earth Bins and Litter
Bins) are that they are eco-friendly, having sufficiently large capacities to prevent
spillage, provide easy and efficient transfer of garbage to trucks, stray dogs & bird
proof, aesthetically appealing and provides an odour free environment.
3 Provision of signages and good road furniture on important roads connecting the
transport centers like bus-stand and railway stations to the core tourist areas is a
vital infrastructural need in a tourist town. The signages act as guide to the visiting
tourists. Clarity and aesthetic appeal of such signages makes a destination user
friendly and popular. The route signages guide visitors to go in their intended
tourist circuits, and to navigate to their destinations without any interruption. The
basic considerations are to provide uniform retro reflective road signages with
proper visibility, earmarking the street names including way dividing signs,
centers/ mandatory/warning signs, land mark signs and tourist information signs.
as per Indian Road Congress (IRC) / National Building Code (NBC) norms.
4 Improved Street Furniture: Street furniture is a collective term for objects and
pieces of equipment (Benches, and Litter Bins etc) installed on streets and roads
for various purposes. The existing Street furniture is inadequate to cater the
requirements of road users and other public. It is required to install high quality
street furniture on the identified road networks to improve the service levels to the
tourists / & to achieve Cleaner and Greener Tourism in Tamil Nadu.
2.3 Components of the Subproject
The following infrastructure services have been identified in Palani Town with
respective to improved basic urban infrastructure and services at tourist destinations
and attractions as follows:
Provision of sanitary complexes for the floating population
Provision of gravity entailed deep earth bins for garbage collection (2.5 cu.m)
Provision of tourism friendly uniform signage‘s for convenience of the tourists
Provision of street furniture such as litter bins and benches for the comfortable
travelling of the tourists
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 18
[[[[[
2.4 Sanitary Complex Location
Except in the case of sanitary complexes, all other components of the project are along
the Road and do not require any additional land. The roads where the components are
proposed belong to the Palani Town. In the case of sanitary complexes, the following
sites have been identified in the table below:
Table 2
Sl. No. Location Survey
Number
1 New Bus Stand South West Corner 836
2 Municipal Higher Secondary School
West Side Ground
7
3 Arul Jothiveethi 843
4 North Car street 208/1
The above sites are under the full ownership of the Palani Town Panchayat and are
free of all encumbrances. Necessary approval from the Municipal council shall be
taken before implementing the projects. (Various Designs / Types of Sanitary
Complex (S1, S3, S4, S5, S6, S7 & S8) and Deep Earth Bins has been enclosed in
Annexure – A (Common for all locations)
2.5 Deployment Schedule
A total of 18 months construction period is being considered. (Refer Appendix – 3.
However, detailed implementation Schedule depending on contractor’s work
programme considering pilgrimages, climate, tourist’s seasonal timings and other
critical factors would be provided on finalization of the contract)
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 19
[[[[[
3.0 DESCRIPTION OF THE EXISTING ENVIRONMENT
3.1 Environmental Profile – Palani, Tamil Nadu
Palani, in Dindigul District of Tamil Nadu, is a major pilgrim centre of South India
next to Tirupathy and Sabarimalai and gains its importance due to the presence of the
temple of Lord Muruga(Subramania) in the town. Palani is one of the 38 heritage
towns identified by the Government of Tamil Nadu. Out of these, 11 towns are
prioritized for assessing the developmental needs, keeping pilgrims and tourists as the
main beneficiaries. Besides being an important religious centre, the town with a
population of 70456 as per the 2011 Census covering an area of 6.63 sq. km also
functions as taluk headquarters
3.1.1 Physical Characteristics
Location: Palani is located at 10° 26‘ N latitude and 77° 31‘ E longitude, at an
elevation of 324 m above mean sea-level. It is situated between Dindigul and Pollachi
on SH 10. It is 120 KM northwest of Madurai, 54 Km west of Dindugul and 105 Km
south east of Coimbatore.
3.1.2 Accessibility
Palani is located at the junction of three national highways (NH-7, NH- 45, and NH-
209), connecting Madurai, Trichy,
and Coimbatore. NH 209 connects
Palani to Coimbatore and Mysore.
The town is easily accessible by rail
too and is an important station on
Dindigul – Coimbatore section of
Southern Railway Train services are
available to Rameswaram, Madurai,
Coimbatore, Dindigul and Palghat.
The nearest airports are Coimbatore,
Trichy and Madurai which are almost
equidistant from the town.
3.1.3 Physical & Geographical features
Hill ranges of Palani, Idumban hillocks, Vaiyapuri tanks and Sirunayakankulam Tank
are the important physical features of the town. Rising to the height of 137 m the
Palani hill ranges are 324 m above the mean sea level. The hill temple can be reached
Figure No.1: Palani Regional Settings
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 20
[[[[[
on foot by a flight of 697 steps and also by another hill road known as the elephant
hill path. There are several temples, Chatrams, mandapams and lodges situated in and
around the town. Important religious land marks include Prime Hill Temple,
Thiruavinankudi Temple, Periyanayakiamman, Shanmuganadhi group of Temples,
Idumban Temple,Vishnu Temple,and temple of Lord Vinayaga.
Climate
The climate of Palani is generally hot. The maximum temperature ranges from 37°C
during summer to 29.°C during winter season with corresponding average minimum
temperature at 26°C and 21.°C respectively. The hot weather lasts from March to
June. The average annual rainfall is about 760 mm. With predominant winds in
Southwest and Northeast directions, wind speeds in Palani were observed to be about
6.2 Km/hr.
Nature of Soil
The soils of the land are mostly black. It is fertile and good for cultivation.
3.1.4 Trade and Commerce
The rich fertile agricultural and hilly tracts in the Palani region provide a good base
for agricultural activities. Around 15.74% of work force in the town is involved in
agricultural activities. Vegetables like, carrot, cauliflower, potato and beet root are
produced and marketed. Commercial activities are concentrated on Adivaram and
bazaar roads. There are no major industries in Palani other than a few service
industries like rice and oil mills.
3.1.5 Administration:
The Municipal Council headed by the Chairman (Political wing) and the
Commissioner (administrative wing) performs the general administration of the town.
The town was constituted as a Municipality on 1st April 1886, with 33 wards.
3.1.6 Tourism:
Because of its unique natural environment, spiritual and traditional rituals, the Hindu
way of life flows undisturbed and thousands of pilgrims are attracted to Palani town.
Maximum number of tourists visits the temple in the months of March, April, May,
October, November & December. The tourist inflow to Palani is around 40, 00,000
per annum. This town has a floating pilgrim population of about 10000 to 12000
during normal days and about 5 to 10 lakh during special religious festival days. The
major festivals of Palani include Panguni Uthiram,Thaipusam, Skanda Shasti, Agni
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 21
[[[[[
Nakshathram and Thirukkarthigai. The town has 18 lodges with 739 rooms 1248 beds,
34 Choultries with 109 rooms with a capacity of 10100 persons . There are 46
Kalyanamandapams apart from 4 Devasthanam choultries and 73 various caste
madams.
3.1.7 Tourism Places
Palani Town has several places of interest for the tourism.
Palani hills: The Palani hills, is an extension of the western Ghats and encompass an
area of 2068 sq.km with an altitude range of 400-2554 m. The hills are located to the
south of the Palghat gap and forms the important Palani- Anaimalai block . On the
western border of the Palani hills are the Indira Gandhi wildlife sanctuary in Tamil
Nadu and the Chinnar wildlife sanctuary in Kerala. A number of rivers such as
Kudraiyar, Pachiar, Porundlar, Palar, Pulavachiar and Konalar originate from these
hills. The hills include a variety of habitat types with diverse flora and fauna that
include several endemic plant and animal species.
Murugan Temple: The Palani
Murugan Temple is a major attraction
of Palani which can be reached by
climbing around 670 steps to the
hilltop. There is also a haulage winch
or a small rope train along with a rope
car travelling to the top of the hill. The
entire town of Palani is visible from the
top of the hill, which is accessible
from Madurai and Trichy. It is
believed that this temple was built by
Cherman Perumal of the Chera
Dynasty. The temple was later
expanded between the 8th and the 13th
centuries by the Cholas and Pandyas,
who added new mandapams and
gopurams at the site. Some of the sculptures at the temple were added by the Nayaka
kings who ruled the region for a brief
Figure No.2: Murugan Temple
Figure No.3: Thiru Avinanakudi Temple
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 22
[[[[[
period.
Thiru Avinanakudi Temple: The temple is also called as the Kulanthai
Velayuthaswamy Temple, one of the oldest temples located at the foot of the Palani
Hills. Usually before going to the main hill temple, devotees visit this temple. The
temple is considered to be the third abode of the Lord Murugan who is depicted here
as a child sitting on a peacock.
Ayakudi: Ayakudi is situated near Palani in Dindugal District, which is surrounded by
the lush green forest. The town is famous for guava cultivation and guava markets. It
is also known for sugar cane, cotton, paddy, lime and mango cultivation that are
exported to various countries. Some of the important temples in the town are
Kaliamman Temple, Alagu Nachiamman Temple, Vinayagar Temple, Ponnalagu
Amman Temple, Eswaran Temple, Karuppannaswamy Temple and Mariamman
Temple. Cholisvara Swami Temple is the prime landmark in Ayakudi. Ayakudi is
connected by a road to Palani and Dindugal and also well connected through railways.
The Mariamman Temple: The Mariamman Temple is devoted to Goddess
Mariamman, who is believed to be an incarnation of Goddess Parvati. The temple is
being visited by many travelers, especially on
Fridays, when the main idol is covered with a
golden sheath.
The Kuthiraiyar Dam Falls: It is situated close
to Pappampatti in Palani and can be reached with
the help of local villagers. From Kumbai visitors
can trek for a kilometer to reach the waterfalls
situated at the back of the dam.
Bison Wells: It is well known for its wildlife and
beautiful vegetation. Wildlife commonly seen in
the area includes bison, birds, elephants, tigers,
monkeys and deer. Bison Wells got its name
from the many bisons that come to drink from
natural wells. The location is known as a great
base in India for those interested in exploring the
region. Naturalists, hikers, trekkers and bird watchers are all drawn to the Palani Hills
and Bison Wells is a fabulous place for such tourists to stay while they are in the area.
Figure No.4: The Kuthiraiyar Dam Falls
Figure No.5: Bison Wells
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 23
[[[[[
3.1.8 Socio-Economic Condition
The working population constitutes 31.25% of the total population and majority of
them are engaged in tertiary activities i.e. 66% in tourism and trade related activities.
Secondary Sector is the second important activity and nearly 24% of the total workers
are engaged in business and related allied activities. Only 10% of the total workers are
engaged in Primary Sector especially in tea plantations and agriculture activities.
3.1.9 Population Details
The population of the town is 70456 as per the 2011 census. Population of the town
has increased from 68907 in 1991, indicating a growth rate of 2.43 %. The gross
density of the town works out to persons 10140 per sq.km. In addition, the floating
pilgrim population is around 40, 00,000 per annum. The decadal growth rate of the
population is given in table 3.
Table - 3 - Population
Sl. No Year Population Growth rate
1 1971 49575 24.46 %
2 1981 64438 29.98 %
3 1991 68747 6.69 %
4 2001 67231 (-) 2.21 %
5 2011 70456 4.80 %
Floating Population: The tourist inflow to Palani is around 40, 00,000 per annum.
This town has a floating pilgrim population of about 10000 to 12000 during normal
days and about 5 to10 lakhs during special religious festival days.
Table – 3 - Tourist Inflow
Sl.no Year Domestic Foreign Total
1 2008 5329276 14219 5343495
2 2009 6949399 11595 6960994
3 2010 7262310 17117 7279427
4 2011 5688338 70735 5761084
5 2012 7568697 75744 7646453
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 24
[[[[[
3.1.10 Existing Infrastructure Facilities
Water Supply:
Water requirement for Palani town is drawn from two sources at present, Kodaikanal
old scheme – a surface water source situated about 15 Km from the town and another
from IV Improvement water Supply scheme from Palar Dam at 7 Km from the town.
Old Scheme – Kodaikanal: 5.64 MLD of water is being drawn from the old scheme.
Besides there are three open wells and, from these wells pumping is effected to
maintain the level in the SS tank since the inflow at SS tank depends upon rainfall in
Kodaikanal.
IV Improvement Scheme: Water level in the Palar Dam is sufficient to cater to the
need of 3.34 MLD of water, which is being pumped daily.In total 9 MLD of water is
being drawn from both the schemes. There is no water supply problem at present.
Distribution System:
Old Scheme – 53.29 Km( Kodaikanal Scheme)
New Scheme – 18.69 Km ( Palar Scheme)
Total – 71.98 Km
Salient Features of the System:
Sources: Kodaikanal and Palar Dam
No. Of Zones: 4
No. Of OHTs: 6
OHTs Capacity: 43.30 LL
Daily Water Supply: 9 MLD
Per Capita Supply: 110 lpcd
Bore well with Power Pumps: 222 No
Public Fountains: 289 No
Bore well with Power Pumps: 49 (Includes 33 mini water tanks)
HSCs: 6148 No
Frequency of Supply: 2 hrs on alternative days
Sewerage & Sanitation:
Palani town is provided with UGD system covering 15% of the total town area.
Sewer mains have been laid for a length of about 6.45 Km covering 13 wards having
738 HSCs. In the uncovered area the sewage, sullage and rainwater is let out in to
open pucca drains covering about 92% of the total road length. The discharge from
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 25
[[[[[
open drains mixed with sewage is reaching Vaiyapuri tank and Sirunaicken Kanmai
causing pollution of above lakes. In Palani, nearly 15,574 total assessments are having
individual private sanitation facilities with septic tank as a major mode of sewage
disposal. In addition, the town has 19 public convenience units with 6 Nos. of ISP
toilet and 9 Nos. of VAMBAY toilets. Further, Pay and Use toilets have been
constructed for the local and commuting population at many places
Storm Drainage: Existing Status
Open Drains – Pucca – 52.60 Km (91.74%)
Open Drains – Kutcha – 4.73 Km (8.26%)
Closed Drains – Nil
Total – 57.33 Km
As regards storm water drainage and rain water harvesting, up gradation of the
existing drains and additional new drains are proposed by the Municipality at a cost of
Rs. 112 Lakhs. In respect of sanitation, the Municipality proposes to construct 13 new
sanitary complexes and improve existing toilets to serve the locals and the floating
population at a cost of Rs 100 Lakhs.
Solid Waste Management:
The total solid waste generation in Palani Town per day is about 40 MT. The garbage
collected is dumped at the existing compost yard near Periyappa Nagar within the
municipal limits. For day to day operation purposes, the town is divided into six
Sanitary Divisions covering all the 33 Municipal Wards. The waste is collected from
door to door by push carts from individual houses and dumped in 45 collection points,
Figure No.6: View of Existing Toilets
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 26
[[[[[
from where the municipal lorries collect the garbage daily to the compost yard.
Waste generated from the vegetable and fish market located on Gandhi Road in the
town constitute the major proportion of the city‘s waste.
Figure 6 - Existing Garbage Collection Bins
As can be seen from the above, most of the garbage collection in the town is through
open garbage bins. This exposure causes smell, over flow, spilling, and attack by
rodents dogs and cats etc. Besides it is always a site of nuisance and major distraction
to visiting tourists
Roads:
The Major roads within the town vested with the Highways Department are Udumalai
road, Dharmapuram road, Dindugal road and Kodaikanal road. Apart from these State
Highways, the Municipality maintains 43.738 Km of local roads. About 85% of the
total length of the Municipal roads is bituminized or concretized.
Street Lighting
Palani town presently has 2921 street light fixtures comprising of 2492 tube lights,
233 Nos. of 250 Watts sodium vapor lamps, 100 Nos. of 100 Watts Mercury vapor
lamps and one High-mast Light.
Figure 7 – Existing Street Lighting
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 27
[[[[[
Education and Health:
There are 35 schools in the town, of which the Municipality maintains only 4
elementary schools.
Industries:
Textile mills, manufacture of panchamirtham, production of vibuthi( sacred ash) ,
making of steel furniture at Govt. pressed metal factory, manufacture of fruit juices
and of stone grinders.
3.2 Environmental Profile – Site Specific
3.2.1 Description of Project:
Construction of sanitary complexes for the floating population, placement of gravity
entailed deep earth bins for garbage collection (2.5 cubic meters), Placement of
tourism friendly uniform signages for convenience of the tourists and Placement of
street furniture such as litter bins, for the comforts of travelling tourists in Palani
Town, Dindugal District, Tamil Nadu.
3.2.2 Site Details:
Sl.no Description Yes / No
1. Protected area No
2. Archaeological site No
3. Forest area No
4. CRZ area No
Notes: Protected Area includes wildlife sanctuary, bird sanctuary, or national park; CRZ =
Coastal Regulation Zone
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 28
[[[[[
4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
The assessment for each of the subprojects has been carried out for potential impacts
during the following stages of the project planning and implementation:
Location impacts. Impacts associated with site selection, including impacts on
environment and resettlement or livelihood related impacts on communities;
Design impacts. Impacts arising from project design, including the technology used,
scale of operations, discharge standards, etc.;
Construction impacts. Impacts resulting from construction activities including site
clearance, earthworks, civil works, etc.; and
O&M impacts. Impacts associated with the operation and maintenance of the
infrastructure built in the project.
The ADB Rapid Environmental Assessment Checklist for Urban Development was
used during preparation of this IEE to screen the subproject for environmental impacts
and categorization of the project (Appendix 2).
4.1 Location Impacts
1) Land Acquisition and Resettlement. The proposed subproject locations are within
the lands available with the government. There are no impacts envisaged on land
acquisition or resettlement due to the proposed subproject components.
2) Site Selection. The locations considered for the subproject are within the areas
designated for tourism support infrastructure development as part of
developing Tamil Nadu‘s conservation, heritage, natural and cultural attractions, and
are outside areas demarcated for habitat protection and conservation. The proposed
infrastructures will not impact any environmentally-sensitive or protected areas
rather it will enhance the tourism experience and livelihood of the local people in
total. The public, Govt & local bodies are very much keen into taking up these
proposed works. The entire town and adjoining areas are under Town Panchayat
control who has proposed this project. This proposal suggests areas which are
uncovered with the needed basic amenities. Further, there is no possibility of
presence of non-titled street vendors and no displacement or shifting of non-titled
street vendors would be required in these sites that have been identified for sub
projects.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 29
[[[[[
3) Priority is to locate construction work camps, stockpile areas, storage areas, and
disposal areas near the subproject sites. However, if it is deemed necessary to locate
elsewhere, sites to be considered will not promote instability and result in destruction
of property, vegetation, irrigation, and drinking water supply systems. Residential
areas will not be considered to protect the human environment (i.e., to curb accident
risks, health risks due to air and water pollution and dust, and noise, and to prevent
social conflicts, shortages of amenities, and crime).
4.2 Design Impacts and Pre-Construction Impacts
1) Impacts arising from the inappropriate designs of proposed facilities would in general
include the inadequate collection and conveyance system for solid waste,
construction materials sourcing and c o n s t r u c t i o n techniques to be adopted, site
selection, etc. The results of interventions are unobtrusive and will be integral part of
the overall ambience so as to avoid impacts on the livelihood of the site.
A structural design has been worked out in such a manner that exposed steel and
concrete structures are avoided.
2) All component designs have been worked out to minimize any impacts on the
adjoining properties, and considering the need of the facilities for the floating
population. Given that the there is a need for disposal of construction wastes, the
contractors will be required to consult with the Project Implementation Unit (PIU),
Panchayat offices, and Tamil Nadu Pollution Control Board for safe disposal sites.
3) Telephone lines, electric poles and wires, water and drainage lines within the
existing right-of- way (ROW) may be damaged. To mitigate the adverse impacts due
to relocation of the utilities, the Design and Supervision Consultants (DSC) and PIU
will:
(i) Identify and include locations and operators of these utilities in the detailed
design documents to prevent unnecessary disruption of services during
construction phase; and
(ii) Require construction contractors to prepare a contingency plan to include actions
to be done in case of unintentional interruption of services
4.3 Construction Impacts
1) The impacts are generic to the construction activities in all subproject locations.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 30
[[[[[
All construction activities to be undertaken at the site will be approved by competent
authority before start of any such activity in the vicinity of the site so that the
history and sanctity as well as the usability of the site by the local people and
projected number of tourists are not hampered. Hence, the EMP emphasizes on the
construction impacts and necessary mitigation measures to be strictly followed by the
contractor and supervised by the DSC. Key impacts during construction, are
envisaged on the following aspects: (i) drainage, (ii) slope cutting and slope Stability
(iii) water bodies and drainage courses (iv) dust generation, air and noise from
construction activities, (v) handling of construction materials at site, (vi) adoption of
safety measures during construction; and (vii) community health and safety.
4.4 Operation and Maintenance Impacts
1) The impacts pertaining to waste collection, cleaning of septic tanks and soakpits,
maintaining hygienic conditions of the toilet facilities, will be addressed through an
assessment of the Operation and Management of the proposed facilities in frequent
intervals/regular inspection. Planning of the extent of facilities and infrastructure in
line with the Maintenance plan as well as the involvement of the local communities
in the management facilities created in the project will address the operation stage
impacts.
2) The proposed facilities will greatly improve the environmental quality in and
around the destinations, and also enhance the livelihood of the local
population. While the enhanced tourist generation due to these improvements may
not be significant, the facilities will enhance the site experience of the
tourist/pilgrim. The project will facilitate environmental improvements through the
provision of training to operators for all sanitation and solid waste facilities
provided by the Project, in order to sustain any improvements made.
4.5 Cumulative Impact Assessment
1) The cumulative impact assessment (CIA) examined the interaction between the
subproject‘s residual effects (i.e., those effects that remain after mitigation measures
have been applied) and those associated with other past, existing and reasonably
foreseeable future projects or activities.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 31
[[[[[
2) Two boundaries, spatial and temporal, were used. Spatial boundary refers to the area
immediately surrounding the subproject location; while the temporal area considers
the potential cumulative effects associated with subproject construction, and
operation and maintenance, and those associated with other past, existing and
reasonably foreseeable projects in the vicinity of the subproject. For the subproject,
the spatial boundary is the area of the subprojects including existing ROWs. The
temporal boundary can be considered as the districts where the subproject sites are
located.
3) The subproject‘s potential cumulative effects were considered with respect to valued
components (VCs), identified in the IEE as air quality, noise, surface water quality,
geophysical (hydrogeological), traffic management, social-economic and socio-
community, and human health. The cumulative impacts were assessed in four areas:
Of any potential residual project effects that may occur incrementally
over time;
Consideration of other known relevant projects or activities within the specified
study area boundaries, even if not directly related to the subproject;
Potential overlapping impacts that may occur due to other developments, even if
not directly related to the proposed project; and
Future developments that is reasonably foreseeable and sufficiently certain to
proceed.
4) Air Quality: The air environment of the sub project areas is generally found to be
good and is free from industries polluting the atmospheric environment. The
ambient air quality in the sub project areas is generally found to be within
acceptable standards. Impact on air quality (if any) during construction stage are due
to operation of various construction equipments and transport vehicles.
Consequently, although emissions of common air contaminants (CAC) and fugitive
dust may be elevated in proximity to the active work sites, this impact will be of
short-term and localized to the immediate vicinity of the project site.
Greenhouse Gas (GHG) emissions may increase as a result of project activities (i.e.,
vehicle and equipment operation, concrete production, disposal of excavated
material, land filling of residual wastes). Given the subproject‘s relatively minor
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 32
[[[[[
contribution to CAC and GHG emissions during construction, the overall
significance rating of both these potential residual effects is considered to be
negligible during construction.
5) Noise Quality: Most part of the sub project area is in quite environment. Noise
intensive industrial operations are not observed along the project influence area.
Noise levels in the immediate proximity of most work sites are expected to increase
during construction. The duration of this exposure will be relatively brief. This
exposure represents temporary, localized, adverse residual effect of low to moderate
significance for affected receptors. While building damage due to ground vibrations
is unlikely, there may annoyance to spatially located receptors during construction.
Noise levels associated with the subproject operations will be largely imperceptible
as civil works will be confined in relatively small sites within the district proper.
6) Since the subproject will be built in existing infrastructures, it will not conflict with
existing or planned land use. However, traffic management concerns will occur
spatially during construction. Site-specific mitigation measures will be
implemented during construction to address temporary disruptions to land use,
limitations on access to roads, sidewalk closures, traffic delays and detours, parking
modifications, and increased volumes of construction–related traffic. There should
be improved traffic movement along the access routes once construction is
completed. During operations of the improved infrastructures and services, added
residential developments, commercial and business facilities and increased densities
are expected to develop and enhance the subproject area. This can be considered a
long-term cumulative benefit of the subproject. (Refer Environmental Management
plan for Sub project Specific impacts and their mitigation measures)
7) No adverse residual effects to human health will occur as a result of subproject
construction or operation. While exposure to elevated noise levels and fugitive dust
and CAC emissions will occur in proximity to subproject work sites during
construction, due to their short term, localized nature, these effects are expected to be
minor and insignificant with no measurable effects on human health. The subproject
operations will benefit the general public by contributing to the long-term
improvement of tourism in Tamil Nadu and livelihood opportunities to the local
people.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 33
[[[[[
4.6 Environment Management Plan
i. The specific measures stated in the EMP will address all adverse environmental
impacts due to the subproject. A detailed monitoring plan prepared as part of this IEE
will ensure negative environmental impacts during implementation are mitigated.
During the Construction stage, the IEE/EMP will be further updated and stand-alone
EMPs will be prepared. EMPs will be appended to the respective contract documents
to enable integration of environmental provisions in the contract.
ii. The project sub-components proposed has been classified as Category B, as it is likely
to have minimal or no adverse environmental impacts and therefore does not require
conducting EIA or IEE. However, an Environmental Management Plan for the
interventions is prepared as described in Chapter 5.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 34
[[[[[
5.0 ENVIRONMENTAL MANAGEMENT PLAN
5.1 Institutional Arrangements
1. The Government of Tamil Nadu through Department of Tourism and Culture
(DOT&C), is the Executing Agency (EA). The EA (i) assumes overall responsibility
for the execution of the Project and reporting; (ii) engage adequate permanent or fixed-
term staff to implement the Project; (iii) setup a state-level project management unit
(PMU) and project implementation units (PIU); (iv) provide overall strategic guidance
on technical supervision and project execution; and (v) ensure overall compliance with
the loan covenants.
2. The implementing agency (IA) is the Tamil Nadu Department of Tourism (DoT). The
IA‘s responsibilities include (i) project planning and budgeting; (ii) day-to-day
assistance, supervision and guidance for the project implementation units and their
consultants; (iii) review subprojects for due diligence requirements and approve
subproject proposals; (iv) bidding, evaluation and contract award; (v) managing and
disbursing funds; (vi) review compliance with loan covenants, contract specifications,
work plans and quality control; and (vii) consolidate and submit progress reports,
finance and accounting / audit reports, and matters requiring higher-level decision to
state-level empowered committee (SLEC) and ADB.
5.2 Program Management
1) State Level steering committee chaired by Minister of Tourism and Chief Secretary
2) State Level Empowered Committees. An SLEC has been established in Tamil
Nadu, chaired by s t a t e Chief Secretary, with Principal Secretary/Secretary of the
Department of Tourism as member secretary and comprised of secretaries from relevant
line departments. The SLEC have been empowered to take all decisions on behalf of
the State and will (i) act as a policy making body, (ii) provide overall advice and
guidance to the State‘s executing agency and PMU, and (iii) accord all approvals under
the Project.
3) Project Management unit: DoT has established a PMU, headed by a full-time Program
Director (PD), and consisting of personnel drawn from relevant line Departments and
market. The PMU is the nodal agency for overall management of all program activities
and will be responsible for: (i) project planning and budgeting; (ii) providing day-to-day
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 35
[[[[[
assistance, supervision and guidance for the PIUs and their consultants; (iii) reviewing
subprojects to satisfy ADB‘s due diligence requirements and approving subproject
proposals submitted by PIU and line departments; (iv) bidding, evaluation and contract
award; (v) managing and disbursing funds; (vi) reviewing compliance with loan
covenants, contract specifications, work plans and quality control; (vii) consolidating and
submitting progress reports, finance and accounting/audit reports, and matters requiring
higher-level decision, to the SLEC and ADB. The PMU will be supported by a team of
consultants.
4) State Level steering committee chaired by Minister of Tourism and Chief Secretary
The members of the Tamil Nadu SLEC will be: Chief Secretary, (chair); Principal
Secretary/Secretary, Tourism and Culture; Secretary, Department of Finance; Secretary,
Planning and Special Initiatives; Secretary, Public Works Department; Secretary,
Highways and Minor Ports; Secretary Forests and Environment; Secretary, Housing and
Urban Development; Secretary, Municipal Administration, Water and Sanitation;
Secretary, Rural Development; Secretary Power; Secretary, Revenue Department;
Secretary, Department of Health and family Welfare; Secretary, Agriculture; Secretary,
Hindu Religious and Charitable Endowments (HR&CE), Commissioner, Department of
Archaeology; Secretary, Department of Transport; and Commissioner, Department of
Tourism.
5) Project Implementation Unit. The IA will have PIUs for the implementation and
monitoring of subprojects, comprising of personnel drawn from relevant line
Departments and outside of Government (market) and each headed by a Project
Manager. The PIUs will be responsible for: (i) prioritizing and preparing subproject
proposals; (ii) providing day-to- day assistance, supervision and guidance to the design
and supervision consultants; (iii) conducting detailed assessments and surveys including
public consultation and input from stakeholders; (iv) preparing detailed designs,
specifications, schedule of quantity, bidding documents, and related documentation; (v)
implementing civil works and related activities; (vi) reporting to PMU; (vii) preparing
regular progress reports for the SLEC, the executing agency and ADB through PMU;
and (viii) supervising construction, conducting quality control, approving progress
payments to contractors; and (ix) maintaining records and accounts on an up-to-date
basis and making these available to ADB, its missions, or auditors for inspection.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 36
[[[[[
6) Project Management Consultants. The Project Management Consultants (PMC)
will be engaged to provide support to the PMU in overall planning, risk
management, implementation, monitoring and evaluation of projects under the
Investment Program. The PMC will also assist the PMU and PIUs in meeting the
relevant requirements of ADB, Government of Tamil Nadu, and Government of India
for project implementation. The PMC will report to and work under the overall guidance
of the PMU. The scope of services of the PMCs will include but not necessarily be
limited to: (i) planning, reporting, and communication; (ii) establishment of
procedures and systems; (iii) review and preparation of plans, manuals and reports; (iv)
overall Investment Program management, monitoring and implementation of PPMS; and
(v) social, environmental, archaeological, occupational health and safety, community
participation and gender action compliance monitoring.
7) Design and Supervision Consultants. The DSCs will be engaged to provide all
necessary support to and coordination with the EA, IAs, PMU and any other consultants
engaged by the authorities to achieve the desired outcomes of the Investment Program.
The DSCs will report to and work under the overall guidance of the PIUs. The scope of
services of the DSCs will include but not necessarily be limited to: (i) surveys,
verification of feasibility studies and base maps; (ii) project planning and management
support to the PIU; (iii) finalization of design criteria, preparation of manuals, guidelines
and systems; (iv) preparation of detailed design and bid documents; (v) construction
management and contract administration; (vi) environmental, social, archaeological,
cultural heritage, community participation and gender action compliance
monitoring; and (vii) capacity building of the service providers for operational
sustainability.
The Implementation Strategy have been prepared with reference to available data and
however it would be revised depending on the contractors work programme and also since
the volume and nature of balance project work under Tranche - 1 and the new projects to be
identified under Tranche -2 is unknown and have not been finalized, the above mentioned
schedule is tentative and shall be revised at the later stage based on the award of contract or
commencement of work.
-
Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)
IEE - Palani
Department of Tourism, GoTN 37
[[[[[
5.2.1 Safeguards Management
1) An Environmental Staff is to be deputized to the PMU, and responsible
for implementations of the environmental safeguard provisions.
2) Within the PMC team, a Safeguards Specialist provides overall direction
for management of environmental and social issues, and provides technical support to
the PMU including implementation of the environmental requirements, according to
ADB requirements, and assists in monitoring impacts and mitigation measures
associated with subprojects. The responsibilities of t he PMC Safeguards Specialist
– Environment include but not limited to:
Review the updated IEE prepared by the DSCs for Project 2 after the
detailed designs, and guide the DSCs/PIUs to address observations from
ADB on the IEEs/EMPs;
Ensure that the project design and specification adequately ref