INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input....

92
Pg. 1 de 92 Ingeteam Energy S.A. Rev._A AAR2000IKI02 1/2010 INGECON HYBRID MS Ingecon Hybrid MS Installation Manual

Transcript of INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input....

Page 1: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 1 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

Ingeteam Energy S.A.

Rev

._A

AA

R20

00IK

I02

1/2010

INGECON HYBRID MS

Ingecon Hybrid MS Installation Manual

Page 2: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 2 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Ingecon® Hybrid MS Installation Manual

1. INTRODUCTION .....................................................................................................51.1 Document purpose .......................................................................................................................51.2 Stand-alone systems .....................................................................................................................51.3 INGECON® HYBRID MS - General description .........................................................................51.4 Operating principle ........................................................................................................................71.5 Location ........................................................................................................................................81.6 Operating, storage and transport conditions .............................................................................. 111.7 Safety instructions ......................................................................................................................131.8 Type of work performed .............................................................................................................15

2. BATTERY CHARGER MODULE ...........................................................................17

2.1 Details of the module...................................................................................................................17

2.2 TechnicalSpecifications ..............................................................................................................17

3. INVERTER MODULE ............................................................................................183.1 Details of the module ..................................................................................................................183.2 TechnicalSpecifications ..............................................................................................................18

4. PHOTOVOLTAIC MODULE ...................................................................................184.1 Details of the module ..................................................................................................................184.2 TechnicalSpecifications ..............................................................................................................19

5. WIND TURBINE MODULE ....................................................................................195.1 Details of the module ..................................................................................................................19

5.2 TechnicalSpecifications ..............................................................................................................20

6. DUMPLOAD ...........................................................................................................206.1 Key characteristics ......................................................................................................................20

7. GENSET ................................................................................................................207.1 Key characteristics ......................................................................................................................20

indexPage

Note: In accordance with our product continuous impro-vement policy, Ingeteam Energy S.A., reserves the right to modify this document without prior notice.

Page 3: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 3 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

8. OTHER DEVICES ..................................................................................................218.1 Genset kit ....................................................................................................................................218.2 Protection devices .......................................................................................................................22

8.3 Galvanic isolation transformer module ....................................................................................... 22

9. INSTALLATION ......................................................................................................239.1 Module assembly ........................................................................................................................239.2 Electrical connection ...................................................................................................................249.3 Internal connection for the secondary modules ..........................................................................29

9.3.1 Location of the components inside the modules .....................................................................299.3.2 Wiring of the electronics block.................................................................................................309.3.3 Wiring in the main charger module..........................................................................................319.3.4 Wiring in a secondary charger module ....................................................................................319.3.5 Wiring in the main inverter module ..........................................................................................329.3.6 Wiring in a secondary inverter module ....................................................................................33

9.4 Connection of the battery bank ...................................................................................................349.5 Connection of the AC line ............................................................................................................359.6 PV array connection ....................................................................................................................359.7 Connection of the wind turbines. Dump load ..............................................................................379.8 Connection of the Genset ...........................................................................................................399.9 Earth connections .......................................................................................................................42

10. USER INTERFACE ................................................................................................4410.1 Keypads Leds .............................................................................................................................4410.2 Menu structure ............................................................................................................................4510.3 Main menu ..................................................................................................................................4510.4 Monitoring ...................................................................................................................................4610.5 Extras ..........................................................................................................................................5410.6 Stop reasons ...............................................................................................................................5510.7 Configuration ...............................................................................................................................5610.8 Settings .......................................................................................................................................6410.9 System data ................................................................................................................................6410.10 Summary table ............................................................................................................................66

Page 4: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 4 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

11. COMMISSIONING .................................................................................................6911.1 Equipment inspection ..................................................................................................................6911.2 Power-up .....................................................................................................................................70

12. PREVENTIVE MAINTENANCE .............................................................................71

12.1 Maintenance tasks ................................................................................................................71

13. TROUBLESHOOTING ...........................................................................................7413.1 LED Indicators .............................................................................................................................74

13.1.1 Green LED ............................................................................................................................7513.1.2 Yellow LED ............................................................................................................................7513.1.3 Red LED ................................................................................................................................75

14. ANNEXES ..............................................................................................................7814.1 REPLACEMENT OF THE <<ELECTRONICS BLOCK>> .........................................................7814.2 BATTERY OPERATION .............................................................................................................8014.3 GENSET.....................................................................................................................................8214.4 VOLTAGE GENERATION. LOAD CONNECTION .....................................................................88

Page 5: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 5 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

1 INTRODUCTION

1.1 Document purposeThis manual will help you understand the operation of stand-alone generation systems and will provide you with the necessary guidelines for correct installation, adequate use and good maintenance of the equipment forming part of a stand-alone system.

It is extremely important that you read and understand all the information and instructions contained in this manual before commencing the equipment installation work.

1.2 Stand-alone systemsA system based on the Ingecon® Hybrid MS is intended to provide those locations that have no access to the conventional electricity grid with electric power of similar characteristics to that provided by the grid. However, a stand-alone system will never have the energy capacity of a conventional distribution network, and this factor should be taken into account when designing the installation.

This equipment is ideal for replacing a diesel generator based system with one which combines a diesel generator with renewable energy sources.

This type of installation is made up of the following equipment:

- Renewable energy generating sources (PV panels, wind turbines…)

- Backup energy generators (genset)

- Accumulation equipment (batteries)

- Associated power converters

Astudyofthesite,renewableresourcesandchargeprofilesshouldfirstbeconductedinorder to determine the most adequate equipment for each particular installation.

1.3 INGECON® HYBRID MS - General descriptionThe Ingecon® Hybrid MS units have been designed for the off-grid generation of pure sine wave three phase electrical power based on renewable energy sources, using batteries as a means of accumulation. Furthermore, the Ingecon® Hybrid MS units can be connected to a backup generator for a guaranteed electricity supply at all times.

Page 6: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 6 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

This is a modular system that can be adapted to suit the requirements of each parti-cular installation. The installer is therefore responsible for optimizing the design and configuration.

A number of power converter modules are available and can be combined to suit the specificinstallationrequirements.Eachmoduleismadeupofan«electronicsblock»,and the switchgear and power devices required by each converter.

An installation shall at least have a battery charger module and an inverter module. A maximum of four modules of each type can be installed.

Battery charger moduleThis module is responsible for managing the battery bank charging and discharging. An installation must have at least one main battery charger module and, optionally, up to three secondary modules.

The main battery charger module is essential for any installation, as it controls communications with the other modules, supervises the status of all inputs and manages the permissions to operate. This module also includes the user interface display.

The main module is also equipped with a 15kW MPPT PV input.

Inverter moduleThis module generates a pure sine wave three phase voltage, with constant amplitude and frequency, adapting the output power to that demanded by the installation loads.

When the backup generator is operating and connected to the loads, this module canoperateasarectifiertorechargethebatteries.

The installation power can be increased by connecting up to a total of four inverter modules in parallel.

Photovoltaic moduleThis module manages three 15 kW PV inputs, with an independent MPPT control. Theseinputscanbeconfiguredtooperateinparallel,therebyobtainingasingleinput with a maximum power of 45 kW.

To increase the power of the installation, up to four modules can be mounted in the same system

Wind turbine moduleA converter to manage three 15 kW wind power inputs with an independent MPPTcontrol.Theseinputscanbeconfiguredtooperateinparallelwithtwooptions:

- The three inputs in parallel forming a single input with a maximum power of 45 kW

- Inputs 1 and 2 in parallel forming a 30 kW input and a 3rd independent input of 15 kW.

In addition, the wind power module can incorporate a dump load system.

Page 7: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 7 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

To increase the installation power, up to four modules can be mounted in the same system.

The installation shall be completed with other external devices, dimensioned in accordancewiththeoverallpowerandconfigurationandwhichcanoptionallybe supplied by INGETEAM ENERGY S.A.

Examples include:

-Breakerforthebatteryfield

- Kit for the backup genset

- AC protections for persons and loads connected.

- Galvanic isolation transformer

- Battery temperature sensor (a product manufactured by INGETEAM ENERGY S.A.)

- Backup generator power meter (a product manufactured by INGETEAM ENERGY S.A.)

1.4 Operating principleThe Ingecon® Hybrid MS is basically designed to generate AC voltage from renewable energy sources. The battery charge / discharge status and the backup generator con-nection / disconnection will depend on the energy generated by the renewable sources and the demand made by the installation loads.

Priority shall always be given to energy extraction from the renewable sources through the use of maximum power point tracking methods.

When the energy available is greater than demand, the surplus energy shall be stored inthebatteries.Oncethebatterybankisfullycharged,itshallbemaintainedinfloatstatus and the power generated shall be adjusted to meet the demand.

On the contrary, when the connected load requires more energy than that generated by the renewable power source, then the system shall absorb the required energy from the battery bank. The time during which this status can be maintained shall depend on the battery charge status and capacity. For this reason, when dimensioning the battery bank capacity, account should be taken of the required autonomy of the installation during those periods in which the renewable sources are not operating.

If the installation needs to provide an uninterrupted power supply, then a backup power source will be necessary, such as a diesel generator. Furthermore, this backup power source is recommended in order to guarantee the supply at times of high consumption (this facility requires a wattmeter).

The connection of the backup generator can occur for different reasons, all of which are configurable(chapter14.3):

·Timesetting.Aperiodoftimefordailyconnectionscanbeconfigured.

· Battery low charge status, to prevent the battery bank from over-discharging.

· High consumption (the INGETEAM ENERGY S.A. wattmeter is required).

· Battery equalisation. To ensure that the equalisation cycle is completed correctly.

· Manually, by a user-given order.

Page 8: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 8 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

When the backup generator is connected, this directly feeds the loads. The Ingecon® Hybrid MS behaves like yet another load, rectifying the voltage in order to charge the batteries.Thebatterychargepowerfromthebackupgeneratorisconfigurablefromzeroup to the Ingecon® Hybrid MS rated power.

We would recommend having a backup generator power that is double that of the equi-pment power in order to guarantee that consumption is supplied and the batteries are charged at the same time.

With the backup generator connected, all the energy available from the renewable sources shall be used to charge the batteries.

1.5 LocationTheIngecon®HybridMSunitsneedtobelocatedinenvironmentswithsomespecificcharacteristics.

This section provides guidelines on selecting and correctly adapting the equipment to a suitable site.

Environment

Locate the units in a place which is easily accessible for installation and maintenan-ce work, with room to operate the keyboard and to read the front LED indicators.

It is forbidden to leave any object on the equipment.

Air outlets and those parts of the cabinet close to the outlets can reach tempera-tures of 85 ºC. Do not place any heat-sensitive material in the vicinity.

Avoid corrosive environments.

The room or enclosure in which the battery bank is installed must be compliant with the safety regulations in force in the particular region or country. For Europe, the corresponding standard is EN 50272-2 and its adaptations to each member state.

The enclosure in which the Ingecon® Hybrid MS unit is installed must incorporate a safety system to restrict access solely to authorised personnel.

IP Rating

The Ingecon® Hybrid MS units have a protection rating against external agents of IP20.

IP20 means that the equipment is protected against the ingress of foreign bodies andagainstfreeaccesstodangerousparts,asdefinedforthisprotectionratingin the IEC60529 standard

.Therefore:

The Ingecon® Hybrid MS must be installed in a covered enclosure.The equipment environment must always be dry and free from dust.It is not suitable for outdoor installation.

Page 9: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 9 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

Ambient temperature

The Ingecon® Hybrid MS units are designed to operate between –10ºC and +40ºC.

Atmospheric conditions

The surrounding air must be clean and the relative humidity must not exceed 50% at more than 40 ºC. Higher percentages of relative humidity, up to 95%, are tolerable at temperature below 30 ºC.

Account should be taken of the fact that, occasionally, moderate condensation may occur as a result of temperature variations. For this reason, in addition to the unit’s own protection system, the equipment should also be monitored when operating at sites which may not come within the atmospheric conditions described above.

Contamination rating

The units have been designed for a grade 3 contamination rating.

Appropriate measures should be taken to locate the equipment in an environment with dust-free, good quality air.

Noise contamination

When operating, the Ingecon® Hybrid MS makes a slight buzzing noise.

Do not locate the units in an occupied room or on lightweight supports which amplify this buzzing noise. The mounting surface must be firm and adequate for the weight of the equipment.

Mounting

The modules have been designed to be stack mounted up to 4 modules high, in stacks of either the same or different types of modules. To facilitate interconnection, modules of the same type should be stacked together.

The mechanical and electrical connections are explained in detail in chapter 9.

Themodulesmustbeinstalledasdeliveredfromthefactory.Anymodificationintheir structure will void the warranty and could also create a risk of malfunction.

Ventilation

For ventilation reasons, there has to be at least 800 mm clearance around each stack. Installer should notice that it is a minimun clearance that we recommend to increase for ease of maintenance.

Air should be allowed to circulate freely in order to ventilate the equipment.

Eachelectronicsblockisequippedwithafanwhichcouldrequireaflowof354m3/h.

Eachmoduleisequippedwithtwofanswhichrequireanairflowof320m3/h.

Page 10: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 10 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

It is forbidden to leave objects on the equipment.

Locate the equipment in a particle free environment, to prevent the ingress of particles through the vents.

Facilitate the circulation of incoming air through the grids located on the left side and rear and the circulation of the outgoing air through the grids located on the right side.

Ventilation of the modules

Page 11: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 11 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

1.6 Operating, storage and transport conditions

Failure to comply with the instructions given in this section could cause damage to the equipment.

INGETEAM ENERGY S.A. assumes no liability whatsoever for any damage derived from non-compliance with these instructions.

Reception of the Ingecon® Hybrid MS Reception

On reception, please check the terms indicated in the Delivery Note, sign the box signature of goods consignee and return the signed copy to the consignor’s address.

Do not unpack the unit until just before it is to be installed. Keep the unit UPRIGHT at all times.

Identification

Eachmoduleisclearlyidentifiedbyitsserialnumber.AllcommunicationswithINGETEAMENERGY S.A., must indicate this number.

Serial Number

Avda. Ciudad de la Innovación, 1331621 Sarriguren (Navarra) [email protected]

Tel 948 288000 Fax 948 288001

Ingecon®HYBRID MS IP 20 2009

Po: 30 KVA

Uo: 3 X 400 Vac Fac: 50 Hz

S/N HMS100401310

INVERTER

Page 12: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 12 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Damage during transport

Should the equipment sustain damage during transport:

1) Do not install it.

2) Immediately notify your distributor of this situation within a 5 day period as of the equipment reception date.

Shoulditbefinallynecessarytoreturntheequipmenttothemanufacturer,theoriginalpackaging should be used.

Handling and unpackingIt is extremely important to correctly handle the equipment in order to ensure that:

•Thepackagingremainsintact,enablingtheequipmenttobemaintainedinoptimumcondition during shipment and until it is unpacked.

•Theequipment isnotknockedand/ordropped,whichcouldaffectthemechanicalcharacteristics such as incorrect door closure, loss of IP rating, etc.

•Everyeffortismadetoavoidvibrations,whichcouldleadtosubsequentmalfunctioning.

Should any anomaly be observed, contact INGETEAM ENERGY S.A immediately.

Packaging disposal

All packaging can be given to an authorised non-hazardous waste manager.

In any event, each part of the packaging shall be deposited at the corresponding collection point.

Moving the equipmentCorrect equipment transport and storageare the first steps required for correct useand operation. Taking into account the indications given in the section above, and as a preventive measure, INGETEAM ENERGY S.A. would recommend working with hauliers specialising in the transport of special and / or fragile equipment.

During transport and storage the equipment should be protected from mechanical impact, vibration, water projection (rain) and any other product or situation which could damage or alter its performance.

INGETEAM ENERGY S.A. assumes no liability whatsoever for a failure to comply with these instructions, which could void the product warranty.

Moving the equipment using a loading vehicle

During transport, the Ingecon® Hybrid MS should be kept upright and correctly anchored for its size and weight in order to prevent it from overturning or being knocked.

Moving the equipment using a fork-lift truck

At least the following points should be observed:

1) Centre the packed equipment over the forks.

2) Try to ensure that the equipment is positioned as close as possible to the connection between the fork and the carriage.

3) Ensure that the forks are perfectly level, in order to prevent the equipment from being tipped off.

4) In any event, observe the instructions provided in the fork-lift truck manual.

Page 13: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 13 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

StorageIf the equipment is not to be installed immediately after reception, the following points should be taken into account in order to prevent deterioration:

•Itmustbestoredupright

•Keeptheequipmentfreefromdirt(dust,shavings,grease,etc)andawayfromrodents.

•Avoidcontactwithwaterprojections,weldingsparks,etc.

•Covertheequipmentwithabreathable,protectivematerialinordertoavoidcondensationcaused by ambient humidity.

•Theequipmentstoredat themanufacturingplantandthatstoredonthecustomer’spremises must be maintained within the ambient conditions indicated in section 1.5.

•Itisextremelyimportanttoprotecttheequipmentfromcontactwithchemicals,whichcould cause corrosion, and also from saline environments.

ConservationIn order to conserve the equipment correctly, the original packing should not be removed until just before the equipment is to be installed.

In the event of prolonged storage, we would recommend storing in a dry place, avoiding abrupt temperature changes as far as possible.

Damaged packaging (cuts, holes etc) will mean that the equipment cannot be maintained in optimum conditions before installation.

INGETEAM ENERGY S.A. assumes no liability if this condition is not complied with.

1.7 Safety instructionsThis section contains the safety instructions to be followed when installing, operating and accessing the equipment.

Failuretocomplywiththese«SafetyInstructions»maycausedamagetotheequipment or result in physical injury or even death.

Pleasereadthese«SafetyInstructions»carefullybeforeoperatingtheequipment.

SymbolsSafety warnings provide information on conditions that could cause damage to the equipment and / or serious bodily injury or even death. Alongside the warning sign, instructions are given with regard to how to avoid such hazards and protect persons and equipment alike.

These symbols are listed below, with an explanation of their meaning.

Danger, high voltage. Stay away!

Warning of high voltage: warning that high voltage is present in the equipment, which could cause physical injury or even death and / or damage to the equipment.

General warning: regarding conditions that could cause physical injury and / or damage to the equipment.

Caution, hot surface: warning regarding hot parts that could cause serious burns.

Page 14: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 14 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Allwork-specificsafetywarningsandnotesareincludedintherelevantchapterandarerepeated and completed at the critical points in that chapter.

Please read this information carefully. It has been written with your personal safety in mind, whilst ensuring the maximum service life for the equipment and for any devices connected to it.

General safety conditions

Installation, commissioning, inspection and maintenance operations may only be performed by suitably qualified personnel, trained to work with electrical equipment (hereinafter qualified personnel). You are reminded that it is mandatory to comply with Royal Decree R.D. 614/2001 for electrical work.

The opening of the various compartment enclosures in no way implies that no voltage is present inside. Access is therefore restricted to qualified personnel, observing the operating safety conditions established in this document.

The set of conditions detailed below should be considered to be the minimum requirements. It is always advisable to cut off the general power supply. The installation could be faulty, causing undesirable voltage returns. There is an electrical discharge hazard.

In addition to the safety measures indicated in this manual, any general measures that may be applicable should also be observed (installation-specific, country-specific, etc).

The electrical installation must not entail fire or explosion hazards. Workers must be properly protected against the risk of accidents caused by direct or indirect contact. The electrical installation and the safety devices must take account of the voltage, all external conditioning factors and the competence of those people having access to the installation parts.

All work equipment must adequately protect exposed workers against the risk of direct or indirect contact with electricity. At any event, the work equipment electrical parts must comply with the provisions of the corresponding specific regulations.

For work with live parts, all workers performing work outdoors shall stop work in the event of storms, heavy rainfall, strong winds, snow or any other unfavourable environmental condition that hinders visibility or the handling of tools. Work on indoor installations directly connected to overhead electricity lines must be interrupted in the event of a storm.

Page 15: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 15 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

INGETEAM ENERGY S.A. assumes no liability for any damage caused by the improper use of the equipment. Any work on any of this equipment involving a change in the original electrical layout, must first be proposed to INGETEAM ENERGY S.A. This proposed new layout must then be studied and authorised by INGETEAM ENERGY S.A..

The necessary safety measures must be in place to prevent unauthorised personnel from getting near to or handling the equipment. Warning signs to indicate the presence of personnel at work:

Adequate lockout mechanisms or mechanical locking by padlock & key, for circuit breakers.

These instructions must be easily accessible, close to the equipment and within easy reach of all users.

Before installing and commissioning the equipment, please read these safety instructions and warnings carefully and all the warning signs placed on the equipment. Ensure that all warning signs are perfectly legible and that any damaged or missing signs are replaced.

1.8 Type of work to be performedPreventive maintenance tasks performed on the electric panels can involve Inspection, Operational or Manipulation tasks, depending on each particular case.

It is strictly forbidden to access the enclosure through a cubicle other than the one described in this manual. Before opening any of the enclosure covers (side, rear, top) theexteriorpowersupplytothepanelmustfirstbecutoff.

Inspection tasksDefinition: Tasks involving the opening of the enclosure to make visual inspections.

Operational tasksDefinition: Tasks involving loading software, checking and regulating the heating / ventilation systems. Voltage checks at safe measurement points.

Equipment preventive maintenance tasks not including the electric panels, performed from the man - machine interface.

Manipulation tasksDefinition: Tasks involving the assembly and / or replacement of parts and components, in addition to the adjustment of the settings on the electric panel.

Page 16: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 16 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

BEFORE COMMENCING MANIPULATION WORK, A CHECK SHOULD ALWAYS BE MADE TO ENSURE THAT NO VOLTAGE IS PRESENT

IT IS MANDATORY TO COMPLY WITH THE FOLLOWING 5 GOLDEN RULES

1. Disconnect

Isolate the installation from all power sources. Capacitors or other devices which hold voltage after disconnection must be discharged using adequate devices.

2. Prevent any possible reconnection of the power.

The switching devices used to disconnect the installation should be blocked to guard against any possible reconnection before the work is complete.

3. Check that no voltage is present

Check all the live parts of the electrical installation in the work area and surrounding area, in order to ensure that no voltage is present.

4. Ground and short circuit the equipment

The parts of the installation where the work is to be performed must be earthed and short-circuited for high voltage installations and, for low voltage installations, when there is a risk that the parts might accidentally become live due to induction or for some other reason.

5. Demarcate and place warning signs in the work area

Personal Protection Equipment (PPE)Inspection:

It is mandatory to wear a helmet compliant with EN 397:1995 and safety footwear compliant with EN 345-1:1992. It is also mandatory to wear safety gloves, of the mechanical type, for voltage free work.

Operational tasks:

It is mandatory to wear a helmet compliant with EN 397:1995 and safety footwear compliant with EN 345-1:1992. It is also mandatory to wear safety gloves, of the mechanical type, for voltage free work.

It is also mandatory to wear dielectric gloves that are compliant with EN-60903-1992 and a safety face mask that provides protection against short electric arcs and is compliant with EN 166-2002 and UNE EN 170-2003, in tasks involving adjusting the heating / ventilation systems, when connecting and disconnecting the voltage and when performing checks at safe measurement points.

Manipulation:

It is mandatory to wear a helmet compliant with EN 397:1995 and safety footwear compliant with EN 345-1:1992.

It is also mandatory to wear dielectric gloves that are compliant with EN-60903-1992 and a safety face mask that provides protection against short electric arcs and is compliant with EN 166-2002 and UNE EN 170-2003, when connecting and disconnecting the voltage and when accessing cubicles with live parts.

Page 17: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 17 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

2 BATTERY CHARGER MODULE

2.1 Details of the moduleThis module controls the charging and discharging of the battery bank, protecting it from overcharges and from deep discharges.

A distinction is made between the main battery charger module and the secondary battery charger module (up to three per installation).

The main battery charger module is essential in any installation, given the fact that it controls communications with the other modules, supervises the status of all the inputs and manages the permissions to operate.

The main battery charger module is also equipped with a 15 kW photovoltaic input with MPPTandtheuserinterfacedisplay,whichservestomodifytheconfigurationandmonitorthe key data for the installation.

Based on the characteristics provided by the battery manufacturer, all the battery parameterscanbeconfiguredtooptimisethemulti-stagechargingprocess(Chapter14.2).

2.2 Technical SpecificationsBattery charger

• Maximum power: 30 kW

• Voltage range: 240 to 500 Vdc

• Maximum current: 100 Adc

Photovoltaic input (only in main module)

• Maximum power: 15 kW

• Voltage range: 150 to 700 Vdc

• Maximum current: 30 Adc

The battery charger voltage range refers to absolute values. Account should be taken of the fact that the battery charge voltage is higher than its rated voltage. The battery bank should be dimensioned to ensure that all the charge voltages required are within the range indicated.

The charge voltage depends on the type of battery and shall be established by each manufacturer. However, as a general rule, the process to charge a lead-acid battery bank with a rated voltage of 450 V requires a voltage that is considerably more than 500 V which would be exceeding the upper range limit.

The charger module limits the power to 30 kW and the battery current to 100 A. This implies that, for example, with a battery voltage of 330 V, the maximum battery current would be 90 A (limit of 30 kW); but also that with a voltage of 240 V the maximum power would be 24 kW, as the current is limited to 100 A.

When modules are connected in parallel, the power and current limits are multiplied by the number of modules, however the voltage range does not vary.

Page 18: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 18 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

3 INVERTER MODULE

3.1 Module detailsThe inverter module is a two-way converter that will function as:

• An inverter, generating a pure sinewave three phase voltagewith a constantamplitude and frequency, when operating without the backup generator.

• Asarectifier,chargingthebatteries,whenthebackupgeneratorisfunctioningandpowering the loads.

• Assupportforthebackupgenerator,ifthisisoperating,thebatteriesarechargedand renewable energy is available.

There is a distinction between the main inverter module (one per installation) and the secondary inverter module (up to three per installation). In general, each inverter module is shipped from factory as a main inverter module. On installation, the internal cabling must be modified to allow it to operate as a secondary inverter module. (See the sectionon«Internalconnexioninsecondarymodules»).

3.2 Technical specifications• Rated power: 30 kVA (10kVA per phase)

• Voltage: 380 to 430 Vac (three phases plus neutral).

• Frequency: 50-60 Hz

• THD <4

• Cos(φ):-1to1

• AC output short-circuitable

• Accessible isolated neutral. If the installation requires the neutral to be earthed, a galvanic isolation transformer module should be installed (Chapter 8.3)

• Supports charge imbalances. The maximum power per phase is 10kVA.

4 PHOTOVOLTAIC MODULE

4.1 Module detailsThe module comprises three 15 kW PV inputs.

Each PV input incorporates an algorithm for tracking the maximum power (MPPT) and another to adjust the power to demand. The algorithm in use will depend on the system conditions at each particular time.

It is important to correctly dimension the PV arrays in order to avoid limiting the input power by exceeding the maximum current.

Thethreeinputscanbeconfiguredas:

- three independent inputs

- Three inputs in parallel, performing like a single input with a maximum power of 45 kW (90 Adc).

Page 19: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 19 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

4.2 Technical Specifications Specificationsforeachinput

• Maximun power: 15 kW

• Voltage range: 150 a 700 Vdc

• Maximun current: 30 Adc

5 WIND TURBINE MODULE

5.1 Module detailsThe module comprises three independent wind power inputs.

Each input incorporates an algorithm for tracking the maximum power (MPPT) and another to adjust the power to the demand. The algorithm in use will depend on the system conditions at each particular time.

It is important to select the right wind turbines in order to avoid limiting the input power by exceeding the maximum current.

Thethreeinputscanbeconfiguresas:

- Three separate inputs

- Inputs 1 and 2 in parallel (30kW) and a third independent input (15kW)

- Three inputs in parallel, performing like a single input with a maximum power of 45 kW.

Photovoltaic input configuration

Page 20: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 20 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

5.2 Technical SpecificationsSpecificationsforeachinput

• Maximun power: 15 kW

• Voltage range: 70 to 495 Vac

• Maximun current: 24 Adc

6 DUMP LOAD

6.1 Key characteristicsThe dump load system is a wind power module accessory designed to brake the wind turbines in order to adjust the power generated to that demanded by the installation, maintaining control over the same.

It comprises three resistor units, one for each wind power input of 15kW.

7 GENSET

7.1 Key characteristicsThe backup generator is responsible for creating the three phase voltage electrical network, whenever it is operating and coupled to the Ingecon® Hybrid MS. This implies thatitshouldhavesufficientpowercapacitytoindependentlymeetthetotaldemandofthe loads.

Wind Power input configuration

Page 21: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 21 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

Furthermore, it is advisable to dimension the generator so that it can be used to charge the batteries at the same time. We would therefore recommend having a backup generator with a rated power that is double that of the rated power of the installation.

For reasons of maintenance and guarantee of supply, an installation can be equipped with up to four generator units connected in parallel. In this case, switching between the generators or, where applicable, synchronisation, is not controlled by the Ingecon® HybridMSandthesysteminstallerisresponsibleforselectingthespecificcontrollertoperform this task. (Chapter 14.3).

Ingecon® Hybrid MS modules don’t include the necessary elements for connection of back up generator. Genset kit has to be acquired.

8 OTHER DEVICES

8.1 Genset kit The kit for the backup genset comprises the following:

- Contactor for the connection of the backup generator

- Thermal magnetic breaker to protect the generator

- Terminal connection strip

- Energy meter (wattmeter)

- Current measurement transformers

- Thermal magnetic breaker for the AC output of the Ingecon Hybrid MS (in Kits for backup gensets of 120kVA, 180kVA or 240kVA).

There are four models, depending on the backup generator rated power:

1- Kit for a 60kVA genset

2- Kit for a 120kVA genset

3- Kit for a 180kVA genset

4- Kit for a 240kVA genset

Note: We would recommend a backup genset power rating that is double that of the inverter modules installed. If the backup genset power rating is greater than the recommended one, this should be taken into account in the kit design.

Page 22: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 22 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

8.2 Protection devicesSome electrical protection devices are included as standard in the Ingecon® Hybrid MS system modules The installation can then be completed with other protection devices:

• Battery bank breaker (mandatory). A breaker to disconnect the battery bank must be installed. It must be dimensioned in accordance with the number of battery charger modules.

• Differential protection. Consult the legal requirements in force in the region in question.

• AC voltage surge arrestor (recommended).

• General thermal magnetic breaker (recommended). In an installation with more than one inverter module, we would recommend including a general breaker to provide a single disconnection point for the AC output. The backup genset kit (chapter 8.1) includes this breaker.

8.3 Galvanic isolation transformer moduleFor safety reasons, it is always recommendable to install a galvanic isolation transformer, which, depending on the legislation in force, may be mandatory.

Should it be necessary to earth the installation neutral, the galvanic isolation transformer is essential for the correct operation of the Ingecon® Hybrid MS. The primary neutral (Ingecon output) must never be earthed.

The galvanic isolation transformer module comprises three single phase transformers with a ratio of 270:270 and a rated power based on the number of inverter modules.

Ingecon® Hybrid MS output

Transformer

Genset kit

AC load

Page 23: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 23 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

9 INSTALLATIONPlease read these instructions carefully before installing the Ingecon® Hybrid MS.

The modules are heavy and cannot be handled by one person. To avoid personal injury, use the appropriate transport and lifting equipment.

Use the connections available. Do not drill or modify the module ports.

The Ingecon® Hybrid MS modules are designed to be stacked up to 4 modules high.

We would recommend stacking modules of the same type together to facilitate interconnection.

The bottom modules shall be equipped with a base.

Once the installation work has been completed, mount the bus bar cover. Inadvertent contact with any of the bus bars represents a serious risk of electrocution, even if the equipment is not operating

.

9.1 Module assemblyThe vertically stacked modules are assembled with the aid of threaded rods. Once the lower module has been positioned, four rods are inserted (see photo).

Module assembly

Page 24: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 24 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Then the next module shall be coupled to it. The two rods at the rear are used as a guide. The two front rods serve as an earth between the modules (chapter 9.9) and shall be firmlysecuredwiththeaidofanut.

9.2 Electrical connection The electrical connections between the modules are made at the rear

• Power connections: By connecting the copper bars.

The number of bars to be connected depends on the module in question.

Thefirst threebarsconstitute thepowerconnectionbetween themodulesandmustbe interconnected one by one (vertically), connecting all the modules in the installation

To connect bars in the same stack, the connecting bars supplied with the equipment shall be used.

Bars from different stacks shall be connected by external cabling.

We recommend wires that can support 200 A.

Securing the modules

Connection of a Battery charger module with an Inverter Module

Page 25: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 25 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

If there are various battery charger modules in an installation, then the remaining bars must also be interconnected one by one (vertically).

Connection of two Battery Charger Modules

If there are various inverter modules in an installation, then the remaining bars must also be interconnected one by one.

Connection of two Inverter Modules

Page 26: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 26 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

• Connectionsofspecificsignals: by external cabling, plug-in connectors.

These connections must only be made between battery charger modules or between inverter modules.

If there is more than one battery charger module in an installation, one (the one including the display, module 1) shall be the main module. The others shall be secondary modules. Inordertooperateinparallel,specificcablingisrequired.SignalsJPandJRmustbeconnected as shown in the wiring table attached here to.

For inverter modules, main module will be determined by its wiring. See section 9.3 «Internalconnectionforthesecondarymodules».

Module connectors

JM1 JM2

JA1 JA2

JP1

JP2

JR1

JR2

JC1

JC2

Connect with:

Module 2 (Secondary)

Module 3 (Secondary)

Module 4 (Secondary)

JP1 JP2 JR1 JR2 JP1 JP2 JR1 JR2 JP1 JP2 JR1 JR2

Mod

ule

to c

onne

ct Mod

ule

1(M

ain)

JP1 XJP2JR1 XJR2

Mod

ule

2(S

econ

dary

) JP1 XJP2JR1 XJR2

Mod

ule

3(S

econ

dary

) JP1 XJP2JR1 XJR2

Page 27: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 27 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

• Connections of general signals: By external cabling, plug-in connectors.

Thefollowingsignalsshouldbeconnectedinseries:JC,JMandJAforall the modules in the installation.

Regardless of the module type, all the modules in the same stack must be connected in accordance with the attached connections table.

Likewise, regardless of the type of module, the stacks must be connected according to the connections table. For this, only one module from each stack should be interconnected.

*See Connections Table and proposed examples.

An installation can have up to 16 modules, which are named Module A, Module B .... Module P, to facilitate the connection work.

Given below are two examples of the connection of various modules, showing two possible solutions for the installation of six modules.

Ascanbeseen,thefinalconnectiondiagramwilldependonthedistributionselectedfor each installation.

Connect withModule B Module C Module D ... Module P

JC1 JC2 JM1 JM2 JA1 JA2 JC1 JC2 JM1 JM2 JA1 JA2 JC1 JC2 JM1 JM2 JA1 JA2 JC1 JC2 JM1 JM2 JA1 JA2

Mod

ule

to c

onne

ct

Mod

ule

A

JC1 XJC2JM1 XJM2JA1 XJA2

Mod

ule

B

JC1 XJC2JM1 XJM2JA1 XJA2

Mod

ule

C

JC1 XJC2JM1 XJM2JA1 XJA2

...M

odul

e O

JC1 XJC2JM1 XJM2JA1 XJA2

Page 28: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 28 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

1

2

3

Connections JC, JR, JP, JA, JM.

ConnectionsJC, JA, JM.

Connection of JM (pines 3 y 4).

Connection of signals between modules

Page 29: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 29 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

9.3 Internal connections for the secondary modulesIn an installation with more than one charger module, one will be the main module and the others will be secondary modules.

In an installation with more than one inverter module, one will be the main module and the others will be secondary modules.

Some of the differences between a main module and secondary module are based on the internalconnectionofthereferencesignals(JR1andJR2cables)andthepermissionssignals(JPcable).

Withregardtothechargermodule,themainmoduleisclearlyidentifiedbythefactthatit is the one containing the display. The others are secondary modules. The internal cablingofJR1,JR2andJPisadaptedduringthemanufacturingprocessand,therefore,nomodificationisrequiredforstart-up.

However, this section should be taken into account when replacing the electronics block. All electronics blocks supplied as spares are manufactured to be directly mounted in themainchargermodule.Specifiedbelowaretheconnectionsformountinginamainmodule and also those for mounting in a secondary module.

With regard to the inverter module, the main module differs from the secondary one in thecablingofJR1,JR2,JP.Generallyspeaking,allinvertermodulesaremanufacturedasmaininvertermodules,and,therefore,needtobemodifiediftheyaretofunctionasa secondary inverter module.

Note: Exceptionally, a main inverter module can be converted to a secondary module at the factory. The installer must examine the internal cabling to identify each module.

Warning: Two Main Inverter Modules cannot coexist in the same installation.

This section should be taken into account during commissioning or after extending the installation and in any work to replace the inverter module or electronics block. The differences between the connections for the main inverter module and secondary module are explained below.

All electronics blocks supplied as spares are manufactured to be directly mounted in a maininvertermodule.Specifiedbelowaretheconnectionsformountinginamainmoduleand also those for mounting in a secondary module.

9.3.1 Location of the components inside the modulesThefollowingcomponentsfirstneedtobelocated.

Reference signals board:

J2J3

Page 30: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 30 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Measurements board:

9.3.2 Wiring of the electronics blockThe electronic blocks supplied as spares for the charger module and for the inverter module are all manufactured to be mounted in a main module.

Acablecanbelocated,connectingJ1(measurementsboard)withJ3(referencesboard).

J7J1

J5

J1

J3

Page 31: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 31 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

9.3.3 Wiring in the main charger moduleThe main charger module must be cabled as follows:

-CableconnectingJ1(measurementsboard)withJ3(referencesboard).

-JR1Cable(comingfromtheenclosurerear)connectedtoJ5(measurementsboard).

-JR2Cablecomingfromtheenclosurerear,shallremainunconnected.

-JPCable(comingfromtheenclosurerear)connectedtoJ7(measurementsboard)andtoJ2(referenceboard)

JR1

J5

J1

J3

JR2 JP1 JP2 JR1 JR2 JP1 JP2

J2

J7Cable JP

9.3.4 Wiring in a secondary charger moduleThe secondary charger module must be cabled as follows:

- EliminationofthecableconnectingJ1(measurementsboard)withJ3(referencesboard). If the electronics block is being replaced, we would recommend holding this cable in reserve as a spare.

- JR1Cable(comingfromtheenclosurerear)connectedtoJ5(measurementsboard).

- JR2Cable(comingfromtheenclosurerear)connectedtoJ1(measurementsboard).

- JPCable(comingfromtheenclosurerear)connectedtoJ7(measurementsboard).The connector on the cable end shall remain unconnected.

J1

J3

Page 32: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 32 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

9.3.5 Wiring in a main inverter moduleA main inverter module must be cabled as follows:

- CableconnectingJ1(measurementsboard)withJ3(referencesboard).

- JR1Cable(comingfromtheenclosurerear)connectedtoJ5(measurementsboard).

- JR2Cablecomingfromtheenclosurerear,shallremainunconnected.

- JPCable(comingfromtheenclosurerear)connectedtoJ7(measurementsboard)andtoJ2(referenceboard)

JR1 JR2 JP1 JP2

J1

J7

J5

JR1

J5

J1

J3

JR2 JP1 JP2 JR1 JR2 JP1 JP2

J2

J7Cable JP

Page 33: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 33 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

9.3.6 Wiring in a secondary inverter module

A secondary inverter module must be cabled as follows:

-EliminationofthecableconnectingJ1(measurementsboard)withJ3(referencesboard). We would recommend holding this cable in reserve as a spare.

-JR1Cable(comingfromtheenclosurerear)connectedtoJ5(measurementsboard).

-JR2Cable(comingfromtheenclosurerear)connectedtoJ1(measurementsboard).

-JPCable(comingfromtheenclosurerear)connectedtoJ7(measurementsboard).The connector on the cable end shall remain unconnected.

J1

J3

JR1 JR2 JP1 JP2

J1

J7

J5

Page 34: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 34 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

9.4 Connection of the battery bank

The battery charger Ingecon® Hybrid MS modules do not include cut-off and protection switchgear for the battery bank. The installer must provide for these devices, in compliance with the regulations in force in the region in question.

When making the connections, the cabling should be voltage free.

The battery bank shall be connected to the connections bus bar, located on the rear of any of the battery charger modules. Cable access is through the ports in either the top or bottom bus bar covers.

The connection shall be made with an M12 ring terminal.

Make the connection paying particular attention to maintain the security clearance between live parts and the enclosure.

Pay particular attention to the polarity. The equipment will be seriously damaged by cables connected with reverse polarity.

Battery charger module

Battery charger module

BA

T -

BA

T +

- +

Acceso cables

Acceso cables cable ports

cable ports

Page 35: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 35 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

9.5 Connection of the AC lineThe cables making up the distribution line are connected to the connections bus bar, on the rear of any of the inverter modules.

The cable access is through the ports in the upper or lower bus bar covers.

The connection is made with an M12 ring terminal.

Make the connection paying particular attention to maintain the security clearance between live parts and the enclosure.

9.6 PV array connection

Never forget that, whenever the panels are exposed to light, voltage is generated at the PV panel terminals. Therefore, whilst connected to the PV array, the equipment may hold extremely hazardous voltages.

Always make the connection with the breakers open.

Pay particular attention to polarity. Connecting the cables with the wrong polarity could seriously damage the equipment.

The PV arrays are connected at the terminals at the rear of the corresponding module

Rated section 16mm2.

Maximum section 25mm2.

Should it be necessary to use a greater cable section, then we would recommend using an external distribution box located close to the equipment in order to make the section change, so that the section is suitable for the one tolerated by the equipment.

Inverter Module

L1 L2 L3 N

Page 36: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 36 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Main battery charger ModuleThe PV array for the main battery charger module must be connected at the rear terminals.

XPV.1 – positive XPV.2 – negative

Photovoltaic ModulesThe PV arrays of the photovoltaic modules must be connected at the rear terminals.

Input1 XPV1.1 – positive XPV1.2 – negative

Input 2 XPV2.1 – positive XPV2.2 – negative

Input 3 XPV3.1 – positive XPV3.2 – negative

Main battery charger module

XPV

1 2

+ -

Photovoltaic module

+ - + - + -

XPV1

1 2 2 2 1 1

XPV2 XPV3

Page 37: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 37 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

9.7 Connection of the wind turbines. Dump load

Never forget that, whilst the wind turbines are rotating, voltage is being generated at their terminals.

Therefore the inverter interior may hold extremely hazardous voltages whilst it remains connected to the wind turbines.

Make the connection with the breakers open.

The wind turbines are connected at the terminals located on the rear of the wind power module.

Rated section 16mm2.

Maximum section 25mm2.

Should it be necessary to use a greater cable section, then we would recommend using an external distribution box located close to the equipment in order to make this section change.

Connection of the wind turbines:

Wind turbine 1: L1 XWT1.1 L2 XWT1.2 L3 XWT1.3

Wind turbine 2: L1 XWT2.1 L2 XWT2.2 L3 XWT2.3

Wind turbine 3: L1 XWT3.1 L2 XWT3.2 L3 XWT3.3

If the installation is equipped with a Dump Load system, this shall be connected at the terminals located on the rear of the wind power module.

Rated section 16mm2.

Maximum section 25mm2.

The following cables shall be interconnected between the Dump Load system and the wind power module

XR1.1 Module XR1.1 Dumpload

XR1.2 Module XR1.2 Dumpload

XR2.1 Module XR2.1 Dumpload

XR2.2 Module XR2.2 Dumpload

XR3.1 Module XR3.1 Dumpload

XR3.2 Module XR3.2 Dumpload

ThepowersupplyfortheDumploadsystemshallbemadethroughtheJMconnector(pins3 and 4). This power supply can be made from any module, with the corresponding order:

JM1.3orJM2.3ModuleJM.3Dumpload

JM1.4orJM2.4ModuleJM.4Dumpload

Page 38: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 38 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Wind power module

JM2 JM1

4 4 3 3

XWT1

1 2 2 2 1 1

XWT2 XWT3

3 3 3

XR1

1 2 2 2 1 1

XR2 XR3

Dumpload

JM1

3 4

XR1

1 2 2 2 1 1

XR2 XR3

JM1

3 4

Page 39: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 39 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

9.8 Connection of the GensetPower wiringThe Ingecon® Hybrid MS modules do not include the switchgear required to connect the backup generator to the system. These devices must be dimensioned taking into account the total power of the installation and the rated power of the backup generator. They can either be supplied by INGETEAM ENERGY S.A. (chapter 8.1) or by the installer.

Thefinalconfigurationmustadapttothefollowingdiagram:

Voltage pick-upIn order to capture the backup generator voltage, cabling must be installed to run from the generator output to terminals XGAUX on the main inverter module.

Asthisissignalcabling,acablesectionof1mm2willbesufficient.

XGAUX.8 –Phase 1

XGAUX.9 – Phase 2

XGAUX.10 – Phase 3

XGAUX.11 – Neutral

Kit Genset

OutputIngecon® Hybrid MS

AC load

XGAUX8 9 10 11

Main Inverter Module

Page 40: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 40 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Remote start / Stop orderThe Ingecon® Hybrid MS shall give the backup generator remote start / stop order through a potential-free contact. In fact there is a normally open (NO) potential free contact and a normally closed (NC) potential free contact available which make it possible to adapt totherequirementsofeachspecificinstallation.Thesecontactshaveratedvaluesof230 Vac and 8 A.

The connection terminals are located on the rear of the main battery charger module: XAUX.

Signal for closing the power contactorThe Ingecon® Hybrid MS gives the order for the power contactor to close through the normally open potential free contact. Contact with rated values of 230 Vac and 8A. The cabling must be such that, when activated, the contactor coil is powered at its rated voltage.

The connection terminals are located on the rear of the main inverter module:

XGAUX.6 - XGAUX. 7.

Main Charger Module

XAUX1 2 3

Main Inverter Module

Power breaker

A1 A2

Page 41: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 41 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

Contactor closure signalThe power contactors for the connection of the backup gensets must be equipped with a normally open (NO) auxiliary contact.

The Ingecon® Hybrid MS checks the effective closure of the contactors by reading its auxiliary contacts, which must be connected to terminals XGAUX.1 to XGAUX.5, located on the rear of the main inverter module.

If the system is to operate with a single generator, then auxiliary contact (contact KM1) must be wired to XGAUX.1 – XGAUX.5.

If the system is to operate with a number of generators, then the auxiliary contact corresponding to each generator should be wired as follows:

XGAUX.1-XGAUX.5- contact KM1 (genset 1)

XGAUX.2-XGAUX.5- contact KM2 (genset 2)

XGAUX.3-XGAUX.5- contact KM3 (genset 3)

XGAUX.4-XGAUX.5- contact KM4 (genset 4)

XGAUX6 7

Main Inverter Module

Page 42: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 42 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

9.9 Earth connectionsThe earthing of the vertically stacked modules is through the two threaded rods located at the front. To earth each module, connect the braided cable located in the module interior toeachrodandfirmlysecurewithanut.(Seephoto)

Main Inverter Module

XGAUX1 2 3 4 5

Braided cable

Earth connections between modules

Page 43: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 43 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

Each stack shall be earthed by running a cable to take the earth connection to it.

To earth each stack, there is a green / yellow terminal located on the rear of the modules (rated section 16 mm2). You only need to earth one module per stack (See photo).

A dumpload system shall be earthed through its green / yellow earth terminal (rated section 16mm2)

Earthing the stacks

The Ingecon® Hybrid MS neutral output must never be earthed. If the installation requires the neutral to be earthed, then the galvanic isolation transformer module must be installed, as indicated in chapter 8.3.

Page 44: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 44 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

10 USER INTERFACE

TheIngecon®HybridMSinvertersareequippedwitha«Screen+Keypad»unitforcommunicatingwiththeinstalleranduser.

This interface displays the key internal parameters and allows the entire system to be adjusted during the installation process.

The parameters, variables and commands are organised into menus and sub-menus.

10.1 Keypad and LEDSThe keypad has four keys:

Esc. Serves to exit the parameter edit mode, to exit a menu and return to a higher level in the structure, or to cancel a change or proposal.

Up. This key serves to scroll up a list of parameters or folders within the same level, or to increase the value of an editable parameter by one basic unit.

Down. This key serves to scroll down a list of parameters or folders within the same level, or to decrease the value of an editable parameter by one basic unit.

OK.Servestovalidateaparameterchange,toaccessalowerlevelmenu,toconfirma change or accept a proposal.

There are three front LEDs:

Green LED.

Constantly on: Equipment operating normally.

Flashing:Invertermoduleactingasarectifier,batterieschargingfromthebackupgenerator.

Yellow LED.

Flashing: Alarm triggered that does not cause an equipment stoppage.

Red LED.

Constantly on: Alarm triggered that causes an equipment stoppage.

Flashing: Equipment stopped by emergency button or through the display.

ESC OK

Page 45: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 45 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

10.2 Menu structureThe initial screen, the default screen, displays the parameters which are of particular interest during the normal operation of the Ingecon® Hybrid MS.

This screen displays (as instantaneous values):

- Actual date and time

- Total alternating power

- Total power generated at the PV inputs

- Total power generated at the wind power inputs

- Battery bank voltage and current

- Battery bank state of charge

All these values for the Ingecon® Hybrid MS are shown in greater detail in the monitoring section.

The scroll keys serve to access the main menu, which heads a structure of sub-menus which makes it possible to intuitively locate any parameter.

Access to the main menu

Access to the main menu

A table summarising all the screens available is detailed later on in this manual.

Note: The scroll keys are used to move up and down a list. Click on the OK key to access the highlighted option. Use the ESC key to access the menu at the next level above.

10.3 Main menuThe main menu displays a list of all the sub-menus:

AC 050.5 kWPV 150.5 kWWT 200.2 kWBAT 240 V 50 A

MAIN MENU

Monitoring ExtrasStop reasons

Start system

0.78%

AC 050.5 kW

PV 150.5 kW

WT 200.2 kW

BAT 240 V 50 A

0.78 %

Page 46: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 46 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

To move up and down the menu, use the scroll keys. Access the highlighted option by clicking on the OK key.

START / STOP SYSTEM

Start or stop the Ingecon® Hybrid MS.

MONITORING

This menu displays the values of the key parameters which provide information on the equipment operating status.

EXTRAS

Submenu of additional operations such as starting the backup generator or performing a battery equalisation charge.

STOP REASONS

To view the most recent stoppage motives for each module in the installation.

ALARMS

To view the alarms present in that moment.

CONFIGURATION

Thismenuservestodisplayandmodifyalltheconfigurablevariables,whichmustbeadaptedtosuitthecharacteristicsofeachspecificinstallation.

SETTINGS

Menu to adjust the settings of the general parameters (Date, time, language, etc.)

SYSTEM DATA

Menutoconfiguretheserialnumberofeachmoduleintheinstallation.

10.4 Monitoring

Once the Monitoring menu has been selected, click on the key to access it.

MAIN MENUAlarmsConfigurationSettings

System data

Monitoring

MAIN MENUStart System

ExtrasStop reasons

Page 47: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 47 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

This menu displays important values to check that the equipment is operating correctly. These values are grouped into a number of sub-menus.

BATTERYVOLTAGE (V)

Battery bank voltage in volts.

CURRENT (A)

Battery bank current in amps.

Ifthecurrentispositive,thenitisflowingintothebatteriesasachargingcurrent

Ifthecurrentisnegative,thenitisflowingoutofthebatteryasadischargingcurrent.

SOC (%)

Estimation of the battery bank state of charge as a %.

STATUS

Indicates the battery bank operating status: discharge, constant current charge, absorption charge,equalizationchargeorfloatstatus.

TEMPERATURE (ºC)

Battery bank temperature (with optional temperature sensor).

VOLTAGE TEMPERATURE COMPENSATION (V)

Compensation applied to the battery voltage due to the effect of temperature on the charging process.

INVERTERFirstly, a screen is displayed summarising all the data for the alternating stage and the operating status of the inverter modules.

BatteryMONITORING

InverterPhotovoltaicWind Turbine

INVERTER MONITORING R S TVRMS (V) 230 231 230IRMS (A) 18 10 5POW. (kW) 4.1 2.3 1.1 ON SYNCHRONISING

ESTADO MODO STATUS MODE

Page 48: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 48 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

VRMS (V) Phases R, S, T

Phase voltages at the inverter output, in volts.

IRMS (A) Phases R, S, T

Output currents for each phase, in amps.

POW. (kW) Phases R, S, T

Power for each phase, in kilowatts.

STATUS Se distingue entre estado PARADO, MARCHA o ERROR.

MODE Modo de funcionamiento del inversor.

STAND BY – Inverter stoppage (due to a manual order or an error)

INVERTER MODE – Inverter generating alternating voltage

WAITING GENS. – Checking the backup generator voltage, on hold until OK to connect.

SYNCHRONISING – Synchronising with the backup generator

RECTIFIER MODE – Auxiliary generator connected and powering the installation.

DESYNCHRONIS. – Disconnecting the backup generator

Click on the key to view the screens displaying the data for voltage, current and power for each inverter module.

PHOTOVOLTAIC

The initial screen displays a summary of the power generated.

PV 1 (kW)

Power generated by the PV input into the battery charger module in kilowatts.

Click on the key to access the sub-menu and get more information on the voltage and current at the said input.

Photovoltaic

MONITORINGBattery Inverter

Wind Turbine

Module 1 (kW) 15

PHOTOVOLTAIC MONITORINGPV 1 (kW) 5

Module 2 (kW) 8Module 3 (kW) 10

Page 49: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 49 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

PV 1 INPUT (V) Voltage of the PV 1 input, in volts.

PV 1 INPUT (A) Current of the PV 1 input, in amps

MODULE 1 (kW)

Total power generated in PV module 1, in kilowatts.

MODULE 2 (kW)

Total power generated in PV module 2, in kilowatts.

MODULE 3 (kW)

Total power generated in PV module 3, in kilowatts.

MODULE 4 (kW)

Total power generated in PV module 4, in kilowatts.

Selectaspecificmoduleandclickonthe , key to get more details of the voltage and current for each module input.

INPUT 1 [V A] Voltage of input 1, in volts.

Current of input 1, in amps.

INPUT 2 [V A] Voltage of input 2, in volts.

Current of input 2, in amps

INPUT 3 [V A] Voltage of input 3, in volts.

Current of input 3, in amps

WIND TURBINE

The initial screen displays a summary of the power generated at each module.

Wind Turbine

MONITORINGBattery InverterPhotovoltaic

WIND TURBINE MONITORING

Module 2 (kW) 8Module 3 (kW) 8Module 4 (kW) 10

Module 1 (kW) 15

Page 50: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 50 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

MODULE 1 (kW)

Total power generated at wind power module 1, in kilowattss.

MODULE 2 (kW)

Total power generated at wind power module 2, in kilowatts.

MODULE 3 (kW)

Total power generated at wind power module 3, in kilowatts.

MODULE 4 (kW)

Total power generated at wind power module 4, in kilowatts

Selectaspecificmoduleandclickonthe key to get more details of the power and frequency for each module input.

INPUT 1 [kW Hz] Power for input 1, in kilowatts.

Frequency for input 1, in hertz

INPUT 2 [kW Hz] Power for input 2, in kilowatts.

Frequency for input 2, in hertz

INPUT 3 [kW Hz] Power for input 3, in kilowatts.

Frequency for input 3, in hertz

GENSETVRMS (V) [L1 L2 L3] RMS voltage for each phase, in volts.

FR (HZ) [L1 L2 L3] Frequency for each phase in hertz.

STATUS Status of the backup generator.

Stopped – Backup generator off

On by SOC – Backup generator operating due to battery state of charge.

Onby:TimeSet–Backupgeneratoroperatingduetothescheduleconfigured.

On by: Overload – Backup generator operating due to high consumption.

On by: Equalization – Backup generator operating to perform an equalization process.

Manual operation – Backup generator operating due to a manual order.

WATTMETERVRMS (V) [R S T] RMS voltage for each backup generator phase, measured by the wattmeter, in volts.

IRMS (A) [R S T] RMS current for each backup generator phase, measured by the wattmeter, in amps.

POW. (kW) [R S T] Active power for each backup generator phase, measured by the wattmeter, in kilowatts.

If the installation has more than one wattmeter, each one will be displayed by clicking on the OK key.

Page 51: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 51 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

OTHERS Menu to display other parameters of interest.

VBUS DC bus voltage in volts.

VBUSP (V) Voltage in volts for the positive half of the DC bus.

VBUSN (V) Voltage in volts for the negative half of the DC bus.

HEATSINK TEMP

Radiator temperature for the electronics block for each module.

It is divided into a number of sub-menus, based on the type of module, displaying the temperature of modules 1 to 4.

NOTICES

Indicators to check the operation and help detect faults in each module.

This menu is divided into a number of sub-menus, based on module type. A hexadecimal number is displayed for each module and, when converted to binary, allows a number of signals to be checked.

Hexadecimal to binary conversion table:

Hexadecimal Binary

0 0 0 0 01 0 0 0 12 0 0 1 03 0 0 1 14 0 1 0 05 0 1 0 16 0 1 1 07 0 1 1 18 1 0 0 09 1 0 0 1A 1 0 1 0B 1 0 1 1C 1 1 0 0D 1 1 0 1E 1 1 1 0F 1 1 1 1

1st digit 2nd digit 3rd digit 4th digit

Low Bus voltage 1Error raising Bus 1Bus balanced 1Battery SOC OK 1Modbus Error 1Temperature error 1Manual operation 1Permission from master 1Drivers OK 1Sensors ready 1

Page 52: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 52 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Battery charger module notices table:

Battery charger module PV input notices table:

Inverter module notices table:

1st digit 2nd digit 3rd digit 4th digit

Bus error 1Temperature derating 1Battery SOC OK 1Modbus error 1Temperature error 1Manual operation 1Permission from master 1Drivers OK 1Sensors ready 1PV input operating 1

1st digit 2nd digit 3rd digit 4th digit

Genset connection error 1Phase 3 synchronised 1Phase 2 synchronised 1Phase 2 synchronised 1Synchronisation command 1Genset voltage phase 3 OK 1Genset voltage phase 2 OK 1Genset voltage phase 1 OK 1Modbus Error 1Temperature error 1

Operation flag 1

Permission from master 1

Drivers OK 1

Bus voltage OK 1

Sensor IL ready 1

Sensors ready 1

1st digit 2nd digit 3rd digit 4th digit

- 0Driver 3 OK 1Driver 2 OK 1Driver 1 OK 1Input voltage 3 OK 1Input voltage 2 OK 1Input voltage 1 OK 1Modbus Error 1Temperature error 1Permission from master 1

Operation flag 1

Drivers OK 1

Bus voltage OK 1

Sensors input 3 ready 1

Sensors input 2 ready 1

Sensors input 1 ready 1

Page 53: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 53 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

PV module notices table:

Wind turbine module notices table:

Example:

The conversion of the hexadecimal number 0388 to binary would be:

Comparing this to the corresponding table:

It can be seen that the unit cannot start because the manual operation is not active (through the display or the on / off control).

Supposing that the battery charger module indicator screen displays:

1st digit 2nd digit 3rd digit 4th digit

- 0Driver 3 OK 1Driver 2 OK 1Driver 1 OK 1Voltage input 3 OK 1Voltage input 2OK 1Voltage input 1 OK 1Modbus Error 1Temperature error 1Permission to operate 1

Operation flag 1

Drivers OK 1

Bus voltage OK 1

Sensors input 3 ready 1

Sensors input 2 ready 1

Sensors input 1 ready 1

1st digit 2nd digit 3rd digit 4th digit

Low bus voltage 0Error raising bus 0Bus balanced 0Battery SOC OK 1Modbus Error 0Temperature error 0

Operation flag 0

Permission from master 1Drivers OK 1

Sensors ready 1

1st digit 2nd digit 3rd digit 4th digit

HEXADECIMAL 0 3 8 8BINARY 0 0 0 0 0 0 1 1 1 0 0 0 1 0 0 0

Notices Module 1 0x0388H 0x0000H Module 2 0x0000H Module 3 0x0000H Module 4 0x0000H

Número hexadecimal

Indicador de PV

hexadecimal number

PV indicator

Page 54: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 54 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

For correct operation, the error indicators must be 0.

10.5 Extras

Click on once the Extras menu has been selected, to access this menu.

The following actions can be executed in this menu.

GENSET START-UP

Manual start-up

Back-up [YES, NO]

Manually stop or start the back-up generator.

The back-up generator start-up shall be performed immediately and it shall remain connected until this same route is used to order it to stop.

MANUAL EQUALIZATION

Manual Equaliz.

[YES, NO] Performs a manual equalization charge of the batteries.

Ifthebackupgeneratorhasbeenconfiguredtoperformtheequalization[415],thisshall start immediately. Otherwise, the equalization shall be performed when the energy available in the system makes this possible.

Extras

MAIN MENUStart systemMonitoring

Stop reasons

Genset start upEXTRAS

Manual equalization

Stop reasons

MAIN MENUStart systemMonitoringExtras

Page 55: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 55 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

10.6 Stop reasons

Click on the key once the Stoppage reasons menu has been selected, to access this menu.

This section displays information on the last stoppage motives for each module making up the installation.

LAST REASONS

This screen displays the four most recent stoppage reasons recorded in the Ingecon® Hybrid MS system.

Details are given of the time, day/month, type and number of the module involved in each stoppage reason. With these details, the corresponding module sub-menu should be accessed where information is given on the time and the stoppage reason category.

CHARGER MODULE

This screen displays the four most recent stoppage reasons recorded for each battery charger module in the installation.

For each stoppage reason, details are given of: the time, date and cause.

INVERTER MODULE

This screen displays the four most recent stoppage reasons recorded for each inverter module in the installation.

For each stoppage reason, details are given of: the time, date and cause

PHOTOVOLTAIC MODULE

This screen displays the four most recent stoppage motives recorded for each PV module in the installation.

For each stoppage reason, details are given of: the time, date and cause

WIND TURBINE MODULE

This screen displays the four most recent stoppage reasons recorded for each wind power module in the installation.

For each stoppage reason, details are given of: the time, date and cause.

Last reasonsSTOP REASONS

Charger moduleInverter modulePhotovoltaic module

Page 56: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 56 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

10.7 Configuration

Parameterconfigurationisprotectedviaanaccesscode,therebypreventingmodificationby unauthorised persons. For configuration changes, you should access sub-menuCONFIGURATION - CHANGE and enter the code (see this section).

BATTERY CONFIGURATION001 CHARGERS NUM

Number of battery charger modules in the installation.

002 I CHARGE (A)

Battery bank charge current in amps.

003 I DISCHARGE (A)

Maximum battery bank discharge current in amps

Click on the keyoncetheConfigurationmenuhasbeenselected,toaccessthismenu.

Thismenuservestodisplayandmodifyalltheconfigurablevariables,andwhichmustbe adapted to suit the characteristics of each particular installation.

Eachconfigurationparametershallbeidentifiedbyanumber,whichshallbereferredtothroughout the document

BatteryCONFIGURATION

InverterPhotovoltaicWind Turbine

Configuration

MAIN MENUStop reasons

SettingsSystem data

Identificationnumber 001 CHARGERS NUM.

Page 57: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 57 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

004 V ABSORPTION (V)

Battery bank absorption voltage in volts.

(Bank charge voltage).

005 V EQUALIZ. (V)

Battery bank equalization voltage in volts.

006 V FLOAT (V)

Batterybankfloatvoltageinvolts.

007 CAPACITY (Ah)

Battery bank capacity (C20), in Ah.

008 EQUALIZ T.

Equalization time in minutes.

Time during which the battery bank should remain at the equalization voltage.

009 CYCLES EQUALIZ.

Number of charge cycles between two equalization charges.

Anequalizationchargeshallbemadeoncethenumberofchargecyclesconfiguredandrecorded here have been made since the last equalization charge.

010 COMPENS (V/ºC)

Battery voltage compensation constant based on temperature, in volts/ºC.

It will be necessary to install an optional temperature sensor.

011 SOC DISCONN. (%)

Battery state of charge, below which the equipment is shutdown, shown as a %.

Stoppage of the equipment to protect against deep discharges.

012 SOC CONNECT. (%)

Battery state of charge, above which the equipment is re-started, shown as a %.

If the equipment has been shut down due to a low battery state of charge, it will not be reconnected until the SOC reaches this value.

013 CHANGE SOC (%)

Manual assignment of the battery state of charge value.

INVERTER CONFIGURATION101 INVERTERS NUM.

Number of inverter modules in the installation.

102 FREQUENCY (HZ)

Frequency of the voltage generated, in hertz.

103 RMS VOLTAGE (V)

RMS value of the phase voltage generated, in volts.

104 OVERLOAD T (S)

Time during which a short-circuit or very high overload should be maintained before stopping the equipment, in seconds.

Page 58: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 58 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

PHOTOVOLTAIC CONFIGURATION

201 PV MODULES NUM

Number of PV modules in the installation.

202 PV 1 INPUT ON / OFF

Enabling of the PV input of the main battery charger module.

Thefollowingmustbeconfiguredforeachavailablemodule:

204 CONFIG MOD

ConfigurationoftheoperatingmodeforthemodulePVinputs.

INDEPENDENT INPUTS – If the inputs are connected to individual PV arrays.

3 INPUTS IN PARALLEL – If the inputs are connected to the same PV array, operating like a single 45kW input.

205.1 INPUT 1

Enabling of PV input 1 of the PV module

ON- Input enabled.

OFF- Input disabled. Prevents it from operating and / or indicates that it is not connected to a PV array.

205.2 INPUT 2

Enabling of PV input 2 of the PV module

ON- Input enabled.

OFF- Input disabled. Prevents it from operating and / or indicates that it is not connected to a PV array

205.3 INPUT 3

Enabling of PV input 3 of the PV module

ON- Input enabled.

OFF- Input disabled. Prevents it from operating and / or indicates that it is not connected to a PV array.

PV CONFIGURATION201 PV Modules Num.202 PV Input 1

Module 2

Module 1

Photovoltaic

CONFIGURATIONBattery Inverter

Wind Turbine

Page 59: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 59 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

WIND TURBINE CONFIGURATION

Thefollowingparametersmustbeconfiguredhere.

301 WT MODULES NUM

Number of wind turbine modules in the installation.

Thefollowingshouldbeconfiguredforeachavailablemodule:

303 MODULE CONF.

Configurationoftheoperatingmodeforthemodulewindpowerinputs.

INDEPENDENT INPUTS – If the inputs have been connected to independent wind turbines.

3 INPUTS IN PARALLEL – If the inputs have been connected to a single wind turbine with a higher power rating, performing as a single 45kW input.

INPUTS 1 AND 2 IN PARALLEL – If inputs 1 and 2 have been connected to one wind turbine and input 3 to another.

304.1 INPUT 1

305 ENABLE INPUT

Enabling of wind power input 1 of the module.

ON- Input enabled.

OFF- Input disabled. Prevents it from going into operation and / or indicates that it is not connected to a wind turbine.

306 WT DATA

Thewindturbinecharacteristicsneedtobeconfigured,forcorrectwindturbinecontrol.

307 RATED Iac (A)

Rated wind turbine current in amps.

Module 2

WT CONFIGURATION301 Modules WT Num. Módule 1

Módule 3

Wind Turbine

CONFIGURATIONBattery InverterPhotovoltaic

Page 60: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 60 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

308 POW - Vdc CURVE

Wind turbine characteristic curve for power (watts) - dc voltage (volts) which should be supplied by the turbine manufacturer.

Four points on the curve are required.

For example:

Note: The Vdc voltage of point 1 shall be taken as the minimum voltage to start-up the wind turbine. If the mean Vdc voltage is below this value, then the input will remain on stand-by, reducing the losses at the converter.

304.2 INPUT 2

305 ENABLE INPUT

Enabling of wind power input 2 of the module.

ON- Input enabled.

OFF- Input disabled. Prevents it from going into operation and / or indicates that it is not connected to a wind turbine.

306 WT DATA

307 RATED Iac (A)

Rated wind turbine current in amps.

308 POWER - Vdc CURVE

Four points of the wind turbine power (watts) - dc voltage (V) characteristic curve.

304.3 INPUT 3

305 ENABLE INPUT

Enabling of wind power input 3 of the module.

ON- Input enabled.

OFF- Input disabled. Prevents it from going into operation and / or indicates that it is not connected to a wind turbine.

306 WT DATA

307 RATED Iac (A)

Rated wind turbine current in amps.

308 POWER - Vdc curve

Four points of the wind turbine power (watts) - dc voltage (V) characteristic curve.

P (W)

Vdc (V)

Pnom

Punto 1 Punto 2

Punto 3

Punto 4 Point 4

Point 3

Point 2Point 1

Prat

Page 61: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 61 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

GENSET

Thefollowingparametersshouldbeconfigured.

401 GENSET.

Configurationoftheback-upgenerator.Indicatewhetherornotabackupgeneratorisavailable in the installation.

402 GENS.POW. 1 (kW)

Rated power of back-up generator 1, in kilowatts.

403 GENS.POW. 2 (kW)

Rated power of back-up generator 2, in kilowatts.

404 GENS.POW. 3 (kW)

Rated power of back-up generator 3, in kilowatts.

405 GENS.POW. 4 (kW)

Rated power of back-up generator 4, in kilowatts.

406 CHARGE PW. (kW)

Battery charging power from the back-up generator, in kilowatts.

This is considered to be the maximum charging power; the power used for the charge will be determined by the battery state of charge.

407 SOC ON (%)

Battery state of charge, below which the back-up generator comes into operation, expressed as a %

408 SOC OFF (%)

Battery state of charge, above which the back-up generator shuts down (if it had been operating due to a low state of charge), expressed as a %

409 ON - - HOUR

410 ON - - MINUTE

Time at which the back-up generator is started up.

The time set shall be maintained for all the days of the week.

Genset

CONFIGURATIONInverterPhotovoltaicWind Turbine

Page 62: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 62 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

411 OFF1 - - HOUR

412 OFF1 - - MINUTE

Time at which the back-up generator is shut down.

If,atthistime,thebatterystateofchargeisbelowthestateofchargelevelconfiguredinparameter408,thentheback-upgeneratorshallcontinuetooperateuptothedefiniteshut down time (parameters 413 and 414).

The time set shall be maintained for all the days of the week.

413 OFF2 - - HOUR

414 OFF2 - - MINUTE

Back-upgeneratordefiniteshutdowntime.

The times set shall be maintained for all the days of the week.

415 GENSET.EQUALIZ.

Indicates whether the back-up generator is to be connected to perform equalization charges.

If this function is required, the generator will continue to operate until the equalization charge has been completed.

416 INST. O-LOAD (%A)

Percentage of the rated inverter current and of the battery discharge current (003) above which the order is given to instantaneously connect the back-up generator.

This value shall always be at least 10% greater than parameter 418.

The connection of the back-up generator for this purpose implies a minimum operating time of 10 minutes.

This feature is only available if the INGETEAM ENERGY S.A. wattmeter has been installed.

417 INST. O-LOAD (S)

Dwell time in seconds before the instantaneous connection is made.

The back-up generator shall be connected if, during this time, consumption is greater than parameter 416.

This feature is only available if the INGETEAM ENERGY S.A. wattmeter has been installed.

418 60S O-LOAD (%A)

Percentage of the inverter rated current and of the battery discharge current (003) which, after exceeding this value for one minute, gives the order to connect the back-up generator.

This shall always be at least 10% less than parameter 416.

The connection of the back-up generator for this purpose implies a minimum operating time of 10 minutes.

This feature is only available if the INGETEAM ENERGY S.A. wattmeter has been installed.

419 SHUTDOWN (%S)

After the back-up generator has been started up due to an overload (416, 418), the power delivered by the generator needs to be below this percentage of the back-up generator rated power in order for the equipment to give the order to disconnect the generator.

This feature is only available if the INGETEAM ENERGY S.A. wattmeter has been installed

Page 63: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 63 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

WATTMETER

Thefollowingparametershouldbeconfigured.

501 WATTMETERS N.

Configurationofthenumberofwattmetersinstalled.

CHANGE

PASSWORD.

Enterthepasswordinordertoobtainauthorisationtoconfiguretheequipmentvariables.

The password is entered through the display, and is 4 3 2 1. (See photo)

Wattmeter

CONFIGURATIONPhotovoltaicWind TurbineGenset

Change

CONFIGURATIONWind TurbineGensetWattmeter

PASSWORD

Press the key 4 times

Press the key 3 times Press the key twice

Press the key once

Page 64: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 64 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Wait for the password to be validated.

Once the correct password has been entered, an asterisk will appear alongside Configuration,toindicatethatthevariablescannowbemodified(seephoto).

IfyouexittheConfigurationmenuorifthedisplayremainsinactiveforsometime,thenauthorisation to modify the variables will be cancelled.

10.8 Settings

This menu serves to modify the following general parameters.

DATE & TIME

Configurationofthedateandtime.

LANGUAGE

Select the display language.

10.9 System Data

For the equipment commissioning process, it is necessary to enter all the serial numbers for all the modules making up the installation.

Photovoltaic

CONFIGURATIONBatteryInverter

Wind Turbine

Settings

MAIN MENUAlarmsConfiguration

System data

System data

MAIN MENUAlarmsConfigurationSettings

Page 65: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 65 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

The battery charger module 1 shall be the one to contain the display (main module). The other battery charger modules shall be considered to be secondary modules.

Inverter module 1 shall be the main module. The other inverter modules shall be considered to be secondary modules and must be wired as such.

WARNING: The secondary inverter module internal wiring must be different from that of the main inverter module. See the section on the internal wiring of secondary modules.

Charger Module

SYSTEM DATA

Inverter ModulePhotovoltaic ModuleWind Turbine Module

Module 1

CHARGER MODULE

Module 2Module 3Module 4

Page 66: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 66 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

10.10 Summary tableGiven below is a summary of all the above mentioned display screens.

START / STOP SYSTEM

START SYSTEM

STOP SYSTEM

MONITORING

BATTERY

VOLTAGE (V)

CURRENT (A)

SOC (%)

STATUS

TEMPERATURE (ºC)

TEMPERATURE VOLTAGE COMPENSATION (V)

INVERTER

[R S T] VRMS (V) IRMS (A) POW. (kW)

STATUS - MODE

MODULE 1[VRMS, IRMS, POW]

MODULE 2[VRMS, IRMS, POW]

MODULE 3[VRMS, IRMS, POW]

MODULE 4[VRMS, IRMS, POW]

PHOTOVOLTAIC

PV 1 (kW)

MODULE 1 (kW)

MODULE 2 (kW)

MODULE 3 (kW)

MODULE 4 (kW)

INPUT PV 1 [V A]

INPUT 1 [V A]INPUT 2 [V A]INPUT 3 [V A]

INPUT 1 [V A]INPUT 2 [V A]INPUT 3 [V A]

INPUT 1 [V A]INPUT 2 [V A]INPUT 3 [V A]

INPUT 1 [V A]INPUT 2 [V A]INPUT 3 [V A]

WIND TURBINE

MODULE 1 (kW)

MODULE 2 (kW)

MODULE 3 (kW)

MODULE 4 (kW)

INPUT 1 [kW Hz]INPUT 2 [kW Hz]INPUT 3 [kW Hz]

INPUT 1 [kW Hz]INPUT 2 [kW Hz]INPUT 3 [kW Hz]

INPUT 1 [kW Hz]INPUT 2 [kW Hz]INPUT 3 [kW Hz]

INPUT 1 [kW Hz]INPUT 2 [kW Hz]INPUT 3 [kW Hz]

Page 67: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 67 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

MONITORING

GENSET

VRMS (V) [L1 L2 L3]FR (HZ)STATUS

WATTMETER

VRMS (V) [R S T]IRMS (A) POW (kW)

OTHERS

VBUS

HEATSINK TEMP

NOTICES

VBUSP (V)VBUSN (V)

TEMPERATURECHARGER MODULEINVERTER MODULEPHOTOVOLTAIC MODULEWIND TURBINE MODULE

NOTICESCHARGER MODULEINVERTER MODULEPHOTOVOLTAIC MODULEWIND TURBINE MODULE

EXTRAS

GENSET START UP

MANUAL EQUALIZATION

STOP REASONS

LAST REASONS

CHARGER MODULE

INVERTER MODULE

PHOTOVOLTAIC MODULE

WIND TURBINE MODULE

CONFIGURATION

BATTERY

001 CHARGERS NUM.002 I CHARGE(A)003 I DISCHARGE (A)004 V ABSORPTION (V)005 V EQUALIZ.. (V)006 V FLOAT (V)007 CAPACITY (Ah)008 EQUALIZ. T (min).009 CYCLES EQUALIZ.010 COMPENS (V/ºC)011 SOC DISCONN. (%)012 SOC CONECT. (%)013 CHANGE SOC (%)

INVERTER

101 INVERTER NUM.102 FREQUENCY (HZ)103 RMS VOLTAGE (V)104 OVERLOAD T (S)

Page 68: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 68 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

CONFIGURATION

PHOTOVOLTAIC

201 PV MODULES NUM.202 INPUT PV 1

MODULE 1MODULE 2MODULE 3MODULE 4

204 CONFIG MOD205.1 INPUT 1205.2 INPUT2205.3 INPUT 3

WIND TURBINE

301 WT MODULES NUM.MODULE 1MODULE 2MODULE 3MODULE 4

303 CONFIG MOD304.1 INPUT 1304.2 INPUT 2304.3 INPUT 3

GENSET

401 GENSET402 GENS.POW. 1 (kW)403 GENS.POW.2 (kW)404 GENS.POW.3 (kW)405 GENS.POW. 4 (kW)406 CHARGE POW.(kW)407 SOC ON (%)408 SOC OFF (%)409 ON -- HOUR410 ON -- MINUTE411 OFF1 -- HOUR412 OFF1 - MINUTE413 OFF2 -- HOUR414 OFF2 - MINUTE415 GENSET EQUALIZER.416 INST O-LOAD (%A)417 INST O-LOAD (S)418 60S O-LOAD (%A)419 SHUT DOWN (%S)

WATTMETER 501 WATTMETERS NUM.

CHANGE PASSWORD

SETTINGSDATE AND TIME

LANGUAGE

SYSTEM DATA

CHARGER

MODULE

INVERTER

MODULE

PHOTOVOLTAIC

MODULE

WIND TURBINE

MODULE

Page 69: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 69 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

11 COMMISSIONING11.1 Equipment inspection

The Ingecon® Hybrid MS are equipped with thermal magnetic breakers to protect different parts of the installation. These breakers need to be set to the OFF position prior to starting-up the installation.

Prior to operating the thermal magnetic breakers, check that the entire equipment interior is free from electrical hazards.

When checking that no voltage is present, It is mandatory to use dielectric gloves and safetyglassescertifiedforelectricalhazards.

Inspection

Before starting up the Ingecon® Hybrid MS, a general inspection should be made of the modules, primarily consisting in:

• Cabling inspection:

• Check that all the cables are correctly connected

• Check that the protective switchgear, thermal magnetic breakers, switches, surge arrestors in general are all in good condition and are in the correct position.

It is strictly forbidden to remove the methacrylate type protections to make the visual inspection.

Hermetic seal

During installation, it is important to ensure that the unit IP rating is maintained.

Allowsufficientcablelengthtoensurethatthereisnopullontheterminalsandconnectionpoints.

Ensure that the bus bar covers located on the equipment rear are correctly positioned, preventing any type of contact with the bars.

Check to ensure that any unused ports are hermetically sealed.

Voltage check

Ensure that all the connections have been made in accordance with the instructions given in this manual, with the correct polarity and complying with the voltage ranges indicated.

Connections with reverse polarity or with an out-of-range voltage will seriously damage the equipment.

The battery bank voltage should be between 240 to 500 Vdc.

The solar array voltage must be between 150 to 700 Vdc.

The maximum wind turbine line voltage must be less than 495 Vac.

Page 70: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 70 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

11.2 Power-upOnce you have made a general visual inspection, checked the cabling and voltages, you can then go on to power up the equipment from the battery bank, whilst using the emergency stop button to maintain it in the stop position.

It is mandatory to perform the tasks indicated in this point with the equipment door permanently closed and the bus bar protection correctly in place, to prevent any possible contact with live parts.

Start-up

Once the equipment has been powered from the battery bank, check that the display lights up.

Do not connect the PV and / or wind power inputs until instructed to do so in this manual.

Access the Equipment Data menu and enter the serial number for each installation module (see Equipment Data section).

Then check that the battery voltage displayed coincides with its mean value and is between the range of 240-500 Vdc.

IntheConfigurationmenu,enterallthevaluesrequired,dependingontheequipmentinstalled (See chapter 10.7)

Connect the PV and wind power inputs.

Check that all the monitoring menu variables are coherent.

The voltage for each PV array must coincide with its mean value and must be within the 150 - 700 Vdc range.

Once the above mentioned tasks have been performed, you can then go on to start-up the equipment by means of the emergency button and display menu.

Non-compliance with the above mentioned checking and inspection tasks shall exempt INGETEAM ENERGY S.A. from any type of liability with regard to potential damages to the installation or to the equipment itself and resulting from the said non-compliance.

Checking and measurement

Once the equipment is generating and powering the loads, the “green” LED will remain on.¡

Check that the monitoring menu parameters are coherent:

•Thesolararrayvoltageshallbebetween150to700vdc.

•Thebatteryvoltageshallbebetween240and500Vdc.

•TheVacvoltageandfrequencyshownonthedisplayshallbethedesiredvalue.

•TheRMSvalueoftheIac1,Iac2andIac3currentsshownmustcorrespondtothoseexpected.

•Themodulesmustnotshowanypresentstoppagemotives

Page 71: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 71 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

12 PREVENTIVE MAINTENANCEThe recommended preventive maintenance tasks shall be performed on a YEARLY basis.

Maintenance operations must be performed by qualified personnel. There is an electrical discharge hazard.

All the maintenance checks included herein should be performed with NO VOLTAGE PRESENT IN THE MODULES and in safe manipulating conditions.

The following sections indicate the actions to follow for the correct maintenance of the Ingecon® Hybrid MS.

12.1 Maintenance tasksCheck the condition of the enclosure.

A visual inspection should be made of the enclosure condition, checking the condition of the seals and doors, in addition to the stacking of the modules at the top and bottom, if applicable. Likewise, the enclosure should be checked to ensure that it is free from knocks, scratches or rust which could degrade the module or cause it to lose its Protection Rating. Should any defects of this nature be observed, then the parts affected should be replaced immediately.

Check the condition of the cables and terminals.

- Check that the cables are laid correctly in order to ensure that they are not in contact with live parts.

- Check the insulation for damage and hot points, inspecting the colour of the insulation and terminals.

Torque of the nuts and bolts securing the bus bars and power cables

Check the torque by applying the forces indicated in the following table:

M8 24 Nm

M10 47 Nm

M12 64 Nm

In accordance with DIN 13.

Make a visual inspection to ensure that the bus bars located on the rear of the modules maintain their initial electrical properties.

Check the cabinet interior for humidity.

If moisture is detected, it is essential to dry it up before making the electrical connections.

Check that the modules are correctly anchored to their corresponding anchors or mounting rods.

Page 72: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 72 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Check that the modules are correctly ventilated. To do so:

Check the condition of the air outlet fans and clean and replace if necessary.

Clean the ventilation grids.

Check theconditionofthesideandrearventilationgridfilters.

Todoso,theairintakegridshouldfirstbedismounted,thegridcontainsthefilter.

- Dismount the grid.

-Removethefilterfrominsidethegrid.

Theaccumulationofdustanddirtinthefiltercanaffectthecoolingcapacityofthefanandcausetheequipmenttooverheat.Toresolvethisproblem,cleanthefilterandgridand re-mount.

-Whenthefilterismoderatelydirtyanddry,tapgentlyuntilthedirthasbeenremoved.

- If it is not possible to eliminate the dirt, then wash in water at 40 ºC.

-Thefiltershouldbereplacedwhenitisverydirtyandfullofoiland/orgrease.

Ventilation of the Modules

Page 73: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 73 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

During normal operation, the Ingecon® Hybrid MS makes a buzzing noise. Check the characteristicsofthesurroundingstoensurethatthisbuzzingnoiseisnotamplifiedortransmitted.

Page 74: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 74 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

13 TROUBLESHOOTINGThis is a guide to help resolve any problems that may arise during the installation of the Ingecon® Hybrid MS.

An explanation is also given with regard to how to perform simple component replacement operations or equipment adjustments.

Any problems occurring in the Ingecon® Hybrid MS must be resolved by qualified personnel, observing the general safety conditions stipulated in this manual.

13.1 LED indicatorsSome of the LEDs indicate some sort of problem in the stand-alone installation:

ESC OK

Page 75: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 75 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

13.1.1 Green LED

This LED is on during the normal operation of the system, whilst the other two LEDS will remain off.

Flashing

WhenthisLEDflashes,itindicatesthattheback-upgeneratorisonandpoweringtheloadsandthattheinvertermoduleisinrectifiermode,chargingthebatteries.

13.1.2 Yellow LED

This LED indicates that some alarms have been triggered in the Ingecon® Hybrid MS.

Flashing

TheflashingLEDindicatesthatanalarmhasbeentriggeredintheIngecon®HybridMS, however the malfunction is not serious enough to cause shut down. The alarm may be due to:

- Protection from high temperatures

- Failure in the back-up generator connection

- Low battery bank SOC

13.1.3 Red LED

This LED indicates that alarms have been triggered which are serious enough to cause the Ingecon® Hybrid MS to shut down.

Constantly on

The Ingecon® Hybrid MS has been shut down because a serious error has occurred in one of the modules. The most common equipment shut down motives are:

Alarm caused by over-heating in one of the battery charger modules. The battery charger module has reached an exceedingly high temperature and the Ingecon® Hybrid MS has ceased to operate. Once the temperature returns to normal, the Ingecon will come on again.

Alarm caused by a failure in the electronics block. Any error detected by the battery charger or inverter module electronics block will cause the Ingecon® Hybrid MS to shut down.

Flashing

Manual Shut down. The equipment has been manually stopped. Check that the emergency stop button has not been accidentally pressed or that the manual shutdown order has not been given from the display.

The following table details some of the problems that could occur in the Ingecon® Hybrid MS and the respective solutions.

Page 76: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 76 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Problem Solution

The display and LEDs do not come on, the equipment appears not to be operating (no sound emitted).

Check that the battery voltage is between 200 and 500 V and that it is connected with the correct polarisa-tion.

The display is on but the equipment appears not to be functioning (no sound emitted and no AC voltage generated)

Check that the stop button has been released.Check that the start-up order has been given from the display menu.Check that NUM BOOSTERS, NUM INVERTERS, NUM PHOTOVOLT and NUM WIND POWER are configured according to the installation.Check the battery Sate of Charge (SOC). It must be greater than SOC DISCONN. BANK

The display is on, the equipment appears to be functioning (sound emitted) but no AC voltage is generated.

Check that the inverter module thermal magnetic breaker is in the ON position.Check that NUM BOOSTERS, NUM INVERTERS, NUM PHOTOVOLT and NUM WIND POWER are configured according to the installation.

The back-up generator does not start

Check that a back-up generator has been configured for the installation (401)Check that the start-up signal has been correctly connected (See chapter 9.8)Check the start-up criteria configured.

No connection is made with the back-up generator.

Check that the back-up generator voltage is correct.In the Back-up Monitoring section on the display, check that the equipment is measuring the VRMS voltage correctly (See chapter 10.4).If not, check the wiring of the capture signals for the back-up generator. (See chapter 9.8).Check that the contactor closure signal has been cor-rectly wired (see chapter 9.8).Check that the inverter module thermal magnetic breaker and the protections installed for the back-up generator are in the ON position.

The contactor to connect the auxiliary ge-nerator closes and opens at intervals lasting several seconds.

Check that the contactor connection signal has been correctly wired (see chapter 9.8).

The batteries are not being charged from the back-up generator

Check that CHARGE POW has been configured other than zero (406).Check that the I CHARGE (002) battery charge cur-rent has been correctly configured and compare it to the actual current.

Page 77: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 77 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

Problem Solution

No power appears to be delivered from the PV input

Check that the PV inputs are correctly configured on the display and that the number of modules is correct (201, 202, 204).Check that the PV input thermal magnetic breakers are in the ON position.Check that the panel voltage is between 200 and 700 V and that it is connected with the correct polarisa-tion. (See chapter 9.6).In the Photovoltaic Monitoring Menu, check that the display is measuring the panel voltage correctly. (See chapter 10.4).

No power appears to be delivered from the wind power input.

Check on the display that the number of modules and the wind power inputs are correctly configured (301,303).Check that the wind power input thermal magnetic breakers are in the ON position.Check that the wind turbine characteristic parameters have been correctly configured (306).In the Wind Power Monitoring menu on the display, check that the wind turbine frequency and voltage are being measured correctly (See chapter 10.4).

Page 78: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 78 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

14 ANNEXES

14.1 REPLACEMENT OF THE «ELECTRONICS BLOCK»All the Ingecon® Hybrid MS have been designed with the same structure, to facilitate component location and replacement.

Theelectronicscardshavebeengroupedtogethertoformwhatistermedan«electronicsblock»,forquickandsimpleassembly.

Warning. There are four types of electronics blocks, one for each module type. The electronics blocks are exclusive to each module type and are not interchangeable.

For the inverter and / or charger modules particular attention should be paid to the wiring of the electronics blocks, which varies depending on whether it is a main or secondary module. See the chapter on Secondary Module Internal wiring.

Occasionally, and always acting on the advice of INGETEAM ENERGY S.A., it may benecessarytoreplacethe«electronicsblock».ThisoperationmustbeperformedbyqualifiedpersonnelandwillentailtheshutdownoftheINGECONHYBRIDforacertainlength of time.

During the operations mentioned below, the use of personal protection equipment (PPE) is mandatory: safety helmet, glasses, gloves and footwear.

After disconnecting the equipment from the power sources, wait at least 10 minutes before opening the door. The internal capacitors can maintain hazardous voltage levels.

Double check to ensure that the batteries and PV panels are not connected.

ToreplaceanyIngecon®HybridMSmodule«electronicsblock»,theproceduredescribedbelow must be followed in sequence:

- Press the stop button, to turn the equipment OFF.

- Open the thermal magnetic breakers for all the inverter modules

- Open the thermal magnetic breakers for all the wind power modules. If necessary, short circuit the wind turbine output using an external device.

- Open the thermal magnetic breakers for all the PV modules.

- Open the thermal magnetic breaker at the main battery charger module PV input.

- Open the battery bank connection breaker.

- Make an electrical check to ensure that none of the power sources is still in electrical contact with any part of the equipment.

- Wait at least 10 minutes.

Page 79: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 79 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

-Checkthatthereisnovoltagepresentbeweenthefirstthreebusbars(Bus+,Mbus,Bus-).

BUS

+

BUS

-

MBU

S

- Open the door of the module in which the block is to be replaced.

-Disconnectallthecablingfromthe«electronicsblock»;plug-inconnectorsfromthefront terminal strip, power cabling from the side terminal strip and signal cabling (in the inverterandchargermodules).Ensurethatallcablingisclearlyidentifiedsothatitcanbe correctly reconnected later.

-The«electronicsblock»isremovedfromtheleftsideofthemodule.Useadequatetooling to remove the screws located on the outside of the module and securing the block in place.

-Removethe«electronicsblock».Handlewithcaretoavoiddamage.(Seephoto).

Removal of the Electronics Block

Toreplacethenew«electronicsblock»proceedinreverseorder.Shouldyouhaveanydoubts with regard to connections, contact the INGETEAM ENERGY S.A technical service.

Before re-starting the Ingecon® Hybrid MS:

- Completely seal the module door.

Start-up the equipment.

Page 80: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 80 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

14.2 BATTERY OPERATIONBattery longevity depends on many factors, the most important being the charge and discharge levels the battery is subjected to, the number of cycles, the cycle temperature, etc. It is therefore exceedingly important to be acquainted with the parameters of the batteries used and the installation operating characteristics.

An Ingecon® Hybrid MS unit executes the charge and discharge cycles according to the parametersconfigured.Theinstallerandheadofmaintenancearethereforeresponsibleforensuringthatthesaidconfigurationisappropriateandthattheenvironmentalconditionsare maintained within the recommended parameters, to avoid damage to the battery and to prevent premature ageing.

- High temperatures accelerate the chemical processes, reducing the battery life.

- High charge voltages lead to the corrosion of the positive pole.

- Low charge currents and long periods with no complete charge, create sulphates on the electrolyte.

- Rapid, incomplete charges can lead to cell imbalance.

-Ifthefloatvoltageistoohigh,itwillcausealossofelectrolyte.

- Long equalization cycles performed at a high temperature will lead to a loss of electrolyte.

In any case, you are recommended to carefully read the manual for the batteries in the installation and consult the battery manufacturer about any doubts you may have.

The Ingecon® Hybrid MS units are equipped with a multi-stage battery charger. This term refers to the different stages of the charging process: a constant current stage; a constantvoltageorabsorptionstage;andafloatchargestage.Thereisadditionallytheoption of an equalization charge stage.

Charge modes:

- Constant current charge. A constant charge current is applied until the battery reaches the absorption voltage value. The current will depend on the battery characteristics and the desired charge speed. It typically varies between C/10 and 2C.

- Constant voltage charge. Also called the absorption stage. A constant voltage is maintained at the battery terminals until the current decreases to reach 1/8 of the constant charge current. The battery can then be considered to be charged.

-Float.Oncethebatteryhasbeenfullycharged,itismaintainedatthefloatvoltage,thereby offsetting the self-discharge rate. Some batteries can be damaged if they are maintained in these conditions for long periods of time.

- Equalization. Charging at a constant, higher voltage in order to equalize the cell stateofchargeandcompensatetheelectrolytestratification.Thisproducesgassing.

Page 81: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 81 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

Thestatesofchargeshallbeadaptedtosuiteachbatterybyconfiguringanumberofparameters:chargecurrent;absorptionvoltage;floatvoltage;equalizationvoltageandtime.Thisdatacanbemodifiedinsitubyanyqualifiedperson.

Multi stage battery charging

Float

Voltage

Absorption

Current

Constant current

Page 82: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 82 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Signal requirements

During the back-up generator connection and operating process, a number of signals need to be sent and monitored, and these must be correctly wired (see the section on the back-up generator wiring).

- Order to start / stop the back-up generator. The main battery charger module shall enable the order for the remote start-up / shut-down of the back-up generator. For this purpose, there is a normally open (NO) potential free contact available and a normally closed (NC) potential free contact, in order to suit the requirements of each specificinstallation.

- Back-up generator voltage capture. The inverter module must read the voltage of the back-up generator (L1, L2, L3, N) in order to perform the correct synchronisation at the time of connection and supervise the subsequent operation.

Genset kit

OutputIngecon® Hybrid MS

AC consumption

14.3 GENSET Connection and operating modesThe Ingecon® Hybrid MS has an input to connect a back-up generator in order to guarantee supply at peak times or during renewable energy low production periods.

Note: the back-up generator can be any machine that generates a three phase voltage of an amplitude and frequency that is equal to that generated by the inverter. The conventional electricity grid can be connected as a back-up generator, although the equipment will not deliver power to the grid.

WARNING. During the connection with the back-up generator, the Ingecon Hybrid neutral must be prevented from being earthed. In such a case, a galvanic isolation transformer should be installed, to isolate the equipment neutral from the rest of the installation.

Although the Ingecon® Hybrid MS modules are designed to manage the back-up generator, external devices need to be installed for the power connection (Back-up Generator kit). These devices shall be dimensioned to suit the rated power of the installation and that of the back-up generator. They can either be supplied by INGETEAM ENERGY S.A. (chapter 8.1) or by the installer.

A four pole thermal magnetic breaker (IAM) is required to protect the back-up generator, a three pole contactor (KM1) with a normally open (NO) auxiliary contact and a terminal strip for the necessary connections.

Page 83: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 83 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

- Signal for the closure of the power contactor. When the voltage generated by the Ingecon® Hybrid MS is synchronised with that generated by the back-up generator, the inverter module enables a signal for the closure of the power contactor. This is a NO contact which should be wired to ensure that, when enabled, the contactor coil is powered at its rated voltage.

- Contactor closure signal. The power contactor to connect the back-up generator must have a NO auxiliary contact which, when wired to the inverter module, will indicate that the contactor has closed.

Operating sequence

The connection and disconnection of the back-up generator shall be performed as a result of the evaluation of a number of criteria which will be explained in detail in the next section.

If the connection of the back-up generator is required, then the main battery charger module shall enable the start-up signal.

From that moment onwards the Ingecon® Hybrid MS shall monitor the voltage generated by the back-up generator, waiting for it to comply with the established amplitude and frequency ranges (190V<Vrms<260V; rated FR ±5Hz).

Once the voltage read is correct and is held stable for 1 second, the process to synchronise the voltage generated by the Ingecon® Hybrid MS with that generated by the back-up generator shall be initiated. In other words, the Ingecon® Hybrid MS shall start to generate a voltage of the same amplitude, frequency and with the same phase as that of the back-up generator.

Once synchronised, the Ingecon® Hybrid MS gives the order to close the power contactor, and awaits the signal to indicate that this closure has been made.

Once the connection signal has been received from the contactor, the Ingecon® Hybrid MS inverter moves to a secondary level, and the loads are powered directly by the back-up generator.

Thesubsequentoperationwillonceagaindependontheconfigurationofeachinstallation:

- With a battery charging power equal to zero (parameter 406), the Ingecon® Hybrid MS will monitor the voltage generated by the back-up generator but will not manage it and will practically play no part in the AC side of the installation. It will only retake control of the AC voltage if it detects a fault in the back-up generator before the order to disconnect is given. In this status, all the power from the renewable sources shall be used to charge the batteries.

- With a battery charging power other than zero (parameter 406), the Ingecon® Hybrid MSshallfunctionlikeaback-upgeneratorload,andshallgointotherectifiermodeinordertochargethebatterieswiththepowerconfigured.Inthisstatus,thepowerfromthe renewable energy sources shall also be used to charge the batteries.

Clarification.Theconfiguredchargingpowerisactuallytheback-upgeneratormaximumbattery charging power limit. The maximum battery charging power shall be limited bythechargingcurrentconfigured(parameter002),whichmustneverbeexceeded.Account should be taken of the fact that part of this current will come from the renewable energies and the rest will be taken from the back-up generator (value of parameter 406 asamaximumvalue).Thegeneratorchargingpowershouldbeconfiguredtoensurethat, in a situation of maximum consumption at the installation, the back-up generator is not overloaded.

To avoid supply problems, it is advisable to have a back-up generator power rating that is double the equipment power rating.

Page 84: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 84 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

When the back-up generator is to be disconnected, the Ingecon® Hybrid MS orders the contactor to open, and undertakes the AC voltage generation and powers consumption. Subsequently, the order to shut-down the generator will be given.

Connection criteria

Theconnectionanddisconnectioncriteriafortheback-upgeneratorareeasilyconfigurable.Anyqualifiedpersoncanmodifythemtosuittherequirementsofaparticularinstallation.

Connection criteria:

• Manual start-up

• Time setting

• Battery state of charge

• High consumption (only with the INGETEAM ENERGY S.A. wattmeter)

• Battery equalization

Note: It will not be possible to connect the back-up generator through the Ingecon® Hybrid MS if the latter is in error status. In order to be able to connect the back-up generator, the Ingecon® Hybrid MS must be correctly generating AC voltage. In the event of an Ingecon® Hybrid MS error, the back-up generator must be started manually and connected to the loads through a bypass contactor.

Manual start-up

(Menu Extras/ Back-up start-up)

This parameter can be used to give a manual order to start-up the back-up generator, regardless of other criteria.

The generator will remain on until the manual start-up is disabled from this same screen (it will only disconnect if there are no other criteria requiring it to be connected).

Time setting

(Parameters 409-410, 411-412, 413-414)

The back-up generator can be connected for a set time. The times set shall be maintained for all the days of the week and can be changed at any moment. This functionality guarantees, on a daily basis, a minimum battery charge and / or can serve to supply loads at peak consumption times.

Parameters 409 and 410: back-up generator start-up time.

Parameters 411 and 412: back-up generator disconnection time. If, at this time, the batterystateofchargeisbelowthestateofchargeconfiguredforparameter408,thentheback-upgeneratorshallremainconnecteduntilthedefiniteshut-downtime(parameters413 and 414).

Parameters413and414:Definiteshut-downtimefortheback-upgenerator,providingthat the other criteria allow this.

Thedisconnectiontimecanbeconfigured(parameters411and412)tobeequaltothedefiniteshut-downtime(parameters413and414),andtherebyhaveasingleshut-downtime, regardless of the battery state of charge.

Page 85: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 85 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

Battery state of charge

(Parameters 407, 408)

The back-up generator shall always start-up when the battery state of charge is below a configuredvalue(parameter407),therebyprotectingthebatteriesfromdeepdischarges.

Thegeneratorwillremainonuntilthebatterystateofchargereachesthelevelconfiguredwith parameter 408.

High consumption

(Parameters 416, 417, 418, 419)

Important note: To be able to start-up the back-up generator due to high consumption, the installation needs to be equipped with the INGETEAM ENERGY S.A. wattmeter in order to measure the power generated by the back-up generator.

If the installation is equipped with the INGETEAM ENERGY S.A. wattmeter (optional component) then the order can be given to start-up the back-up generator at times of high consumption, thereby mitigating the effect of consumption peaks on the battery bank or in order to supply loads that are greater than the equipment rated power. In this latter case, the back-up generator must be dimensioned to supply the loads.

The wattmeter is a device which measures the power delivered by the back-up generator when connected, giving information on the installation power consumption at all times.

In general terms, the back-up generator will start-up if the consumption is high (higher thanaconfigurablevalue),andwillremainonforaminimumtimeof10minutesandwillthenshut-downwhenconsumptionislowerthananotherconfigurablevalue.

There are two ways to connect the back-up generator for high consumption:

- Instantaneous connection. The connection is made if an instantaneous consumption greater than the value of parameter 416 is detected. If required, this connection can be configuredtobemadeonlyifthesaidconsumptionismaintainedforatimeperiodwhichisconfigurablethroughparameter417.

- 60 second timed connection. The connection will be made if a consumption greater than the value of parameter 418 is detected for one minute.

Anumberofparametersmustbeconfigured:

Parameter 416: Value of the current, above which the back-up generator will start-up due to high consumption. This parameter is given as a percentage and is applied to the inverter ratedcurrentandtothebatterydischargecurrent.Ifduringaspecifictime(parameter417) the inverter AC current exceeds this % of its rated current in any of the phases or thebatterycurrentexceedsthis%ofthevalueconfiguredasthemaximumdischargecurrent (parameter 003), the order shall be given to connect the back-up generator.

Parameter 417: Connection dwell time. This is the time during which the inverter or battery current must remain above the value of parameter 416 in order to order the connection of the back-up generator. This must be programmed taking into account the start-up peaks required for motors and similar machinery in order to avoid the undesired connection of the back-up generator in this situation.

Parameter 418: Value of the current above which the back-up generator is connected due to high consumption. This parameter is given as a percentage and is applied to the inverter rated current and to the battery discharge current. If during one minute the inverter AC current exceeds this % of its rated current in any of the phases or the battery currentexceedsthis%ofthevalueconfiguredasthemaximumdischargecurrent,theorder shall be given to connect the back-up generator.

Parameter 419: Power supplied by the back-up generator and which permits the generator disconnection. This parameter is given as a percentage and is applied to the back-up generator rated power. To disconnect the generator, the power consumed by the loads

Page 86: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 86 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

must be less than this % of the generator rated power.

Note: These parameters are not applicable if the INGETEAM ENERGY S.A. wattmeter has not been installed.

Battery equalisation

(Parameter 415)

Optionally, it is possible to force the back-up generator to start-up in order to perform a battery equalisation charge.

The equalization charge can be required manually or after a certain number of charge cycles (parameter 009). In both cases the back-up generator can be programmed to remain connected until the equalization has been completed, ensuring that this charge is performed correctly.

If this option is not enabled, then the equalisation process will depend on the availability of the renewable energies.

Disconnection criteria

The back-up generator will disconnect once the cause of the connection order has disappeared and if there are no other criteria which require it to remain on.

Manual start-up

If the generator has been started-up manually, then it must be disconnected in the same way. The Ingecon® Hybrid MS will check the other criteria.

– Operation with a number of back-up generatorsSome installations require the use of a number of back-up generators in parallel. The Ingecon® Hybrid MS can read the connection of up to four generators.

Observations:

- The Ingecon® Hybrid MS will give a single order to start-up the back-up generator. The selection of the generator to be started-up is a task that is external to the Ingecon.

- The Ingecon® Hybrid MS will give a single order to close the power contactor. The selection of the contactor to be closed is a function that is external to the Ingecon.

- The start-up, synchronisation and parallel connection of the other generators shall be performed with a control device which is external to INGETEAM ENERGY S.A. Thisdevicemustrecordtheoperatingpointofeachgenerator,forefficientoperation.

- At the time when the generator is disconnected, the Ingecon® Hybrid MS will send a single signal to the open the power contactor.

- At the time when the generator is shut-down, the Ingecon® Hybrid MS will send a single signal to shut-down the generator.

Page 87: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 87 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

OutputIngecon® Hybrid MS

Kit Genset 4

Kit Genset 3

Kit Genset 2

Kit Genset 1

AC Loads

Page 88: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 88 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

14.4 VOLTAGE GENERATION. LOAD CONNECTIONThere are a great variety of inverters used for off-grid installations, producing wave forms with different characteristics. Normally a distinction is made between inverters producing asquarewave,modifiedsinewaveorpuresinewave.Thelatteristhewavewhichmostresembles the AC voltage of the conventional electricity grid.

Square wave

Modified sine wave

Pure sine wave

V

The Ingecon® Hybrid MS units provide a pure sine wave voltage, thereby achieving the correct operation for the majority of the loads currently on the market.

In any case, it should not be forgotten that this is not a conventional electrical system in which the consumption of the installation is negligible compared to the grid capacity. We are dealing with an off-grid system, whose stability is compromised by the relationship between the power being consumed at any given time and the total power for which the system has been dimensioned. This should be taken into account when distributing loads, in order to try and avoid load interaction as much as possible.

It is also advisable to balance consumption in the three phases.

In some cases, it may be necessary to install starters or speed controllers to limit the start-up peak of motors, pumps, etc.

Page 89: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 89 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

NOTAS

Page 90: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 90 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

NOTAS

Page 91: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 91 de 92Ref.: AAR2000IKI02Rev.:_A Jan-2010

NOTAS

Page 92: INGECON HYBRID MS - Ingeteam Manual.pdfThe main module is also equipped with a 15kW MPPT PV input. Inverter module This module generates a pure sine wave three phase voltage, with

Installation ManualIngecon® Hybrid MS

Pg. 92 de92 Ref.: AAR2000IKI02 Rev._A Jan-2010

Ingeteam Energy S.A.www.ingeteam.com

Avda. Ciudad de la Innovación, 1331621 Sarriguren (Navarra)

Tel +34-948 288 800Fax +34-948 288 801

http://www.ingeteam.com