Page 1: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Information Management Consortium

CMBHS IT Program

HHSC Program & IT Applications-CMBHS

January 30 & February 01, 2019

Page 2: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Agenda

1. Complete Roadmap Phase II

2. Home and Community Based Services-Adult Mental Health (HCBS-AMH) Automation

3. Change Requests and Release Planning

4. Electronic Visit Verification (EVV)

5. ICD-10 Annual Updates

6. LTSS Referrals

7. LOC-R Issues (BECL, CANS, ANSA)

2/7/2019 2

Page 3: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

CMBHS Complete Roadmap Phase II

2/7/2019 3

Prashant Gupta

Page 4: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Complete Roadmap Phase-IIDeployment Milestones

2/7/2019 4

Initiative & Change Request Deployment MilestonesDeployment

Date%

Complete

Deploy IPC & Provider Setup Accessibility Fixes 11/27/2017 100%

Deploy YES Assessment CANS, CE and Consent 01/12/2018 100%

Deploy CR -114-Modifications to Inpatient Care Waitlist 01/12/2018 100%

Deploy CR -112- Modifications to PPI Screening 04/02/2018 100%

Deploy CR -111- Modifications to Close Case Screen 04/02/2018 100%

Deploy CR -110 - New Life Event Notes Screen 05/11/2018 100%

Deploy CR -106 - Associate provider with regions 05/11/2018 100%

Deploy CR -056 - SUD Data Downloads 10/05/2018 100%

Deploy CR -098 – Option to print Consent in Spanish 10/05/2018 100%

Deploy CR -078 - Court Ordered Commitments Changes 01/25/2019 100%

Deploy new BO reports for RSS Program (10 reports)

……………………………………………….Set #1 (2 reports) 11/16/2018 100%

……………………………………………….Set #2 (1 reports) 01/25/2019 100%

……………………………………………….Set #3 (3 reports) 03/08/2019 30%

……………………………………………….Set #4 (2 reports) 04/19/2019 15%

……………………………………………….Set #5 (2 reports) 05/31/2019 15%

Deploy CR -039 – Limit Payments of Claims not Compliant with Service Delivery Requirements

04/19/2019 35%

Deploy SUD Medicaid Billing Changes 05/31/2019 25%

Page 5: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Complete Roadmap Phase-IIDeployment Milestones

2/7/2019 5

Initiative & Change Request Details (1 of 6)

1. IPC & Provider Setup Accessibility Fixes - Objective is to make online IPC and Provider Setup Section 508 compliant. (Deployed on 11/25/2017)

2. YES Assessment CANS, CE and Consent –

2a. New YES Assessment Child and Adolescent Needs and Strengths (CANS) online - Introduces the new CANS Assessment for the YES Waiver Program.

2b. Modification of Clinical Eligibility business rules -Enhancement to the Clinical Eligibility to link with the new YES Assessment CANS.

2c. Consent Modifications - Enhancement to the Consent to display the new YES Assessment CANS. (Online only).

(Deployed on 1/12/2018)

Page 6: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Complete Roadmap Phase-IIDeployment Milestones

2/7/2019 6

Initiative & Change Request Details (2 of 6)

3. CR 114-Modifications to Inpatient Care Waitlist -Add two new questions (Higher level of care needed? and Meets mental health civil commitment criteria?) to the Inpatient Care Waitlist Entry and the Inpatient Care Waitlist.

(Deployed on 1/12/2018)

4. SA Data Downloads - Contracted SUD providers can download records during business hours in XML or EXCEL format using a new online request in CMBHS. Will also enhance existing download functionality.

(Iteration #1 (5 Features Deployed on 1/12/2018);

(Iteration #2 (9 Features Deployed on 6/22/2018);

(Iteration #3 (25 Features Deployed on 8/03/2018);

(Final Iteration #4 (3 Features Deployed on 10/05/2018)

Page 7: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Complete Roadmap Phase-IIDeployment Milestones

2/7/2019 7

Initiative & Change Request Details (3 of 6)

5. CR 112-Modifications to Pregnant & Postpartum Intervention (PPI) Screening- The objective is to add a few new questions and associated business rules to the PPI screen. (Deployed on 4/2/2018)

6. CR -111- Modifications to Close Case – Add 3 new questions to Close Case when the case type is PPI Case Management. New questions:

▪ Did the client’s children receive all recommended well-child visits?

▪ Client reports abstinence at close case from PPI Program?

▪ Is client’s family currently involved with DFPS CPS?

(Deployed on 4/2/2018)

Page 8: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Complete Roadmap Phase-IIDeployment Milestones

2/7/2019 8

Initiative & Change Request Details (4 of 6)

7. CR 110 - New Life Event Notes Screen - Implement a non-billable Life Event Note to collect PPI data .

(Deployed on 5/11/2018)

8. CR 106 - Associate provider with regions - Associate provider organizations with regions and counties so data can be easily and accurately retrieved for reporting purposes. (Deployed on 5/11/2018)

9. CR 098 - Option to Print a Consent in Spanish –Build a Spanish translated printout of the Consent so clients with limited English proficiency can better understand what they are signing. (Deployed on 10/05/2018)

Page 9: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Complete Roadmap Phase-IIDeployment Milestones

2/7/2019 9

Initiative & Change Request Details (5 of 6)

10. SUD Medicaid Billing – Deploy prior authorization and claims processing for Medicaid SUD Fee for Services clients. (Scheduled for 5/31/2019)

11. CR 078 - Court Ordered Outpatient Commitment –Add a page in CMBHS for Local Mental Health Authorities (LMHAs) to report information related to non-criminal outpatient court-ordered commitment(s) information for mental health treatment.

(Scheduled for 1/25/2019)

Page 10: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Complete Roadmap Phase-IIDeployment Milestones

2/7/2019 10

Initiative & Change Request Details (6 of 6)

12. CR -039 - Limit Payment of Claims Not Compliant with Service Delivery Requirements- Implement new business rules and screen changes whereby the CMBHS system will not pay contracted SUD providers for services they are not delivering as required by contract.

(Scheduled for 4/19/2019)

13. Deploy new BO reports for the Recovery Support Service (RSS) Program - The objective of this initiative is design and develop 10 new BusinessObject reports for the RSS Program.

(1st release on 11/16/18, 2nd release on 1/25/19, 3rd

release on 3/8/19, 4th release on 4/19/19, 5th release on 5/31/19) .

Page 11: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Release Schedule for the BO Reports for RSS Program

2/7/2019 11

S. No

Report Name IterationRelease

Date

1RSS Active Participants Overview - Enrollment Report

1 11/16/2018

2 RSS Client Status Notes Report 1 11/16/2018

3 RSS Intensity of Need Report 2 1/25/2019

4RSS Upcoming and Overdue Recovery Checkups Report

3 3/8/2019

5 RSS Missing Recovery Plan Report 3 3/8/2019

6RSS Participants in Pre-Enrollment Status Report

3 3/8/2019

7 RSS Recovery Coach Load Report 4 4/19/2019

8 RSS Closed Case Report 4 4/19/2019

9 RSS Documents in Draft Status Report 5 5/31/2019

10 RSS Demographic Summary Report 5 5/31/2019

Page 12: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Home and Community Based Services-Adult Mental Health

(HCBS-AMH) Automation

2/7/2019 12

Thuhang Tran

Page 13: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

HCBS-AMH Automation

2/7/2019 13

Project Insights:

▪ Home and Community Based Services - Adult Mental Health (HCBS-AMH).

▪ The HCBS-AMH Program was created in response to a mandate from the 83rd Texas Legislature.

▪ This project will automate the business processes of the HCBS-AMH program in the CMBHS system.

▪ The functionality will allow HCBS-AMH providers to use CMBHS to document required client information for the HCBS-AMH program and submit claims for payment.

Page 14: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

HCBS-AMH Automation

2/7/2019 14

Project Activities:

• The Program team is reviewing forms (Individual Recovery Plan, Safety Plan, Respite Relative Provider Forms, Provider Selection/Enrollment, etc.)

▪ Identifying what will be automated into CMBHS

▪ How it will look and workflows

• IT Planning - Project Delivery Framework Documents

▪ Obtaining approvals to start project and procure contractor resources

Page 15: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

HCBS-AMH AutomationDeployment Milestones

2/7/2019 15

Initiative Deployment MilestonesDeployment

Dates%

Complete

Project start date 09/01/18 100%

Budget approval 10/15/18 100%

QAT approval letter for resource solicitation 01/31/19 0%

Resource hiring and onboarding 02/01/19 0%

Requirements elicitation sessions 03/28/19 0%

Requirements sign off and approval 03/29/19 0%

Iterative: design, development, testing 09/09/19 0%

Vendors system changes and verification [90 days. Online & Batch - (5/31/19-8/31/19)]

09/09/19 0%

User acceptance test (UAT) with SMEs 10/13/19 0%

UAT with providers, system interface group 10/13/19 0%

Regression test 11/15/19 0%

Acceptance to deploy 11/16/19 0%

IT Go/No-Go 11/21/19 0%

Deployment 12/06/19 0%

Stabilization - Warranty support 02/28/20 0%

Project closeout 02/28/20 0%

Page 16: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Change Request and Release Planning

2/7/2019 16

Latha Kaliyur

Page 17: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Change Requests - Deployed

2/7/2019 17

Change Requests Status

CR #

TFS #

DescriptionRelease

Date

131 13850

YES Waiver 95-Day Limit: This change request enables the providers to create Service Notes and submit claims with Service Dates 95 days past the date of service, via batch and online process, to TMHP, so that HHSC IT is not required to do data insertion or extraction to remediate claims denied by TMHP for being 95 days or older.

Deployed on 11/16/2018

179 16335Medication Service Billing and Medication Orders for Buprenorphine/Naloxone Sublingual Film.

Deployed on 12/14/2018

Area: Change Request and Release PlanningManager: Latha Kaliyur

Objectives – Plan, analyze, estimate and execute the change requests prioritized by BHS Program area staff and other internal customers.

Page 18: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Change Requests - In Progress

2/7/2019 18

Change Requests Status

CR # TFS # Description Release Date

0185 16416 Order of Qualifying Diagnosis TBD

Area: Change Request and Release PlanningManager: Latha Kaliyur

Objectives – Plan, analyze, estimate and execute the change requests prioritized by BHS Program area staff and other internal customers.

Page 19: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Electronic Visit Verification (EVV)

2/7/2019 19

Courtney Seals

Page 20: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Electronic Visit Verification (EVV)

2/7/2019 20

21st Century Cures Act

▪ Scope of Impact

o Personal Care Services – January 1, 2020

o Home Health Services – January 1, 2023

▪ Impact to Behavioral Health Services

o Youth Empowerment Services (YES) waiver:

✓ In-Home Respite

o Home and Community-Based Services –Adult Mental Health (HCBS-AMH):

✓ In-Home Respite and Supported Home Living

Page 21: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

Texas EVV Implementation Project

2/7/2019 21

▪ Soft Launch/Evaluation Group

o Broadcast #337

o January 2019-March 2019

o Biweekly feedback session – focused on use of the current EVV system

▪ Next Steps

o Test claims processes tentatively scheduled for June 15-August 2

o Update policy, rules, and contracts

o Launch in September 2019

o Deadline 1/1/2020

Page 22: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

EVV Communications

2/7/2019 22

21st Century Cures Act Webpage• https://hhs.texas.gov/doing-business-hhs/provider-

portals/long-term-care-providers/resources/electronic-visit-verification/21st-century-cures-act

EVV Alerts via GovDelivery• https://service.govdelivery.com/accounts/TXHHSC/subs

criber/new

EVV Toolkit

• Monthly alerts (1st and 15th) and Q&A webinars (22nd), FAQs

EVV Operations Team

[email protected].

Page 23: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

ICD-10 Annual Updates

2/7/2019 23

Jackie Webster

Page 24: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

LTSS Referrals

2/7/2019 24

Robyn Strickland

Page 25: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

LOC-R Issues

2/7/2019 25

Kathleen Fairchild

Page 26: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones

LOC-R Issues (BECL, CANS, ANSA)

2/7/2019 26

Fixes

Defect #

DescriptionRelease

Date

16906Non-Qualifying issues with CANS LOC-R Logic

Jan. 25th

2019

16907

Child and Adolescent Uniform Assessment LOC Calculation error (partly related to 16906 and related to CR185)

Jan. 25th

2019

16908LOC calculating to LOC -1 but should be a higher calculation (related to CR185)

Jan. 25th

2019

Page 27: Information Management Consortium CMBHS IT Program€¦ · Prashant Gupta. Complete Roadmap Phase-II Deployment Milestones 2/7/2019 4 Initiative & Change Request Deployment Milestones