Industrial Wastewater Requirements for Concrete Batch Plants. Yanisa Angulo and Ilia Balcom Industrial Wastewater Program DEP Southwest District. SWD IW Jurisdiction. Citrus, Desoto, Hardee, Hernando, Hillsborough, Manatee, Pasco, Pinellas, Polk, Sarasota, Sumter, and west Marion County. - PowerPoint PPT Presentation

Transcript of Industrial Wastewater Requirements for Concrete Batch Plants

Page 1: Industrial Wastewater Requirements for Concrete Batch Plants

Industrial Wastewater Requirements for Concrete

Batch PlantsYanisa Angulo and Ilia BalcomIndustrial Wastewater Program

DEP Southwest District

Page 2: Industrial Wastewater Requirements for Concrete Batch Plants

SWD IW Jurisdiction

Citrus, Desoto, Hardee, Hernando, Hillsborough, Manatee, Pasco, Pinellas, Polk, Sarasota, Sumter, and west Marion County

Page 3: Industrial Wastewater Requirements for Concrete Batch Plants

Why do we care about Concrete Batch Plants

(CBPs)?Primary concern is contaminated storm water and interior truck mixer drum wash- out water.

Page 4: Industrial Wastewater Requirements for Concrete Batch Plants

Why do we care about Storm Water?

In general, storm water can contain high levels of contaminants.*sediments, nutrients, heavy metals,

pathogens, toxins, oxygen demand For CBP pollutants of concern are: pH,

suspended solids (TSS), petroleum hydrocarbons (TRPH) and specific conductance.

Page 5: Industrial Wastewater Requirements for Concrete Batch Plants

Two “Types” of Wastewater (Contaminated Storm Water &

Process Wastewater)Type I Wastewater Includes:

*Contact storm water (Exposure areas)*Runoff from aggregate piles (process)*Washdown water not including interior

mixer drum washout (process)

Page 6: Industrial Wastewater Requirements for Concrete Batch Plants

Type I WastewaterWashdown water

*Water sprayed for dust control (process)*Does not include equipment washing or

truck undercarriage washing (process)*Includes washing of exterior of mixer

trucks and mixer truck chutes, or other washing operations (slump racks, etc.)

Page 7: Industrial Wastewater Requirements for Concrete Batch Plants

Type II WastewaterWastewater generated from the washout of

the interior of a concrete truck mixer drum and any water that comes into contact with this wastewater.

Excludes reclaimed Type II wastewater used to spray aggregate piles.

Page 8: Industrial Wastewater Requirements for Concrete Batch Plants

Permit CoverageRule 62-621.300(3)(a), F.A.C.

Permit coverage is under Chapter 62-621.300(3)(a), F.A.C., effective May 1997.

http://www.dep.state.fl.us/water/wastewater/iw/docs/62-621.300_3a.pdf

Need to meet the permit criteria. Coverage is for 5 years.

An application of renewal of coverage is required to be submitted 180 days prior expiration of the current permit coverage.

Page 9: Industrial Wastewater Requirements for Concrete Batch Plants

Two Types of CBP Systems Existing: In operation before May 1996

Includes Unpermitted Existing Systems Unpermitted existing systems were covered

under the voluntary consent order that required to obtain permit coverage after construction of system was completed.

New: In operation after May 1996 Currently there are 137 permitted CBPs in the

SWD

Page 10: Industrial Wastewater Requirements for Concrete Batch Plants

The difference in requirements between New

and Existing CBP New - Basically the storm water treatment

requirements for wet detention/retention systems are more stringent.

New - Must account for non contact storm water. Non-contact storm water includes those areas on the site that do not have exposure to industrial pollutants (roof runoff, parking areas, etc).

Page 11: Industrial Wastewater Requirements for Concrete Batch Plants

Requirements of a Permit Application

Notice of Intent to Use Generic Permit for Discharges from Concrete Batch Plants, DEP Form 62-621.300(3)(b)

$500 Application FeeEngineering Report signed and sealed by a

Professional Engineer registered in Floridahttp://www.dep.state.fl.us/water/wastewater

/forms.htm

Page 12: Industrial Wastewater Requirements for Concrete Batch Plants

What Does CBP GP Require? Retain Type II wastewater and runoff from Type

II area up to 25-year/24-hour storm. Control/Treat Type I Wastewater and Storm

water with Wet Detention or Dry Retention Ponds.

Implementation of Wastewater and Storm water Management Practices (WSMP).

Page 13: Industrial Wastewater Requirements for Concrete Batch Plants
Page 14: Industrial Wastewater Requirements for Concrete Batch Plants

Engineering Report Includes Description of Type I, Type II, and non-contact

stormwater management systems and how they operate.

Description of how solids are handled, used or disposed of.

Description of close-loop vehicle/equipment wash facility, if applicable.

Site plan indicating existing and proposed wastewater and stormwater management systems, drainage basins, direction of flow, and discharge points, receiving waters, pervious and impervious areas.

Page 15: Industrial Wastewater Requirements for Concrete Batch Plants

Engineering Report Includes (Cont.)

Design Criteria:Calculation of designed daily Type I and Type II flow, stormwater runoff calculations,Design stormwater an sources of dataStage/storage calculationsPercolation rate determination

Page 16: Industrial Wastewater Requirements for Concrete Batch Plants

Paving, Grading, Drainage Plan

Page 17: Industrial Wastewater Requirements for Concrete Batch Plants

Type II System

Page 18: Industrial Wastewater Requirements for Concrete Batch Plants

Type II System Design Requirements – (New and Existing

Facilities) Impermeable containment Contain produced Type II wastewater plus direct rainfall into

and storm water runoff from Type II area, resulting from 25-yr, 24-hr storm events

No direct discharge from the Type II system to groundwater or surface waters

Runoff from ribboning area should be directed to the type II System

Overflow from the Type II system shall discharge to a Type I system or an emergency holding pond only as a result of rainfall in excess of the 25-yr, 24-hr storm event.

Page 19: Industrial Wastewater Requirements for Concrete Batch Plants

Ribboning

Page 20: Industrial Wastewater Requirements for Concrete Batch Plants

Type I System

Page 21: Industrial Wastewater Requirements for Concrete Batch Plants

Type I System Design Requirements – (Existing

Facilities) Wet detention

Sediment trap(s), mostly constructed of concreteOffline wet detention to treat first ½ inch of runoff from Type I area plus produced Type I wastewaterDrawdown (control) device: orifice, v- or square-notch weirOverflow device: standpipe or weirOne-half of the treatment volume is recovered within the first 48-60 hours following a rain event

Page 22: Industrial Wastewater Requirements for Concrete Batch Plants

Type I System Design Requirements (Cont.)

Dry RetentionThe retention system must retain produced Type I wastewater plus one of the following:– runoff from 10-year, 24-hr storm – runoff from the first 1-inch of rainfall – the first ½ inch of runoff

Demonstrate recovery of system storage capacity within 72 hrs following any runoff producing event through percolation to ground water and evaporation

Page 23: Industrial Wastewater Requirements for Concrete Batch Plants

Type I System Design Requirements (New Facilities)

Wet detention-Off line wet detentionSediment trap(s)Offline wet detention to treat first ½ inch of runoff from Type I areaOne-half of the treatment volume is recovered within the first 48-60 hours following a rain eventDrawdown(control)device: orifice, v-or square-notch weir Overflow device: standpipe or weir

Page 24: Industrial Wastewater Requirements for Concrete Batch Plants

Type I System Design Requirements– New Facilities

(Cont.) Final Wet Detention

One-half of the treatment volume is recovered within the first 48-60 hours following a rain eventDetain and treat the discharge from the off-line system and runoff from the type I area and non-contact storm water area of the siteDrawdown (control) device: orifice, v-or square-notch weirOverflow device: standpipe of weir

Page 25: Industrial Wastewater Requirements for Concrete Batch Plants

Type I System Design Requirements – New

Facilities (Cont.) Dry Retention

The retention system must retain run off from the Type I area of the site, including all produced Type I wastewater and runoff from non-contact area resulting from 10-year, 24-hr stormDemonstrate recovery through percolation to ground water and evaporation

Page 26: Industrial Wastewater Requirements for Concrete Batch Plants

Type I System Design Review – New Facilities (Cont.)

Pre vs. Post-developmentPost-development rate of discharge of storm water runoff must not exceed pre-development rate of discharge for –A 25-yr, 24-hr storm event or –A 100-yr, 24-hr storm event for a closed drainage

basin

Page 27: Industrial Wastewater Requirements for Concrete Batch Plants

Wastewater and Storm Water Management Plan (WSMP)

WSMP identifies storm water pollution prevention and Best Management Practices (BMPs).

Pollution prevention includes things like clean up of petroleum/hydraulic fluid spills and other spills. Use of low volume wash waters for wash down and reuse (there have been some innovative designs).

Page 28: Industrial Wastewater Requirements for Concrete Batch Plants

Wastewater and Storm Water Management Plan (WSMP) –

Cont. Pollution prevention is required to prevent the

discharge of contaminants from storm water related events.

BMPs include on-site procedures and practices implemented to ensure long term operation and maintenance for storm water and Type II systems.

Page 29: Industrial Wastewater Requirements for Concrete Batch Plants

Wastewater and Storm Water Management Plan (WSMP) –

Cont. BMPs include practices for beneficial reuse of

Type I and Type II solids and wastewater. BMPs include proper procedures for solids

disposal. The WSMP specifies how often Type I and Type

II systems must be inspected, and inspections shall be documented on the WSMP.

BMPs should address ribboning practices, including rain events

Page 30: Industrial Wastewater Requirements for Concrete Batch Plants

Sweeping Requirement Facilities shall prevent or minimize the discharge of spilled

cement, aggregate (including sand or gravel), kiln dust, fly ash, settled dust and other significant materials in stormwater from paved portions of the site that are exposed to stormwater. Measures used to minimize the presence of these materials may include regular sweeping, or other equivalent measures. The plan element shall indicate the frequency of sweeping or other measures. The frequency shall be determined based upon consideration of the amount of industrial activity occurring in the area and frequency of precipitation, but shall not be less than once per week when cement, aggregate, kiln dust or fly ash are being handled or otherwise processed in the area.

Page 31: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance Evaluation Inspections

Inspections conducted on an annual basis. Inspectors evaluate compliance with permit

requirements, including record keeping and operation and maintenance.

DEP is required to conduct unannounced inspections.

Inspections can also be initiated by a complaint.

Page 32: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems General

Failure to apply for renewal of permit coverage as required (180 days prior expiration).Failure to submit abandonment plant prior to closure of a facility and inactivation of a permitFailure to construct the treatment systems in accordance with the permit requirements or as designed.

Page 33: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.) Record Keeping Issues:

Failure to have a copy of the permit on-site.Failure to have a copy of the “as-builts” (engineering drawings) on-site.Failure to develop a Wastewater and Storm Water Management Plan (WSMP) as required. Or, if developed, WSMP was not on-site, or not updated.Failure to implement WSMP.

Page 34: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.) Recordkeeping Issues (Cont.)

Failure to conduct inspections required by the WSMP. If conducted, failure to properly document them (complete checklists).Lack of training of on-site personnel regarding WSMPs and CBP permit requirements.Failure to submit completion of construction and record drawing notification forms.

Page 35: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.) Type II system Issues:

Improper handling of truck wash water and other wash waters.Improper dewatering of Type II solids.Spills as a result of cleaning sediment pits.Spills as a result of cleaning Type II systems.Unauthorized overflows (discharges) from the Type II system caused by lack of maintenance.Co-mingling of Type II and Type I wastewater

Page 36: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 37: Industrial Wastewater Requirements for Concrete Batch Plants
Page 38: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 39: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 40: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 41: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 42: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.) Type I System Issues:

Failure to clean sediment pits.Failure to clean out solids from storm water ponds.Clogging of outlet structures in the storm water ponds.Failure to address erosion control in storm water ponds.Excessive vegetation that affects the pond’s performance and hinders inspection of berms.Unpermitted discharges due to loss of capacity or breached berms.

Page 43: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 44: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 45: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 46: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 47: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 48: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.)

Page 49: Industrial Wastewater Requirements for Concrete Batch Plants

Compliance issues for Existing/New Permitted

Systems (cont.) Although a CBP operating under the Generic Permit is

not required to sample, the facility must meet applicable ground and surface water quality standards. If for some reason there isn’t reasonable assurance that the facility can meet standards, samples may be required to ensure that BMPs, WSMPs, and systems were adequately designed. Main pollutants of concern include: pH, turbidity, TSS (suspended solids), TRPH (petroleum hydrocarbons), and specific conductance.

Page 50: Industrial Wastewater Requirements for Concrete Batch Plants

Potential Penalties associated with violations of the Generic Permit

The Department has the statutory authority to impose fines for up to $10,000 per day.

Under the Environmental Litigation Reform Act, the following amounts apply to specific violations:

Unpermitted Discharge: $2,000 if no violations of water quality standards, $5,000 if violations of water quality standards.Failure to install, maintain or operate a pollution control device: $4,000.Failure to submit required notification: $1,000.Failure to prepare, maintain, submit or use required reports or other documentation $500 .These amounts could be higher if the violation occurs more than one time (multi-day) or if there is a history of non-compliance.

Page 51: Industrial Wastewater Requirements for Concrete Batch Plants

Resources Available EPA Office of Water Web page has

*Storm water BMP for industrial facilities*Other storm water web links

DEP has a web site: www.dep.state.fl.us*Rules and regulations for Water Resource

Management Program, etc. Our office is always available for assistance

Page 52: Industrial Wastewater Requirements for Concrete Batch Plants

SWD IW DEP Contacts http://www.dep.state.fl.us/southwest/contacts The DEP inspector assigned to the County

where the facility is located. Phone Number: (813) 632-7600

Page 53: Industrial Wastewater Requirements for Concrete Batch Plants

DEP Tallahassee Contacts Allen Hubbard- Industrial Wastewater

Administrator (850) [email protected]

Abel Agosto - CBP Coordinator (850) [email protected]

Page 54: Industrial Wastewater Requirements for Concrete Batch Plants