Indian Power Grid Developments - Mississippi State …...India’s first local manufacture of GIS up...
Transcript of Indian Power Grid Developments - Mississippi State …...India’s first local manufacture of GIS up...
Rathin Basu
March 25th 2015
Indian Power Grid Developments
Country President, Alstom Grid,
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 18/03/2015 – P 2
kV
1990 1950 1960 1970 1980
35~ 110kV
220 kV
330 kV
500 kV AC/DC
2000
1200 kV
2005
1100 kV
765kV
750kV
800 kV HVDC
2011
2012
154 kV
765kV
220 kV
KOREA
CHINA
INDIA
400 kV
Evolution of Voltage level of Indian Grid…
Anticipated the evolution &
Timely Investment in
Indian Facilities
2013
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 18/03/2015 – P 3
Grid in 2011
South Grid
South
West
North
East
Northeast
Till 1991
5 Regional Grids
5 Frequencies
October 1991
East & Northeast
synchronized
March 2003
West synchronized
with East & Northeast
August 2006
North synchronized
With Central Grid
Central Grid
World’s Largest
Syncronised Grid
259 GW
Dec.’14
31st Dec’13
One Country
One Grid
One Frequency
Milestones towards One Country-One Grid - One Frequency
44 GW of Inter Regional Transfer
29 of 50 substations @ 765kV
3 HVDC Back to Back stations
National Load Dispatch Centre
3 Regional Load Dispatch Centre
National Transmission Asset Management Centre
(under commissioning)
Worlds largest Wide Area Monitoring Project
(under execution)
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 18/03/2015 – P 4
Building India’s Transmission Grid EHV/UHV AC backbone for increasing Power Flow
- 29 out of 50 Substations @ 765 kV AC have Alstom Grid technology
Establishing India’s Power Backbone @ 765 kV ● Established India’s first 765 kV project at NTPC Sipat ● Maximum 765kV AC (EHV) substation orders awarded to Alstom Grid ● 29 out of 50 substations to have Alstom Products
● India’s first local manufacture of 765 kV power transformer ● India’s first local manufacture of GIS up to 400 kV ● India’s first local manufacture of 1200 kV CVT for Power Grid Bina
testing station
India’s first 765 kV SS
at NTPC Sipat 765 kV substations built
India’s first locally
manufactured 400 kV
GIS
India’s first locally
manufactured 1200 kV
CVT for Power Grid
Note: EHV - Extra High Voltage (765 kV)
UHV - Ultra High Voltage (1200 kV)
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 18/03/2015 – P 5
Building India’s Transmission Grid 800 kV HVDC links for increasing Power Flow & Reactive Power Control
HVDC Projects In India ● Pioneer in Inter-Regional Power bulk power transfer by building 3
Back-to-Back HVDC projects ● In addition to the transmission of real power between the regions, the
links provided also perform a reactive power control role, which helps to stabilize the network voltage.
● 2,000 MW Voltage level: 500 kV
- 3 Back to Back HVDC built by Alstom Grid
- 2 Large HVDC each of 800 kV / 3000 MW under execution
Chandrapur:
1000 MW interconnection
between the Western and
Southern networks
Visakhapatnam:
500 MW interconnection
between the Eastern &
Southern networks
Sasaram, India:
500 MW interconnection
of the Eastern and
Northern networks
HVDC links by Alstom Grid
HVDC Convertor Station at
Sasaram
HVDC Thyristors at
Chandrapur
800 kV/3,000 MW HVDC
Champa-Kurushetra
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 18/03/2015 – P 6
Strong Leadership in Network Management System in India
3 out of 5 Regional Load Dispatch Centre
4 out of 4 National Load Dispatch Centers in India,
Bangladesh, Bhutan and Sri Lanka (under execution).
National Load dispatch center for India handles 136 GW
of power flow.
Load Dispatch Centers at Bangladesh and Bhutan handle
100 % of power flow in the respective countries.
NTAMC, world’s largest Remote Asset Management
project (under commissioning)
URTDSM, World’s largest wide area monitoring project
(under execution)
70% of India’s Transmission Grid Power flow is managed by Alstom Grid technology
NLDC, India NLDC, Bangladesh NLDC, Bhutan Regional Load Dispatch Centers
(RLDC) by AG
National Load Dispatch Center
(NLDC) by AG
NLDC Bangladesh
NLDC Bhutan
NLDC
NLDC Sri Lanka
Backup National Load Dispatch
Center (BNLDC) by AG
Regional Load Dispatch Centers
by 3rd party
SRLDC
NERLDC NRLDC
WRLDC ERLDC
Bkup NLDC
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 18/03/2015 – P 7
NTAMC (Under Commissioning) – National Transmission Asset Management Centre
By Implementing NTAMC & ULDC, Power Grid has
segregated the Operation & Asset Management
functions with a common set of field measurement
devices
Access Control, Visual Monitoring, Video
Conferencing, IP Telephony integrated into system
Objectives met by NTAMC:
Enable unmanned remote maintenance operation
of transmission assets
Redeploy & optimise skilled resources at
maintenance hubs & reduce administrative costs
Remote fault finding/analysis - reduced down time
SRLDC
NERLDC NRLDC
NLDC
NLDC Bhutan
NLDC Bangladesh WRLDC ERLDC
Regional Load Dispatch Centers
(RLDC) by AG
National Load Dispatch Center
(NLDC) by AG
NLDC Sri Lanka
Backup National Load Dispatch
Center (BNLDC) by AG
Regional Load Dispatch Centers
by 3rd party
NTAMC by AG
Backup NTAMC by AG
RTAMC by AG
NTAMC
Bkup NTAMC
Bkup NLDC
Integrated World’s Largest Transmission Asset Management System Involving 192 Grid Substations
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 18/03/2015 – P 8
URTDSM (Under Execution) – World’s Largest Wide Area Monitoring Project
PMUs located at State Sector
Substations
PMUs located at Power Grid
S/S, Central Sector S/S
PMUs located at State Sector Sector
Substations
OFC Cloud
PMUs located
at IPPs
Super PDC at NLDC Super PDC at Bkup NLDC
Project to integrate ~1400 PMUs to the
Grid Control Centres
To enhance Grid Stability thru closer
monitoring of Phasor Angle differences
and the state of damping of low signal
oscillations
Maximise Power Flow
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 18/03/2015 – P 9
Benefits Power Grid India’s Technology Road Map
Power Grid can leverage Alstom Grid’s local world class manufacturing facilities of both EHV &
UHV AC-DC Technologies for bulk power transport across India’s five electrical regions which is
expected to reach ~66 GW by 2017.
This industrialisation to help Power Grid,
Manage the largest synchronised grid in the world (installed capacity of 259 GW)
Deal with Power transport between India and neighbouring countries in India Region
To manage significant increase of Grid Interactive renewable power generation, from 13%
(33.8 GW) today to 21% by 2022
Digital Substation technology for AIS & GIS have demonstrated a paradigm shift in,
Reduction in copper use and size of bay
Safety considerations
Engineering & implementation time of bays and
Enabling wide area protection and control
Decade Ahead:
AC backbone to transit from 765 kV to 1200 kV
Expansion of HVDC for bulk power transport and reactive power control
Expansion of Digital Substation technology
Renewable Management to be part of Grid Control Centres
Smart Grid:
Transmission Grid already smart due to extensive deployment of technologies
Smart Distribution Grid thru Smarter Substations, Smart Power Quality Metering, Demand
Response and Storage technologies
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 18/03/2015 – P 10