India RE Markets and impact of REC Mechanism
-
Upload
yasir-altaf -
Category
Documents
-
view
220 -
download
0
Transcript of India RE Markets and impact of REC Mechanism
-
8/7/2019 India RE Markets and impact of REC Mechanism
1/7
-
8/7/2019 India RE Markets and impact of REC Mechanism
2/7
IndiaRenewableEnergyMarketsandImpactofRECMechanismYasirAltafandPramodKSingh
14%
80%
2% 4%GenerationMix
23%
64%
3%10%
CapacityMix
Hydro Thermal Nuclear Renewable
Figure3:REcapacitymixandenergymixasofSeptember2010
at 17 GW, representing 10 percent of the total installed capacity. However, RE
generation is less than 4 percent of the total generation (Figure 3). Tax holidays,accelerated depreciation, and customs exemption given to the developers
resulted in capacity installation, but there was no additional monetary incentive to
generate from these plants. This led to little contribution of RE sources to the
total electricity mix.
Under the RPO, states fixed a percentage of electricity that their power
distribution companies (DISCOMS) need to buy from RE sources. The minimum
RPO level varied across the states with the available RE potential in the state.Some states defined resource wise target common for all DISCOMS, whereas
others had different targets for different DISCOMS. However, the RPO has not
been able toachieve the level of capacity addition when compared to the vast
technical potential available in the country. The main shortcomings in the state
level RPO scheme were the following.
o Higher RE potential states such as Rajasthan, Karnataka, and TamilNadu had no incentives to look beyond their RPO targets.
o States such as Delhi, Punjab, and Haryana could not apply RPO due tothe non-availability of RE sources.
o Limited flexibility to market participants to buy and sell renewablepower.
o No financial liability or penalty for non-fulfillment of the RPO. OnlyMaharashtra and Rajasthan have shortfall clause in place but it gets
rendered ineffective since mandatory purchase of RE energy issubjected to availability of RE based power
Hence, there was a need for a mechanism that could facilitate inter-state
exchange of power generated from RE sources
SellingEntities
REGenerators
Power
BilateralPrice
ExchangePrice
AveragePowerCost
ExchangePrice
ObligatedEntities:DISCOMS
OpenAccessCustomer
CaptiveUser
RECPower+REC
ObligatedEntities:DISCOMS
OpenAccessCustomer
CaptiveUser
AnyCustomer
Feedintariffs
Figure4:ModesforREtransactionsunderRECregulations
-
8/7/2019 India RE Markets and impact of REC Mechanism
3/7
-
8/7/2019 India RE Markets and impact of REC Mechanism
4/7
IndiaRenewableEnergyMarketsandImpactofRECMechanismYasirAltafandPramodKSingh
In the initial years of REC scheme, easier to implement and low cost RE sources are expected to lead capacity additions. However, less endowed and more costly
technologies would be taken up in the later years. In light of these possible developments, the REC prices would therefore increase in future as the scheme progresses not
only due to the increased renewable energy targets in the later years and but also due to the exhaustion of cheaper and easier to implement resources in the initial year.
Figure7:Keychallengesfacingthedevelopersimmediatelyandintheforeseeablefuture
-
8/7/2019 India RE Markets and impact of REC Mechanism
5/7
-
8/7/2019 India RE Markets and impact of REC Mechanism
6/7
-
8/7/2019 India RE Markets and impact of REC Mechanism
7/7
IndiaRenewableEnergyMarketsandImpactofRECMechanismYasirAltafandPramodKSingh
Transmission
capacity
Entry and exit
decisions,
Capacity builds
POWER WORLD
TM
GE-PSLFTM
IPM
Power
Markets
Environment
Markets
Fuel
Markets
Transmission
interface limits
Illustrative outputs:
REC price forecasts
RE Capacity additions
Target off-taker states for power & RECs
Capacity under short and long termcontracts
Plant dispatch analysis
Load Flow and Congestion Analysis
Transmission Losses
Transmission flows, congestion
Grid impact on dispatch
Asset value
Figure10:
ICFs
customized
suite
of
modeling
tools
and
integrated
analysis
providesforrobustindustryassessment
Although, the effectiveness of REC mechanism for mobilizing new investments
into the RE sector would be tested, but global experience suggests that REC can
be a facilitator in development of new renewable potential. Regulators will have a
greater role to play to ensure renewable development by proper implementation
and monitoring of the REC system, as envisaged. A larger role for RE with
supporting REC markets will definitely help India achieves the objectives of theenergy security and emission reductions in the longer term.