India Infrastructure Jun10

download India Infrastructure Jun10

of 20

Transcript of India Infrastructure Jun10

  • 8/6/2019 India Infrastructure Jun10

    1/20

    This product has been prepared in collaboration with Feedback Ventures. Refer page 20 for details.BNP Paribas research is available on Thomson Reuters, Bloomberg, and on http://equities.bnpparibas.com.Please contact your salesperson for authorisation. Please see the important notice on the inside back cover.

    THINK TANK SERIES

    In collaboration with Feedback Ventures

    June 2010

    Ind ia Transpor t In f ras t ruc t ure B igger

    oppor t un i t ies , t ougher qua l i f ica t ions

    We are witnessing an increase in the average project size, tightening of pre-

    qualification norms and unfavorable geographical concentration of highway

    projects. Although the aggregate opportunity size remains about INR1.9t,

    cherry-picking the right project is gaining importance. IRB Infrastructure has won

    only 3% market share year to date, implying cautious bidding. IL&FS

    Transportation Networks has captured the highest share, at 9%.

    Our analysis of recent bids reveals that some smaller players were veryaggressive bidders. Competition remains fragmented, implying a positive effect

    from the changes recommended by the B K Chaturvedi Committee. We expect

    this trend to reverse in the case of mega projects (tighter restrictions).

    The Dedicated Freight Corridor (DFC) is the next biggest opportunity in the

    railways segment (INR650b). The progress has been slow with only two partial

    stretches having been awarded so far. Partial financing has been tied up with

    multilateral agencies and a Japanese agency. Land acquisition remains the

    biggest challenge. L&T should be a major beneficiary in our sector coverage.

    Finally, metro projects are showing some progress. Hyderabad Metro (INR121b)

    will be re-bid in July 2010. Two other projects Jaipur (INR75b) and Pune

    (INR79b) are on the anvil. L&T and Reliance Infrastructure could be major

    beneficiaries of these opportunities.

    Vishal Sharma, CFA

    BNP Paribas Securities India Pvt Ltd

    (91 22) 6628 2441

    [email protected]

    Shashank Abhisheik

    BNP Paribas Securities India Pvt Ltd

    (91 22) 6628 2446

    [email protected]

    PREPARED BY BNP PARIB AS SECURITIES ASIA THIS MATERIAL HAS BEEN APPROVED FOR U.S DISTRIBUTION. IMPORTANT DISCLOSURES CAN BE FOUND IN THE DISCLOSURES APPENDIX.

  • 8/6/2019 India Infrastructure Jun10

    2/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    2 BNP PARIBAS

    Contents

    1) Changes in national highway business opportunity............................ ................................................................... ................. 3Change in average project size of the balance NH pipeline........... ..................................................................... ................ 3Change in pre-qualification norms............................. ................................................................ .......................................... 3Change in geographical concentration.................................................. ...................................................................... ........ 3

    2) Project pipeline: Is it getting riskier? ......................................................... ..................................................................... .......... 4What are the naxal-affected areas? .................................................... ........................................................................ ........ 4Why is this issue a big deal? ..................................................... ........................................................................ .................. 4Who is affected? What to watch out for?................................... ......................................................................... ................. 4How to tackle the issue? What are the steps taken by the government? ...................................................... ...................... 4

    3) Analysis of recent bids ........................................................ .......................................................................... ............................. 5Annuities versus Tolls ...................................................... ....................................................................... ............................ 5Fragmented competition........................................... ....................................................... .................................................... 5Are the bids aggressive?............... ........................................................ ..................................................................... ......... 6

    4) Dedicated Freight Corridor.................................. ............................................................ ........................................................... 8Project administration........... ........................................................... .......................................................................... .......... 8Dedicated freight lines.......... ....................................................... ..................................................................... ................... 8Logistic parks ..................................................... ........................................................... ...................................................... 8Funding ......................................................... ............................................................ .......................................................... 9Technologically advanced................................................... .................................................................... ............................ 9Projects awarded ................................................... ........................................................ ..................................................... 9Major challenges ................................................... ........................................................... ................................................... 9

    5) Metro projects................................................. ............................................................ ............................................................... 11Hyderabad metro .................................................... ....................................................... ................................................... 11Jaipur metro .......................................................... ......................................................................... ................................... 12Pune metro.......................................... ....................................................... ....................................................................... 12

    6) About Feedback Ventures ....................................................... ........................................................................ ......................... 14

    Looking for an alternative way to invest i n the views and themes covered in thisreport? Explore BNP Paribass

    Asia Pacific Sector Swap

    Covering eight key markets and 13 sectors, Sector Swap gives investors all the tools t o

    profit from macro events, including long and/or short Sector Swaps as well as options

    strategies.

    Available on Bloomb erg at BNSW [GO]

    Winner Lee, Asia Equities Derivatives Strategist; +852 2108 5658; [email protected]

    Please see India Research Team list on page 15.

    Cover page pictures courtesy:

    Mumbai Metro I - Reliance Infrastructures

    Mumbai Monorail Larsen and Toubro

    Naini-Allahabad Bridge HCC with Hyundai E&C

  • 8/6/2019 India Infrastructure Jun10

    3/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    3 BNP PARIBAS

    Changes in nat ional h ighw ay bus iness oppor t un i tyThe national highway (NH) opportunity for developers is changing rapidly. The changes

    can be categorised along the following:

    Change in average pro ject s ize of the balance NH pipel ineAn analysis of NHAI projects with bid dates in the months of May and June 2010

    indicates that the average project size is increasing. The average project length is

    150kms (compared with the 100kms for last year) and average project cost is above

    INR9b.

    In the current pipeline, there are at least five projects with project sizes of above

    INR20b. Very few Indian players are likely to qualify for projects of this size, allowing

    larger players a higher chance of winning such projects.

    Change in pre-qual i f icat ion normsRecent changes in the pre-bid qualification criteria of the NHAIs concessions have

    altered the scenario for Indian players considerably. In line with expectations of more

    stringent technical and financial requirements, the method of calculating the technical

    and financial scores of consortiums has been changed.

    The new method requires taking a weighted average of scores (technical and financial)

    in proportion to the equity share for each member in a consortium. This means that thesize of the players and their credentials need to be substantially bigger to fit the bill.

    The magnitude of the change can be understood from the fact that, for a INR50b

    project, in the past two players with a combined technical score of 5,000 would have

    sufficed; now in the most favourable scenario, the combined technical score would have

    to be 5,000, multiplied by the number of members in the consortium. This means that

    the requirement for financial and technical scores for a consortium has gone up by a

    factor equal to (or greater than) the number of members in it.

    We estimate only 10-15 Indian players have more than 2,500 technical points on their

    own to qualify for projects of INR25b. This means that rest of the players would need to

    form consortiums with larger players to bid for large projects and competition in these

    projects would be limited.

    Change in geographica l concentrat ionThe remaining opportunities in the highways development program are getting

    concentrated with filtered projects. Some of these opportunities did not attract bids in

    the initial rounds, due to the non-viability of the projects or they were located in the

    disturbed areas, where it becomes difficult to execute projects. We discuss this in detail

    in the next section of this report.

  • 8/6/2019 India Infrastructure Jun10

    4/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    4 BNP PARIBAS

    Projec t p ipe l ine: Is i t get t ing r isk ier?Incidents such as the Dantewada (Chattisgarh) Maoist attacks raise questions about

    the implementation of the infrastructure development program in India. We analyze this

    with respect to transport infrastructure specifically. Naxal activities (terrorist activities)

    affect development in two ways: 1) they create challenges in acquiring land (one of the

    biggest impediments in infrastructure development); and 2) make the work environment

    dangerous for workers, repelling private contractors from these regions.

    What are the naxal-af fected areas?Naxal-affected areas in India are notified by the Central Government under the Terrorist

    Affected Areas (Special Courts) Act 1984. Accordingly, the Central Government has

    identified 131 districts that are at least marginally naxal-affected, of which 51 are

    severely affected and 18 moderately affected. The government notifies an area as

    naxal affected based on the gravity of the (terrorist) offence. The states that are

    particularly affected are Andhra Pradesh, Chattisgarh, Jharkhand, Jammu & Kashmir,

    North-eastern states, parts of West Bengal, Orissa, Bihar, Karnataka, Madhya Pradesh,

    Maharashtra and Tamil Nadu.

    Why is th is issue a b ig deal?As long as there were projects available in attractive, higher-growth regions of India,

    projects in naxal-affected areas did not get sufficient bidder interest. Consequently, asignificant portion of the projects that are going to be awarded now, especially in

    highways sector, are in these areas. For instance, 2,800kms (23% or INR280b) of

    NHAIs Work Plan I and 6,000kms (50% or INR600b) of Work Plan II are in the naxal-

    affected areas. Separately, two of the UMPPs that have yet to be bid out are in the

    states of Orissa and Chattisgarh (one each). Additionally, in the railway sector, parts of

    the Dedicated Freight Corridors (Eastern) pass through these areas, which will likely to

    create impediments in land acquisition.

    Who is a f fec ted? What t o w atc h ou t fo r?Private developers that take up projects in these areas face issues in executing them.

    On the positive side, profitability in these projects is typically higher than average.

    Investors should judge historical success of execution of such projects before choosing

    to invest in a specific developer. Hindustan Construction (HCC IN, CP: INR117,REDUCE) is one of the developers that has expertise in executing projects in these

    areas.

    How to t ack le t he issue? What a re the s teps tak en by thegovernment?In almost all infrastructure projects, the onus of land acquisition is on the government.

    Private developers typically start work after the possession of land has been given.

    However, in certain cases, we believe effective execution of the project is ensured if the

    private developer works with the government in educating the benefits of development

    and inclusive growth. For instance, in highways, the NHAI has the option to award the

    projects on BOT-Toll or BOT-Annuity or EPC basis. In naxal-affected areas, the choice

    is typically annuity (eliminates traffic risk) or EPC (eliminates ownership risk) contracts.

    Therefore, by reducing or eliminating certain risks from the projects, NHAI can still

    award these projects and ensure development in the naxal-affected areas.

  • 8/6/2019 India Infrastructure Jun10

    5/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    5 BNP PARIBAS

    Analysis o f r ecent b ids

    Annui t ies versus Tol lsWe analyze 3,611kms of highway project awards worth INR417b (43 projects) since

    November 2009. The average cost per kilometer for these projects is INR99m and the

    average cost per lane kilometer is INR23m. Annuities comprised 28% of the highway

    universe by length and 34% by value, implying that the average cost of annuity projects

    was higher than the toll awards.

    Exhibit 1: Share By Length During Nov 2009-Jun 2010 Exhibit 2: Share By Value, During Nov 2009-Jun 2010

    Toll

    72%

    Annuity

    28%

    Toll

    66%

    Annuity

    34%

    Sources: NHAI; BNP Paribas Sources: NHAI; BNP Paribas

    Fragmented compet i t ionCompetition in the market remains fragmented. The highest market share was garnered

    by IL&FS Transportation Network (ILFT IN, CP: INR289; Not rated) with a 9% share of

    the total awards in the universe. Nagarjuna Construction (NJCC IN, CP: INR188, BUY),Reliance Infrastructure (RELI IN, CP: INR1,188, BUY), Hindustan Construction, Soma

    (in consortium; not listed), Transtroy (in consortium; not listed), Navyuga (in consortium;

    not listed), and IVRCL (IVRC IN, CP: INR185, BUY)were other major gainers (5% or

    more market share). IRB Infrastructure (IRB IN, CP: INR276, BUY) bagged one project

    that translates into 3% market share.

    Exhibit 3: Fragmented Competition

    Soma-

    Isolux

    7%Transstroy

    6%

    SEL

    4%

    Shapoorji

    4%

    IRB

    3%

    Navyuga

    6%

    Oriental-

    Leighton

    5%

    Others (15)

    27%

    IL&FS

    10%NCC

    8%

    RELI8%

    HCC

    7%

    IVRCL

    5%

    Sources: NHAI; BNP Paribas

  • 8/6/2019 India Infrastructure Jun10

    6/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    6 BNP PARIBAS

    Are the b ids aggressive?We have classified the bids into three categories:

    1 Annuity-based projects: In these projects, the concessionaire receives a fixed

    amount (the bid amount) from the NHAI every six months (semi-annual payout) for

    the duration of the concession. There is no traffic risk in these projects for the

    concessionaire. We have compared the difference of the net present value of the

    winning bid and the next best bid as a proportion to the total project cost (TPC) todecide if the project was aggressively bid for.

    Exhibit 4: Annuity-Based Bid

    TPC Bidder Bid

    NPV

    of bid

    Variation in

    NPV of L1

    and L2

    Variation in

    NPV as % of

    TPC

    (INR m) (INR m) (INR m) (%)

    L1 Navyuga KPCL 2,450 37,820Quazigund-Banihal 19,870

    L2 Coastal SREI 3,334 51,46713,646 68.68

    L1 GPT Infraprojects/RDS Projects (annuity) 71 1,029Forbesganj - Jogbani 735

    L2 JKM Infra Projects Pvt Ltd. 100 1,450420 57.21

    L1 BSC-C&C 524 7,598Muzaffarpur - Sonbarsa 3,120

    L2 Madhucon 640 9,2801,682 53.91

    L1 Transstroy (I) Pvt Ltd 213 3,088

    Trichy-Karaikudi including Trichy bypass 3,740 L2 GVR Infra 344 4,988 1,899 50.79L1 Transstroy - OJSC consor 205 2,972

    Dindigul-Theni- and Theni-Kumli Sect 5,010L2 GVR Galfar 371 5,379

    2,407 48.04

    L1 Madhucon 654 9,483Chhapra - Hazipur 6,910

    L2 BSC & C&C 879 12,7453,262 47.21

    L1 Shapoorji 2,019 29,274Jammu to Udhampur 18,140

    L2 Gammon 2,350 34,0734,799 26.46

    L1 ILFS 3,175 46,035Chennai Nashri 25,190

    L2 Gammon 3,600 52,1986,162 24.46

    L1 SREI Gulfar 1,356 19,661Udhampur Ramban 9,710

    L2 BSC & C&C 1,499 21,7352,073 21.35

    L1 Pratibha 130 1,670Bhopal-Sanchi 2,090

    L2 JMC 157 2,017347 16.60

    L1 IL&FS 725 10,512Jorbat-Shillong (SARDP) 2,170

    L2 Oriental 739 10,715203 9.35

    L1 Ramky 1,348 19,545Srinagar Banihal 11,010

    L2 BSC & C&C 1,380 20,009

    464 4.21

    Sources: NHAI; BNP Paribas

    2 Toll-based projects bid on a grant to be received from NHAI: In these projects,

    the concessionaire would receive a grant from the NHAI during the construction

    period. This grant is to augment toll revenues, which were insufficient to provide an

    adequate return on the construction and other O&M costs. Here, the aggressive bid

    is the one where the difference between the winning bid and the next best bid as a

    proportion of the total project cost is higher than the average.

    Exhibit 5: Toll-Based Bids (Grant)

    TPC Bidder Bid

    NPV of

    bid

    Variation in

    NPV of L1

    and L2

    Variation in

    NPV as % of

    TPC

    (INR m) (INR m) (INR m) (%)L1 Transstroy - OJSC 1120 1,120

    Kar/Ker Border to Kannur 12,350L2 Patel KNR 3490 3,490

    2370 19.19

    L1 Transstroy 550 550Tirupathi-Tirutani-Chennai 5,700

    L2 IRB 1080 1,080530 9.30

    L1 Soma-Isolux 5640 5,640Varanasi - Aurangabad 28,480

    L2 Gammon-Macquarie 7140 7,1401,500 5.27

    L1 SEL 2736 2,736Bijapur-Hungund section of NH 13 7,480

    L2 GMR-Oriental 2799 2,79963 0.84

    L1 GMR-Oreintal (51:49) 3409 3,409Hungund-Hospet section of NH13 9,460

    L2 SEL 3476 3,47667 0.71

    L1 NCC 1240 1,240Dankuni-Baleshwar 20,340

    L2 Soma 1330 1,33090 0.44

    L1 Navayuga 612 612Hyderabad - Bangalore of NH 7 6,800

    L2 SEL 620 6208 0.12

    L1 Abhijeet 1392 1,392Barhi-Hazaribagh 3,980

    L2 -

    Sources: NHAI; BNP Paribas

  • 8/6/2019 India Infrastructure Jun10

    7/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    7 BNP PARIBAS

    3 Toll-based projects bid on a premium: In these projects, the toll revenues are

    adequate to compensate for the costs incurred on the project. Hence, the

    concessionaire agrees to share a fixed amount of money with NHAI in the first year

    of operations, which increases by 5% per annum throughout the concession

    period. In this case, the difference between the net present values of the winning

    bid and the second best bid as a proportion to the total project cost would indicate

    whether a bid has been aggressive.

    Exhibit 6: Toll Based Bids (Premium)

    TPC Bidder Bid

    NPV of

    bid

    Variation in

    NPV of L1

    and L2

    Variation in

    NPV as % of

    TPC

    (INR m) (INR m) (INR m) (%)

    L1 DLF-Gayatri (241) (2,333)Indore-Dewas 3,250

    L2 Ashoka Buildcon (51) (494)1,839 56.58

    L1 GVK (486) (4,619)Deoli - Kota 5,934

    L2 IRB (270) (2,566)2,053 34.60

    L1 IRB (1404) (14,023)Tumkur-Chitradurga 12,000

    L2 BSCPL (1271) (12,694)1,328 11.07

    L1 RELI (669) (6,475)Hosur Krishnagiri 9,300

    L2 Ashoka Buildcon (602) (5,826)648 6.97

    Sources: NHAI; BNP Paribas

  • 8/6/2019 India Infrastructure Jun10

    8/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    8 BNP PARIBAS

    Dedicat ed Fre ight Corr idor

    Pro jec t admin is t ra t ion A special purpose vehicle (SPV), Dedicated Freight Corridor Corp of India Ltd

    (DFCCIL), was set up in October 2006 to implement the Dedicated Freight Corridor

    project.

    While the design, construction and development will be done by DFCCIL, the

    operations will be handled by Indian Railways.

    The implementation will be in a combination of EPC and PPP models. Consultants

    have been appointed to finalize the framework for implementation.

    Dedicated f re ight l ines The project envisages construction of 2,800kms of rail corridor spanning seven

    states. The maximum length will be in Uttar Pradesh (UP) (37%). Total land

    required is 12,500 hectares.

    The DFC is divided into two Eastern Corridor and Western Corridor. The Eastern

    Corridor will connect Ludhiana (Punjab) and Son Nagar (Bihar) (1,279kms) and the

    Western Corridor will connect Dadri (UP) to Jawaharlal Nehru Port Trust, Mumbai(Maharashtra) (1,483kms).

    Beneficiaries are civil contractors, Larsen & Toubro (LT IN, CP: INR1,836, BUY) for

    civil, mechanical and electrical works), Kalindee Rail Nirman (KRNE IN; CP:

    INR133; Not rated), Texmaco (TXM IN, CP: INR133; Not rated), Stone India

    (STON IN; CP: INR54; Not rated), BEML (BEML IN, CP: INR1,036; Not rated),

    Titagarh Wagons (TWM IN, CP: INR379; Not rated), Kernex Microsystems (KMSI

    IN, CP: INR95; Not rated)and MIC Electronics (MICE IN, CP: INR41; Not rated).

    Log ist ic parks The DFC envisages setting up a complete supply chain that includes logistic parks

    located along railways. Multimodal Logistic Parks (MMLPs) are envisaged at

    selected locations along the DFCs.

    The locations for the logistic parks are Navi Mumbai, Vapi, Ahmedabad,Gandhidham, Jaipur, and Rewari on the Western Corridor and Ludhiana and

    Kanpur on the Eastern Corridor. This initiative will be through the Public Private

    Partnership (PPP) route. The total opportunity is worth INR200b.

    Beneficiaries are logistics companies such as Sical Logistics (SICL IN, CP: INR74;

    Not rated), World Windows Infrastructure (not listed), Container Corp of India

    (CCRI IN, CP: INR1,297; Not rated), DHL Logistics (not listed), Mahindra Logistics

    (not listed), Transport Corporation of India (TRPC IN, CP: INR117; Not rated),

    GATI (GTIC IN, CP: INR62; Not rated)and Adani Logistics (not listed).

    Exhibit 7: Implementation Phases Of The DFC

    Corridor Stretch Distance Expected Financing

    completion Institution amount Cost

    Western

    Phase I Rewari-Vadodara 920 kms 2009-16 JICA INR180b 0.20%

    Phase II Vadodara-JNPT 430 kms 2010-17

    Phase III Rewari-Dadri 140 kms 2010-17

    Eastern

    Phase IA Sonenagar-Mughalsarai na 2009-16

    Phase IB Mughalsarai-Khurja 710 kms 2010-16 World Bank INR125b (USD2.5b) 5.50%

    Phase II Khurja-Ludhiana 413 kms 2011-17

    Note: JICA: Japan International Cooperation Agency; ADB: Asian Development Bank; na: Not availableSources: DFCCIL; BNP Paribas

  • 8/6/2019 India Infrastructure Jun10

    9/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    9 BNP PARIBAS

    Funding DFCCILs most recent estimate of DFC is INR650b. This expenditure is likely to be

    funded in 2:1 debt-to-equity ratio.

    The sources of funds are the Ministry of Railways (MoR) internal generation,

    budgetary support, multilateral/bilateral agencies, PPP and debt.

    The World Bank has in principle approved USD2.5b for construction of theMughalsarai-Khurja stretch on the Western Corridor.

    The Asian Development Bank (ADB) has proposed to provide technical assistance

    of USD1.5b for feasibility study of the 430km of Ludhiana-Khurja stretch on the

    Western Corridor. Both loans are at an annual interest of 5.5%.

    JICA has committed to INR180b at 0.2% for funding 920kms stretch between

    Rewari and Vadodara on the condition that at least 30% of the total equipment is

    sourced from Japan.

    Technologica l ly advanced The DFC will employ technology that is more advanced than that used now. The

    corridor will be made of double lines with an upgraded design and dimensions of

    containers. The project aims to run double stack containers to carry goods such as

    passenger cars.

    The speed of the carriages will be enhanced to an average of 100kmph from the

    existing 50kmph.

    Increase in axle load from 23-25 tonnes to 32.5 tonnes and train load from 4,000

    tonnes to 15,000 tonnes.

    Train dimensions will increase (length to double to 1,500 meters, height increase

    from 4.26 meters to 7.1 meters, width from 3.2 meters to 3.66 meters).

    Pro jec ts aw ardedTwo major projects have been awarded on the Eastern Corridor:

    Soma Enterprises has been awarded an INR6.05b contract in February 2009.

    A consortium of B. Seenaiah and Co (not listed) and C&C Constructions (CCON

    IN; CP: INR243; Not rated)has been awarded a contract for INR7.81b.

    Major chal lenges Land acquisition is a major impediment. Examples, such as Kolkata Metro

    extension, Ajmer-Pushkar rail line and Munger Rail Bridge, are indicative of the

    challenges involved as these projects were delayed due to incomplete land

    acquisition. Additionally, land acquisition is much more difficult in crowded urban

    areas due to encroachments.

    The Indian Railways has special powers to acquire land for major infrastructure

    projects; a notification u/s 20E has been issued for acquisition of 6,000 hectares of

    land.

    Indian firms ability and capacity to execute large packages of specialized works inmechanized track-laying, electrification, and signalling work is limited.

  • 8/6/2019 India Infrastructure Jun10

    10/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    10 BNP PARIBAS

    Exhibit 8: Current Status Of DFC

    Corridor Stretch Distance Expected Current status

    CompletionWestern

    JICA funding available; land acquisition by mid-2011; civilcontractor selection by end-2011; testing & commission by 2016

    Loan agreement signed in March 2010 for 25% of commitment,tenders to be finalized by mid-2010

    Phase I Rewari-Vadodara 920kms 2009-16

    30% of the project cost to be spent on Japanese equipment.

    Phase II Vadodara-JNPT 430kms 2010-17 Land acquisition by mid-2011; civil contractor by end-2012;testing & commissioning by 2017

    Phase III Rewari-Dadri 140kms 2010-17 Land acquisition by mid-2011; civil contractor by end-2012;testing & commissioning by 2017

    Eastern

    Phase IA Sonenagar-Mughalsarai na 2009-16

    World Bank funding available, land acquisition to be completedby end-2010, Testing & Commission in 2016

    Loan agreement to be signed in September 2010

    Phase IB Mughalsarai-Khurja 710kms 2010-16

    Parsons Brinckerhoff India, Halcrow Group (UK), Wilbur Smithand Lee Associates appointed as consultants for systemdesign, bid document, and construction supervision for Khurja-Kanpur

    ADB funding proposed, land acquisition to be completed byend-2010, Testing & Commission in 2017

    Phase II Khurja-Ludhiana 413 kms 2011-17

    ADB appointed consultant submitted feasibility report inNovember 2009

    Sources: DFFCIL; BNP Paribas

  • 8/6/2019 India Infrastructure Jun10

    11/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    11 BNP PARIBAS

    Met ro p rojec t sThe previous editions of this newsletter have discussed contract awards in Kolkata,

    Bengaluru and Chennai metros which are being implemented on an EPC basis. This

    newsletter edition discusses two metro projects coming up on a PPP basis in Pune and

    Jaipur. We also provide an update on the Hyderabad metro, where financial bids are

    due in July 2010.

    Since the metro rail projects are not financially viable on their own, they need either

    viability gap funds (the Government typically allows a maximum grant of 40% of the

    project cost 20% from the Centre and 20% from the state) or bundling with real estate

    to enhance viability.

    Hyderabad and Jaipur are being planned as bundled metro rail and real-estate projects.

    Pune is likely to be awarded as a pure metro rail project, supported by grants from the

    Government and municipality.

    Hyderabad met roThis project was earlier awarded to a consortium of Maytas Infra (MAY IN, CP: INR205;

    Not rated), Navabharat Ventures (NBVL IN; CP: INR428; Not rated), Ital Thai of

    Thailand (ITD TB, CP: THB3; Not rated)and IL&FS (not listed) in July 2008.However,since the consortium failed to achieve financial closure in the stipulated period, thecontract was scrapped in July 2009, and is now being re-bid.

    Project length and features: Metro rail line of 71.16kms (fully elevated) and real

    estate development rights over 269 acres of land.

    Project cost: INR121.32b (metro rail component only).

    Short-listed bidders: The following bidders have submitted applications for pre-

    qualification for the project in response to the Global RFQ floated by Hyderabad Metro

    Rail. All eight bidders have pre-qualified for the RFP Phase of the project.

    Exhibit 9: Hyderabad Metro Short-listed Bidders

    Larsen & Toubro Ltd

    Lanco Infratech-OHL Concesiones SL consortium

    Reliance Infrastructure-Reliance Infocomm consortium

    Essar-Leighton-Gayatri-VNR consortium

    GVK-Samsung C&T Corporation consortium

    GMR Infrastructure Ltd

    Transstroy-OJSC Transstroy-CR 18G-BEML consortium

    Soma-Strabag AG (Austria) consortium.

    Source: Feedback Ventures

    Timelines (for bidding, construction and concession period):

    The bid for the project is due on 14 July 2010. The concession period is for 35 years,

    which includes five years for construction of the metro. The concession period is

    extendable by another 25 years.

    Alignment:

    Hyderabad Metro Rail Project consists of three corridors joining important locations in

    the Hyderabad Metropolitan Region:

    Corridor-I : Miyapur to L B Nagar: 29.87kms;

    Corridor-II : Jubilee Bus Station to Falaknuma: 14.78kms;

    Corridor-III : Nagole to Shilparamam: 26.51kms.

    Key risks:

    Political uncertainty regarding the fate of Hyderabad in the wake of the Telangana

    issue has increased the political risk associated with the project.

  • 8/6/2019 India Infrastructure Jun10

    12/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    12 BNP PARIBAS

    The high real estate component of the project, especially when Hyderabad real

    estate is in over-supply mode: The project envisages development of 269 acres of

    land to make it financially viable for investments.

    What the project would mean for the winning entity/consortium:

    Hyderabad Metro would be a prestigious project for the winning consortium. While the

    viability of the project largely rests on real estate development, the project would provelucrative for developers who are able to tap the potential of the real estate component.

    Ja ipur metroJaipur Metro Rail project was planned as a Government-funded project until recently,

    when it was decided to use the PPP model. The project has been in the limelight

    recently due to the political will shown by Chief Minister Ashok Gehlot to ensure that the

    project is expedited. A Comprehensive Mobility Plan (CMP) survey outcome indicates

    that the population of the Jaipur region would be 6.7m by the year 2031, with the peak

    hour vehicular trip increasing 2.8 times from the current level.

    Project length and features: 28.5kms in Phase I (6.5kms underground, while 22kms is

    elevated).

    Project cost: INR75.03b (metro rail component only).

    Likely bidders: The project has generated high interest among many developers,

    many being first-time entrants in the metro rail arena.

    Timelines:

    All surveys and DPR completed for project to be undertaken on EPC basis.

    Government decided to implement the project on PPP basis in April 2010; the

    Planning Commission has indicated a viability gap funding of 20% from the Centre

    if executed through the PPP route.

    Government is in the process of appointing a consultant for preparing the bid

    documents and managing the award transaction.

    The bid process is likely to commence in about six months.

    Key risks:

    With the recent shift to the PPP model of operation for the metro, the project may

    get delayed by at least a year as fresh proposals are to be submitted for the

    Central Government nod.

    Lack of agreement over the applicability of PPP model of operation for the Jaipur

    metro.

    Planning Commission had raised concerns about the expected traffic for the metro;

    only 19% of Jaipurs population depends on public transport for commuting, so

    shifting them to the metro would take a long time and there would be a smaller

    traffic load for the proposed rail service.

    What the project would mean for the winning entity/consortium:

    The project is likely to have very high dependence on real estate revenues higher

    than other metro rail projects due to lower fare box revenues. Hence, the project

    viability remains a question mark until more details about project structuring are

    announced.

    Pune met roThe Pune Metro project, conceptualized in 2006, has seen significant delays and local

    protests. With the current resolve of the Municipal Body to expedite the implementation

    process, the project is now likely to move faster.

    Pune Metro is currently being planned as a PPP project the proposed funding mix as

    given below.

  • 8/6/2019 India Infrastructure Jun10

    13/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    13 BNP PARIBAS

    Exhibit 10: Pune Metro SPV Planned Holding Structure

    Pune

    Municipal

    Corp

    10%

    State Govt

    20%

    Central

    Govt

    20%

    Private

    Parties

    50%

    Source: Ministry of Urban Development

    Project length and features: 42.5kms in Phase I; total envisaged length is 75.5kms (only

    5kms underground, with the balance being elevated).

    Project cost: INR78.97b for the first component of 31.5kms (metro rail component

    only).

    Likely bidders: Likely to witness very high interest levels, as this is likely to be a pure

    metro rail project (no bundling with real estate) supported by viability grant funds from

    the Government. Pune is also considered very attractive due to its rapid growth and the

    Pune-Mumbai development corridor.

    Timelines:

    The timelines are yet uncertain for the Pune Metro due to the various unresolved

    issues related to the project.

    The DPR is ready (and approved by the Maharashtra Government) for the corridor

    falling with the limits of the Pune Municipal Corporation (PMC). Pimpri-Chinchwad

    Municipal Corporation (PCMC) PCMC asked DMRC to prepare a DPR for the

    metro route falling within PCMC limits in March 2010. (Pimpri and Chinchwad are

    suburbs of Pune city, with much of the industrial activity concentrated here).

    Key issues and reasons for delay:

    Lack of agreement on cost sharing between PMC and PCMC.

    Public dissent regarding past proposals to award high FSI in regions surrounding

    the metro rail alignment.

    Public dissent on choice of technology: Proposed standard gauge to be imported at

    high cost as against broad gauge, which is already available in India. Lowercapacity of standard gauge trains means longer trains and, hence, longer

    platforms, stations and yards, resulting in higher cost.

    Assessed traffic not sufficient for Metro in the short term.

    Linear metro design for a city radial in shape.

    High number of intersections of tracks at various levels.

    What the project would mean for the winning entity/consortium:

    While we await the project contours to take final shape, Pune is a fast growing city and

    development of metro rail in the city would be an attractive project for the winning

    consortium.

  • 8/6/2019 India Infrastructure Jun10

    14/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    14 BNP PARIBAS

    About Feedback Ventur esFeedback Ventures is Indias leading integrated infrastructure services company, with a

    mission of Making Infrastructure Happen. Totally focused on infrastructure

    development, Feedback Ventures offers an integrated suite of services across the core

    and social sectors of infrastructure.

    Feedback is known for its innovative work and for operationalizing challenging projects

    in difficult locations. Some 17 of Indias 50 biggest listed companies are Feedbacks

    clients. So are the governments 22 of the 28 Indian states and 4 of Indias 7 Union

    Territories.

    Feedback Ventures is presently working on more than 35,000 MW of new power

    generation capacity; 20,000 km of National and State Highways; 100,000 acres of real

    estate development and a building area of more than 22 million square feet.

    Feedback is enabled by a large pool of multidisciplinary experts; cutting-edge functional

    and domain knowledge; an all-India network of offices; and a strong shareholding

    L&T, IDFC, and HDFC.

    Feedback Venture Product Offerings

    Feedback offers:An INTEGRATED SUITE OF SERVICES covering all the steps

    From Concept to Commissioning

    FEEDBACK WORKS ACROSS ALL CORE AND SOCIAL SECTORS OF INFRASTRUCTURE

    Transportation & Logistics

    Highways

    Railways

    MRTS

    Ports

    Airports

    Logistics

    Energy

    Power Generation

    Power Transmission

    Power Distribution

    Power Trading

    Power Regulation

    Coal

    Oil and Gas

    Realty & Townships

    Water & Sanitation

    SEZs

    Hospitals

    Urban Planning &

    Development

    IT Parks, Offices,BuildingsHotels, Clubs, Convention

    Centres

    Feedback today has Indias largest independent group of multi-disciplinary

    infrastructure professionals. The team comprising planners, architects, engineers,

    social and environmental scientists, and MBAs is considered the best in the industry.

    Having the right mix of experience and expertise with a commitment to stay ahead of

    the competition has made Feedback the most admired infrastructure services company.

  • 8/6/2019 India Infrastructure Jun10

    15/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    15 BNP PARIBAS

    Ind ia Research Team

    MANISHI RAYCHAUDHURIHead of India ResearchBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    GAUTAM MEHTAAssociateBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    KARAN GUPTAMetals & MiningBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    VISHAL SHARMA, CFAInfrastructure - E&CBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    SHASHANK ABHISHEIKInfrastructure - E&C (Associate)BNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    AVNEESH SUKHIJAReal Estate (Associate)BNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    LAKSHMINARAYANA GANTICapital Goods/CementBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    CHARANJIT SINGHCapital Goods/Cement (Associate)BNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    GIRISH NAI RUtilitiesBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    AMIT SHAHOil & GasBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    SRIRAM RAMESHOil & Gas (Associate)BNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    ABHIRAM ELESWARAPUTech - ITBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    AVINASH SINGHTech - IT (Associate)BNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    SAMEER NARINGREKARTech - TelecomBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    KUNAL VORA, CFATech - Telecom (Associate)BNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    VIJ AY SARATHI, CFAFinancial ServicesBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    ABHISHEK BHATTACHARYAFinancial Services (Associate)BNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    JOSEPH GEORGEConsumerBNP Paribas Securities India Pvt Ltd+91 22 6628 2452

    [email protected]

    MANISH A GUPTAConsumer (Associate)BNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

    ANMOL GANJOOHealthcareBNP Paribas Securities India Pvt Ltd+91 22 6628 [email protected]

  • 8/6/2019 India Infrastructure Jun10

    16/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    16 BNP PARIBAS

    NOTES

  • 8/6/2019 India Infrastructure Jun10

    17/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    17 BNP PARIBAS

    NOTES

  • 8/6/2019 India Infrastructure Jun10

    18/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    18 BNP PARIBAS

    NOTES

  • 8/6/2019 India Infrastructure Jun10

    19/20

    VISHAL SHARMA, CFA INDIA TRANSPORT INFRASTRUCTURE 22 JUNE 2010

    19 BNP PARIBAS

    D I S C L A I M E R S & D I S C L O S U R E S

    ANALYST(S)

    Vishal Sharm a, CFA, BNP Paribas Securi t i es India Pvt Lt d, +91 22 6628 2441, vishal.sharm [email protected] s.com .

    Shashank Abh ishe ik , BNP Par ibas Secur i t ies Ind ia Pvt L td , +91 22 6628 2446,

    shashank .abhisheik @asia.bnppariba s.com .

    This report was produced by a member company of the BNP Paribas Group (Group)1. This report is for the use of intended recipients only and

    may not be reproduced (in whole or in part) or delivered or transmitted to any other person without our prior written consent. By accepting thisreport, the recipient agrees to be bound by the terms and limitations set out herein.

    The information contained in this report has been obtained from public sources believed to be reliable and the opinions contained herein areexpressions of belief based on such information. No representation or warranty, express or implied, is made that such information or opinions isaccurate, complete or verified and it should not be relied upon as such. This report does not constitute a prospectus or other offering document oran offer or solicitation to buy or sell any securities or other investments. Information and opinions contained in this report are published for referenceof the recipients and are not to be relied upon as authoritative or without the recipients own independent verification or taken in substitution for theexercise of judgement by the recipient. All opinions contained herein constitute the views of the analyst(s) named in this report, they are subject tochange without notice and are not intended to provide the sole basis of any evaluation of the subject securities and companies mentioned in thisreport. Any reference to past performance should not be taken as an indication of future performance. No member company of the Group acceptsany liability whatsoever for any direct or consequential loss arising from any use of the materials contained in this report.

    The analyst(s) named in this report certifies that (i) all views expressed in this report accurately reflect the personal views of the analyst(s) withregard to any and all of the subject securities and companies mentioned in this report and (ii) no part of the compensation of the analyst(s) was, is,or will be, directly or indirectly, related to the specific recommendation or views expressed herein.

    This report is prepared for professional investors and is being distributed in Hong Kong by BNP Paribas Securities (Asia) Limited to persons whosebusiness involves the acquisition, disposal or holding of securities, whether as principal or agent. BNP Paribas Securities (Asia) Limited, a

    subsidiary of BNP Paribas, is regulated by the Securities and Futures Commission for the conduct of dealing in securities, advising on securitiesand providing automated trading services. This report is being distributed in the United Kingdom by BNP Paribas London Branch to persons whoare not private customers as defined under U.K. securities regulations. BNP Paribas London Branch, a branch of BNP Paribas, is regulated by theFinancial Services Authority for the conduct of its designated investment business in the U.K. This report may be distributed in the United States byBNP PARIBAS SECURITIES ASIA or by BNP Paribas Securities Corp.

    Where this report has been distributed by BNP PARIBAS SECURITIES ASIA it is intended for distribution in the United States only to majorinstitutional investors (as such term is defined in Rule 15a-6 under the Securities Exchange Act of 1934, as amended) and is not intended for theuse of any person or entity that is not a major institutional investor. Where this report has been distributed by BNP Paribas Securities Corp, a U.S.broker dealer, it will have been reviewed by a FINRA S16 qualified registered supervisory analyst or a S24 qualified and authorized person, inaccordance with FINRA requirements concerning third party affiliated research.

    All U.S. institutional investors receiving this report should effect transactions in securities discussed in the report through BNP Paribas SecuritiesCorp. BNP Paribas Securities Corp. is a member of the New York Stock Exchange, the Financial Industry Regulatory Authority and the SecuritiesInvestor Protection Corporation. Reproduction, distribution or publication of this report in any other places or to persons to whom such distribution orpublication is not permitted under the applicable laws or regulations of such places is strictly prohibited.

    Information on Taiwan listed stocks is distributed in Taiwan by BNP Paribas Securities (Taiwan) Co., Ltd.

    Distribution or publication of this report in any other places to persons which are not permitted under the applicable laws or regulations of suchplaces is strictly prohibited.1

    No portion of this report was prepared by BNP Paribas Securities Corp personnel.

    D i s c l o s u r e a n d A n a l y s t C e r t i f i c a t i o n

    BNP Paribas represents that:

    Within the next three months, BNPP or its affiliates may receive or seek compensation in connection with an investment banking relationship withone or more of the companies referenced herein.

    The analyst(s) named in this report certifies that (i) all views expressed in this report accurately reflect the personal view of the analyst(s) withregard to any and all of the subject securities and companies mentioned in this report; (ii) no part of the compensation of the analyst(s) was, is, orwill be, directly or indirectly, relate to the specific recommendation or views expressed herein; and (iii) BNPP is not aware of any other actual ormaterial conflicts of interest concerning any of the subject securities and companies referenced herein as of the time of publication of the researchreport.

    R e c o m m e n d a t i o n s t r u c t u r eAll share prices are as at market close on 21 June 2010 unless otherwise stated. Stock recommendations are based on absolute upside(downside), which we define as (target price* - current price) / current price. If the upside is 10% or more, the recommendation is BUY. If thedownside is 10% or more, the recommendation is REDUCE. For stocks where the upside or downside is less than 10%, the recommendation is

    HOLD. In addition, we have key buy and key sell lists in each market, which are our most commercial and/or actionable BUY and REDUCE callsand are limited to at most five key buys and five key sells in each market at any point in time.

    Unless otherwise specified, these recommendations are set with a 12-month horizon. Thus, it is possible that future price volatility may cause atemporary mismatch between upside/downside for a stock based on market price and the formal recommendation.

    *In most cases, the target price will equal the analyst's assessment of the current fair value of the stock. However, if the analyst doesn't think the marketwill reassess the stock over the specified time horizon due to a lack of events or catalysts, then the target price may differ from fair value. In most cases,therefore, our recommendation is an assessment of the mismatch between current market price and our assessment of current fair value.

    R a t i n g d i s t r i b u t i o n ( a s a t 1 8 J u n e 2 0 1 0 )Out of 540 rated stocks in the BNP Paribas coverage universe, 353 have BUY ratings, 108 are rated HOLD and 79 are rated REDUCE. Withinthese rating categories, 1.85% of the BUY-rated companies either currently are or have been BNP Paribas clients in the past 12 months, 4.82% ofthe HOLD-rated companies are or have been clients in the past 12 months, and 6.33% of the REDUCE-rated companies are or have been clients inthe past 12 months.

    Should you require additional information please contact the relevant BNP Paribas research team or the author(s) of this report.

    2010 BNP Paribas Group

  • 8/6/2019 India Infrastructure Jun10

    20/20

    HONG KONG

    BNP Paribas Securities (Asia) Ltd63/F, Two International Finance Centre8 Finance Street, CentralHong Kong SARChinaTel (852) 2825 1888Fax (852) 2845 9411

    BEIJING

    Beijing Representative OfficeUnit 1618, South TowerBeijing Kerry Centre1 Guang Hua Road, Chao Yang DistrictBeijing 100020, ChinaTel (86 10) 6561 1118Fax (86 10) 6561 2228

    SHANGHAI BANGKOK

    (In cooperation with BNP Paribas)Thanachart Securities Public Co Ltd28/F, Unit A1 Siam Tower Building989 Rama 1 Road, PatumwanBangkok 10330ThailandTel (66 2) 617 4900Fax (66 2) 658 1470

    KUALA LUMPUR

    BNP Paribas Capital (Malaysia) Sdn. Bhd.Suite 21.03 Level 21 Menara Dion27 Jalan Sultan Ismail50250 Kuala LumpurMalaysiaTel (60 3) 2050 9928Fax (60 3) 2070 0298

    SEOUL

    BNP Paribas Securities Korea Co Ltd22/F, Taepyeongno Building310 Taepyeongno 2-gaJung-gu, Seoul 100-767KoreaTel (82 2) 2125 0500Fax (82 2) 2125 0593

    SINGAPORE

    BNP Paribas Securities(Singapore) Pte Ltd(Co. Reg. No. 199801966C)20 Collyer Quay#08-01 Tung CentreSingapore 049319Tel (65) 6210 1288Fax (65) 6210 1980

    TAIPEI

    BNP Paribas Securities(Taiwan) Co Ltd

    NEW YORK

    BNP ParibasThe Equitable Tower787 Seventh AvenueNew YorkNY 10019, USATel (1 212) 841 3800Fax (1 212) 841 3810

    BASEL

    BNP ParibasAeschengraben 26CH 4002 BaselSwitzerlandTel (41 61) 276 5555Fax (41 61) 276 5514

    FRANKFURT

    BNP ParibasMainzer Landstrasse 1660325 FrankfurtGermanyTel (49 69) 7193 6637Fax (49 69) 7193 2520

    GENEVA

    BNP Paribas2 Place de Hollande1211 Geneva 11SwitzerlandTel (41 22) 787 7377Fax (41 22) 787 8020

    LONDON

    BNP Paribas10 Harewood AvenueLondon NW1 6AAUKTel (44 20) 7595 2000Fax (44 20) 7595 2555

    LYON

    BNP Paribas Equities FranceSocit de Bourse3 rue de L Arbre Sec69001 LyonFranceTel (33 4) 7210 4001Fax (33 4) 7210 4029

    MADRID

    BNP Paribas SA, sucursal en EspanaHermanos Becquer 3PO Box 5078428006 MadridSpainTel (34 91) 745 9000Fax (34 91) 745 8888

    MILAN

    BNP Paribas Equities Italia SIM SpAPiazza San Fedele, 220121 MilanItalyTel (39 02) 72 47 1Fax (39 02) 72 47 6562

    PARIS

    BNP Paribas Equities FranceSocit de Bourse20 boulevard des Italiens75009 ParisFranceTel (33 1) 4014 9673Fax (33 1) 4014 0066

    ZURICH

    BNP ParibasTalstrasse 418022 ZurichSwitzerlandTel (41 1) 229 6891Fax (41 1) 267 6813

    MANAMA

    BNP Paribas BahrainPO Box 5253ManamaBahrainTel (973) 53 3978Fax (973) 53 1237

    BNP Paribas Equities (Asia) Ltd

    TOKYO

    BNP Paribas Securities (Japan) LtdGranTokyo North Tower1-9-1 Marunouchi, Chiyoda-KuTokyo 100-6740JapanTel (81 3) 6377 2000Fax (81 3) 5218 5970

    MUMBAI

    BNP Paribas Securities India Pvt Ltd6/F, Poonam ChambersB-Wing, Shivsagar EstateDr Annie Beasant Road, WorliMumbai 400 018IndiaTel (91 22) 6628 2300Fax (91 22) 6628 2455

    BNP Paribas Equities (Asia) LtdShanghai Representative OfficeRoom 2630, 26/FShanghai World Financial Center100 Century AvenueShanghai 200120, ChinaTel (86 21) 6096 9000Fax (86 21) 6096 9018

    JAKARTA

    PT BNP Paribas Securities IndonesiaGrand Indonesia, Menara BCA,

    JI. M.H. Thamrin No. 1Jakar ta 10 0IndonesiaTel (62 21) 2358 6586Fax (62 21) 2358 7587

    35/F

    31

    72 F, Taipei 101No. 7 Xin Yi Road, Sec. 5Taipei, Taiwan

    (886 2) 8729 7000Fax (886 2) 8101 2168Tel

    /