IND: Rajasthan Urban Sector Development …...sub-projects, 08 packages in Alwar, 6 packages in...
Transcript of IND: Rajasthan Urban Sector Development …...sub-projects, 08 packages in Alwar, 6 packages in...
Environmental Monitoring Report
This report has been submitted to ADB by Rajasthan Urban Infrastructure Development Project, Jaipur and the Asian Development Bank and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 40031-023/40031-033 November 2016 Period: January 2016 – June 2016
IND: Rajasthan Urban Sector Development Investment Program - Tranche 1 & 2
Submitted by: Rajasthan Urban Infrastructure Development Project, Jaipur
Environmental Monitoring Report
Semi-annual Environmental Monitoring Report
Tranche 1 (Loan Number 2366 – IND)
Document Stage: Final
Project Number: 40031
Month Year: June 2016
IND: Rajasthan Urban Sector Development Investment
Program
Prepared by Local Self Government Department
This report has been submitted to ADB by the Local Self-Government Department of the Government of Rajasthan and is made publicly available in accordance with ADB’s public communications policy (2005), it does not necessarily reflect the views of ADB
Environmental Monitoring Report
TABLE OF CONTENTS
I. INTRODUCTION ................................................................................................................................. 1
A. BACKGROUND ................................................................................................................................... 1
B. PROJECT PURPOSE ............................................................................................................................ 1
C. PROJECT PROFILE .............................................................................................................................. 1
II. APPLICATION OF EMP ....................................................................................................................... 3
III. ENVIRONMENTAL PROCEDURE REVIEW ......................................................................................... 24
A. ENVIRONMENTAL LEGAL REQUIREMENTS ...................................................................................... 24
B. COMPLIANCE WITH ENVIRONMENTAL REGULATIONS ................................................................... 25
C. COMPLIANCE OF ENVIRONMENTAL LOAN COVENANTS ................................................................ 27
D. ENVIRONMENTAL ORGANIZATION AND MANAGEMENT ............................................................... 28
E. GRIEVANCE REDRESSAL ................................................................................................................... 29
IV. ENVIRONMENTAL MONITORING AND EVALUATION ...................................................................... 32
V. CONCLUSIONS AND RECOMMENDATIONS ..................................................................................... 36
LIST OF TABLES, FIGURES AND ANNEXURES
TABLE: 1 IMPLEMENTATION STATUS OF SUB-PROJECTS UNDER TRANCHE - 1 ......................................... 2
TABLE: 2 IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT PLAN ............................................... 3
TABLE: 3 EMP COMPLIANCE STATUS OF ALWAR WASTE WATER SUBP‘OJECT ………………………………….. 4
TABLE: 4 EMP COMPLIANCE STATUS OF JAISALMER WATER SUPPLY SUBPROJECT ............................... 10
TABLE: 5 EMP COMPLIANCE STATUS OF JAISALMER WASTE WATER SUBPROJECT ............................... 16
TABLE 6: ACTION REQUIRED ENSURING SUBPROJECTS COMPLY WITH NATIONAL ENVIRONMENTAL
LAWS………………………………………………………………………………………………………………………………………………….24
TABLE 7: PRESENT STATUS OF ENVIRONMENT, FOREST & OTHER CLEARANCES - (TR-1) ....................... 25
TABLE 8: METHODOLOGY OF SAMPLING AND ANALYSIS AND EQUIPMENTS USED ............................... 32
TABLE 9: AIR QUALITY MONITORING RESULTS ....................................................................................... 33
TABLE 10: NOISE QUALITY MONITORING RESULTS ................................................................................ 34
TABLE 11: WATER QUALITY MONITORING RESULTS .............................................................................. 35
FIGURE 1: INSTITUTIONAL RESPONSIBLY- ENVIRONMENTAL ORGANIZATION RUSDIP .......................... 30
FIGURE 2 GRIEVANCE REDRESS PROCESS ................................................................................................ 31
ANNEXURE - 1 ENVIRONEMNTAL POLLUTION CONT‘OL ACT“ …………………………………………………………..38
ANNEXURE – 2 MAJOR WORKS AND PROGRESS- TRANCHE 1 ............................................................. 4140
ANNEXURE – 3 ENVIRONMENTAL MONITORING SCHEDULE .................................................................. 44
ANNEXURE – 4 INSURANCE DOCUMENTS OF LABOURERES
……………………………………….………………………466
ANNEXURE-5 MOBILIZATION SCHEDULE…………………………………………………………………………………………….48
ANNEXURE-6 MONITO‘ING ‘EPO‘T“…..…………………………………………………………………..……………………….49
ANNEXURE - PHOTOG‘APH“ …..………………………………………………………………………………………………………
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 1 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
I. INTRODUCTION
A. Background
1. Rajasthan Urban Sector Development Investment Program (RUSDIP) is intended to optimize
social and economic development in 15 selected towns in the State, particularly district
headquarters and towns with significant tourism potential. This will be achieved through
investments in urban infrastructure (water supply; sewerage and sanitation; solid waste
management; urban drainage; urban transport and roads), urban community upgrading (community
infrastructure; livelihood promotion) and civic infrastructure (art, culture, heritage and tourism;
medical services and health; fire services; and other services). RUSDIP will also provide policy
reforms to strengthen urban governance, management, and support for urban infrastructure and
services. The assistance will be based on the State-level framework for urban reforms, and
institutional and governance reforms recommended by the Government of India (GoI) through the
Jawaharlal Nehru National Urban Renewal Mission (JNNURM) and Urban Infrastructure
Development Scheme for Small and Medium Towns (UIDSSMT).
2. RUSDIP Phase II to be implemented over a seven year period beginning in 2008, and will be
funded by a loan via the Multi tranche Financing Facility (MFF) of the ADB. The Executing Agency
(EA) is the Local Self-Government Department (LSGD) of the Government of Rajasthan (GoR); and
the Implementing Agency (IA) is the Project Management Unit (PMU) of the Rajasthan Urban
Infrastructure Development Project (RUIDP), which is currently in the construction stage (Tr-1, Tr-2
and Tr- 3). Alwar, Jaisalmer and Jhalwar/ Jhalarapatan are the towns chosen to benefit from the first
tranche of RUSDIP investment. In addition 12 other towns namely, Bharatpur, Karauli, Dholpur,
Sawai Madhopur, Churu, Sikar, Barmer, Nagaur, Chittorgarh, Rajsamund, Bundi and Baran-Chabra
are considered under tranche 2 and 3 (Tr-2 & 3).
3. This report presents environmental monitoring for the period of January to June 2016 for
only Tranche-1 sub-projects.
B. Project Purpose
4. RUSDIP will improve infrastructure through the development, design and implementation of
a series of subprojects, each providing improvements in a particular sector (water supply, sewerage,
solid waste etc) in one town. RUSDIP has been classified by ADB as environmental assessment
category B (some negative impacts but less significant than category A) and the impacts of
subprojects were assessed through Initial Environmental Examination (IEE) reports prepared
according to ADB Environment Policy (2002) and Environmental Assessment Guidelines (2003).
5. The nature of the sub-projects may change during their subsequent development,
particularly during detailed design. This report is the Environmental Monitoring Report (EMR) to
describe the implementation of the mitigation measures and monitoring recommended in the IEE
and summary Initial Environmental Examination (SIEE).
C. Project Profile
6. Till 30th June 2016, 16 sub-projects under Tranche-1 have been awarded. Out of those 16
sub-projects, 08 packages in Alwar, 6 packages in Jaisalmer and 2 packages in Jhalawar-Jhalrapatan
have been awarded. In this report period field work continued for 5 sub-projects. One sub-project,
construction of sanitary landfill site at Jaisalmer has been terminated due to non availability of
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 2 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
environmental clearance. Construction of sanitary landfill at Jhalawar is completed after getting
environmental clearance. Six (06) packages at Alwar (RUSDIP/TR-01/ALW/WW/01-Lot-1), (RUSDIP/TR-
01/ALW/WS/02), (RUSDIP/ TR-01/ALW/WW/02Lot-1), (RUSDIP/TR-01/ALW/WW/02Lot-2), (RUSDIP/TR-
01/ALW/BR/01) and (RUSDIP/TR-01/ALW/SW/05), two packages (RUSDIP/TR-01/ JSL/DR-01) and
(RUSDIP/TR-01/ JSL/WS-01) at Jaisalmer and two package (RUSDIP/TR-01/JHL/WS-02) & (RUSDIP/TR-1/
JHL/SW/08) at Jhalwar have been completed and handed over to Municipal Council. The
implementation status of sub-projects has been summarized in Table -1.
Table 1: Implementation Status of Sub-projects under Tranche - 1
Town
Number of Sub-projects
Awarded Under-
implementation Completed
Yet to
be
started
Work
Stopped
Terminated/
Dropped
Alwar
08 02 06 - - -
Jaisalmer
06 03 02 - - 01
Jhalwar-
Jhalrapatan
02 00 02 - - -
Total 16 05 10 - - 01
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 3 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
II. APPLICATION OF EMP
7. This section presents the compliance status of Environmental Management and Monitoring
Plans of tranche-1 subprojects under implementation. In this report period field work continued for
5 sub-projects under tranche-1 as presented in Table 2. The progress of implementation of the EMP
has been monitored for each ongoing sub-project. The detailed list of projects under review is
presented in Table 2. Overall compliance status of EMP application and actions needed are discussed
below and shown in Table 3 to Table 5.
8. The EMP has been implemented in all ongoing sub-projects and status of the same is being
monitored. Annexure 2 shows summary of the scope of works, present work status, and expected
changes from the approved objectives, remedial measures for fulfillment of objective and key risks/
assumption for attainment of objectives.
9. T ai i g has ee gi e to the o t a to s, D“C s o ito i g spe ialist a d IPIU representative on environmental safeguard requirement. The status/progress of EMP
implementation is also being reviewed in quarterly review meetings and necessary training is being
provided. Moreover instruction is given to contractors to follow the specified clause of BID
document to mitigate environmental and social impacts.
10. In this report period field work continued for 05 sub-projects under tranche-1 as presented
in Table-1. The progress of implementation of the EMP has been monitored for each ongoing sub-
project. For the purpose of monitoring of EMP and progress reporting project sector specific formats
were developed according the expected activities. The compliance with the EMP are expressed
below for each sub-project:
Table: 2 Implementation of Environmental Management Plan
Sr. No. Project Town Packages
1 Alwar Waste Water: Supply, laying, jointing, testing and commissioning of various
Main and arterial sewer Network connecting to outfall, along with road
restoration and all necessary manholes appurtenances etc. at Alwar town.
(RUSDIP/TR-01/ALW/WW/03)
2 Waste Water: Additional Sewerage System in UIT colonies at Alwar
(RUSDIP/TR-01/ALW/WW/05)
3 Jaisalmer Water Supply: Providing, Laying, Jointing, Testing & Commissioning of water
pipe line for the strengthening of distribution system and rising main pipeline;
Construction and Commissioning of Elevated service reservoirs and providing
pumping system and ancillary works;
Package No: { RUSDIP/TR-01/ JSL/WS-02}
4 Waste Water – Sewerage and Waste stabilization Ponds in Phase-I in
Jaisalmer; Package No: {RUSDIP/TR-01/ JSL/WW-01}
5 Waste Water : Providing, laying, jointing, testing and commissioning of main
sewer, various intercepting sewer collecting lateral sewers house sewer
connections, road restoration along with all appurtenances in Gandhi colony,
Indira colony, RP colony, part of Gafur Bhatta and GAD colony, construction
commissioning of civil, mechanical and and maintenance of intermediate
sewage pumping stations in Gandhi Colony at Jaisalmer Town {RUSDIP/TR-01/
JSL/WW-09}
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 4 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Table: 3 EMP Compliance Status of Alwar Waste Water Subproject: {RUSDIP/TR-01/ALW/WW-03 & WW/05}
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Pre Construction Stage
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control
of Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish is not
required as scope include only
laying of pipes in both of the
package
Tree cutting is not required
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium
or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure
that any chance finds are recognized and measures are taken
to ensure they are protected and conserved.
Complied It was confirmed by
consultations with various
stakeholders that the site has
no archaeological potential
Instruction has been given to
the contractor to ensure that
any chance finds are
recognized and measures are
taken to ensure they are
protected and conserved
No such occurrence till date
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in
the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in
destruction of property, vegetation, irrigation, and drinking
water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will inconvenience
Complied All the facilities related to
construction are located
within project site
There are neither any work
camps nor hot mix plants
established for project works.
Construction materials are
temporarily stored at sites
with due consideration of
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 5 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
the community. safeguard norms taking into
account vegetation, irrigation,
and drinking water supply
systems.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the
suitability of all material sources and to obtain the approval
of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied All the material is being taken
from approved mines
Nil DSC/ IPIU
Construction Stage
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied All the material is being taken
from government approved
quarry sites
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied Air quality monitoring has
been conducted in the
reporting period.
Construction materials have
been stockpiled at designated
areas in consultation with IPIU
Water sprinkling is being done
as and when required
Nil Contractor/ DSC/
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
Complied Ground water quality
monitoring has been
Nil Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 6 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from
any drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface water quality inspection according to
the Environmental Management Plan (EMP).
conducted during monitoring
period.
Excavated soil is being reused
for backfilling and excess
material is being disposed in
low lying areas
surface water quality
inspection is not required as
there is no surface water body
near subproject site
Oil & lubricant has been
stored away from drainage
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in least
disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or more
from the vehicle/s.
Complied Noise level monitoring has
been conducted in the
reporting period.
Activities with the greatest
potential to generate noise
have been planned in
consultation with IPIU and are
being conducted in day time
Construction equipment are
properly maintained by
contractor to minimized the
noise
Nil Contractor/DSC/
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
Complied Overburden and excavated
materials from construction
sites has been reused for
backfilling and excess material
has been disposed to
designated areas
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 7 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(iv) Recover used oil and lubricants and reuse or remove
from the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required;
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(vi) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak
hours; and
(vii) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction works
and contact numbers for concerns/complaints
Complied Short period traffic diversions
is being provided as per
requirement
Haulage activities are not
significant in and around work
sites.
Sign boards informing nature
and duration of construction
works and contact numbers
for concerns/complaints has
been provided at each
construction site.
Nil DSC/ IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied Planks/metal sheets is being
provided across trenches
whenever required for easy
excess
Nearby residents and
businesspeople are informed
about the nature of work in
advance by public
consultation
Adequate workforce has
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 8 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
provided at critical areas
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km immediate
area if manpower is available; and
(ii) Secure construction materials from local market.
Complied At present most of the
workforce is hired locally
which is more than 50%.
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a)
excluding public from the site; (b) ensuring all workers are
provided with and use Personal Protective Equipment; (c) H
and S Training for all site personnel; (d) documented
procedures to be followed for all site activities; and (e)
documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers
to ensure that they are apprised of the basic site rules of
work at the site, personal protective protection, and
preventing injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances
may be present. Ensure also that visitor/s do not enter
hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
complied Use of PPE at work site is
seen.
Proper toilets with soak pits
have been provided.
Adequate first-aid facility has
been provided at each site
Group insurance has been
provided to workers
Drinking water has been
provided at all sites
high visibility vests are
provided to workers
Back-up alarms are not
provided in moving
equipment
Workers are not exposed to
high noise for 8 hours
OHS training has been
provided to labor from time
to time.
Contractor has been
instructed complete
compliance of
measure specified in
EMP and especially to
pay particular
atte tio to o ke s safety
Contractor/DSC
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 9 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(x) Ensure moving equipment is outfitted with audible back-
up alarms;
(xi) Mark and provide sign boards for hazardous areas such
as energized electrical devices and lines, service rooms
housing high voltage equipment, and areas for storage and
disposal. Signage shall be in accordance with international
standards and be well known to, and easily understood by
workers, visitors, and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove
from the site;
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Not
Applicable
At present most of the
workers employed are local.
Contractor has not
constructed any camp
Nil Contractor
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 10 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Table: 4 EMP Compliance Status of Jaisalmer Water Supply subproject {RUSDIP/TR-01/JSL/WS-02} SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Pre-Construction Stage
1 Environmental Clearances
Site preparation work completed by IPIU including
necessary clearance
Complied
Consent to Establish is not
required
Tree cutting is not required
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the
site;
(ii) Consider alternatives if the site is found to be of
medium or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can
be made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure
that any chance finds are recognized and measures are
taken to ensure they are protected and conserved.
Complied
It was confirmed by
consultations with various
stakeholders that the site has no
archaeological potential
Instruction has been given to
the contractor to ensure that
any chance finds are recognized
and measures are taken to
ensure they are protected and
conserved
No such occurrence till date
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space
in the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in
destruction of property, vegetation, irrigation, and drinking
water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will
inconvenience the community.
Complied
All the facilities related to
construction are located within
project site
Nil DSC/ IPIU
4 Sources of Materials Complied All the material is being taken Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 11 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the
suitability of all material sources and to obtain the
approval of IPIU; and
(iii) If additional quarries will be required after construction
is started, inform construction contractor to obtain a
written approval from IPMU.
from approved mines
Construction Stage
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (
IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken
from government approved
quarry sites
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air
pollution control devices which are operating correctly.
Partially
Complied
Adequate sprinkling of water is
required for arresting fugitive
dust considering the arid climate
of the area
Air quality monitoring has not
been conducted during
reporting period
Adequate watering is
required at work site And
A log register to be
maintained at site
Complete Covering of
purposefully stockpiled
soils & fine construction
materials for short
duration only,
with Tarpaulin-sheets;
Monitoring need to be
conducted at the
Contractor/IPIU/
DSC
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 12 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
earliest.
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins
along the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from
any drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities
in designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Excess excavated soil will be
reused for backfilling
Oil & lubricant has been stored
away from drainage
Nil
Contractor/IPIU/
DSC
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in
least disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or
more from the vehicle/s.
Partially
Complied
Activities with the greatest
potential to generate noise have
been planned in consultation
with IPIU and are being
conducted in day time
Noise monitoring has not been
conducted during reporting
period
Instruction has been
given to contractor to
conduct noise monitoring
and it will be included in
the next EMR.
Contractor/IPIU/
DSC
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 13 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to
designated areas;
(iv) Recover used oil and lubricants and reuse or remove
from the sites;
(v) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no
longer required; and
(vii) Request IPIU/DSC to report in writing that the
necessary environmental restoration work has been
adequately performed before acceptance of work.
Complied
The unusable extra excavated
materials and over burdens are
being disposed at low laying
area
No leakage of oil and lubricant
observed at site from
construction machinery
Nil Contractor/IPIU/
DSC
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-
peak hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(v) Drive vehicles in a considerate manner;
(vi) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak
hours; and
(vii) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction
Complied
The vehicles carrying materials
to the work site follow only
designated route to the site
sign boards informing nature
and duration of construction
works and contact numbers for
concerns/complaints has been
provided
Nil Contractor/IPIU/
DSC
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 14 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
works and contact numbers for concerns/complaints
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature
and duration of construction works and contact numbers
for concerns/complaints.
Complied
The work schedule has been
prepared as per consultation
with local public
Proper access across trenches
for people and vehicles has
provided
Significant work force has been
provided
Nil IPIU/DSC
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km immediate
area if manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the
workforce is hired locally
Nil PIU/DSC
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety
(H and S) Plan which will include measures such as: (a)
excluding public from the site; (b) ensuring all workers are
provided with and use Personal Protective Equipment; (c)
H and S Training for all site personnel; (d) documented
procedures to be followed for all site activities; and (e)
documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all
times. Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
Partially
Complied
Health and Safety Plan has been
implemented.
PPE are being used on sites.
First-aid facility has been
provided at each site
Group insurance has been
provided to workers
Drinking water has been
provided at all sites
H&S training is being provided
Contractor has been
instructed complete
compliance of measure
specified in EMP
Contractor/DSC
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 15 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers
to ensure that they are apprised of the basic site rules of
work at the site, personal protective protection, and
preventing injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can
gain access to areas where hazardous conditions or
substances may be present. Ensure also that visitor/s do
not enter hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of
high visibility vests when working in or walking through
heavy equipment operating areas;
(x) Ensure moving equipment is outfitted with audible
back-up alarms;
(xi) Mark and provide sign boards for hazardous areas such
as energized electrical devices and lines, service rooms
housing high voltage equipment, and areas for storage and
disposal. Signage shall be in accordance with international
standards and be well known to, and easily understood by
workers, visitors, and the general public as appropriate;
and
(xii) Disallow worker exposure to noise level greater than
85 dBA for a duration of more than 8 hours per day
without hearing protection. The use of hearing protection
shall be enforced actively.
to workers by DSC regularly
high visibility vests are provided
to workers
Back-up alarms are provided in
moving equipment
Sign board are provided at all
site
Workers are not exposed to high
noise for 8 hours
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting
Complied
At present most of the workers
employed are local.
Nil Contractor
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 16 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
of trees for firewood;
(v) Train employees in the storage and handling of
materials which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove
from the site;
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary
structures (such as buildings, shelters, and latrines) which
are no longer required; and
(ix) Request IPIU/DSC to report in writing that the camp
has been vacated and restored to pre-project conditions
before acceptance of work.
Table: 5 EMP Compliance Status of Jaisalmer Waste Water subproject {RUSDIP/TR-01/JSL/WW-01 & WW-09}
Sr.
No
.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
1 Environmental Clearances
Site preparation work completed by IPIU including
necessary clearance
Consent to Establish under Water (Prevention and
Control of Pollution) Act
Consent to Establish under Air (Prevention and Control
of Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish has been
obtained from RPCB for STP
under WW/01 package. Consent
was valid upto 30.11.15. work is
completed & Consent to
establish is not required
anymore.
Tree cutting is not required
Application of Consent to
Operate has been
submitted to RPCB. Trail
run under progress.
DSC/IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the
Complied It was confirmed by
consultations with various
stakeholders that the site has no
Nil DSC/IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 17 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No
.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
site;
(ii) Consider alternatives if the site is found to be of
medium or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can
be made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure
that any chance finds are recognised and measures are
taken to ensure they are protected and conserved.
archaeological potential
Instruction has been given to
the contractor to ensure that
any chance finds are recognized
and measures are taken to
ensure they are protected and
conserved
No such occurrence till date
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space
in the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in
destruction of property, vegetation, irrigation, and drinking
water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will
inconvenience the community.
Complied All the facilities related to
construction are located within
project site
Nil Contractor /
DSC/IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the
suitability of all material sources and to obtain the
approval of IPIU; and
(iii) If additional quarries will be required after construction
is started, inform construction contractor to obtain a
written approval from IPMU.
Complied All the material is being taken
from approved mines
Nil DSC/IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 18 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No
.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Construction Stage
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (
IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied All the material is being taken
from government approved
quarry sites
Nil DSC/IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air
pollution control devices which are operating correctly.
Partially
Complied
Sprinkling of water is being done
but required in adequate
interval considering the arid
climate of the area
Air quality monitoring has not
been conducted during
reporting period.
Adequate watering is
required at work site
Monitoring need to be
conducted at the
earliest.
A log register for
watering is required to
be maintained at site
Instruction has been
given to contractor to
use tarpaulins to cover
fine material when
transported.
Contractor/IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
Complied Surface water quality is not
required during reporting period
as there is no surface water near
sites.
No surface water was
available near the project
site
Contractor /IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 19 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No
.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins
along the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from
any drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities
in designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in
least disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80
decibels (dbA) when measured at a distance of 10 m or
more from the vehicle/s.
Partially
Complied
Activities with the greatest
potential to generate noise have
been planned in consultation
with IPIU and are being
conducted in day time
Noise monitoring has not been
conducted for reporting period
Noise monitoring is
required to be conducted
and to be reported in
next EMR.
Contractor/IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to
designated areas;
(iv) Recover used oil and lubricants and reuse or remove
from the sites;
(v) Manage solid waste according to the following
Complied The unusable extra excavated
materials and over burdens are
being disposed at low laying
area as per direction of ULB of
Jaisalmer town
Oil and lubricants leakage not
observed from any construction
machinery
Nil Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 20 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No
.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
preference hierarchy: reuse, recycling and disposal to
designated areas;
(vi) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no
longer required; and
(vii) Request IPIU/DSC to report in writing that the
necessary environmental restoration work has been
adequately performed before acceptance of work.
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-
peak hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(v) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak
hours; and
(vi) Notify affected sensitive receptors by providing sign
boards informing nature and duration of construction
works and contact numbers for concerns/complaints
Complied The trucks carrying materials to
the work site follow only
designated route to the site
sign boards informing nature
and duration of construction
works and contact numbers for
concerns/complaints has been
provided
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
Complied Proper access across trenches
for people and vehicles has
been provided
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 21 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No
.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(v) Provide sign boards for pedestrians to inform nature
and duration of construction works and contact numbers
for concerns/complaints.
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km immediate
area if manpower is available; and
(ii) Secure construction materials from local market.
Complied At present most of the
workforce is hired locally
DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety
(H and S) Plan which will include measures such as: (a)
excluding public from the site; (b) ensuring all workers are
provided with and use Personal Protective Equipment; (c)
H and S Training for all site personnel; (d) documented
procedures to be followed for all site activities; and (e)
documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all
times. Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers
to ensure that they are apprised of the basic site rules of
work at the site, personal protective protection, and
preventing injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can
gain access to areas where hazardous conditions or
substances may be present. Ensure also that visitor/s do
not enter hazard areas unescorted;
Partially
Complied
Health and Safety Plan is under
implementation.
PPE are being used partially.
First-aid facility has been
provided at each site
Drinking water has been
provided at all sites
H&S training is being provided
to workers by DSC regularly
high visibility vests are provided
to workers
Sign board are provided at all
site
Workers are not exposed to high
noise for 8 hours
Wo ke s insurance has been
provided by the contactor
Contractor has been
instructed complete
compliance of measure
specified in EMP
Safety officer is has been
nominated by contractor
Contractor
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 22 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No
.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(ix) Ensure the visibility of workers through their use of
high visibility vests when working in or walking through
heavy equipment operating areas;
(x) Ensure moving equipment is outfitted with audible
back-up alarms;
(xi) Mark and provide sign boards for hazardous areas such
as energized electrical devices and lines, service rooms
housing high voltage equipment, and areas for storage and
disposal. Signage shall be in accordance with international
standards and be well known to, and easily understood by
workers, visitors, and the general public as appropriate;
and
(xii) Disallow worker exposure to noise level greater than
85 dBA for a duration of more than 8 hours per day
without hearing protection. The use of hearing protection
shall be enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting
of trees for firewood;
(v) Train employees in the storage and handling of
materials which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove
from the site;
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary
structures (such as buildings, shelters, and latrines) which
Partially
Complied
Work camp has been
established in consultation with
IPIU/DSC
Labour camp has been
established near STP site
(Package WW/01)
Poor water and sanitation
facilities need more
improvement, contractor has
provided cooking gas/stove in
labour camp
Contractor has instructed
to provide proper water,
sanitation facilities
cooking gas in the camp
Contractor
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 23 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Sr.
No
.
Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
are no longer required; and
(ix) Request IPIU/DSC to report in writing that the camp
has been vacated and restored to pre-project conditions
before acceptance of work.
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 24 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
III. ENVIRONMENTAL PROCEDURE REVIEW
A. Environmental Legal Requirements
11. Annexure 1 lists those Acts; Rules, Policies and Regulations currently in force in India and
deal with environmental issues that could apply to infrastructure development. However, because of
the relatively minor negative impacts of most of the types of the subproject likely to be developed
under RUSDIP, it is expected that most subproject should not fall within the scope of these legal
instruments. Subprojects and activities that will need to comply with certain laws are:
o Any components that require the acquisition of forest land;
o Any construction activities located in areas covered by the Aravalli Range Notification in
Alwar;
o Water Treatment Plants (WTP) and Sewage Treatment Plants (STP);
o Composting and landfill facilities;
o Common waste management facilities, including composting, landfills, transfer stations;
o Common waste management facilities within 10 km of the boundary of protected areas
(such as National Parks, Sanctuaries, Notified areas and Biosphere Reserves);
o Mobile diesel generators
12. The specific requirements to ensure compliance by these components and subprojects are
shown in Table 6.
Table 6: Action Required Ensuring Subprojects Comply with National Environmental Laws
Component Applicable Legislation Compliance Action Required
1. All components that
require acquisition of forest
land
Forest (Conservation) Act
1980; Wildlife (protection)
Act 1972
Approval from
Ministry of
Environment and
Forests (MoEF)
Identify non- forest land and
formulate an afforestation
program
2. Water Treatment Plant
(WTP) and Sewage Treatment
Plant (STP)
Water (Prevention and
Control of Pollution)Act
1974
Consent to Establish
(CTE) and Consent
to Operate (CTO)
from RSPCB
Based on project review and
site inspection RSPCB
provides CTE before
construction, and stipulate
the disposal standards to be
met during operation.
After completion of
construction, CTO is issued
confirming compliance with
the CTE conditions, if any
Renewal of CTO
during operation
(STP)
Based on the performance of
the STP and its compliance
with the disposal standards
CTO is renewed every year
3. All composting and landfill
facilities
Municipal Solid Wastes
(Management and handing)
Rules 2000
Authorization of
proposed site by
RSPCB
Authorization is issued based
on land use in and around
the site and groundwater
condition
Water (Prevention and
Control of Pollution ) Act
1974; Air(Prevention and
Control of Pollution ) Act
1981
CTE and CTO from
RSPCB
Same as for STPs (above)
4. Common waste Environment (Protection) Requires Based on preliminary
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 25 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Component Applicable Legislation Compliance Action Required
management facilities
including composting,
landfills and transfer stations
Act 1986: Environmental
Impact Assessment
Notification 2006, amended
in 2009 Category B
environmental
clearance from
State Environment
impact Assessment
Authority (SEIAA)
information and site visits, if
required, project will be
categorized as B1 or B2. B1
projects require EIA study for
approval
5. Common waste
management facilities within
or 10 km outside the
boundary of protected areas
such as National Parks,
Sanctuaries, Notified Areas
and Biosphere Reserve
Environmental Impact
Assessment Notification,
2006 Category A
Requires
environmental
clearance from the
federal Ministry of
Environment and
Forests (MoEF)
Conduct EIA study
Category A and B1 projects
require public consultation
as part of EIA
6. Mobile diesel generators
Air (Prevention and Control
of Pollution ) Act 1981
CTE and CTO from
RSPCB
CTO renewal every year
based on performance
B. Compliance with Environmental Regulations
13. Table 7 below shows present clearance status for different sub-projects under Tr-1. The GoI
EIA Notification of 2006 and its subsequent amendment (replacing the EIA Notification of 1994), sets
out the requirement for Environmental Assessment in India. This states that Environmental
Clearance (EC) is required for specified activities/projects. Projects are categorized as A o B depe di g o the s ale of the p oje t a d the atu e of its i pa ts. Catego ies A p oje ts e ui e Environmental Clearance from the National Ministry of Environment and Forests (MoEF) and
Catego y B p oje ts e ui e e i o e tal lea a e f o the “tate E i o e t I pa t Assessment Authority (SEIAA).
14. The only type of infrastructure provided by the RUSDIP that is specified in the EIA
Notification is Common Municipal Solid Waste Management facility (CMSWMF1), where EC is
required. Thus Environmental Clearance (EC) is not required for other sub-project under RUSDIP.
15. Co se t to Esta lish fo setti g up “e age T eat e t Pla t a d Wate T eat e t Pla t a d Co se t to Ope ate efo e pla t sta ts its ope atio is e ui ed f o “tate Pollutio Co t ol Board (RPCB) under the Water (Prevention and Control of Pollution) Act. 1974. As per the present
status consent to establish has obtained for all the running sub-projects under Tr-1. Attention
should be given by respective IPIUs to obtain Consent to Operate before commissioning of STP/WTP.
Table 7: Present Status of Environment, Forest & Other Clearances - (Tr-1)
Town Work
(Package No.)
Applicable
Legislation/ Type
of clearance
Clearance given by
and date
Subject
/ Issue
Remarks/ Action
needed
Alwar (Tr-1) Alwar Waste
Water
(RUSDIP/Tr-
01/ALW-/WW-
02)
Water
(Prevention and
Control of
Pollution) Act.
1974/
Consent for 20
Consent to Operate
obtained from
Pollution Control
Board –
Consent valid upto
31.07.2015
PHED has applied
for renewal of
consent to
Operate
Project has been
handed over to
PHED.
Operational
Work completed
Date:30/07/2012
1 For the purpose of EIA Notification, common municipal solid waste management facilities may be referred as
centralized MSW facility for an given town, city, region. It is further to mention a common facility need not
have surrounding ULBs included.(Technical EIA Guidance Manual for CMSWMF)
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 26 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Town Work
(Package No.)
Applicable
Legislation/ Type
of clearance
Clearance given by
and date
Subject
/ Issue
Remarks/ Action
needed
MLD STP from
Pollution Control
Board
by RSPCB order No.
2012-2013/MUID/
1099
Handed over on
7/03/2013.
PHED to follow
up with RPCB for
renewal of CTO.
Alwar Solid
Waste
(RUSDIP/Tr-
01/ALW-/SW-
01)
EIA notification
2006
Authorization issued
from Rajasthan
Pollution Control
Board (RPCB)
EC obtained vide
letter no.
F1(4)SEIAA/SEAC-
Raj/ Sectt/Project/
Cat7(i) B1(86)/08-09
Complied
Handed over to
municipal
council.
operational
Work completed
Jaisalmer
(Tr-1)
Waste Water
(RUSDIP/TR-
01/JSL/WW-01)
Water
(Prevention and
Control of
Pollution) Act.
1974/
Consent to
establish of 10
MLD STP from
Pollution Control
Board
Consent to
operate will be
required before
operation
Consent to Establish
obtained from
Pollution Control
Board – Order No.
2012-
2013/MUID/1141
dated 03.12.2012
Consent valid upto
30.11.2015
Consent to
Establish expired
on dtd
30.11.2015. Work
completed.
Application of
Consent to
Operate has been
submitted to
RPCB.
Since the work
has been
completed
Application for
Consent to
Operate has been
submitted to
RPCB and is
under process.
Plant will be
operational after
receiving CTO.
Jaisalmer Solid
Waste
((RUSDIP/Tr-
01/JSL-/SW-07))
EIA notification
2006
EC applied on
01.10.08 (for
categorization
submitted to
RPCB on
02.09.08)
Authorization issued
from Rajasthan
Pollution Control
Board (RPCB)
Discussion in
SEAC meeting
held on 17.11.08
again it is
discussed in 3rd
meeting of SEAC
on 26.12.08. TOR
issued by SEAC
for EIA and
Environmental
Clearance
Project
Terminated
Jhalawar-
Jhalrapatan
(Tr-1)
Jhalwar Solid
Waste
(RUSDIP/Tr-01/
JHL -/SW-08)
EIA notification
2006
Authorization issued
from Rajasthan
Pollution Control
Board (RPCB).
Environmental
Clearance issued by
SEIAA vide letter no.
F1(4) SEIAA/SEAC
Raj/Sectt/project/Cat
7(i)B1(123)/08-09 on
30.07.2012
Consent to Establish
The work has
been completed
and renewal of
Consent to
Establish is not
required.
Complied
Handed over to
Nagar Parishad.
Not operational
as compost plant
has not been
built by Nagar
Parishad. Handed
over on
Date – 25/03/
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 27 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Town Work
(Package No.)
Applicable
Legislation/ Type
of clearance
Clearance given by
and date
Subject
/ Issue
Remarks/ Action
needed
obtained by PCB
order no 2012-
2013/SWMC/1579
dated 15.10.2012
valid upto
31.07.2015
2015
C. Compliance of Environmental Loan Covenants
16. The status of o plia e of ADB s ajo E i o e tal Loa Co e a ts sho elo :
Project Specific Covenants Status / Issues
Environmental
The EA shall ensure that: (LA Sched 5 Para 13)
(a) the project is carried out and all subproject facilities designed,
constructed, operated, maintained, and monitored in compliances
with the environmental law and regulations of the Borrower, the
state, ADB s E i o e tal Guideline (2002), and the EARF;
Under compliance in accordance with ADB s
Environmental Assessment Guidelines
(b) Subproject encroaching any National Park or its buffer zone
shall not be included in the Project; however, Subproject in or
close to the wildlife sanctuary or any other lower grade
environmentally sensitive area may be allowed subject to the EA
obtaining all statutory clearances;
No as such encroachment in sanctuaries or any
other lower grade environmentally sensitive
area recorded till date.
If it happens in future, environmental clearance
will be taken up as per Govt. procedure
(c) an IEE as required, including an EMP with budget identifying
the cost of its implementation as incorporated in the related bid
document if any, when adequate public consultation for each sub-
project, in accordance with the EARF shall be submitted to ADB for
review and approval before award of related contract. In case of
any EIA or SIEE for sub-project classified as A or B sensitive, this
shall be subject to the 120 day public disclosure requirement
u de ADB s E i o e tal Poli y , 9
An IEE have been prepared for each sub-project
where EMP, budget for application of EMP and
issues of public consultation are enclosed.
Budget and EMP components are incorporated
in the bid document
All the reports approved by ADB.
At present all the sub-projects are classified as
class B (only IEE will be required)
As per National rules EIA will be required for
landfill site handling more than 50 MT/day
municipal solid waste
(d) all mitigation measures identified in the IEE, SIEE, EIA or SEIA
and the related EMP, as applicable, for each sub-project, shall be
incorporated in sub-project design, and carried out during
construction, and O & M, and disclosed to the stakeholders;
Under compliance: IEE screening of potential
environmental impact and mitigation measures
applied according to project location, specific
sector development and associated design
requirements.
EMP s p epa ed a d egula ly o ito ed fo compliance of stated mitigation measures.
During construction process within the city
consultation with local communities on
environmental issues are considered
Last EMP biannual Report (July -December
2015) has been submitted.
(e) if there are any changes in specific locations or alignments of
any sub-project facilities after completion of the process of IEE (or
EIA) or due to detailed design or implementation that has an
impact on the environmental assessment carried out thus far,
then additional environmental assessment shall be carried out in
EMP already revised in case of change of scope/
location for few sub-projects under Tr-1.
For minor change in location of project facilities
EMP has been revised for monitoring purpose
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 28 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Project Specific Covenants Status / Issues
a o da e ith ADB s E i o e tal Poli y , 9 a d the EARF, and prior approval of ADB obtained before further physical
implementation of the sub-project;
(f) all environmental clearances required by applicable laws, and
regulations at Borrower, State, or local levels shall be obtained in
a timely manner, prior to commencement of civil works for the
relevant subproject
Under compliance: All necessary clearances
presently under pursuance. Specific clearance
details are now compiled for appropriate
contract packages.
Clearance Plan prepared to a scheduled
timeframe, which is monitored for submissions
to the various agencies in obtaining the
necessary clearances.
(g) semi-annual progress reports on the implementation of the
EMPs, measures under the IEE/EIA, and the environmental
monitoring shall be carried out as a part of the project.
Implementation for review and disclosure in accordance with
ADB s Pu li Co u i atio s Poli y
Semi- annual progress report on application of
EMP is being prepared regularly
Field monitoring continued as per monitoring
plan
During construction process within the town
limit consultation with local communities on
environmental issues is continued in most of the
locations
D. Environmental Organization and Management
17. Environmental issues of the project coordinated by an Environmental Specialist within the
IPMU/ IPMC, who ensures that all subprojects, comply with environmental safeguards. An
Environmental Monitoring Specialist (EMS) who is part of the DSC team implement the
Environmental Monitoring Plan from each IEE to ensure that mitigation measures are provided and
protect the environment as intended. Figure 1 shows institutional responsibility for implementation
of environmental safeguard monitoring at different level. Details about the mobilization schedule of
environmental safeguard personals are provided at Annexure 5
18. EMP shows that most of the mitigation activities are the responsibility of the Construction
Contractors (CC) employed to build the infrastructure during the construction stage or the O&M
Contractors employed to conduct maintenance or repair work when the system is operating.
Responsibility for the relevant measures assigned to the Contractors via the contracts through which
they are appointed, so they legally required taking the necessary action. There are also some actions
that need to be taken by LSGD in their role as project proponent, and some actions related to the
design that would be implemented by the DSC.
19. A program of monitoring would be conducted to ensure that all parties take the specified
action to provide the required mitigation, to assess whether the action has adequately protected the
environment, and to determine whether any additional measures may be necessary. This would be
conducted by a qualified Environmental Monitoring Specialist (EMS) from the DSC. The EMS
responsible for all monitoring activities and reporting the results and conclusions to the IPMU, and
recommend remedial action if measures are not being provided or are not protecting the
environment effectively. The EMS may be assisted by environmental specialist in particular technical
fields, and junior or medium-level engineers of IPIU (designated as environmental officer) who can
make many of the routine observations on site. Post-construction monitoring will be conducted by
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 29 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
the relevant Government Agency (GA) to whom responsibility for the infrastructure will pass once it
begins to operate2.
20. EMP shows that most of the mitigation measures are fairly standard methods of minimizing
disturbance from building in urban areas (maintaining access, planning work to avoid sensitive times,
finding uses for waste material, etc), and experienced Contractors should be familiar with most of
the requirements. Monitoring of such measures normally involves making observations in the course
of site visits, although some require more formal checking of records and other aspects. There are
also be some surveys of residents, as most of the measures are aimed at preventing impacts on
people and the human environment.
E. Grievance Redressal
21. The City Level Committee (CLC), acting as a grievance redress committee (GRC) is chaired by
the District Collector with representatives from the ULB, state government agencies, IPIU,
community-based organizations (CBOs) and NGOs. As GRC, the CLC meets at regular intervals based
on the availability of the CLC /GRC members and also as per requirement or pending issues. The
grievance redress mechanism is provided in Figure 2. The information w.r.t CLC/GRC is
communicated to APs personally by the ACO in the concerned town. Further, the complete detail of
the CLC eeti g is also displayed at the IPIU oti e oa d a d the oti e oa d of the olle to s office too.
22. IPIUs along with ACOs and DSCs have been entrusted with the responsibility to maintain a
proper register of the grievance (if any) which will be endorsed by the all three agencies involved in
implementation. General directions for registering grievances of APs were communicated in the
meeting organized on 26.12.2011 followed by minutes issued vide letter no. 32060-67dated
30.12.2011. GRC registers are in place at all the towns. Further ACOs have been given instructions to
arrange more public consultations and register all the grievances (including verbal) in writing
whether substantial or non substantial and put them up for the perusal of IPIU for proper disposal.
23. It is important to mention that 28 Grievances were received during reporting period out of
which 8 were reported in Alwar, 20 were reported in Jaisalmer and no grievance was reported in
Jhalwar. Related issues like water line damages, road restoration, excess / accumulation of soil
moulds etc. these grievances are resolved by the IPIUs as and when received. But grievances like
demand of water or sewerage connection/line etc. are resolved as per the scope of work through
proper approval from RUIDP
2 In the operational period some infrastructure will be the responsibility of the Municipal Boards/Councils, whilst others will be the responsibility of the appropriate branch of the State government (such as PWD, PHED, etc)
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 30 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Figure 1: Institutional Responsibly- Environmental Organization RUSDIP
Ministry of Urban Development (MoUD), LSGD- EA
Government of Rajasthan
Rajasthan Urban Sector Development Investment
Program (RUSDIP) Project Implementation
Implementing Agency
-Investment Program Implementation
Units (IA - IPMU)- Environmental Officer
Several Construction Packages for different tranche under each
IPIU – (Nominated Environmental
Monitoring Engineer/ Officer)
Design and Supervision Consultants
(DSC)
Construction Contractors (CC)
Environmental Monitoring Specialist
(EMS) Provided by DSC
Independent Environmental Testing & Monitoring
Agency
IMPLEMENTATION OF EMP
ADB
Investment Program Management
Consultancy (IPMC) Appointed by RUSDIP
Environmental Expert of IPMC
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 31 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Figure 2 Grievance Redress Process
CLC = City Level Committee,
GRC = Grievance Redress Committee,
IPIU=Investment Program Implementation Unit,
IPMU = Investment Program Management Unit,
NGO = Nongovernmental organization,
SDS = Social Development Specialist.
IPIU
Not Addressed
APs
IPMU
Grievance
Addressed
GRC/CLC
Grievance
Addressed
Not Addressed
Grievance
Addressed
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 32 ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
IV. ENVIRONMENTAL MONITORING AND EVALUATION
24. For effective monitoring, selected environmental parameters have been identified as
indicators which may be qualitatively and quantitatively measured and compared over a period of
time in order to assess/ensure the compliance of EMP. The environmental performance indicators
are physical, biological and social characteristics identified as most important in affecting the
environment at critical locations all along the sub-project corridors. The parameters identified as
performance indicators are:
o Air, noise and water quality
o Compliance to EMP
o Compliance to local/state/national environmental regulations
25. After starting of construction work for STP, WTP air pollutants should be measure at core
and buffer zone of the proposed STP/ WTP site. If any water body exists near the STP, WTP physico-
chemical properties of the water should be measure as part of base line environment as per
Annexure- 3
26. Also during construction of landfill site monitoring in respect to air, noise, and water quality
are required as per Annexure- 3.
27. At pipe laying area air and noise quality monitoring should be done as per scope of work
depicted in Annexure- 3. Monitoring reports are attached in annexure-6.
28. Ambient Air Quality Monitoring - It is indispensable to assess the existing ambient air quality
of the environment for baseline information in order to quantify the impact of the proposed project
activities on the ambient air quality of the site. The existing ambient air quality at the proposed
project site was assessed with respect to Respirable Particulate Matter (PM10), Particulate Matter
(PM2.5), Sulphur dioxide (SO2), Nitrogen dioxide (NO2) and Carbon monoxide (CO), measured
through an intended field monitoring.
Table 8: Methodology of Sampling and Analysis and Equipment Used
SN Parameter Protocol Analysis
Procedure Instrument Used
1 PM 10 IS: 5182 (Part-23)-
2006 Gravimetric
High volume Sampling
using Respirable Dust
Sampler APM 460 BL
2 PM 2.5 Instrument manual Gravimetric Fine Particulate Sampler
APM 550
3 SO2 IS: 5182 (Part-2)-2001 Colorimetric Spectrophotometer
4 NO2 IS: 5182 (Part-6)-1975
Reaffirmed 1998 Colorimetric Spectrophotometer
5 CO IS: 5182 (Part-10)-
1999 Colorimetric Spectrophotometer
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 33 ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
29. Ambient Air and noise quality monitoring has been carried out in Alwar but could not be
carried out in Jaisalmer. Since work has been completed in Jhalawar therefore ambient air and noise
quality monitoring is not required in Jhalawar.
30. The results of the monitoring results for Alwar town are as tabulated below:
Table 9: Average Ambient Air Quality Monitoring Data
Project Sampling
Location
Date of
Monitoring
Results of monitoring (µg/m3) Remarks
PM10 PM2.5 SO NO CO
mg/m3
ALWAR
RUSDIP/TR-
01/ALW/WW
/03 & WW-05
Scheme
No.02
14.01.2016 142.68 57.99 10.62 12.38 450 During construction PM is found
above the standard limit but below
baseline limit. Therefore pollution
was not caused due to construction
activity.
Scheme
No.03
13.01.2016 213.12 55.98 10.67 13.58 650 During construction PM is above
the standard limit & baseline which
indicates pollution was caused due
to construction activity. Mitigation
measures like water sprinkling has
been carried out and construction
machinery has been equipped with
pollution control devices.
Alka Puri 12.01.2016 94.67 53.96 7.30 16.77 450 During construction PM is
below the standard limit as well as
baseline limit which indicates, no
pollution was caused due to
construction activity.
Baseline
Data
April- 2012 184.5 106.6 9.74 13.7 340
National Ambient Air Quality Standard 100 60 80 80 4000
31. Causes of high PM and PM .₅
PM a e high, all othe pa a ete s a e ithi sta da d li it as the sites ostly lie in the dry
weather and desert areas of Rajasthan the particulate matter due to movement of machinery and
construction activities may at times exceed the standard limit.
32. Corrective actions / Mitigation Measures Taken –
Air Quality
(i) Stockpiling of clay, soils, gravel, and other construction materials at designated areas;
(ii) Damp down exposed soil and any stockpiled on site by spraying with water when necessary
during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution control devices which are operating
correctly.
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 34 ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Noise Levels Monitoring – For the assessment of the background noise levels around the
construction sites ambient noise monitoring was conducted. Day and Night time Leq values
calculated from the measured values are presented in Table 10.
Table 10: Noise Quality Monitoring Results
SN Project Location Date of
Monitoring
Results of monitoring Remarks
Lday time
dB(A)
Lnight time
dB(A)
ALWAR
1
RUSDIP/TR-
01/ALW/WW/0
3 & WW-05
Scheme No.02 14.01.2016 61.7 45.6
Noise level is well within the
CPCB standards
2 Scheme No.03 13.01.2016 59.3 44.7
3 Transport Nagar 12.01.2016 62.8 50.9
4 Budhh Vihar 12.01.2016 54.9 48.2
5 Alka Puri 12.01.2016 58.6 49.4
Baseline April -2012 59.14 47.02
National Ambient Noise Standard
I Industrial Area 75 70
Ii Commercial/Mixed Area 65 55
Iii Residential/Rural 55 45
Iv Sensitive area 50 40
Conclusion: Noise levels are found within the permissible commercial/ mixed area limit both
during day and night time.
33. Groundwater Quality Monitoring- In order to assess groundwater quality in the vicinity of
the waste water project site at Alwar, a sampling location at UIT office was identified and borewell
water monitoring was carried out for certain parameters including physico-chemical, major and
trace elements, etc. Based on drainage pattern, water utilization, areas representing likely impacted
and baseline conditions etc., the location for groundwater source was identified and sample was
collected from a bore-well. The results are presented in Table 11.
Table11: Water Quality Monitoring Results
SN Parameters Unit Protocol Results Desirable Limit
(Max) Borewell
1 pH(at 25oc) - APHA 22nd Edition, 4500-
H+B
6.62 6.5 – 8.5
2 Total dissolved
solids
Hazen
Unit
IS: 3025 (Part -4), 1985,
Reaffirmed 2012
162 5/15*
3 Total Hardness
as CaCO3
mg/l IS: 3025 (Part -21), 1985,
Reaffirmed 2009
48 200/600*
4 Alkalinity as
CaCO3
mg/l APHA 22nd Edition, 3500
Ca B
200 200/600*
5 Chloride as Cl mg/l APHA 22nd Edition, 2320 B 32.67 250/1000*
6 Magnesium as mg/l APHA 22nd Edition, 4500 4.86 30/100*
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 35 ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
SN Parameters Unit Protocol Results Desirable Limit
(Max) Borewell
Mg CN-CD
7 Sulphate as SO4 mg/l APHA 22nd Edition, 2540 C 11.75 200/400*
8 Fluoride as F mg/l APHA 22nd Edition, 4500 E 1.0 1/1.5*
9 Nitrate as NO3-
N
mg/l APHA 22nd Edition, 4500-
F-D
41.21 45
10 Iron as Fe mg/l IS 3025 (P-34) 1988 BDL (<0.01) 0.3
11 Aluminium as Al mg/l APHA 22nd Edition, 3500-
Fe B
BDL (<0.03) 0.03/0.2*
12 Boron mg/l APHA 22nd Edition, 3111B BDL (<0.20) 0.50/1.0*
13 Phenolic
Compounds
mg/l APHA 22nd Edition, 4500B
C
BDL (<0.001) 0.001/0.002*
14 Anionic
Detergents as
MBAS
mg/l APHA 22nd Edition, 5530 C
Photometric method
5530D
BDL (< 0.02) 0.2/1.0*
15 Zinc as Zn mg/l APHA 22nd Edition, 3111B 0.130 5/15*
16 Copper as Cu mg/l APHA 22nd Edition, 3111B BDL (<0.02) 0.05/1.5*
17 Manganese as
Mn
mg/l APHA 22nd Edition, 3111B BDL (<0.10) 0.1/0.3*
18 Cadmium as Cd mg/l APHA 22nd Edition, 3111B 0.003 0.003
19 Lead as Pb mg/l APHA 22nd Edition, 3111B 0.01 0.01
20 Selenium as Se mg/l APHA 22nd Edition, 3111B BDL (<0.01) 0.01
21 Arsenic as As mg/l APHA 22nd Edition, 3111B 0.01 0.01/0.05*
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 36 ADB Loan No.: 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
V. CONCLUSIONS AND RECOMMENDATIONS
34. For protection of local environment during construction phase application of mitigation
measures continued as per specified EMP. Pubic consultation during construction/implementation
phase has not been carried out during this reporting period as the work is about to be completed.
Public consultations carried out in previous reporting period generated significant awareness among
people.
35. The status of compliance with EMP for sub-project under tranche-1 has been discussed in
Table 3 to Table 5 of Chapter II of the report including action required for lapses and responsibility
for the same.
36. During the construction phase, impacts mainly arise from the need to dispose of large
quantities of waste soil; and from the disturbance of residents, businesses, traffic and important
buildings by the construction work. These are common impacts of construction in urban areas, and
there are well developed methods for their mitigation. These include:
o Finding beneficial uses for waste material;
o Covering soil and sand during transportation and when stored on site;
o Planning work to minimize disruption of traffic and communities;
o Providing temporary structures to maintain access across trenches where required.
37. Improvement is observed in the management of excess excavated soil, use of Personal
Protective Equipment (PPE), condition of work/ labour camp, provision of excess for people and
ehi le th ough ope t e hes at fe pla es a d ai uality o ito i g. ‘e kless ess at o t a to s end has been observed to follow mitigation measure as per EMP for the same. The main area of
concern has been summarized below
Environmental Statutory Clearance: The consent to establish has been obtained from RPCB
for STP at Jaisalmer, landfill site of Jaisalmer and Jhalawar. The work of STP and landfill at
Alwar has been completed thus consent to operate has been obtained from RPCB. Consent
to operate will be required for STPs and landfills before operation. Since, Environmental
Clearance (EC) is not obtained for Jaisalmer landfill site from SEIAA seeking NOC of Air force
authority which is within 20 km of the site, the project is dropped. It has been observed that
felling of tree is not required for any of the package under Tr-01.
Air, Water & Noise Quality: Work order was issued to the monitoring agency but monitoring
has not been conducted in Jaisalmer due to delay on the side of motoring agency.
Monitoring agency has been pursued continuously to carry out monitoring. Solid waste
management Project has been completed in Jhalawar therefore monitoring is not required.
Landscape and Aesthetics: The unusable extra excavated materials are being disposed at
low laying area in consultation with ULBs. However excavated soil management is required
to be prepared and executed.
Socio-Economic – (Income & Employment): It was observed in few cases that proper access
across open trenches for people and vehicles has not been provided. In this regard
contractor has instructed to provide walkways and metal sheets where required to maintain
access. However in all cases more than 50% of the work force has been appointed locally.
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 37 ADB Loan No.: 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Occupational Health and Safety: Safety measures during work execution are the main issue
of concern. A limited use of personal protective equipment (PPE) was observed. The First-aid
facility is partially available at sites. It should be ensured that qualified first-aid facilities are
available at all sites all the time without fail. The safety officer is required to be appointed
for all packages by the contractor.
Work Camps: The basic facilities in worker camp has been improved as per EMP. Proper
Sanitary and solid waste management facilities is required in all work camps. Cooking gas
has been provided on most of the work sites to avoid cutting of trees for firewood.
38. Apart from the these common lapses to achieve full EMP compliance, sub-project wise
status of EMP compliance and mitigation measure for lapses have been discussed in Chapter II of the
report. Insurance is attached in annexure -4, mobilization schedule is shown in annexure-5 and
photographs of ongoing work is shown in annexure -7.
39. Necessary instructions have been given to the contractor by concerned DSC/IPIU for
improvement in compliance level. Following are the recommendations on the basis of the findings of
the report
Ensure regular monitoring for complete compliance on the lapses observed in bi-
annual environmental monitoring reports (EMR)
Provide copy of the environmental monitoring results to the concern contractors to
take necessary actions and include the mitigation measure in the training program
for high levels of observed parameters.
Ensure timely completion of environmental monitoring in all towns in future.
In case of any change in scope/location of project components, environmental
assessment for the same is required following approval of revised IEE from ADB.
Conduct ground water monitoring to assess any impact on ground water quality due
to construction activities for each sub-project as suggested by ADB
Ensure training for field staff including construction contractor staff on regular basis
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 38 ADB Loan No.: 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Annexure - 1
The Government of India has formulated various policy guidelines; acts and regulations aimed at the
sustenance of environment in general, which are briefly summarized and applicable acts with the
projects, are described in the following sub-sections.
Environmental Legislation and Pollution Control Acts
Sl. No. Sources Legislation
1 Water Pollution The Water (Prevention and Control of Pollution) Act, 1974, as
amended in 1988
2 Air Pollution The Air (Prevention and Control of Pollution) Act, 1981, as amended
by Amendment Act, 1987
3 Noise Pollution The Noise Pollution (Regulation and Control) Rules, 2000
4 Environment The Environment (Protection) Act, 1986
5 Public Liability The Public Liability Insurance Act, 1991
The Public Liability Insurance Rules, 1991
6 Hazardous Waste Hazardous Waste (Management and Handling) Rules, 1989
Batteries (Management and Handling) Rules, 2001
Manufacture, Storage and Import of Hazardous Chemical Rules,
1989
Emergency Planning Preparedness and Response for Chemical
Disasters Rules, 1995
Manufacturing, Use, Import, Export and Storage of Hazardous
Microorganisms, Genetically Modified Engineered Organisms or
Cell Rules, 1993
Hazardous Microorganisms and Genetically Modified Organisms
(Manufacture, Use Import Expert and Storage) Rules, 1999
Bio- Medical Waste (Management and Handling) Rules, 2000
7 Municipal Solid Waste Municipal Solid Waste (Management and Handling) Rules, 2000
Recycled Plastics Manufacturing and Usage Rules, 1999
8 EIA Notification The Ministry of Environment and Forests has revised the EIA
notification, 1994, and issues the revised EIA notification on 14th
September 2006
9 Use and Management of Explosive The Explosives Act, 1884 and The Explosives Rules, 1983
The Environment Protection act, 1986 and the EIA Notification, 1994
The Environmental (Protection) Act, 1986 is the umbrella legislation providing for the protection
of environment in the country. This Act provided for the Environment (Protection) Rules, which
ha e ee fo ulated u de the a t The E i o e tal I pa t Assess e t Notifi atio , 99 and the Amendments / Revised EIA notification on 14th “epte e .a d Yea 9.
The Forest (Conservation) Act, 1980
The Forest (Conservation) Act, 1980 pertains to the cases of diversion of forest area and felling
of roadside plantation. Depending on the size of the tract to be cleared, clearances are applied
for at the following levels in the governments:
If the area of forests to be cleared or diverted exceeds 20 ha (or, 10ha in hilly area),
the prior permission of the Central Government is required;
If the area of forest to be cleared or diverted is between 5 to 20 ha, the Regional
Office of Chief Conservator of Forests is empowered to approve;
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 39 ADB Loan No.: 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
If the area of forest to be cleared or diverted is below or equal to 5 ha, the State
Government can give permission;
and If the area to be clear-felled has a forest density of more than 40%, permission
to undertake any work is needed from the Central Government, irrespective of the
area to be cleared.
The Wildlife (Protection) Act, 1972
The Wildlife Protection Act has allowed the government to establish a number of National
Parks and Sanctuaries over the past 25 years, to protect and conserve the flora and fauna of
the state.
The Water and Air (Prevention and Control of Pollution) Acts 1974
The water (Prevention and Control of Pollution) Act, 1974 resulted in the establishment of
the Central and State level Pollution Control Boards whose responsibilities include managing
water quality and effluent standards, as well as monitoring water quality, prosecuting
offenders and issuing licenses for construction and operation of certain facilities. The SPCB is
also empowered to set air quality standards and monitor and prosecute offenders under the
air (Prevention and Control of Pollution) Act, 1981.
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 40 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Environmental Monitoring Report
Annexure – 2
Major Works and Progress
40. On date project works continued in all the 3 towns under Tranche 1 for water supply, waste
water and solid waste management sectors. Table below shows summary of the scope of works
along with present work status. Also expected changes from the approved objectives, remedial
measures for fulfillment of objective and key risks/ assumption for attainment of objectives are
mentioned in the table.
41. Monitoring and reporting on Environmental and Social safeguard have been started. At
present no as such adverse effect of project activities on social and environmental components.
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 41 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Major works and progress- Tranche 1
Locations Sub-projects Components
(Package No.)
What type of works continued at present Expected
changes from
approved scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions
and risks that
affect attainment
of the objectives
Alwar Waste Water - Supply, laying,
jointing, testing and
commissioning of various Main
and arterial sewer Network
connecting to outfall, along with
road restoration and all necessary
manholes appurtenances etc. at
Alwar town.
(RUSDIP/TR-01/ALW/WW/03)
Outfall (17.0 Km): 14.33 Km laid
Lateral Sewers (15.0 Km): 14.5 Km laid
Manholes (668 Nos.): 1080 Nos.
Hydro-testing:
1. Outfall (14.33 Km):14.33 Km
2. Laterals (14.5 Km): 14.5 Km
3. Manholes (668 Nos.): 1080 Nos.
Road Restoration (7.38 Km): 6.76 Km
Sewer Connections (1707 Nos.): 824 Nos.
No change
expected
o Effective
monitoring and
application of EMP
No risk
Alwar Waste Water:Additional
Sewerage System in UIT colonies
at Alwar
(RUSDIP/TR-01/ALW/WW/05)
Outfall (7.43 Km): 6.59 Km laid
Lateral Sewers (40.81 Km): 38.49 Km
laid
Manholes (1541 Nos.): 1365 Nos.
Hydro-testing:
1. Outfall (3.07 Km): 4.53 Km
2. Laterals (17.10 Km): 24.21 Km
3. Manholes (693 Nos.): 1365 Nos.
Road Restoration (15.01 Km): 14.83 Km
Sewer Connections (3964 Nos.): 1468 Nos.
No change
expected
o Effective
monitoring and
application of EMP
No risk
Jaisalmer Water Supply - Providing, Laying,
Jointing, Testing &
Commissioning of water pipe line
for the strengthening of
distribution system and rising
main pipeline; Construction and
Commissioning of Elevated
Supply from three reservoirs JNV Colony,
Gaffur Bhatta and JNV colony has been
started. Pump houses at Gajroop Sagar
and Gaffur Bhatta has been commissioned
Pipe line procured:- 67.13 km ( DI- 7.8 km,
uPVC-59.33km )
Pipe line Laid- 61.4 Km( DI-7.69 Km, uPVC-
No change
expected till
date.
o Effective
monitoring and
application of EMP
No risk
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 42 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Locations Sub-projects Components
(Package No.)
What type of works continued at present Expected
changes from
approved scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions
and risks that
affect attainment
of the objectives
service reservoirs and providing
pumping system and ancillary
works {RUSDIP/TR-01/ JSL/WS-
02}
53.82Km)
Line commissioned: 41.608 km (DI- 7.305
km, uPVC- 34.303 km).
ESR- 03 Nos completed
Domestic water Meter- 5000 nos
procured, 4583 nos installed.
Line tested- 41.608 Km ( DI- 7.305 Km,
uPVC-34.303 Km)
Interconnection and laying of distribution
line works in under progress.
Jaisalmer Waste water - Sewerage and
Waste stabilization Ponds in
Phase-I in Jaisalmer {RUSDIP/TR-
01/ JSL/WW-01}
Outfall (7.31Km) – completed 7.31 km
Lateral (35.566 Km) – 25.63 Km
Man Hole- 1130 Nos completed
STP – 95 % fencing work completed
No change
expected
o Effective
monitoring and
application of EMP
No risk
Jaisalmer Waste Water: Providing, laying,
jointing, testing and
commissioning of main sewer,
various intercepting sewer
collecting lateral sewers house
sewer connections, road
restoration along with all
appurtenances in Gandhi colony,
Indira colony, RP colony, part of
Gafur Bhatta and GAD colony,
construction commissioning of
civil, mechanical and and
maintenance of intermediate
sewage pumping stations in
Gandhi Colony at Jaisalmer Town
Outfall- (1.72 Km) – 1.72 Km completed
uPVC Pipe lateral sewer- Procured and
laid 20.31 Km,
property connections -101
Manholes- 1171
Civil work of SPS is 100% completed.
Pump House- civil work of Boundary wall,
Sump, inlet chamber, screen bar chamber
and pump room have been completed.
Works at IPS has been completed.
No change
expected
o Effective
monitoring and
application of EMP
No risk
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 43 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Locations Sub-projects Components
(Package No.)
What type of works continued at present Expected
changes from
approved scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions
and risks that
affect attainment
of the objectives
{RUSDIP/TR-01/JSL/WW/09}
Jhalawar-
Jhalrapatan
Solid Waste- Development of
Sanitary landfill Sites in Jhalawar
{RUSDIP/ TR-01/JHL/SW/08}
Excavation of landfill trenches has been
completed. Internal road and boundary
wall work & Tubewell is completed.
No change
expected
o Effective
monitoring and
application of EMP
No risk
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 44 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Annexure – 3
Environmental Monitoring Schedule
Monitoring Project
Type
Parameters Frequency No. of location Remarks
Ambient Air Quality Monitoring
Air quality
parameters
STP, WTP,
pump
house
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
4 days 24 Hrs
basis Semi-
annually
2 locations
nearby STP,
WTP, pump
house site
Intake
location
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
2 days 24 Hrs.
basis- Semi-
annually
1 location
nearby the
project site
Bridge,
Drainage
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
3 days 24 Hrs
basis Semi-
annually
2 locations
nearby bridge
Pipe laying
area
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
3 days 24 Hrs
basis Semi-
annually
3 locations
nearby working
zone
Ambient Noise Level Monitoring
Sound Pressure
Level
STP, WTP,
pump
house
Leq One time in
six months
(day & night)
3 nearby
locations
Intake
location
Leq One time in
six
months(day &
night)
2 nearby
locations
Bridge Leq One time in
six
months(day &
night)
5 nearby
locations
Pipe laying
area
Leq One time in
six
months(day &
night)
3 nearby
locations
Water Quality Monitoring
Surface water
Quality parameters
STP, WTP General: Turbidity NTU,
pH, Total Suspended
Solids, TDS, Total
Hardness as CaCO3 and DO
Organic Matters: BOD,
and COD
Nutrients: Nitrate and
Phosphate.
Anions: Chloride, Sulphate, Fluorine, Cl
(residual free).
Metals: Na, K, Ca, Mg, Fe,
Mn, Cd, As, Cr, Cu, Mg, Pb,
Se, Al, Zn, and Bo.
Other Organics: Phenolic
Compounds, Cyanide.
one time in six
months
2 locations
(pond, river,
nala)
(if location exist)
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 45 ADB Loan No. 2366 IND (Tr-1) Date: June 2016
Monitoring Project
Type
Parameters Frequency No. of location Remarks
Intake
location
Turbidity in NTU, pH, Total
Suspended Solid, TDS,
Total Hardness as CaCO3,
DO, BOD, and COD.
One time in
six months
2 locations
upstream and
downstream
River
bridge
As above One time in
six months
At least 2
location (pond,
river, nala)
upstream and
downstream
Ground water
Quality parameters
STP General: pH, Total
Dissolved Solids (TDS),
Total Hardness as CaCO3,
Alkalinity, and DO.
Anions: Cl, Sulphate,
Nitrate, and Phosphate.
Metals: Fe, Mg. Cd, As, Cr,
Co, Mg, Pb, and Zn
Organics: Phenolic
Compounds.
One time in
six months
At least 3
location (tube
well/ hand
pump/ bore
well)
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 46 ADB Loan No. 2366 IND (Tr-1) Date: Dec 2015
Annexure – 4
Sample Insurance Document for labors
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 47 ADB Loan No. 2366 IND (Tr-1) Date: Dec 2015
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 48 ADB Loan No. 2366 IND (Tr-1) Date: Dec 2015
Annexure -5
Details of Mobilization Schedule of Environmental Safeguard Personal
PMU
Responsibility Name Designation Duration
Overall supervision of Project and Environmental Compliance as per ADB
Policy
Mr. D R Jangid Project Officer Environment
Full Time
IPMC
Responsibility Name Designation Duration
Overall supervision of all towns
Dr. Ardhendu Mitra Environmental Expert
Intermittent
Shubhra Panwar Support Engineer Full time
Structure adopted at 15 towns
Nodal Officer of IPIU DSC Consultants
Towns Nodal Officer Designated by PMU
DSC I
Name Designation Duration
Alwar Mr. Saurabh Kr. Tayal Mr. Manoj Kumar Research Associate Intermittent
Dr. Sanjay Sharma Environmental Monitoring Specialist
Full time
Towns Nodal Officer Designated by PMU
DSCII
Name Designation Duration
Jaisalmer Mr. Amit K. Kumawat Dr. Amar Sarkar Research Associate Intermittent
Mr. Arvind Rajput Environmental Monitoring Specialist
Full time
Towns Nodal Officer Designated by PMU
DSC III
Name Designation Duration
Jhalawar Mr. J S Meena Mr. Abhay Srivastav Research Associate Intermittent
PMU; Project Management Unit; IPIU: Investment Program Implementation Unit; IPMC: Investment Program Management Consultant; DSC: Design Supervision Consultant Note: Nodal officers are engineer from IPIU having additional duty of safeguard
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 49 ADB Loan No. 2366 IND (Tr-1) Date: Dec 2015
Annexure -6
Environment Monitoring Report
AIR
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 50 ADB Loan No. 2366 IND (Tr-1) Date: Dec 2015
NOISE
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 51 ADB Loan No. 2366 IND (Tr-1) Date: Dec 2015
WATER
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 52 ADB Loan No. 2366 IND (Tr-1) Date: Dec 2015
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 53 ADB Loan No. 2366 IND (Tr-1) Date: Dec 2015
Annexure -7
Photographs
WW-05 Tej Mandi Road
WW-05 Near Railway Station
Barricaded Work sites under ongoing package WW-05 ALWAR
Environmental Monitoring Report
Semi-annual Environmental Monitoring Report
Tranche 2 (Loan Number 2506 –IND)
Document Stage: Final
Project Number: 40031
Month Year: June 2016
IND: Rajasthan Urban Sector Development
Investment Program
Prepared by Local Self Government Department
This report has been submitted to ADB by the Local Self-Government Department of the Government
of Rajasthan and is made publicly available in accordance with ADB’s public communications policy (2005), it does not necessarily reflect the views of ADB
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: I ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Contents
SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT ......................................................................... 1
A).BACKGROUND ........................................................................................................................................................... 1
B) PROJECT PURPOSE ...................................................................................................................................................... 1
C) PROJECT PROFILE ....................................................................................................................................................... 1
II. APPLICATION OF ENVIRONMENTAL MANAGEMENT PLAN ................................................................... 2
III. ENVIRONMENTAL PROCEDURE REVIEW ............................................................................................ 95
A).ENVIRONMENTAL LEGAL REQUIREMENTS ..................................................................................................................... 95
B). COMPLIANCE OF ENVIRONMENTAL REGULATIONS ........................................................................................................ 96
C). COMPLIANCE OF ENVIRONMENTAL LOAN COVENANTS ................................................................................................ 100
D). ENVIRONMENTAL ORGANIZATION AND MANAGEMENT ............................................................................................... 101
E). GRIEVANCE REDRESSAL .......................................................................................................................................... 102
IV.ENVIRONMENTAL MONITORING AND EVALUATION ........................................................................ 105
List of Tables Table 1 Sub-project Status- Tranche 2 (as on 30.06.2016) ....................................................................... 2
Table 2 Ongoing sub projects under review for Implementation of Environmental management Plan
(January - June 2016) ............................................................................................................................... 3
Table 3: Compliance of EMP for Alwar Waste Water sub-project {RUSDIP/TR-02/ALW/WW-06} ............. 5
Tabel 4: Compliance of EMP for Sawai Madhopur Water Supply {RUSDIP/TR-02/SMD/WS-02} ............. 11
Table 5: Compliance of EMP for Bhratpur ROB sub-project {RUSDIP/TR-02/BPR/BR/01} ........................ 18
Table 6: Compliance of EMP for Dholpur Water Supply sub-project {RUSDIP/TR-02/DLP/WS/03} .......... 24
Table 7: Compliance of EMP for Dholpur Waste Water {RUSDIP/TR-02/DLP/WW/04, WW/05, WW/08 &
WW/11} ................................................................................................................................................. 31
Table 8: Compliance of EMP for SIkar Water Supply sub Project {RUIDP/TR-02/SKR/WS-04} ................. 37
Table 9: Compliance of EMP for Nagaur Waste Water {RUSDIP/TR-02/NGR/WW/02-Lot-2} ................. 44
Table 10: Compliance of EMP for Barmer Waste Water {RUSDIP/TR-02/BMR/WW/03 Lot-1 & Lot-2} ... 50
Table 11: EMP Compliance Status of Churu subproject (RUSDIP/TR-02/CHU/WS-04) ............................ 57
Table 12: Compliance of EMP for Bundi Road sub-project {RUSDIP/TR-02/BND/ST/04} ......................... 63
Table 13: Compliance of EMP for Bundi waste water sub-project {RUSDIP/TR-02/BND/WW/06} .......... 69
Table 14: Compliance of EMP for Rajsamand Water Supply {RUSDIP/TR-02/RSM/WS/03} ..................... 76
Table 15: Compliance of EMP for Rajsamand Waste Water {RUSDIP/TR-02/RSM/WW/03} .................... 82
Table 16: Compliance of EMP for Jhalawar Waste Water {RUSDIP/TR-02/JHL/WW/02} ................. 88
Table 17: Action Required Ensuring Subprojects Comply with National Environmental Laws ................. 95
Table 18: Present Status of Environment and Forest & Other Clearances .............................................. 97
Ta le 19: Status of o plia e of ADB’s ajor E viro e tal Loa Cove a ts .................................. 100
Table 20: Town-wise number of Grievances......................................................................................... 102
Table 21: Methodology of Sampling and Analysis and Equipment Used ............................................... 105
Table 22: Average Ambient Air Quality Monitoring Data ...................................................................... 106
Table 23: Noise Quality Monitoring Results.......................................................................................... 108
Table 24: Groundwater Quality Results ........................................................................................... 110
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: II ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
List of Annexures
Annexure 1: Environmental Legislation and Pollution Control Acts ...................................................... 116
Annexure 2: Major works and progress- Tranche 02 ............................................................................ 118
Annexure 3: Environmental Monitoring Schedule ................................................................................ 125
Annexure 4: AIR, WATER & NOISE MONITORING REPORT .................................................................... 127
Annexure 5: Public Consultation ……………………………………….………………………………………………………..142
Annexure 6: Mobilization Schedule ...................................................................................................... 145
Annexure 7: Photographs...…………………………………………………………………………………………………………..146
List of Figures Figure 1: Institutional Responsibly-Environmental Organization RUSDIP .............................................. 103
Figure 2 Grievance Redressal Process .................................................................................................. 104
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 1 ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
I. INTRODUCTION
A). Background
1. Rajasthan Urban Sector Development Investment Program (RUSDIP) is intended to optimize
social and economic development in 15 selected towns in the State, particularly district headquarters
and towns with significant tourism potential. This will be achieved through investments in urban
infrastructure (water supply; sewerage and sanitation; solid waste management; urban drainage;
urban transport and roads), urban community upgrading (community infrastructure; livelihood
promotion) and civic infrastructure (art, culture, heritage and tourism; medical services and health;
fire services; and other services). RUSDIP will also provide policy reforms to strengthen urban
governance, management, and support for urban infrastructure and services. The assistance will be
based on the State-level framework for urban reforms, and institutional and governance reforms
recommended by the Government of India (GoI) through the Jawaharlal Nehru National Urban
Renewal Mission (JNNURM) and Urban Infrastructure Development Scheme for Small and Medium
Towns (UIDSSMT).
2. RUSDIP Phase II to be implemented over a seven year period beginning in 2008, and will be
funded by a loan via the Multi tranche Financing Facility (MFF) of the ADB. The Executing Agency (EA)
is the Local Self-Government Department (LSGD) of the Government of Rajasthan (GoR); and the
Implementing Agency (IA) is the Project Management Unit (PMU) of the Rajasthan Urban
Infrastructure Development Project (RUIDP), which is currently in the construction stage (Tr-1 & Tr-2).
Construction has also been started for Tr-3 sub-projects. Alwar, Jaisalmer and Jhalwar/ Jhalarapatan
are the towns chosen to benefit from the first tranche of RUSDIP investment. While 12 other towns
namely, Bharatpur, Karauli, Dholpur, Sawai Madhopur, Sikar, Barmer, Nagaur, Chittorgarh, Rajsamand
and Bundi are considered under tranche 2 and 3 (Tr-2 & 3).
3. This report presents environmental monitoring for reporting period from January to June
2016 for Tranche 2 sub-projects.
B) Project Purpose
4. RUSDIP will improve infrastructure through the development, design and implementation of
a series of subprojects, each providing improvements in a particular sector (water supply, sewerage,
solid waste etc.) in one town. RUSDIP has been classified by ADB as environmental assessment
category B (some negative impacts but less significant than category A) and the impacts of subprojects
were assessed through Initial Environmental Examination (IEE) reports prepared according to ADB
Environment Policy (2002), SPS 2009 and Environmental Assessment Guidelines (2003).
5. The nature of the sub-projects may change during their subsequent development, particularly
during detailed design. This report is the Environmental Monitoring Report (EMR) to describe the
implementation of the mitigation measures and monitoring recommended in the IEE and summary
Initial Environmental Examination (SIEE).
C) Project Profile
6. Till 30th June 2016, 48 sub-projects under Tranche 2 have been awarded. Details of which is
shown in table -1. During this reporting period work completed in total three packages i.e. two in
Bharatpur (BPR/ ST-01 & BPR/ WS-05) and one package in Dholpur (DLP/WW-05) in the month of
January and February 2016. The construction work for two new projects i.e. one package in Bharatpur
(RUSDIP/TR-02/BPR/BR/02) and one package in Churu (CHU/WS-04) had started during the previous
reporting period.
7. In the report period actual field work is continued in 18 sub projects. The application of EMP
in all ongoing sub-projects is shown in tables below in this chapter. The implementation status of sub-
projects under Tranche 2 has been summarized in Table -1.
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 2 ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Table 1 Sub-project Status- Tranche 2 (as on 30.06.2016)
SN
Town
Number of Sub-projects
Awarded Under-
implementation Completed
Yet to be
started
Work
Stopped
Terminated/
Dropped
1 Alwar 2 1 1 - - -
2 Karauli 1 1 - - -
3 Sawai
Madhopur 3 1 2 -
- -
4 Bharatpur 5 1 4 - -
5 Dholpur 5 5 - - -
6 Sikar 8 1 6 - - 1
7 Nagaur 4 1 2 - - 1
8 Churu 3 1 1 - - 1
9 Barmer 5 2 2 - - 1
10 Baran 2 0 2 - - -
11 Bundi 4 2 1 - - 1
12 Chittorgarh 1 - 1 - - -
13 Rajsamand 4 2 - - - 2
14 Jhalawar 1 1 - - - -
Total 48 18 23 00 - 07
II. APPLICATION OF ENVIRONMENTAL MANAGEMENT PLAN 8. At present there are 48 sub-projects under Tranche 2 have been awarded to the contractors.
Major Field activities are ongoing for 18 sub-projects. EMP has been implemented for 18 sub- projects
(3 sub projects were completed by February 2016) as per IEE report. The detailed list of projects under
review is presented in Table 2. Overall compliance status of EMP application and actions needed are
discussed below and shown in Table 3 to Table 16.
9. The EMP has been implemented in all ongoing sub-projects and status of the same is being
monitored. Annexure 2 shows summary of the scope of works, present work status, and expected
changes from the approved objectives, remedial measures for fulfillment of objective and key risks/
assumption for attainment of objectives.
10. Traini g has ee gi e to the o t a to s, D“C s o ito i g spe ialist a d IPIU ep ese tati e on environmental safeguard requirement. The status/progress of EMP implementation is also being
reviewed in quarterly review meetings and necessary training is being provided. Moreover instruction
is given to contractors to follow the specified clause of BID document to mitigate environmental and
social impacts.
11. In this report period field work continued for 18 sub-projects under tranche-2 as presented in
Table-2. The progress of implementation of the EMP has been monitored for each ongoing sub-
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 3 ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
project. For the purpose of monitoring of EMP and progress reporting project sector specific formats
were developed according the expected activities. The compliance with the EMP are expressed below
for each sub-project:
Table 2 Ongoing sub projects under review for Implementation of Environmental management
Plan (January - June 2016)
Sr. No. Project
Town
Packages
TR-2
1 Alwar Waste Water: Waste Water work in Alwar
Package No: {RUSDIP/TR-02/ ALW/WW/06}
2 Sawai
Madhopur
Water Supply: Construction of OHSRs, CWRs, Pump houses and rising & distribution lines.
Package No: {RUSDIP/TR-02/SMD/WS/02}
3 Bharatpur Bridge: Reconstruction of ROB and Approaches at Bharatpur town.
Package No: {RUSDIP/TR-02/BPR/BR/01}
4 Dholpur Water Supply: Design, Construction and Commissioning of 15 MLD capacity Water Treatment Plant
including commissioning of equipments at Sagarpada; Construction of CWRs & OHSRs including
supply, laying and commissioning with testing of DI & uPVC pipelines and replacing of leakaged
pipeline etc. for UWSS Dholpur.
Package No: {RUSDIP/ TR-02/ DLP/WS/03}
Waste Water: Supply, Laying, Jointing, Testing and Commissioning of outfall sewer, trunk sewers,
lateral sewers, lateral sewers along with construction of manholes, appurtenances etc. at Dholpur.
Package No. : (RUSDIP/TR-02/DLP/WW/04)
Waste Water: Design, construction, supply, erection, testing, commissioning and 5 year operation and
maintenance of 10 MLD sewage treatment plant based on UASB process with sewage pumping/lifting
station including all civil, electrical, mechanical, pumping and allied works in Dholpur town
Package No.: (RUSDIP/TR-02/DLP/WW/05) (work completed in January 2016)
Waste Water: Dholpur Sewerage work
RUSDIP/TR-02/DLP/WW/08
Waste Water: Design, construction, supply, erection, testing, commissioning and 5 years operation
and maintenance of 3 MLD Sewage Treatment Plant (STP) based on SBR process with sewage
pumping/lifting station including all civil, electrical, mechanical, pumping and allied works at Dholpur
town.
Package No.: {RUSDIP/TR-02/DLP/WW/11}
5 Sikar Water Supply: Additional work for augmentation of production of drinking water from newly proposed
Intermediate pumping Stations to various reservoirs in Sikar town. Package No: (RUSDIP/ TR-02/
SKR/WS/04)
6 Nagaur 8 MLD STP (RUSDIP/TR-02/NGR/WW-02 (Lot-02)
7 Barmer Waste water: Supply, sewer line work
Rajasthan Urban Sector Development Investment Program Project Number: 40031 Page: 4 ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Project
Town
Packages
{RUSDIP/TR-2/BMR/WW/03 (Lot-1)}
Waste water: STP 10 MLD
{RUSDIP/TR-2/BMR/WW/03 (Lot-2)}
8 Churu Water Supply: Water Supply Project in churu city
RUSDIP/ TR-02/ CHU/ WS/04
9 Bundi Roads: Widening and Strengthening of 13 different Roads in Bundi city. (RUSDIP/TR-02/BND/ST/04)
Waste Water: Construction of STP 8 MLD, 1 nos. SPS, out fall and trunk sewer 13.130 Kms
Package Number : (RUSDIP/TR-02/BND/WW/06)
10 Rajsamand Water Supply: Design, Construction and Commissioning of intake well & 17 MLD capacity Water
Treatment Plant including commissioning of equipments; Construction of CWRs & OHSRs including
supply, laying and commissioning with testing of DI & uPVC pipelines
Package No: {RUSDIP/ TR-02/ RSM/WS/03}
Waste Water: Design, Construction, Supply, erection testing, commissioning and five years operation &
maintenance of left over works of Sewage Treatment plant 5 MLD with Sewage pumping station
including all civil, electrical, mechanical, pumping and other allied works and supply, laying joining,
testing and commissioning of outfall sewer, various Trunk sewers, collecting and lateral sewers along
with all necessary manholes, appurtenances etc. at Rajsamand.
Package No: (RUSDIP/TR-02/RSM/WW /03)
11 Jhalawar Waste Water: Laying of Sewer line network at Jhalawar & Jhalarapatan town{RUSDIP/TR-
02/JHL/WW/02}
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 5
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Table 3: Compliance of EMP for Alwar Waste Water sub-project {RUSDIP/TR-02/ALW/WW-06}
Sr.
No. Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Pre- Construction Stage
1 Environmental Clearances
Site preparation works completed by IPIU including necessary
clearances
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish is not required as
the scope of work includes only laying of
pipes under this package.
Tree cutting is also not required.
Nil DSC / IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain
an expert assessment of the archaeological potential of the
site;
(ii) Consider alternatives if the site is found to be of
medium or high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure that
any chance finds are recognized and measures are taken to
ensure they are protected and conserved.
Complied It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential.
Instruction has been given to the
contractor to ensure that if any chance
finds are recognized, measures are taken
to make sure they are protected and
conserved.
No such occurrence found till date.
Nil DSC / IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
sub-project sites;
Complied All the facilities related to construction
are located within project site.
Nil Contractor/ DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 6
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas; and
(iv) Take extreme care in selecting sites to avoid direct disposal
to water body or in areas, which will inconvenience the
community.
No hot mix plant established for the
package.
Proper care has been taken to safeguard
property, vegetation, irrigation &
drinking water supply systems.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all
material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied All the material is being taken from
approved mines in consultation with
IPIU.
Nil DSC / IPIU
Construction Stage
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval
of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and
(iv) Submit documentation of sources of materials to DSC on a
monthly basis.
Complied All the material is being taken from
government approved quarry sites in
consultation with IPIU/DSC.
Nil DSC / IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying of water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
Complied Air quality monitoring has been carried
out during reporting period.
Construction materials have been
stockpiled at designated areas in
consultation with IPIU.
Nil Contractor /DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 7
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
(iv) Fit all heavy equipments and machineries with air pollution
control devices which are operating correctly.
Water sprinkling is being done as and
when it required.
The fine material carrying vehicles are
kept covered.
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface water quality inspection according to the
Environmental Management Plan (EMP).
Complied Ground water monitoring has been
carried out in reporting period.
Excavated soil is being reused for
backfilling and excess material is being
disposed in low lying areas.
Surface water quality inspection is not
required as there is no surface water
body near sub-project site.
Nil Contractor /DSC /
IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least
disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipments by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from
the vehicle/s.
Complied Noise level monitoring has been carried
out in the monitoring period.
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time.
Construction equipments are properly
maintained by contractor to minimize
the noise.
Noise level monitoring has not been
conducted in the reporting period.
Although the Monitoring Plan for the
Nil Contractor /DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 8
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
sub-projects has already been provided
by DSC to IPIU.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
(iv) Recover used oil and lubricants and reuse or remove from
the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
and
(vi) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer
required.
Complied Overburden and excavated materials
from construction sites are being reused
for backfilling and excess material is
disposed to designated areas.
Nil DSC / IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of
delivery sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Locate entry and exit points in areas where there is low
potential for traffic congestion;
(iv) Keep the site free from all unnecessary obstructions;
(v) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids, if
transportation activities cannot be avoided during peak
hours; and
(vi) Notify affected sensitive receptors by providing sign boards
informing nature and duration of construction works and
contact numbers for concerns/complaints.
Complied Short period traffic diversions are being
provided as per requirement.
Haulage activities are not significant
across the construction site.
Sign boards informing nature and
duration of construction works, and
contact numbers for
concerns/complaints has been provided
at each construction site.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 9
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets wherever required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied Planks/metal sheets is provided across
trenches, whenever required for easy
excess.
Nearby residents and business people
are informed about the nature of work in
advance through public consultation.
Adequate workforce has been provided
at critical areas.
Nil DSC / IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2 km immediate area, if
manpower is available; and
(ii) Secure construction materials from local market.
Complied At present most of the workforce is hired
locally which is more than 50%.
Nil DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided
with and use Personal Protective Equipments; (c) H and S
Training for all site personnel; (d) documented procedures
to be followed for all site activities; and (e) documentation of
work-related accidents;
(ii) Ensure that qualified first-aid is provided at all times.
Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
complied Proper use of PPEs by workers at site was
observed.
DSC is interacting frequently with
labours and site supervisor to aware
them about the necessity of use of PPEs
and to motivate labours for complete
use of PPEs at work site.
Adequate first-aid facility has been
provided at each site.
Group insurance has been provided to
workers.
Contractor has been
instructed for complete
compliance of measures
specified in EMP.
Contractor/
DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 10
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work
at the site, personal protective protection, and preventing
injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances
may be present. Ensure also that visitor/s do not enter
hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing
high voltage equipment, and areas for storage and disposal.
Signage shall be in accordance with international standards
and be well known to, and easily understood by workers,
visitors, and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
Drinking water has been provided at all
sites.
High visibility vests are provided to
workers.
Back-up alarms are not provided in
moving equipment.
Workers are not exposed to high noise
for 8 hours.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
Not
Applicable
At present most of the workers
employed are local.
Contractor has not constructed any
camp.
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 11
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Tabel 4: Compliance of EMP for Sawai Madhopur Water Supply sub-project {RUSDIP/TR-02/SMD/WS-02}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRE-CONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control
of Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
No clearances are required from
Pollution Control Board.
Tree cutting is not required.
Nil DSC / IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the
site;
(ii) Consider alternatives, if the site is found to be of medium
or high risk;
Complied
It was confirmed by consultations
with various stakeholders that the
site has no archaeological potential.
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures
Nil DSC / IPIU
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 12
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can
be made available; and
(iv) Develop a protocol for use by the construction
contractors in conducting any excavation work, to ensure
that any chance finds are recognized and measures are
taken to ensure they are protected and conserved.
are taken to ensure they are
protected and conserved.
No major excavation work required
at present.
No such occurrence recorded till
date.
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in
the subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider
sites that will not promote instability and result in
destruction of property, vegetation, irrigation, and
drinking water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct
disposal to water body or in areas which will
inconvenience the community.
Complied
All the facilities related to
construction are located within
project site.
No work camp & hot mix plant
established for the package.
Proper care has been taken
safeguard property, vegetation,
irrigation & drinking water supply
systems.
Nil DSC / IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining
Department;
(ii) If other sites are necessary, inform construction
contractor that it is their responsibility to verify the
suitability of all material sources and to obtain the
approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a
written approval from IPMU.
Complied
All the material is being procured
from approved mines in consultation
with IPIU.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 13
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain
approval of Investment Program Implementation Unit (
IPIU);
(iii) If additional quarries will be required after construction
has started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken from
government approved quarry sites in
consultation with IPIU/DSC.
Nil DSC / IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material
when transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
Works involving excavation of soil is
completed hence monitoring is not
required.
Nil Contractor/ DSC / IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the
monsoon season unless covered by tarpaulins or plastic
sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
Complied
Excavation works are almost
completed and excess spoils have
been utilized for backfilling.
Since no surface water is present
Surface water quality monitoring is
not required.
Nil
Contractor/ DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 14
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Place storage areas for fuels and lubricants away from
any drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities
in designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that
activities with the greatest potential to generate noise are
conducted during periods of the day which will result in
least disturbance;
(ii) Require horns not be used unless it is necessary to warn
other road use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from
the vehicle/s.
Complied
Noise monitoring is not conducted as
work has been completed.
Nil
Contractor/ DSC / IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to
designated areas;
(iv) Recover used oil and lubricants and reuse or remove
from the sites;
Complied
Excess excavated soil has been
removed and disposed off at
designated areas.
Nil
DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 15
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(v) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not
use narrow local roads, except in the immediate vicinity
of delivery sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary
road diversions and with for provision of traffic aids if
transportation activities cannot be avoided during peak
hours;
Complied
Works are carried out without
causing any congestion to the
existing traffic condition.
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Work almost completed, all ongoing
activities are within confined site
premises and no hindrance for access
to any residence or critical areas
Sign board has been provided at site.
Nil DSC / IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the
maximum extent, local persons within the 2-km
immediate area if manpower is available; and
Complied
At present most of the workforce is
hired locally.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 16
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Secure construction materials from local market.
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a)
excluding public from the site; (b) ensuring all workers
are provided with and use Personal Protective
Equipment; (c) H and S Training for all site personnel; (d)
documented procedures to be followed for all site
activities; and (e) documentation of work-related
accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible
throughout the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not
exposed to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of
work at the site, personal protective protection, and
preventing injuring to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or
substances may be present. Ensure also that visitor/s do
not enter hazard areas unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
Complied
Proper use of PPE observed.
Boundary will have to be constructed
after land demarcation.
Contractor has provided adequate
first-aid box at site.
Group insurance has been provided
to workers.
Proper barricading has been provided
to avoid unauthorized intrusion at
Commerce college OHSR site.
Drinking water has been provided at
sites.
H&S training is being provided to
workers by DSC regularly.
Workers are not exposed to high
noise level for more than 8 hrs.
Ensure complete use of
PPE.
Proper provision of
safety during working
at height should be
ensured.
Proper barricading is
required at Commerce
college OHSR site.
Contractor/DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 17
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(x) Ensure moving equipment is outfitted with audible back-
up alarms;
(xi) Mark and provide sign boards for hazardous areas such
as energized electrical devices and lines, service rooms
housing high voltage equipment, and areas for storage
and disposal. Signage shall be in accordance with
international standards and be well known to, and easily
understood by workers, visitors, and the general public as
appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices,
sheds, and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove
from the site;
(vii) Manage solid waste according to the following
preference hierarchy: reuse, recycling and disposal to
designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no
longer required;
Complied
At present most of the workers
employed are local.
No camp is constructed by the
contractor.
Nil Contractor / DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 18
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Table 5: Compliance of EMP for Bhratpur ROB sub-project {RUSDIP/TR-02/BPR/BR/01}
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
No clearances are required from Pollution
Control Board.
Tree cutting is not required.
Nil DSC / IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an
expert assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and
historical authorities, and interest groups in consultation
forums as project stakeholders so that their expertise can be
made available; and
(iv) Develop a protocol for use by the construction contractors
in conducting any excavation work, to ensure that any chance
finds are recognised and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC / IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
Complied
All the facilities related to construction
are located within project site.
There are neither any work camps nor hot
mix plants established for project works.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 19
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal
to water body or in areas which will inconvenience the
community.
Construction materials are temporarily
stored at sites with due consideration of
safeguard norms taking into account
vegetation, irrigation, and drinking water
supply systems.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all
material sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC / IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval
of Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of
sources of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC / IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
Complied
Ambient air quality monitoring has been
carried out in the reporting period.
Water sprinkling is being done as and
when it is required.
Nil Contractor/ DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 20
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
The fine material carrying vehicles are
kept covered.
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along
the drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Water quality monitoring has been carried
out in the reporting period.
Presently the excavation is started and
materials are dumped safely near the site
premises and will be utilized beneficially
for backfilling.
Surface water quality monitoring is not
required as there is no water body within
the site influence area.
Nil Contractor/ DSC /
IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn
othe oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
Partially
complied
Noise level monitoring has been
conducted in the reporting period.
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time.
Construction equipment are properly
maintained by contractor to minimize the
noise.
Nil Contractor/ DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 21
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of
excess excavated soils or immediately dispose to designated
areas;
(iv) Recover used oil and lubricants and reuse or remove from
the sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Excavated materials are dumped safely
near the site premises and will be utilized
beneficially for backfilling.
Nil DSC / IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Works are being carried out without
causing any congestion to the existing
traffic condition.
Transportation is being carried out during
non peak hours
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
Complied
All activities are within confined site
premises and no hindrance for access to
any residence or critical areas.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 22
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
(iv) Consult businesses and institutions regarding operating
hours and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided with
and use Personal Protective Equipment; (c) H and S Training for
all site personnel; (d) documented procedures to be followed
for all site activities; and (e) documentation of work-related
accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed
to hazardous or noxious substances;
Partially
complied
Use of PPE was observed at work site.
Qualified First-aid box has been provided
at site.
Group insurance has been provided to
workers
Proper barricading has been provided to
avoid unauthorized intrusion.
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
Awareness is done by the ACO, CAPP. The
contractor has nominated
All activities are within
confined site premises and no
hindrance for access to any
residence or critical areas.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 23
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at
the site, personal protective protection, and preventing injuring
to fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may
be present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing
high voltage equipment, and areas for storage and disposal.
Signage shall be in accordance with international standards and
be well known to, and easily understood by workers, visitors,
and the general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
representative for H & S (safety of
workers/public)
Workers are not exposed to high noise
level more than 8 hrs.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of
trees;
(iii) Provide water and sanitation facilities for employees;
Partially
Complied
Contractor has established a small
workers camp near RMC plant.
New toilets and bathroom have been
constructed.
Contractor has been instructed
for complete compliance of
EMP immediately.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 24
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr.
No.
Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from
the site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures
(such as buildings, shelters, and latrines) which are no longer
required;
Basic facilities in the camp at RMC plant
is better now but needs further
improvement.
New Toilets and bathroom have been
constructed.
Improved sanitation at camp was
observed. Soak pit has been constructed.
Adequate number of Cots for labours is
not provided yet.
Kerosene stove for cooking is provided by
contractor.
Table 6: Compliance of EMP for Dholpur Water Supply sub-project {RUSDIP/TR-02/DLP/WS/03}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Complied
Consent to Establish obtained from
Pollution Control Board for WTP. Consent
valid up to 31.05.2015. Work has been
completed. Plant will be operational after
receiving CTO.
Fpllow up with RPCB DSC and IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 25
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Application for Consent to Operate has
been submitted to RPCB.
Tree cutting is not required
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC / IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction
are located within project site
No work camp & hot mix plant established
for the package.
Proper care has been taken safeguard
property, vegetation, irrigation & drinking
water supply systems.
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 26
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC / IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC / IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
Air Quality Monitoring has been
conducted in the reporting period.
Excavation works are complete and excess
spoils have been utilized for backfilling.
Nil Construction/ DSC /
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
Complied
Ground Water quality monitoring has
been carried out in the reporting period.
Nil Construction/ DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 27
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Overburden and excavated materials
from construction sites are being utilized
in backfilling of trenches and remaining
material is used for leveling of nearby
low lying area
Surface water sampling is not required.
There is no water body nearby the sub-
project site
Oil & Lubricant has been stored away
from the drainage
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Complied
Noise level quality monitoring has been
carried out during reporting period.
Excavation works are complete and
excess spoils have been utilized for
backfilling.
Nil Construction/ DSC /
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling of trenches and remaining
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 28
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
material is used for leveling of nearby
low lying area
Leakage of oil and lubricant has not been
observed on site
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Easy access road is available for
transportation of construction materials.
Any inconvenience due to this is very
unlikely.
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Proper access is being provided as and
when required
Sign board has been provided at site
Nil DSC / IPIU
8 Socio-Economic – Employment Complied
At present most of the workforce is hired
locally
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 29
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
Complied
PPE are being used.
Qualified First-aid box is available at site.
Group insurance has been provided to
workers
Proper arrangement has been provided
to avoid unauthorized intrusion.
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
More H&S training is required for
contractor staff
Workers are not exposed to high noise
level more than 8 hrs
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 30
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Not Applicable
There is no camp for workers at present.
Most of the workers are local.
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 31
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Table 7: Compliance of EMP for Dholpur Waste Water sub-project {RUSDIP/TR-02/DLP/WW/04, WW/05, WW/08 & WW/11}
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
For WW-04 & WW-08 no consent to
eatablish is required as it is only pipe
laying work.
For WW-05 Consent to Establish obtained
from Pollution Control Board with validity
upto 31.07.2015 for 10 MLD STP under
package WW/05. The STP work is
complete.
The Application for Consent to Operate
has been submitted to RSPCB & is under
process. Not operational yet.
Consent to Establish for 3 MLD STP under
package WW/11 has been obtained and
is valid upto Valid till 30/09/2017
Permission has been obtained for cutting
of 3 trees under WW/04 package from
local administration.
Follow up with RPCB for CTO DSC & IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
Nil DSC & IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 32
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction
are located within project site
No hot mix plant established for the
package.
Proper care has been taken to safeguard
property, vegetation, irrigation &
drinking water supply systems.
Nil DSC & IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines in consultation with IPIU
.Nil DSC & IPIU
CONSTRUCTION STAGE
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 33
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites in
consultation with IPIU/DSC.
Nil DSC & IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
Air quality monitoring has been carried
out in the reporting period.
Sprinkling of water is being carried out as
per requirement at site in order to arrest
dust.
Fine material carrying vehicles are
properly covered to avoid dust problem.
Nil Contractor/ DSC &
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
Complied
Water quality monitoring has been
carried out in reporting period.
Tarpaulin is used to cover overburden
excavated materials which in turn is
being utilized further for refilling
activities and/or disposed off to
designated disposal location.
Surface water sampling is not required.
There is no surface water body nearby
the sub-projects sites.
Nil Contractor/ DSC &
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 34
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Complied
Noise level monitoring has been carried
out in reporting period.
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time.
Construction equipment are properly
maintained by contractor to minimize the
noise.
Generator sets and concrete mixtures are
provided with acoustic enclosures.
Nil Contractor/ DSC &
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Partially
Complied
Overburden and excavated materials
from construction sites are being
stockpiled for utilization in backfilling of
trenches
Prompt disposal of surplus excavated
material (if any after backfilling) to
designated area is required
No leakage of oil & lubricant has been
observed on site
Waste management plan is required
Instruction has been given to
contractor to disposed excess
excavated soil to designated
disposal areas in consultation
with IPIU/DSC.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 35
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Easy access road is available for
transportation of construction materials.
Nil Contractor/ DSC &
IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Proper access is being provided as and
when required
Sign board has been installed at site
Nil DSC / IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
Partially
complied
Reasonable use of PPE observed. Ensure complete use of PPE &
proper barricading at sites.
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 36
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
Barricading is not appropriate at some of
the sewer pipe laying sites.
Qualified first-aid box has been provided.
Wo ke s G oup i su a e has ot ee updated.
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
More H&S training is required for
contractor staff
Workers are not exposed to high noise
level more than 8 hrs
Wo ke s G oup insurance
needs to be updated urgently.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 37
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project
activities
Compliance
Explanation Action Proposed Responsibility
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Partially
complied
A small worker camp cum construction
yard has been established but the
arrangement is improper
Sanitation facilities need to be improved.
Instruction has been given to
contractor to discuss with
IPIU/DSC before camp
establishment and proper
compliance of EMP
Proper sanitation facilities is
required
Contractor
Table 8: Compliance of EMP for Sikar Water Supply sub Project {RUIDP/TR-02/SKR/WS-04}
Sr. No.
Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 38
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent/approval from Pollution Control
Board is not required for any component
under package.
Tree cutting permission is not required.
Nil DSC / IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC / IPIU
3 Construction work camps, hot mix plants, stockpile areas, storage
areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
Complied
All the facilities related to construction
are located within project site
Nil Contractor/ DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 39
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC / IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC / IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Sprinkling of water is being carried out as
per requirement at site in order to arrest
dust
Air quality monitoring has not been
carried out during report period
Adequate watering is required
at work site
Monitoring to be carried out in
next reporting period.
A log register for watering is
required to be maintained at
site.
Instruction has been given to
contractor to use tarpaulins to
Contractor/ DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 40
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
cover fine material when
transported
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Surface water quality monitoring is not
required as there is no surface water
source.
Ground water quality monitoring has
not been conducted in this reporting
period. Result will be repoted in the next
reporting period..
No surface water is available
near the project site
Contractor/ DSC /
IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
Noise monitoring has not been
conducted during report period,
Nil Contractor/ DSC /
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 41
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling of trenches and leveling of
low lying area as per direction of ULB of
Sikar town
Leakage of oil & lubricants has not been
observed on site.
Nil DSC / IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
The vehicles carrying materials to the
work site follow only designated route to
the site
Traffic diversions is not required at
present
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided
Nil DSC / IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
Complied
The work schedule has been prepared as
per consultation with local public
Proper access across trenches for people
and vehicles has provided
Nil DSC / IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 42
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Significant work force has been provided
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC / IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
Partially
complied
Health and Safety Plan has been
implemented on site.
PPE are being used.
First-aid box is available but not as per
standard
Group insurance has been provided to
workers
Barricading, safety tapes and delineators
have been adequately provided at work
fronts as public safety measures
Drinking water has been provided at sites
H&S training is being provided to workers
by DSC regularly
high visibility vests are provided to
workers
Contractor has been instructed
complete compliance of
measure specified in EMP
Safety officer is nominated by
contractor
IPIU/Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 43
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
Training for health and safety measures
have been given to contractor by DSC.
Workers are not exposed to high noise
level more than 8 hrs
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
Complied
At present most of the workers
employed are local.
Contractor has constructed temporary
camp at ESR sites (WS/02) which is now
removed as work has completed
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 44
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No.
Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Table 9: Compliance of EMP for Nagaur Waste Water sub-project {RUSDIP/TR-02/NGR/WW/02-Lot-2}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish for STP from
Pollution Control Board has been
obtained. Consent is valid up to
31.07.2015
CTE has been renewed via order number
2016-2017/PLG/1011 dated 27/07/2016
valid till 31/07/2018.
Tree cutting is not required
CTO will be obtained in
completion of the work.
IPIU/ DSC
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Nil IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 45
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
3 Construction work camps, hot mix plants, stockpile areas, storage
areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites that
will not promote instability and result in destruction of property,
vegetation, irrigation, and drinking water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction
are located within project site
Storage & leakage of oil and lubricants is
done as per the norms i.e. stored away
from the drainage.
Nil IPIU/ DSC
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor that
it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil IPIU/ DSC
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government; Complied
All the material is being taken from
government approved quarry sites
Nil IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 46
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources of
materials.
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling of
clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by spraying
with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
Air quality monitoring has been
conducted during report period
Sprinkling of water is being carried out as
per requirement at site in order to arrest
dust
Fine material carrying vehicles are
properly covered to avoid dust problem
Nil Contractor/ IPIU/
DSC
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with IPIU/DSC
on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling.
No surface water body near the working
area hence surface water monitoring is
not required.
Ground water quality monitoring is not
required as ground water is naturally high
in fluoride content and is unsuitable for
domestic use and is not extracted from
ground for use.
Nil
Contractor/ IPIU/
DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 47
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted during
periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
road users or animals of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
Noise monitoring has been conducted
and monitoring results has been provided
to the contractor for necessary mitigation
measure
Nil Contractor/ IPIU/
DSC
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling
No oil & lubricant leakage has been
observed on site.
Nil IPIU/ DSC
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
Complied
The trucks carrying materials to the work
site follow only designated route to the
site.
Sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided.
Nil IPIU/ DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 48
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to maintain
access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as institutions,
place of worship, business establishment, hospitals, and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Proper access is being provided as and
when required
Sign board has been provided at site
Nil IPIU/ DSC
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if manpower
is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil Contractor
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and S)
Plan which will include measures such as: (a) excluding public from
the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout the
site;
complied
PPE are being used partially.
Health and Safety Plan has been provided.
Contractor has provided first-aid box at
each site
Group insurance has been provided to
workers
Contractor has been instructed
complete compliance of
measure specified in EMP
Safety officer nominated by
contractor
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 49
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain access
to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
Barricading, safety tapes and delineators
have been adequately provided at work
fronts as public safety measures
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
Workers are not exposed to high noise
level more than 8 hrs
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 50
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds, and
construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials which
can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Partially
Complied
At present most of the workers employed
are local.
Labour camp has been established near
STP site
Poor water and sanitation facilities, use
of firewood are observed in labour camp
Contractor has instructed to
provide proper water and
sanitation facilities and cooking
gas to the worker
Contractor
Table 10: Compliance of EMP for Barmer Waste Water sub-project {RUSDIP/TR-02/BMR/WW/03 Lot-1 & Lot-2}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish has been obtained for
10 MLD STP under WW/03 Lot-2 package
from Pollution Control Board. The consent
is valid up to 01.07.2015. As the work is
already completed.
CTO has been applied to RPCB
Follow up with RPCB for CTO DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 51
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
The STP will be operational after obtaining
CTO.
Tree cutting is not required
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are recognised and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance finds
are recognized and measures are taken to
ensure they are protected and conserved
No such occurrence till date
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas, storage
areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction are
located within project site
Nil DSC/ IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department; Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 52
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Adequate sprinkling of water is required for
arresting fugitive dust
Biannual air quality monitoring has not
been conducted during reporting period.
Monitoring will be conducted in the next
reporting period.
Adequate watering is required
at work site
Monitoring results to be
reported in the next monitoring
Period.
A log register for watering is
required to be maintained at
site
Instruction has been given to
contractor to use tarpaulins to
cover fine material when
transported.
Contractor/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 53
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Surface water quality monitoring is not
required to be conducted during report
period as no surface water is available near
the project site.
Ground water quality monitoring is
required to be conducted.
Water quality monitoring to be
conducted in the next reporting
period.
Contractor/IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
The activities with the greatest potential
to generate noise are planned to conduct
during the day
Noise level monitoring is required to be
conducted during next reporting.
Noise quality monitoring to be
conducted in the next reporting
period.
Contractor/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 54
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(ii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials from
construction sites has been reused for
backfilling and excess material has been
disposed to designated areas
Any oil and lubricants leakage not
observed at site
Nil DSC/ IPIU
6 Accessibility
Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Traffic diversions are provided at
necessary points and as per requirement
sign boards informing nature and
duration of construction works and
contact numbers for concerns/complaints
has been provided
Nil DSC/ IPIU
7 Socio-Economic – Income
Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
Increase workforce in front of critical areas such as institutions,
place of worship, business establishment, hospitals, and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Proper access across trenches for people
and vehicles has been provided Sign
board has been provided at site
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 55
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC/ IPIU
9 Occupational Health and Safety
(i)Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
Partially
complied
PPE are being used completely
First-aid box is available at site
Group insurance has been provided to
workers
Proper barricading for unauthorized
intrusion has been provided except few
stretches of pipe laying areas
Drinking water has been provided at sites
Training for health and safety measures
have not been conducted by contractor
Workers are not exposed to high noise
level more than 8 hrs
Contractor has been instructed
complete compliance of
measure specified in EMP
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 56
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iii) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
complied
At present most of the workers employed
are local.
Labour camp has been established near
STP site (RUSDIP/TR-2/BMR/WW/03 (Lot-
2))
Poor water and sanitation facilities, use of
firewood are observed in labour camp
Contractor has instructed to
provide proper water and
sanitation facilities and cooking
gas to the worker
DSC / Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 57
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Table 11: EMP Compliance Status of Churu subproject (RUSDIP/TR-02/CHU/WS-04)
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish is not required
Tree cutting permission is not required.
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are 57hysic57ize and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
No such occurrence till date
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas, storage
areas, and disposal areas
(1) Prioritize areas within or nearest possible vacant space in the
subproject sites;
Complied
All the facilities related to construction
are located within project site.
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 58
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
2 Air Quality
(1) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
Partially
Complied
Adequate sprinkling of water is done for
arresting fugitive dust at all the running
sites
Adequate watering is required
at work site
A log register for watering is
required to be maintained at
site
Contractor/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 59
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iii)Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Air quality monitoring has been
conducted during report period.
Instruction has been given to
contractor to use tarpaulins to
cover fine material when
transported
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
In the pipe laying works excavated soil is
being back filled immediately after pipe
laying and excess soil is removed from
site
No surface water body near the working
area therefore surface water quality
monitoring is not required.
Nil Contractor/ DSC/
IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
Complied
Noise monitoring has been conducted
during reporting period
Activities are planned in consultation
with PIU
DGs are not being used but concrete
mixtures are not provided with acoustic
enclosures
Nil Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 60
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Maintenance of construction equipment
is required
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials
from construction sites has been reused
for backfilling and excess material has
been disposed to designated areas
Nil DSC/ IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
The vehicles carrying materials to the
work site follow only designated route to
the site
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided
Nil DSC/ IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
Complied
The work schedule has been prepared as
per consultation with local public
Significant work force has been provided
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 61
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
Partially
complied
PPE are being used.
First-aid box is available at site
Group insurance has been provided to
workers
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
Workers are not exposed to high noise
level more than 8 hrs
Contractor has been instructed
complete compliance of
measure specified in EMP
Contractor/IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 62
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
(iv) Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
Complied
At present most of the workers
employed are local.
Contractor has constructed temporary
camp at ESR sites which is removed as
work has been completed.
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 63
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Table 12: Compliance of EMP for Bundi Road sub-project {RUSDIP/TR-02/BND/ST/04}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Necessary clearances from various
departments have been taken before start
of project
Tree cutting is not required
Forest NOC has been obtained prior to
start of the work for all sites
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
Complied
It was confirmed by consultations with
various stakeholders that the sites has no
archaeological potential except Raniji ki
Baori.
It was confirmed in consultation with
nodal officer since it is a state protected
monument & there is no activity within
the monument, no permit is required for
the sub project.
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 64
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
are 64hysic64ize and measures are taken to ensure they are
protected and conserved.
3 Construction work camps, hot mix plants, stockpile areas, storage
areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Complied
All the facilities related to construction
are located within project site away from
residential area
Nil DSC/ IPIU
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 65
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Air quality monitoring is required to be
conducted.
Water sprinkling for arresting fugitive dust
is not being practiced.
air quality monitoring is required to be
conducted.
DG sets and other heavy equipment are
fitted with pollution control devices
Instruction has been given to
contractor for water sprinkling
at batching plant and to use
tarpaulins to cover fine
material when transported and
stored
Air quality monitoring is
required to be conducted.
Regularly by
Contractor
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Partially
Complied
Excavated soil is reused for surface
leveling and backfilling and excess soil is
being dumped in designated low lying
areas only
Fuels and lubricants are kept in
construction camp which is away from any
surface water source
Surface water quality inspection is being
carried out, no surface water exist near
running sites therefore surface water
quality analysis is not required
Ground water quality monitoring is
required to be conducted.
Ground water quality
monitoring is required to be
conducted in next reporting
period.
DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 66
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
Noise monitoring is required to be
conducted.
concrete mixtures are not being used
presently and DG sets are having noise-
reducing mufflers
Provide enclosures in concrete
mixtures
Noise monitoring is required to
be conducted at the earliest.
Contractor
IPIU
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials
from construction sites are being utilized
in backfilling of trenches
Nil DSC/ IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
Partially
Complied
The vehicles carrying materials to the
work site follow only designated route to
the site
sign boards informing nature and
duration of construction works and
contact numbers for
Contractor has been instructed
for complete compliance of
EMP
Contractor/IPIU/
DSC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 67
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
concerns/complaints has been provided
in most of the sites
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Not Complied
Proper access across trenches for people
and vehicles has not been provided
Significant work force has been provided
to finish work.
Provide proper access to shops
and residences
DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
Partially
complied
Site-specific Health and Safety Plan has
been prepared and communicated to
contractor and being followed at site
PPE are not being used completely in
some sites
First-aid facility has not been provided at
each site
Contractor has been instructed
complete compliance of
measures specified in EMP
Provide Proper PPEs in all the
sites
Provide sign boards in all
working sites with name and
contact numbers of the
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 68
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
Group insurance has been provided to
workers
Drinking water has been provided at all
sites
H&S training is being provided to workers
by DSC regularly
Sign board are not provided at some sites
Workers are not exposed to high noise for
8 hours
concerned site engineers of
IPIU, DSC and contractors
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 69
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Complied
Most of workers are local,
no workers camps is established by
contractor
NIL
Contractor
Table 13: Compliance of EMP for Bundi waste water sub-project {RUSDIP/TR-02/BND/WW/06}
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Pre-Construction Stage
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 70
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Complied
Encumbrance free site for proposed
STP handed over to contractors. All the
necessary clearances from various
departments have been taken before
start of project.
Tree cutting is not required.
Forest NOC has been obtained prior to
start of the work for all sites
Consent to Establish for STP has been
applied in RPCB
Follow up with RPCB for CTE DSC/ IPIU
2 Social and Cultural Resources
Any risk that any work involving ground disturbance can uncover
and damage archaeological and historical remains
Consult ASI to obtain an expert assessment of the archaeological
potential of the site;
Consider alternatives if the site is found to be of medium or high
risk;
Complied
It was confirmed by consultations with
various stakeholders that the sites has
no archaeological potential.
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas,
storage areas, and disposal areas
Do not consider residential areas for these purposes, sites
considered should not promote instability and result in
destruction of property, vegetation, irrigation, and drinking
water supply systems.
Complied
Construction camps are located away
from residential areas and do not affect
any supply system
Nil Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 71
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
4 Sources of Materials
Prioritize sites already permitted by the Mining Department;
otherwise verify the suitability of all material sources and
obtain the approval of IPIU
Complied
All the material is being taken from
quarry sites approved from IPIU
Nil DSC/ IPIU
Construction Stage
1 Sources of Materials
Prioritize sites already permitted by the Mining Department;
otherwise verify the suitability of all material sources and
obtain the approval of IPIU
Complied
All the material is being taken from
government approved quarry sites
with prior approval of IPIU
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for
stockpiling of clay, soils, gravel, and other construction
materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Partially
Complied
Water sprinkling for arresting fugitive
dust is not being practices
Air quality monitoring is pending for
which work order has been issued to
monitoring agency.
DG sets and concrete mixtures are not
fitted with pollution control devices
Instruction has been given to
contractor for water
sprinkling at all sites and to
use tarpaulins to cover fine
material when transported
and stored
Provide enclosures and
proper stake height in DG
sets and Concrete mixture to
reduce noise and dust
Conduct air quality
monitoring in the next
reporting period.
Regularly by
Contractor
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 72
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(iv) Dispose any wastes generated by construction activities in
designated sites; and
(v) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Partially
Complied
Excavated soil is reused for surface
leveling and backfilling and excess soil is
being dumped in designated low lying
areas only
Fuels and lubricants are kept in
construction camp which is away from
any surface water source
Surface water quality inspection is
being carried out, no surface water
exist near running sites therefore
surface water quality analysis is not
required
Contractor / IPIU
4 Noise Levels
(i) Plan activities with the greatest potential to generate noise
are conducted during periods of the day which will result in
least disturbance;
(ii) Minimize noise from construction equipment by using
vehicle silencers, fitting jackhammers with noise-reducing
mufflers, and portable street barriers the sound impact to
surrounding sensitive receptor; and
(iii) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
concrete mixtures and DG sets being
used are not having enclosures
Monitoring is required to be conducted
at the earliest.
Provide enclosures in
concrete mixtures
Noise monitoring is required
Contractor
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 73
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
The excavated soil is reused in surface
leveling works
Nil DSC/ IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Coordinate with Municipal Traffic Office for temporary road
diversions and for provision of traffic aids if transportation
activities cannot be avoided during peak hours; and
(vii) Notify affected sensitive receptors by providing sign boards
informing nature and duration of construction works and
contact numbers for concerns/complaints
Partially
Complied
The vehicles carrying materials to the
work site follow only designated route
to the site
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has not been
provided in most of the sites, road
signage for road safety is lagging in
some sites
Provide road signage and
road safety measures at all
sites
Contractor/ DSC/
IPIU
7 Socio-Economic – Income
(i) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(ii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment,
hospitals, and schools;
Not Complied
Metal sheets/wood planks are not
provided for access to shops at many
places
Provide safe access for
pedestrians by metal
sheets/wood planks
Increase work force to finish
the works quickly in city areas
Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 74
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
Significant work force has not been
provided in city area to complete work
in time
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is
hired locally
Most of the construction materials are
purchased from local market, if
available
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H
and S) Plan which will include measures such as: (a) excluding
public from the site; (b) ensuring all workers are provided with
and use Personal Protective Equipment; (c) H and S Training
for all site personnel; (d) documented procedures to be
followed for all site activities; and (e) documentation of work-
related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
(iii) Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
Partially
Complied
Site-specific Health and Safety Plan has
been prepared and communicated to
contractor and being followed at site
PPE are being used completely in some
sites
First-aid facility has been provided at
each site
Group insurance has been provided to
workers
Drinking water has been provided at all
sites
H&S training is being provided to
workers by DSC regularly
Sign board are not provided at some
sites
Contractor has been
instructed complete
compliance of measures
specified in EMP
Provide sign boards in all
working sites with name and
contact numbers of the
concerned site engineers of
IPIU, DSC and contractors
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 75
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
SN Environmental components related to project activities Compliance Explanation Action Proposed Responsibility
(vi) Provide clean eating areas where workers are not exposed
to hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at
the site, personal protective protection, and preventing injuring
to fellow workers;
(viii) Ensure moving equipment is outfitted with audible back-
up alarms;
(xii) Disallow worker exposure to noise level greater than 85
dBA for a duration of more than 8 hours per day without
hearing protection. The use of hearing protection shall be
enforced actively.
Workers are not exposed to high noise
for 8 hours
10 Work Camps
(i) Provide water and sanitation facilities for employees;
(iii) Prohibit employees from poaching wildlife and cutting of
trees for firewood;
(iii) Remove all wreckage, rubbish, or temporary structures; and
(ix) Request IPIU/DSC to report in writing that the camp has
been vacated and restored to pre-project conditions before
acceptance of work.
Not Complied
Temporary workers camps are
established in STP site which is not
having basic facilities like drinking
water, sanitation, solid waste
management etc
Provide appropriate workers
camp with all the basic
facilities
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 76
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Table 14: Compliance of EMP for Rajsamand Water Supply sub-project {RUSDIP/TR-02/RSM/WS/03}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish for 18 MLD capacity
Water Treatment Plant has been
obtained from pollution control board
valid upto 28.02.2019.
Tree cutting is done by forest department
after deposition of appropriate fees to
forest department
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are 76hysic76ize and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the sites have
no archaeological potential.
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas, storage
areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
Complied
All the facilities related to construction
are located within project site
Nil Contractor/DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 77
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
Partially
Complied
All the stockpiling is done at project area
only
Air quality monitoring has not been
conducted during the reporting period..
Air Quality monitoring need to
be conducted.
IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 78
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Partially
Complied
Excess excavated soil will be reused for
backfilling
Fuel and lubricants are stored away from
drainage
Surface water quality inspection is being
done regularly
Surface water quality monitoring has not
been conducted
Water quality monitoring need
to be conducted
IPIU/ Contractor
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time only
Noise level monitoring has not been
conducted
Noise level monitoring need to
be conducted
IPIU/ Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 79
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
The excavated soil is kept for reuse
whereas unusable extra excavated
materials and over burdens are being
disposed at low laying areas with proper
permission of concerned authorities
Nil DSC/ IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Presently construction vehicles and
transportation vehicles are not in use
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided
at sites
Nil DSC/ IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Presently excavation works are completed
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 80
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
At present only water meter and house
connections works are in progress in
which most of the workforce is hired
locally
Construction materials being procured
from local market where possible
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
Complied
First-aid box is available at site
Group insurance has been provided to
workers
Proper barricading for unauthorized
intrusion has been provided at all sites
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
Workers are not exposed to high noise
level more than 8 hrs
Contractor has been instructed
for complete compliance of
measures specified in EMP
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 81
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
At present most of the workers
employed are local.
Contractor has constructed temporary
camp at WTP site which is having
adequate facilities
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 82
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Table 15: Compliance of EMP for Rajsamand Waste Water sub-project {RUSDIP/TR-02/RSM/WW/03}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of
Pollution) Act
Tree-cutting Permit
Complied
Consent to Establish is obtained for
construction of STP and renewed which is
valid till 30/04/2018.
Tree cutting is done by forest department
after deposition of appropriate fees to
forest department
Consent to Operate for STP
from Pollution Control Board to
be taken before start of
operation
DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or
high risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
are 82hysic82ize and measures are taken to ensure they are
protected and conserved.
Complied
It was confirmed by consultations with
various stakeholders that the sites have
no archaeological potential.
Nil DSC/ IPIU
3 Construction work camps, hot mix plants, stockpile areas, storage
areas, and disposal areas Complied
All the facilities related to construction
are located within project site
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 83
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites
that will not promote instability and result in destruction of
property, vegetation, irrigation, and drinking water supply
systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor
that it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
(iv) Submit to DSC on a monthly basis documentation of sources
of materials.
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling
of clay, soils, gravel, and other construction materials;
Partially
Complied
All the stockpiling is done at project area
only.
Air quality monitoring is
pending.
Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 84
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Damp down exposed soil and any stockpiled on site by
spraying with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
No dust problem noticed at sites
Air quality monitoring is required to be
conducted.
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with
IPIU/DSC on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
NA
No surface water source near the work
sites
Ground water quality monitoring need to
be conducted.
Monitoring to be conducted Contractor/ DSC/
IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted
during periods of the day which will result in least disturbance;
(ii) Require horns not be used unless it is necessary to warn other
road users or animals of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time only
Noise monitoring is required to be
conducted.
Construction equipment being used are
having silencers except concrete mixtures
Concrete mixtures are required
to have enclosure to reduce
noise
Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 85
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
which are not having enclosures and
create noise during operation
IPIU needs to complete
environmental monitoring at
the earliest
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
The excavated soil is kept for reuse
whereas unusable extra excavated
materials and over burdens are being
disposed at low laying areas with proper
permission of concerned authorities
Nil Contractor/ DSC/
IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak
hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
Heavy vehicles traverse in non peak
hours through designated routes
Vehicle entry permission is being taken
from traffic authority
Nearby community and residents are
being informed prior to start of work and
project information boards are also
displayed at prominent sites
Nil DSC/ IPIU
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to
maintain access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as
institutions, place of worship, business establishment, hospitals,
and schools;
Complied
Walkways and access is provided to
shops and residence where possible
otherwise route diversion is done
Sufficient work force is deployed to finish
the works quickly
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 86
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if
manpower is available; and
(ii) Secure construction materials from local market.
Complied
Most of the unskilled labor are hired
from local people
Construction materials being procured
from local market where possible
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and
S) Plan which will include measures such as: (a) excluding public
from the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout
the site;
Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
complied
First-aid box is available at site
Group insurance has been provided to
workers
Proper barricading for unauthorized
intrusion has been provided at all sites
Drinking water has been provided at sites
Training for health and safety measures
have been given to contractor by DSC.
Workers are not exposed to high noise
level more than 8 hrs
Contractor has been instructed
for complete compliance of
measures specified in EMP
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 87
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(viii) Provide visitor orientation if visitors to the site can gain
access to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced
actively.
10 Work Camps
(i) Consult with IPIU/DSC before locating project offices, sheds,
and construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
Provide water and sanitation facilities for employees;
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials
which can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
Complied
At present most of the workers
employed are local.
Contractor has been instructed to
p o ide ade uate fa ilities i o ke s camp.
Provide all the basic facilities in
workers camp
Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 88
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Table 16: Compliance of EMP for Jhalawar Waste Water sub-project {RUSDIP/TR-02/JHL/WW/02}
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
PRECONSTRUCTION STAGE
1 Environmental Clearances
Site preparation work completed by IPIU including necessary
clearance
Consent to Establish under Water (Prevention and Control of
Pollution) Act
Consent to Establish under Air (Prevention and Control of Pollution)
Act
Tree-cutting Permit
Complied
All the site preparation works completed
including necessary clearances and sites
are handed over to contractor
Tree cutting is not anticipated presently.
Nil DSC/ IPIU
2 Social and Cultural Resources
(i) Consult Archaeological Survey of India (ASI) to obtain an expert
assessment of the archaeological potential of the site;
(ii) Consider alternatives if the site is found to be of medium or high
risk;
(iii) Include state and local archaeological, cultural and historical
authorities, and interest groups in consultation forums as project
stakeholders so that their expertise can be made available; and
(iv) Develop a protocol for use by the construction contractors in
conducting any excavation work, to ensure that any chance finds
Complied
It was confirmed by consultations with
various stakeholders that the site has no
archaeological potential
Instruction has been given to the
contractor to ensure that any chance
finds are recognized and measures are
taken to ensure they are protected and
conserved
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 89
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
are 89hysic89ize and measures are taken to ensure they are
protected and conserved.
No such occurrence till date
3 Construction work camps, hot mix plants, stockpile areas, storage
areas, and disposal areas
(i) Prioritize areas within or nearest possible vacant space in the
subproject sites;
(ii) If it is deemed necessary to locate elsewhere, consider sites that
will not promote instability and result in destruction of property,
vegetation, irrigation, and drinking water supply systems;
(iii) Do not consider residential areas;
(iv) Take extreme care in selecting sites to avoid direct disposal to
water body or in areas which will inconvenience the community.
Partially
Complied
Construction work camps and hot mix
plants are not present for this project.
Some storage and stockpile areas are
located within habitation for which
written consent from land owner is taken
and will not affect any vegetation and
drinking water supply systems
Disposal area is identified by Nagar
Parishad
Take prior written permission
from land owner to any
stockpile and storage area in
private place,
Avoid storage and stockpile
areas in or near habitations
Rehabilitate the stockpile and
storage areas up to the previous
conditions, used for
construction works
Contractor
4 Sources of Materials
(i) Prioritize sites already permitted by the Mining Department;
(ii) If other sites are necessary, inform construction contractor that
it is their responsibility to verify the suitability of all material
sources and to obtain the approval of IPIU; and
(iii) If additional quarries will be required after construction is
started, inform construction contractor to obtain a written
approval from IPMU.
Complied
All the material is being taken from
approved mines
Nil DSC/ IPIU
CONSTRUCTION STAGE
1 Sources of Materials
(i) Use quarry sites and sources permitted by government;
(ii) Verify suitability of all material sources and obtain approval of
Investment Program Implementation Unit ( IPIU);
(iii) If additional quarries will be required after construction has
started, obtain written approval from PMU; and;
Complied
All the material is being taken from
government approved quarry sites
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 90
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Submit to DSC on a monthly basis documentation of sources of
materials.
2 Air Quality
(i) Consult with IPIU/DSC on the designated areas for stockpiling of
clay, soils, gravel, and other construction materials;
(ii) Damp down exposed soil and any stockpiled on site by spraying
with water when necessary during dry weather;
(iii) Use tarpaulins to cover sand and other loose material when
transported by trucks; and
(iv) Fit all heavy equipment and machinery with air pollution
control devices which are operating correctly.
Complied
No dust problems noticed at work sites
PUCs of equipment is not available with
contractors
Air quality monitoring has been
conducted during reporting period.
Instruction has been given to
contractor to submit PUCs of all
vehicles being used
Contractor / DSC/
IPIU
3 Surface water quality
(i) Avoid stockpiling of earth fill especially during the monsoon
season unless covered by tarpaulins or plastic sheets;
(ii) Prioritize re-use of excess spoils and materials in the
construction works. If spoils will be disposed, consult with IPIU/DSC
on designated disposal areas;
(iii) Install temporary silt traps or sedimentation basins along the
drainage leading to the water bodies;
(iv) Place storage areas for fuels and lubricants away from any
drainage leading to water bodies;
(v) Dispose any wastes generated by construction activities in
designated sites; and
(vi) Conduct surface quality inspection according to the
Environmental Management Plan (EMP).
Complied
Excavated soil is being reused for
backfilling after pipe laying and Excess
soil is being disposed in designated areas
for leveling the low lying areas no need to
store the soil
Proper disposal of dewatered water is
being done in existing drains
No surface water source exist near to
existing sites
Dispose any wastes generated
by construction activities in
designated sites
Contractor / DSC/
IPIU
4 Noise Levels
(i) Plan activities in consultation with IPIU/DSC so that activities
with the greatest potential to generate noise are conducted during
periods of the day which will result in least disturbance;
Partially
Complied
Activities with the greatest potential to
generate noise have been planned in
consultation with IPIU and are being
conducted in day time
Nil Contractor/ DSC/
IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 91
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(ii) Require horns not be used unless it is necessary to warn other
oad use s o a i als of the ehi le s app oa h; (iii) Minimize noise from construction equipment by using vehicle
silencers, fitting jackhammers with noise-reducing mufflers, and
portable street barriers the sound impact to surrounding sensitive
receptor; and
(iv) Maintain maximum sound levels not exceeding 80 decibels
(dbA) when measured at a distance of 10 m or more from the
vehicle/s.
Noise monitoring has been conducted
for reporting period. .
5 Landscape and Aesthetics
(i) Prepare and implement Waste Management Plan;
(ii) Avoid stockpiling of excess excavated soils;
(iii) Coordinate with Municipal Board for beneficial uses of excess
excavated soils or immediately dispose to designated areas;
(iv) Recover used oil and lubricants and reuse or remove from the
sites;
(v) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
Complied
Overburden and excavated materials
from construction sites has been reused
for backfilling and excess material has
been disposed to designated areas
Nil DSC/ IPIU
6 Accessibility
(i) Plan transportation routes so that heavy vehicles do not use
narrow local roads, except in the immediate vicinity of delivery
sites;
(ii) Schedule transport and hauling activities during non-peak hours;
(iii) Coordinate with Municipal Traffic Office for temporary road
diversions and with for provision of traffic aids if transportation
activities cannot be avoided during peak hours;
Complied
The vehicles carrying materials to the
work site follow only designated route to
the site
sign boards informing nature and
duration of construction works and
contact numbers for
concerns/complaints has been provided
Temporary road diversion is being done
with consultation of municipal
authorities for non peak hours with
proper indication and boards
Nil DSC/ IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 92
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
7 Socio-Economic – Income
(i) Leave spaces for access between mounds of soil;
(ii) Provide walkways and metal sheets where required to maintain
access across trenches for people and vehicles;
(iii) Increase workforce in front of critical areas such as institutions,
place of worship, business establishment, hospitals, and schools;
(iv) Consult businesses and institutions regarding operating hours
and factoring this in work schedules; and
(v) Provide sign boards for pedestrians to inform nature and
duration of construction works and contact numbers for
concerns/complaints.
Complied
Excavated trenches are being back filled
immediate after the laying of pipes.
Significant work force has been provided
to finish the works quickly near sensitive
receptors
Nil DSC/ IPIU
8 Socio-Economic – Employment
(i) Employ at least 50% of the labour force, or to the maximum
extent, local persons within the 2-km immediate area if manpower
is available; and
(ii) Secure construction materials from local market.
Complied
At present most of the workforce is hired
locally
Construction materials are being secured
from local markets if available
Nil DSC/ IPIU
9 Occupational Health and Safety
(i) Develop and implement site-specific Health and Safety (H and S)
Plan which will include measures such as: (a) excluding public from
the site; (b) ensuring all workers are provided with and use
Personal Protective Equipment; (c) H and S Training for all site
personnel; (d) documented procedures to be followed for all site
activities; and (e) documentation of work-related accidents;
(ii) Ensure that qualified first-aid can be provided at all times.
Equipped first-aid stations shall be easily accessible throughout the
site;
Provide medical insurance coverage for workers;
(iv) Secure all installations from unauthorized intrusion and
accident risks;
(v) Provide supplies of potable drinking water;
Partially
complied
Contractor has provided site-specific
Health and Safety Plan but following the
EMP given in IEE
PPEs are not being used completely
during works
First-aid facility has been provided at
each site
Group insurance has been provided to
workers
Contractor has been instructed
complete compliance of
measure specified in EMP
Contractor is also instructed to
depute HSE personnel to look
after the EMP issues
Ensure proper use of PPEs
during construction works
Provide back-up alarms in all
moving equipments
Contractor, IPIU
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 93
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(vi) Provide clean eating areas where workers are not exposed to
hazardous or noxious substances;
(vii) Provide H and S orientation training to all new workers to
ensure that they are apprised of the basic site rules of work at the
site, personal protective protection, and preventing injuring to
fellow workers;
(viii) Provide visitor orientation if visitors to the site can gain access
to areas where hazardous conditions or substances may be
present. Ensure also that visitor/s do not enter hazard areas
unescorted;
(ix) Ensure the visibility of workers through their use of high
visibility vests when working in or walking through heavy
equipment operating areas;
(x) Ensure moving equipment is outfitted with audible back-up
alarms;
(xi) Mark and provide sign boards for hazardous areas such as
energized electrical devices and lines, service rooms housing high
voltage equipment, and areas for storage and disposal. Signage
shall be in accordance with international standards and be well
known to, and easily understood by workers, visitors, and the
general public as appropriate; and
(xii) Disallow worker exposure to noise level greater than 85 dBA
for a duration of more than 8 hours per day without hearing
protection. The use of hearing protection shall be enforced actively.
Drinking water has been provided at all
sites
H&S training is being provided to workers
by DSC and CAPP regularly
Back-up alarms are not provided in
moving equipment
Sign board are provided at all sites
Workers are not exposed to high noise for
8 hours
Contractor has not deputed HSE
personnel
10 Work Camps
(i)Consult with IPIU/DSC before locating project offices, sheds, and
construction plants;
(ii) Minimize removal of vegetation and disallow cutting of trees;
Provide water and sanitation facilities for employees;
Complied
At present most of the workers
employed are local.
Contractor has taken rental rooms for
workers and staff, most of the labors are
local and no camp is established in site
Nil Contractor
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 94
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Sr. No. Environmental components related to project activities Compliance
Explanation Action Proposed Responsibility
(iv) Prohibit employees from poaching wildlife and cutting of trees
for firewood;
(v) Train employees in the storage and handling of materials which
can potentially cause soil contamination;
(vi) Recover used oil and lubricants and reuse or remove from the
site;
(vii) Manage solid waste according to the following preference
hierarchy: reuse, recycling and disposal to designated areas;
(viii) Remove all wreckage, rubbish, or temporary structures (such
as buildings, shelters, and latrines) which are no longer required;
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 95
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
I. ENVIRONMENTAL PROCEDURE REVIEW
A). Environmental Legal Requirements
12. Annexure 1 lists those Acts; Rules, Policies and Regulations currently in force in India and deal with
environmental issues that could apply to infrastructure development. However, because of the relatively minor
negative impacts of most of the types of the subproject likely to be developed under RUSDIP, it is expected that
most subproject should not fall within the scope of these legal instruments. Subprojects and activities that will
need to comply with certain laws are:
Any components that require the acquisition of forest land;
Any construction activities located in areas covered by the Arvalli Range Notification in Alwar;
Water Treatment Plants (WTP) and Sewage Treatment Plants (STP);
Composting and landfill facilities;
Common waste management facilities, including composting, landfills, transfer stations;
Common waste management facilities within 10 km of the boundary of protected areas (such as
National Parks, Sanctuaries, Notified areas and Biosphere Reserves);
Mobile diesel generators
13. The specific requirements to ensure compliance by these components and subprojects are shown in
Table 17.
Table 17: Action Required Ensuring Subprojects Comply with National Environmental Laws
Component Applicable Legislation Compliance Action Required
1. All components that require
acquisition of forest land
Forest (Conservation) Act
1980; Wildlife (protection) Act
1972
Approval from
Ministry of
Environment and
Forests (MoEF)
Identify non- forest land and
formulate an afforestation
program
2. Water Treatment Plant (WTP)
and Sewage Treatment Plant
(STP)
Water (Prevention and Control
of Pollution)Act 1974
Consent to Establish
(CTE) and Consent to
Operate (CTO) from
RSPCB
Based on project review and
site inspection RSPCB provides
CTE before construction, and
stipulate the disposal standards
to be met during operation.
After completion of
construction, CTO is issued
confirming compliance with the
CTE conditions, if any
Renewal of CTO
during operation (STP)
Based on the performance of
the STP and its compliance with
the disposal standards CTO is
renewed every year
3. All composting and landfill
facilities
Municipal Solid Wastes
(Management and handing)
Rules 2000
Authorization of
proposed site by
RSPCB
Authorization is issued based
on land use in and around the
site and groundwater condition
Water (Prevention and Control
of Pollution ) Act 1974;
CTE and CTO from
RSPCB
Same as for STPs (above)
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 96
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Component Applicable Legislation Compliance Action Required
Air(Prevention and Control of
Pollution ) Act 1981
4. Common waste management
facilities including composting,
landfills and transfer stations
Environment (Protection) Act
1986: Environmental Impact
Assessment Notification 2006,
amended in 2009 Category B
Requires
environmental
clearance from State
Environment impact
Assessment Authority
(SEIAA)
Based on preliminary
information and site visits, if
required, project will be
categorized as B1 or B2. B1
projects require EIA study for
approval
5. Common waste management
facilities within or 10 km
outside the boundary of
protected areas such as
National Parks, Sanctuaries,
Notified Areas and Biosphere
Reserve
Environmental Impact
Assessment Notification, 2006
Category A
Requires
environmental
clearance from the
federal Ministry of
Environment and
Forests (MoEF)
Conduct EIA study
Category A and B1 projects
require public consultation as
part of EIA
6. Mobile diesel generators
Air (Prevention and Control of
Pollution ) Act 1981
CTE and CTO from
RSPCB
CTO renewal every year based
on performance
B). Compliance of Environmental Regulations
14. Table 23 below shows present clearance status for different sub-projects under Tr-2. GoI EIA
Notification of 2006 and its subsequent amendment (replacing the EIA Notification of 1994), sets out the
requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required
for specified activities/projects. Projects are categorized as A o B depe di g o the s ale of the p oje t a d the atu e of its i pa ts. Catego ies A p oje ts e ui e E i o e tal Clea a e f o the National Ministry of
E i o e t a d Fo ests MoEF a d Catego y B p oje ts e ui e e i o e tal lea a e f o the “tate Environment Impact Assessment Authority (SEIAA).
15. The only type of infrastructure provided by the RUSDIP that is specified in the EIA Notification is
Common Municipal Solid Waste Management facility (CMSWMF1), where EC is required. Thus Environmental
Clearance (EC) is not required for other sub-project under RUSDIP.
16. Co se t to Esta lish fo setti g up “e age T eat e t Pla t a d Wate T eat e t Pla t a d Co se t to Ope ate efo e the pla t sta ts its ope atio is e ui ed f o “tate Pollutio Co t ol Boa d ‘PCB u de the Water (Prevention and Control of Pollution) Act. 1974.
1 For the purpose of EIA Notification, common municipal solid waste management facilities may be referred as centralized
MSW facility for an given town, city, region. It is further to mention a common facility need not have surrounding ULBs
included.(Technical EIA Guidance Manual for CMSWMF)
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 97
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
17. As per the present status consent to establish has obtained for all the running sub-projects under Tr-2.
Attention is required by respective PIUs to obtain Consent to Operate before commissioning of STP/WTP.
Table 18: Present Status of Environment and Forest & Other Clearances
City Work (Package No.) Applicable
Legislation/ Type of
clearance
Clearance given by and
date
Subject
/ Issue
Remarks/ Action
needed
Sawai
Madhopur
(Tr-2)
Waste Water
(RUSDIP/TR-
02/SMD/WW-01)
Package No.
Changed as:
RUSDIP/TR-
02/SMD/WW-02
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 10 MLD STP from
Pollution Control
Board
Consent to Establish
obtained from
Pollution Control Board
– Order No. 2012-
2013/MUID/ 1013
dated 25.10.2012
Consent valid upto
30.04.2015
Consent to Operate for
DG set at STP obtained
from PCB- Order no.
2012-2013/MUID/1012
dated 25.10.2012.
Consent valid upto
31.08.2015
Consent to Operate has
been renewed via
order number 2016-
2017/PLG/1015 dated
07/10/2016, valid till
31/03/2019.
Nil Complied
Dholpur
(Tr-2)
Water supply
(RUSDIP/TR-
02/DLP/WS-03)
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 15 MLD WTP from
Pollution Control
Board
Consent to operate
will be required
before operation
Consent to Establish
obtained from
Pollution Control Board
– Order No. 2012-2013
/Bharatpur/ 885 dated
03.10.2012
Consent valid upto
31.05.2015
Application submitted
to RPCB for Consent to
Operate and is Under
process.
Renewal of CtE not
required as work
was completed.
Application
submitted to RPCB
for Consent to
Operate on
29/01/2015 and is
Under process. WTP
Work completed In
November 2015
Trial run &
commissioning
under process. Will
be operational after
getting Consent to
Operate.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 98
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
City Work (Package No.) Applicable
Legislation/ Type of
clearance
Clearance given by and
date
Subject
/ Issue
Remarks/ Action
needed
Dholpur
(Tr-2)
Waste Water
(RUSDIP/TR-
02/DLP/WW/04,
RUSDIP/TR-
02/DLP/WW/05 &
RUSDIP/TR-
02/DLP/WW/11 )
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 10 MLD STP from
Pollution Control
Board
Consent to operate
will be required
before operation
Consent to Establish
obtained from
Pollution Control Board
– Order No. 2012-
2013/MUID/943 dated
19.09.2012
Consent to establish
valid up to 31.07.2015
Consent to establish
has been obtained
from RPCB for 3 MLD
STP under WW/11
which is valid upto
30/09/2017
Application has been
submitted to RSPCB for
consent to operate 10
MLD STP on
02/02/2016 under
package WW/05 & is
under process.
CtO for 10 MLD STP
to be obtained
Complied
Application for CTO
has been submitted
to RPCB for 10 MLD
STP.
STP will be
operational after
getting Consent to
Operate.
Barmer
(Tr-2)
Waste Water
(RUSDIP/TR-
02/BMR/WW-03)
Lot-2
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 10 MLD STP from
Pollution Control
Board
Consent to operate
will be required
before operation
Consent to Establish
obtained from
Pollution Control Board
– Order No. 2012-
2013/MUID/945 dated
19.09.2012
Consent valid upto
31.07.2015
Work completed
Application for Consent
to Operate has been
submitted to RPCB.
CTO to be obtained
from RPCB
IPIU/ DSC to follow
up with RPCB.
STP will be
operational after
getting Consent to
Operate.
Nagaur RUSDIP/TR-
02/NGR/WW/02
(Lot-2)
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent for 8 MLD
STP from Pollution
Control Board
Consent to Establish
obtained from
Pollution Control Board
– Consent valid upto
31.07.2015
by RSPCB order No.
2012-2013/MUID/ 944
CTO to be obtained
from RPCB
CTE complied.
IPIU/ DSC to follow
up with RPCB for
CTO.
STP will be
operational after
getting Consent to
Operate.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 99
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
City Work (Package No.) Applicable
Legislation/ Type of
clearance
Clearance given by and
date
Subject
/ Issue
Remarks/ Action
needed
CtE renewed via order
number 2016-
2017/PLG/1011
Consent valid upto
31.07.2018
Application for CtO
submitted to RPCB
Rajsamand
(Tr-2)
Waste Water
(RUSDIP/TR-
02/RSM/WW-01)
Package No.
changed as
RSM/WW/03 Lot-1
& Lot-2
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 5 MLD STP from
Pollution
Control Board
Consent to operate
will be required
before operation
Consent to Establish
obtained from
Pollution Control Board
– Order No. 2012-
2013/MUID/877
dated 30.07.2012
Consent valid upto
30.04.2015
CtE renewed via order
number 2016-
2017/PLG/1010 and
valid upto 30/04/2018
CtO to be obtained
after completion of
the work
Complied
Rajsamand
(Tr-2)
Water supply
(RUSDIP/TR-
02/RSM/WS-01)
Package No.
changed as
RUSDIP/TR-
02/RSM/WS-03
Water (Prevention
and Control of
Pollution) Act. 1974/
Consent to establish
of 17 MLD WTP from
Pollution Control
Board
Consent to Establish
obtained from
Pollution Control Board
– Order No.
RPCB/ROU/Raj/W-
4/6155 dated 27.11.08
received on 02.04.09
Validity of the consent
is not written in the
CTE received
Consent to Operate has
been obtained via
order no. 2014-2015/
Bhilwara/3406 dated
05/12/2014
Validity- 06/03/2014 –
28/02/2019
- Complied
Bundi Waste Water
(RUSDIP/TR-
02/BND/WW-06)
Water (Prevention
and Control of
Pollution) Act. 1974/
Application to obtain
consent to Establish for
8 MLD STP has been
CtE to be obtained
from RPCB
Application to
obtain Consent to
Establish was
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 100
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
City Work (Package No.) Applicable
Legislation/ Type of
clearance
Clearance given by and
date
Subject
/ Issue
Remarks/ Action
needed
Consent to establish
for 8 MLD STP from
Pollution control
board
submitted on
30.03.2015 to RPCB.
submitted to RPCB
on 30/03/2015.
DSC/ IPIU to follow
up with RPCB.
C). Compliance of Environmental Loan Covenants
Table 19: Status of o plia e of ADB’s ajor Environmental Loan Covenants
Project Specific Covenants Status / Issues
Environmental
1.The EA shall ensure that: (LA Sched 5 Para 13)
(a) the project is carried out and all subproject facilities designed,
constructed, operated, maintained, and monitored in compliances
with the environmental law and regulations of the Borrower, the
state, ADB s E i o e tal Poli y , a d the EA‘F;
Under compliance in accordance with ADB
Environmental Policy and Environmental Assessment
Guidelines
2. Subproject encroaching any National Park or its buffer zone shall
not be included in the Project; however, Subproject in or close to the
wildlife sanctuary or any other environmentally sensitive area may
be allowed subject to the EA obtaining all statutory clearances;
No subproject will be taken up encroaching any
National Park or its buffer zone.
No sub-project in or close to the wildlife sanctuary or
any other lower grade environmentally sensitive area
recorded till date.
If it happens in future, environmental clearance will
be taken up as per Govt. procedure
3 an IEE as required, including an EMP with budget identifying the
cost of its implementation as incorporated in the related bid
document if any, when adequate public consultation for each sub-
project, in accordance with the EARF shall be submitted to ADB for
review and approval before award of related contract. In case of any
EIA or SIEE for sub-project classified as A or B sensitive, this shall be
subject to the 12 day pu li dis losu e e ui e e t u de ADB s Environmental Policy (2002, 2009)
An IEE have been prepared for each sub-project
where EMP, budget for application of EMP and issues
of public consultation are enclosed.
Budget and EMP components are incorporated in the
bid document
All the reports approved by ADB.
At present all the sub-projects are classified as class B
(only IEE will be required)
As per National rules EIA will be required for landfill
site handling more than 50 MT/day municipal solid
waste
4 all mitigation measures identified in the IEE, SIEE, EIA or SEIA and
the related EMP, as applicable, for each sub-project, shall be
incorporated in sub-project design, and carried out during
construction, and O & M, and disclosed to the stakeholders;
Under compliance: IEE screening of potential
environmental impact and mitigation measures
applied according to project location, specific sector
development and associated design requirements.
EMP s p epa ed a d egula ly o ito ed fo compliance of stated mitigation measures.
During construction process within the city
consultation with local communities on
environmental issues are considered
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 101
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Project Specific Covenants Status / Issues
Last EMP semi-annual Report (July - December 2015)
submitted and approved by ADB.
5 if there are any changes in specific locations or alignments of any
sub-project facilities after completion of the process of IEE (or EIA) or
due to detailed design or implementation that has an impact on the
environmental assessment carried out thus far, then additional
environmental assessment shall be carried out in accordance with
ADB s E i o e tal Poli y , 9 a d the EA‘F, a d p io approval of ADB obtained before further physical implementation of
the sub-project;
EMP already revised in case of change of scope/
location for few sub-projects under Tr-2.
In case of change in scope or location IEE will be
revised.
For minor change in location of project facilities EMP
has been revised for monitoring purpose
6 all environmental clearances required by applicable laws, and
regulations at Borrower, State, or local levels shall be obtained in a
timely manner, prior to commencement of civil works for the
relevant subproject
Under compliance: All necessary clearances presently
under pursuance. Specific clearance details are now
compiled for appropriate contract packages.
Clearance Plan prepared to a scheduled timeframe,
which is monitored for submissions to the various
agencies in obtaining the necessary clearances.
7 semi-annual progress reports on the implementation of the EMPs,
measures under the IEE/EIA, and the environmental monitoring shall
be carried out as a part of the project. Implementation for review
a d dis losu e i a o da e ith ADB s Pu li Co u i ations
Policy (2005)
Semi -annual progress report on application of EMP is
being prepared regularly
Field monitoring continued as per monitoring plan
During construction process within the city
consultation with local communities on
environmental issues has already initiated and
continued in most of the locations
D). Environmental Organization and Management
18. Environmental issues of the project coordinated by an Environmental Specialist within the IPMU/ IPMC,
who ensures that all subprojects, comply with environmental safeguards. An Environmental Monitoring
Specialist (EMS) who is part of the DSC team implement the Environmental Monitoring Plan from each IEE to
ensure that mitigation measures are provided and protect the environment as intended. Figure 1 shows
institutional responsibility for implementation of environmental safeguard monitoring at different level. Details
about the mobilization schedule of environmental safeguard personals are provided in Annexure 5.
19. EMP shows that most of the mitigation activities are the responsibility of the Construction Contractors
(CC) employed to build the infrastructure during the construction stage or the O&M Contractors employed to
conduct maintenance or repair work when the system is operating. Responsibility for the relevant measures
assigned to the Contractors via the contracts through which they are appointed, so they legally required taking
the necessary action. There are also some actions that need to be taken by LSGD in their role as project
proponent, and some actions related to the design that would be implemented by the DSC.
20. A program of monitoring would be conducted to ensure that all parties take the specified action to
provide the required mitigation, to assess whether the action has adequately protected the environment, and
to determine whether any additional measures may be necessary. This would be conducted by a qualified
Environmental Monitoring Specialist (EMS) from the DSC. The EMS responsible for all monitoring activities and
reporting the results and conclusions to the IPMU, and recommend remedial action if measures are not being
provided or are not protecting the environment effectively. The EMS may be assisted by environmental
specialist in particular technical fields, and junior or medium-level engineers of IPIU (designated as
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 102
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
environmental officer) who can make many of the routine observations on site. Post-construction monitoring
will be conducted by the relevant Government Agency (GA) to whom responsibility for the infrastructure will
pass once it begins to operate2.
21. EMP shows that most of the mitigation measures are fairly standard methods of minimizing disturbance
from building in urban areas (maintaining access, planning work to avoid sensitive times, finding uses for waste
material, etc), and experienced Contractors should be familiar with most of the requirements. Monitoring of
such measures normally involves making observations in the course of site visits, although some require more
formal checking of records and other aspects. There are also be some surveys of residents, as most of the
measures are aimed at preventing impacts on people and the human environment.
E). Grievance Redressal
22. The City Level Committee (CLC), acting as a grievance redress committee (GRC) is chaired by the District
Collector with representatives from the ULB, state government agencies, IPIU, community-based organizations
(CBOs) and NGOs. As GRC, the CLC meets at regular intervals based on the availability of the CLC /GRC members
and also as per requirement or pending issues. The grievance redress mechanism is provided at Figure 2. The
information w.r.t CLC/GRC is communicated to APs personally by the ACO in the concerned town. Further, the
complete detail of the CLC meeting is also displayed at the IPIU notice board and the notice board of the
olle to s offi e too. 23. IPIUs along with ACOs and DSCs have been entrusted with the responsibility to maintain a proper
register of the grievance (if any) which will be endorsed by the all three agencies involved in implementation.
General directions for registering grievances of APs were communicated in the meeting organized on 26.12.2011
followed by minutes issued vide letter no. 32060-67dated 30.12.2011. GRC registers are in place at all the towns.
Further ACOs have been given instructions to arrange more public consultations and register all the grievances
(including verbal) in writing whether substantial or non substantial and put them up for the perusal of IPIU for
proper disposal.
24. During this reporting period about 71 Grievances were received during past 6 months but these
grievances were generally related to issues like water line damages, road restoration, excess / accumulation of
soil moulds etc. A high number of grievances reported in Bharatpur (23). Detail about other towns is provided
in Table No. 20.
25. These grievances are resolved by the IPIUs as and when received. But grievances like demand of water
or sewerage connection/line etc. are resolved as per the scope of work through proper approval from RUIDP.
Table 20: Town-wise number of Grievances
Sl. No Town Number of
Grievance Sl. No Town Number of Grievance
1 Alwar 4 9 Jaiselmer 0
2 Baran 0 10 Jhalawar 0
3 Barmer 7 11 Karauli 0
4 Bharatpur 23 12 Nagaur 2
5 Bundi 6 13 Rajsamand 14
6 Chittorgarh 0 14 Sikar 8
7 Churu 2 15 Swai Madhopur 0
8 Dholpur 5 Total 71
2 In the operational period some infrastructure will be the responsibility of the Municipal Boards/Councils, whilst others will be the
responsibility of the appropriate branch of the State government (such as PWD, PHED, etc)
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 103
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Figure 1: Institutional Responsibly-Environmental Organization RUSDIP
Ministry of Urban Development (MoUD), LSGD-
EA
Government of Rajasthan
Rajasthan Urban Sector
Development Investment
Program (RUSDIP)
Implementing Agency
Investment Program Implementation
Units (IA - IPMU)
Several Construction Packages for
different tranches under each
IPIU(Nominated Environmental Monitoring
Engineer/ Officer)
Design and Supervision
Consultants (DSC)
Construction Contractors (CC)
Environmental Monitoring Specialist
(EMS) Provided by DSC
Independent Environmental
Testing & Monitoring Agency
(On need basis)
IMPLEMENTATION OF
EMP
ADB
Investment Program
Management Consultancy
(IPMC)
Appointed by RUSDIP
Environmental
Expert of IPMC
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 104
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
CLC = City Level Committee,
GRC = Grievance Redress Committee,
IPIU=Investment Program Implementation Unit,
IPMU = Investment Program Management Unit,
NGO = Nongovernmental organization,
SDS = Social Development Specialist.
Not Addressed
APs
IPIU
IPMU
Grievance
Addressed
GRC/CLC
Grievance
Addressed Not Addressed
Grievance
Addressed
Figure 2 Grievance Redressal Process
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 105
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
IV. ENVIRONMENTAL MONITORING AND EVALUATION 26. For effective monitoring, selected environmental parameters have been identified as indicators which
may be qualitatively and quantitatively measured and compared over a period of time in order to assess/ensure
the compliance of EMP. The environmental performance indicators are physical, biological and social
characteristics identified as most important in affecting the environment at critical locations all along the sub-
project corridors. The parameters identified as performance indicators are:
Air, noise and water quality
Compliance to EMP
Compliance to local/state/national environmental regulations
27. After starting of construction work for Intake, STP, WTP air pollutants should be measure at core and
buffer zone of the proposed STP. WTP site. If any water body exists near the STP, WTP physico-chemical
properties of the water should be measure as part of base line environment. Environment monitoring reports
are at attached in Annexure -4.
28. Also during construction of landfill site monitoring in respect to air, noise, and water quality are required.
29. At bridge construction site monitoring of ambient air quality are also necessary. Environment monitoring
reports are shown in Annexure 4.
30. At pipe laying area air and noise quality monitoring should be done as per scope of work depicted in
Annexure 3.
31. The air, water and noise quality monitoring have been carried out during reporting period in most of the
towns except Barmer, Sikar and Rajsamand. Work is in completion stage and no substantial work was carried
out in the reporting period therefore monitoring is not required in Barmer and Sikar. Whereas in Rajsamand,
work order has been issued and monitoring is expected to be carried out soon.
32. Ambient Air Quality Monitoring - It is indispensable to assess the existing ambient air quality of the
environment for baseline information in order to quantify the impact of the proposed project activities on the
ambient air quality of the site. The existing ambient air quality at the proposed project site was assessed with
respect to Respirable Particulate Matter (PM ), Particulate Matter (PM .₅), Sulphur dioxide (SO ), Nitrogen
dioxide (NO ) and Carbon monoxide (CO), measured through an intended field monitoring.
33. Selection of Sampling Locations and Methodology of analysis - Meteorological conditions and landuse
type of the likely impacted areas near to the proposed project construction sites were taken into account while
deciding on sampling locations for assessing ambient air quality of the study area. The methodology adopted for
analysis is summarized in Table 21.
Table 21: Methodology of Sampling and Analysis and Equipment Used
SN Parameter Protocol Analysis Procedure Instrument Used
1 PM 10 IS: 5182 (Part-23)-2006 Gravimetric High volume Sampling using Respirable
Dust Sampler APM 460 BL
2 PM 2.5 Instrument manual Gravimetric Fine Particulate Sampler APM 550
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 106
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
SN Parameter Protocol Analysis Procedure Instrument Used
3 SO2 IS: 5182 (Part-2)-2001 Colorimetric Spectrophotometer
4 NO2 IS: 5182 (Part-6)-1975
Reaffirmed 1998 Colorimetric Spectrophotometer
5 CO IS: 5182 (Part-10)-1999 Colorimetric Spectrophotometer
Table 22: Average Ambient Air Quality Monitoring Data
Project Sampling
Location
Date of
Monitoring
Results of monitoring (µg/m3) Remarks
PM PM .₅ “O NO CO
mg/m3
Alwar
RUSDIP/TR-
02/ALW/WW-
06
Ambedkar
Nagar 12.01.2016 142.68 57.99 10.62 12.38 450
Du i g o st u tio PM is a o e the standard limit but below the baseline
limit which indicates PM did not rise
because of construction activity. “O and
CO are slightly above the baseline limit
but much below standard limit.
Budh Vihar 12.01.2016 214.87 67.71 9.49 11.07 240
Du i g o st u tio PM was found to
be above the standard & baseline limit.
Mitigation measures like water sprinkling
has been carried out regularly.
Transport
Nagar 12.01.2016 138.89 48.45 6.61 16.36 330
Du i g o st u tio PM is found to be
slightly above the standard but below
baseline limit which indicates there is no
increase in PM due to construction
activity & NO is found to be slightly
above baseline limit but much below
standard limit.
Baseline Data April- 2012 184.5 106.6 9.74 13.7 340
Bharatpur
RUSDIP/TR-
02/BPR/BR-01, Bud ki Hat 05.02.2016 167.41 50.64 7.47 16.64 260
Du i g o st u tio PM is a o e the standard limit but below baseline limit
which indicates there is no increase in
PM due to construction activity
Baseline data PHED Pump
house April 2012 213.2 77.3 11.2 20.2 >500
Dholpur
RUSDIP/TR-
02/DLP/WS/03-
WTP
WTP 28.05.2016 286.73 62.39 8.44 20.36 280
Du i g o st u tio PM & PM .₅ is
above the standard as well as baseline
limit, which indicates construction
activity has caused increase in the PM &
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 107
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Project Sampling
Location
Date of
Monitoring
Results of monitoring (µg/m3) Remarks
PM PM .₅ “O NO CO
mg/m3
PM .₅ levels. Regular water sprinkling has
been carried out as a Mitigation measure
to reduce PM & PM .₅ levels .NO is
found to be slightly above baseline limit
but much below standard limit.
RUSDIP/TR-
02/DLP/WW/04
-05- STP
STP 28.05.2016 185.37 27.83 3.61 13.16 310
Du i g o st u tio PM is above the
standard as well as baseline limit which
indicates construction activity has caused
increase in the PM levels. Mitigation
measures like regular water sprinkling is
carried out to control increase in PM
levels.
RUSDIP/TR-
02/DLP/WW/08 Ondilla road 28.05.2016 256.18 82.92 6.92 16.43 340
Du i g o st u tio PM & PM .₅ is above the standard as well as baseline
limit which indicates construction activity
has caused increase in the PM & PM .₅ levels.
RUSDIP/TR-
02/DLP/WW/11 Court road 28.05.2016 238.88 36.14 4.48 18.39 380
Du i g o st u tio PM is above the
standard as well as baseline limit which
indicates construction activity has caused
increase in the PM levels. Mitigation
measures like regular water sprinkling is
carried out to control increase in PM
levels.
Baseline Bus Stand May – June
2012 139.3 55.5 9.9 18.1 >500
NAGAUR
RUSDIP/TR-
02/NGR/WW/0
2 (Lot-2)
Near Dhulaya
Nada IPS 31.05.2016 92.5 46.2 9.1 17.4 260
All parameters within permissible limits
Baseline Data April-May
2012 191.4 21.2 13.6 21.2 <1.15
Churu
RUSDIP/TR-
02/CHU/WS/04
Near Pankha
Cirlce
26.05.2016 145.8 63.2 12.6 24.2 410 Du i g o st u tio PM & PM .₅ is
above the standard limit but below
baseline limit which indicates there is no
increase in PM & PM .₅ due to
construction activity. NO is found to be
slightly above baseline limit but much
below standard limit.
Baseline Data Johri Talab Feb 2013 226 89.5 14.2 16.4 <1.15
Jhalawar
RUSDIP/TR-
2/JHL/WW-02
Near STP &
Landfill site
06.01.2016 201.15 56.5 9.83 15.74 340 Du i g o st u tio PM is above the
standard limit but below baseline limit
which indicates there is no increase in
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 108
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Project Sampling
Location
Date of
Monitoring
Results of monitoring (µg/m3) Remarks
PM PM .₅ “O NO CO
mg/m3
PM due to construction activity though
mitigation measures are taken.
Anand Dham
Temple
05.01.2016 87.51 51.43 10.42 19.88 290 All parameters are within permissible
limit except NO which is found to be
slightly above baseline limit but much
below standard limit.
Baseline 14.12.2012. 273.3 71.79 12.76 15.61 330
National Ambient Air Quality Standard 100 60 80 80 4000
34. Corrective actions / Mitigation Measures Taken –
Air Quality
(i) Stockpiling of clay, soils, gravel, and other construction materials designated areas;
(ii) Damp down exposed soil and any stockpiled on site by spraying with water when necessary during
dry weather;
(iii) Use tarpaulins to cover sand and other loose material when transported by trucks; and
(iii) Fit all heavy equipment and machinery with air pollution control devices which are operating
correctly.
Noise Levels Monitoring – For the assessment of the background noise levels around the construction sites
ambient noise monitoring was conducted. Day and Night time Leq values calculated from the measured values
are presented in Table 23.
Table 23: Noise Quality Monitoring Results
SN Project Location Date of
Monitoring
Results of monitoring Remarks
Lday time
dB(A)
Lnight time
dB(A)
Alwar
1
RUSDIP/TR-
02/ALW/WW-06
Ambedkar Nagar 12.01.2016 66.7 50.9
During construction noise level
slightly above the standard specified
for commercial areas and baseline
results
Budh Vihar 12.01.2016 54.9 48.2 Noise levels are within permissible
limits for commercial area
Transport Nagar 12.01.2016 62.8 50.9 Noise levels are within permissible
limits for commercial area
Baseline Data April- 2012 59.14 47.02
Bharatpur
1 RUSDIP/TR-
02/BPR/BR-01,
WW-01(Lot-01 &
Lot-02)
SPS-3 near Gopal
Nagra Village 05.02.2016 62.8 53.4
Noise levels are within permissible
limits for commercial area
STP site 05.02.2016 65.3 50.8 Noise levels are within permissible
limits for commercial area
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 109
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
SN Project Location Date of
Monitoring
Results of monitoring Remarks
Lday time
dB(A)
Lnight time
dB(A)
Baseline data PHED Pump house July 2014 64.2 50.98 Noise levels are within permissible
limits for commercial area
Dholpur
1 RUSDIP/TR-
02/DLP/WS/03-
WTP 28.05.2016 62.4 55.3
Noise levels are within permissible
limits for commercial area
2 RUSDIP/TR-
02/DLP/WW/04-
05-
STP 28.05.2016
60.9 51.3 Noise levels are within permissible
limits for commercial area
3 RUSDIP/TR-
02/DLP/WW/08 -
Ondilla road 28.05.2016 65.6 58.4
Noise levels are within permissible
limits for commercial area
4 RUSDIP/TR-
02/DLP/WW/11-
Court road 28.05.2016 50.2 67.4
Noise levels are within permissible
limits for commercial area
Baseline data June 2012 74.18 70.10
NAGAUR
1 RUSDIP/TR-
02/NGR/WW/02
(Lot-2)
Near Dhulaya Nada
IPS
17.12.2015
47.12 38.39 Noise levels are within permissible
limits for commercial area
Churu
1 RUSDIP/TR-
2/CHU/WW/03
(Lot-01 & Lot-02)
and RUSDIP/TR-
02/CHU/WS/04
STP site 08.12.2015 50.2 38.4
Noise levels are within permissible
limits for commercial area
2 Near Pankha Cirlce 08.12.2015
53.8 43.5 Noise levels are within permissible
limits for commercial area
Jhalawar
1 RUSDIP/TR-
2/JHL/WW-02
Near STP & Landfill
site
06.01.2016
67.4 53.8
During construction noise level
slightly above the standard specified
for commercial areas
Anand Dham Temple 05.01.2016 69.3 55.7
National Ambient Noise Standard
I Industrial Area 75 70
Ii Commercial/Mixed Area 65 55
iii Residential/Rural 55 45
Iv Sensitive area 50 40
Conclusion: Noise levels are found within the permissible industrial area limit both during day and night time.
Groundwater Quality Monitoring- In order to assess groundwater quality in the vicinity of the STP project site at
Dholpur, Bharatpur and and drinking water at UIT office a sampling location near Tegawali village in Dholpur,
Rajendra Bagwal borewell in Bharatpur and UIT office in alwar was identified and groundwater monitoring was
carried out for certain parameters including physico-chemical, major and trace elements, etc. Based on drainage
pattern, water utilization, areas representing likely impacted and baseline conditions etc., the location for
groundwater source was identified and sample was collected from a bore-well. The results are presented in Table
24.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 110
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Table 24: Groundwater Quality Results for Alwar
SN Parameters Unit Protocol Results Desirable Limit
(Max)
1 pH(at 25oc) - APHA 22nd Edition, 4500-H+B 6.62 6.5 – 8.5
2 Colour Hazen
Unit
IS: 3025 (Part -4), 1985,
Reaffirmed 2012
BDL (<5.0
Hazen)
5/15*
3 Turbidity NTU IS: 3025 (Part -10), 1985,
Reaffirmed 2006
BDL (<1.0 ) 1.0
4 Odour - APHA 22nd Edition, 2150 Agreeable Agreeable
5 Taste - APHA 22nd Edition, 2160 Agreeable Agreeable
6 Total Hardness as
CaCO3
mg/l IS: 3025 (Part -21), 1985,
Reaffirmed 2009
48 200/600*
7 Dissolved oxygen mg/l APHA 22nd Edition, 2340 C 9.8 -
8 Alkalinity as
CaCO3
mg/l APHA 22nd Edition, 3500 Ca B 23 200/600*
9 Chloride as Cl mg/l APHA 22nd Edition, 2320 B 32.67 250/1000*
10 Magnesium as
Mg
mg/l APHA 22nd Edition, 4500 CN-
CD
4.86 30/100*
11 Total Dissolved
Solids
mg/l APHA 22nd Edition, 2340 B 162 500/2000*
12 Sulphate as SO4 mg/l APHA 22nd Edition, 2540 C 11.75 200/400*
13 Fluoride as F mg/l APHA 22nd Edition, 4500 E 0.11 1/1.5*
14 Nitrate as NO3-N mg/l APHA 22nd Edition, 4500-F-D 41.21 45
15 Hexa Chromium
as Cr+6
mg/l APHA 22nd Edition, 5540-C BDL (<0.01) -
16 Zinc as Zn mg/l APHA 22nd Edition, 3111B 0.13 5/15*
17 Copper as Cu mg/l APHA 22nd Edition, 3111B BDL (<0.01) 0.05/1.5*
18 Manganese as
Mn
mg/l APHA 22nd Edition, 3111B BDL (<0.01) 0.1/0.3*
19 Cadmium as Cd mg/l APHA 22nd Edition, 3111B BDL (0.001) 0.003
20 Lead as Pb mg/l APHA 22nd Edition, 3111B BDL (<0.01) 0.01
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 111
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Groundwater Quality Results for Dholpur
SN Parameters Unit Protocol Results Baseline data
(Max)
Desirable
Limit (Max)
1 pH(at 25oc) - APHA 22nd Edition, 4500-
H+B
8.26 9.18 6.5 – 8.5
2 Colour Hazen
Unit
IS: 3025 (Part -4), 1985,
Reaffirmed 2012
BDL (<5.0
Hazen)
5/15*
3 Turbidity NTU IS: 3025 (Part -10), 1985,
Reaffirmed 2006
BDL (<1.0 ) 1.0
4 Odour - APHA 22nd Edition, 2150 Agreeable Agreeable
5 Taste - APHA 22nd Edition, 2160 Agreeable Agreeable
6 Total Hardness as
CaCO3
mg/l IS: 3025 (Part -21), 1985,
Reaffirmed 2009
288 1520 200/600*
7 Dissolved oxygen mg/l APHA 22nd Edition, 2340
C
6.2 -
8 Alkalinity as
CaCO3
mg/l APHA 22nd Edition, 3500
Ca B
448 1086 200/600*
9 Chloride as Cl mg/l APHA 22nd Edition, 2320
B
597.83 1953 250/1000*
10 Magnesium as
Mg
mg/l APHA 22nd Edition, 4500
CN-CD
44.71 30/100*
11 Total Dissolved
Solids
mg/l APHA 22nd Edition, 2340
B
2102 500/2000*
12 Sulphate as SO4 mg/l APHA 22nd Edition, 2540
C
360 1017 200/400*
13 Fluoride as F mg/l APHA 22nd Edition, 4500
E
0.64 3.7 1/1.5*
14 Nitrate as NO3-N mg/l APHA 22nd Edition, 4500-
F-D
86.11 242 45
15 Hexa Chromium
as Cr+6
mg/l APHA 22nd Edition, 5540-
C
BDL (<0.01) -
16 Zinc as Zn mg/l APHA 22nd Edition,
3111B
0.13 5/15*
17 Copper as Cu mg/l APHA 22nd Edition,
3111B
BDL (<0.01) 0.05/1.5*
18 Manganese as
Mn
mg/l APHA 22nd Edition,
3111B
BDL (<0.01) 0.1/0.3*
19 Cadmium as Cd mg/l APHA 22nd Edition,
3111B
BDL (0.001) 0.003
20 Lead as Pb mg/l APHA 22nd Edition,
3111B
BDL (<0.01) 0.01
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 112
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Groundwater Quality Results for Bharatpur
SN Parameters Unit Protocol Results Baseline data
(average)
Desirable
Limit (Max)
1 pH(at 25oc) - APHA 22nd Edition, 4500-
H+B
7.52 8.33 6.5 – 8.5
2 Colour Hazen
Unit
IS: 3025 (Part -4), 1985,
Reaffirmed 2012
BDL (<5.0
Hazen)
5/15*
3 Turbidity NTU IS: 3025 (Part -10), 1985,
Reaffirmed 2006
BDL (<1.0 ) 1.0
4 Odour - APHA 22nd Edition, 2150 Agreeable Agreeable
5 Taste - APHA 22nd Edition, 2160 Agreeable Agreeable
6 Total Hardness
as CaCO3
mg/l IS: 3025 (Part -21), 1985,
Reaffirmed 2009
960 1085 200/600*
7 Dissolved
oxygen
mg/l APHA 22nd Edition, 2340
C
8.25 -
8 Alkalinity as
CaCO3
mg/l APHA 22nd Edition, 3500
Ca B
292 200/600*
9 Chloride as Cl mg/l APHA 22nd Edition, 2320
B
608.04 1265 250/1000*
10 Magnesium as
Mg
mg/l APHA 22nd Edition, 4500
CN-CD
157.95 227.35 30/100*
11 Total
Dissolved
Solids
mg/l APHA 22nd Edition, 2340
B
1650 3232 500/2000*
12 Sulphate as
SO4
mg/l APHA 22nd Edition, 2540
C
77.50 1432 200/400*
13 Fluoride as F mg/l APHA 22nd Edition, 4500
E
0.23 4.4 1/1.5*
14 Nitrate as
NO3-N
mg/l APHA 22nd Edition, 4500-
F-D
3.34 45
15 Hexa
Chromium as
Cr+6
mg/l APHA 22nd Edition, 5540-
C
BDL (<0.01) -
16 Zinc as Zn mg/l APHA 22nd Edition,
3111B
0.06 5/15*
17 Copper as Cu mg/l APHA 22nd Edition,
3111B
BDL (<0.01) 0.05/1.5*
18 Manganese as
Mn
mg/l APHA 22nd Edition,
3111B
BDL (<0.01) 0.1/0.3*
19 Cadmium as
Cd
mg/l APHA 22nd Edition,
3111B
BDL (0.001) 0.003
20 Lead as Pb mg/l APHA 22nd Edition,
3111B
0.39 0.01
Conclusion:
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 113
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
1) Alwar - The Drinking water parameters are within the permissible limits which indicates there is no water
contamination in the drinking water in Alwar.
2) Bharatpur & Dholpur - The ground water parameters are within the baseline data but beyond the
permissible limits which indicates that increase in the levels of water parameters is not due to construction
activity but due to natural geomorphic conditions.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 114
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
V. CONCLUSIONS AND RECOMMENDATIONS 35. For protection of local environment during construction phase application of mitigation measures
started as per specified EMP. Pubic consultation during construction/implementation phase has been carried
out in Bundi, Rajsamand and Jhalawar. Public consultation will be carried out at other places in next reporting
period. The issues and public opinion are shown in Annexure 5. The project specific lapses, corresponding
recommendations with responsibility are presented in Chapter II of the report.
36. For proper implementation of EMP during various phases of project execution, review meeting and
training are being organized by IPMC quarterly. The representative of all IPIUs (Nodal officers), environmental
personal of DSCs and CAPP staff attended the same. The details of mobilization schedule are presented in
Annexure 6.
37. Photographs of completed work is shown in Annexure -7.
38. The status of compliance with EMP for sub-project under tranche-2 has been discussed in Table 3 to
Table 16 of Chapter II of the report including action required for lapses and responsibility for the same.
39. The environmental monitoring has been completed in most of the towns and it will be considered as
the final monitoring at completion as most of the projects are about to be completed.
40. Improvements are observed in compliance of EMP activities in the present report as compared to
the last report except, particularly in environmental monitoring. The environmental monitoring is carried out
successfully in most of the project towns.
41. Improvement in use of PPEs are also observed although more attention and awareness is required to
achieve full compliance level. Improvement is required in Labour camps condition. The contractors have been
instructed to provide basic facilities in all labour camps. IPIU and DSC are monitoring to ensure the same. The
main area of concern has been summarized below
Environmental Statutory Clearance: The consent to establish has been obtained from Rajasthan
Pollution Control Board (RPCB) to establish STP at Dholpur, Karauli, Nagaur, Barmer and Rajsamand
and for WTP in Dholpur and Rajsamand. The work of STP at Sawai Madhopur has been completed thus
consent to operate has been obtained from RPCB which expired on 31.08.2015 and renewed on
07/10/2016 which is valid till 31/03/2019. The civil work of Dholpur WTP is complete, Consent to
operate from RPCB is under process. Consent from RPCB for RMC plant established for Bharatpur
circular road package has been obtained. The consent to establish 3 MLD STP at Dholpur has been
obtained with is valid till September 2017. The work of 10 MLD STP at Dholpur has been completed
thus consent to operate has been applied for and at present under the process with RSPCB. The civil
work of Rajsamand WTP is completed Consent to operate from RPCB has been obtained. Consent to
establish for RMC plant established for Bharatpur circular road package has been obtained. Permission
for cutting of trees for Sikar road package has been obtained from forest department.
Air, Water & Noise Quality: The final environmental monitoring has been completed in most of the
towns . Regarding monitoring in Rajsamand, work order was issued to the monitoring agency but
monitoring was not carried out by the monitoring agency and future monitoring will be conducted at
the earliest.
Landscape and Aesthetics: The unusable extra excavated materials are being disposed at low laying
area in consultation with ULBs. Some grievances related to removal of soil mounts and proper leveling
of backfilled soil were received in towns which were resolved accordingly. However excavated soil
management is required to be prepared.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 115
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Socio-Economic – (Income & Employment): It was observed in few cases that proper access across
open trenches for people and vehicles has not been provided. Some grievances were also received in
this regard in towns. In this regard contractor has instructed to provide walkways and metal sheets
where required to maintain access. As far as engagement of local labour is concern, in all cases more
than 50% of the work force has been appointed locally.
Occupational Health and Safety: Improvement in use of personal protective equipment (PPE) has been
noticed. DSC and CAPP personal have been instructed to conduct more trainings and awareness
campaigns to motivate the labors to achieve full compliance. The qualified First-aid facility is available
at most of the sites. It should be ensured that first-aid facilities are available at all sites all the time
without fail. Few contractors have appointed safety officer at site, other have been instructed for
compliance immediately.
Work Camps: The basic facilities in worker camp needs to be improved as per EMP. Contractor has
been instructed to provide proper Sanitary and solid waste management facilities in all work camps.
Cooking gas has been provided in most of the camps to avoid cutting of trees for firewood.
42. Apart from these common lapses to achieve full EMP compliance, sub-project wise status of EMP
compliance and recommended mitigation measure have been discussed in Chapter II of the report.
43. Necessary instructions have been given to the contractor by concerned DSC/IPIU for improvement in
compliance level. Following are the recommendations on the basis of the findings of the report
ensure regular monitoring for complete compliance on the lapses observed in bi-annual
environmental monitoring reports (EMR)
provide copy of the environmental monitoring results to the concern contractors to take necessary
actions and include the mitigation measure in the training program for high levels of observed
parameters.
ensure timely completion of environmental monitoring in all towns in future.
In case of any change in scope/location of project components, environmental assessment for the
same is required following approval of revised IEE from ADB.
Conduct ground water monitoring to assess any impact on ground water quality due to construction
activities for each sub-project as suggested by ADB
ensure training for field staff including construction contractor staff on regular basis
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 116
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Annexure 1: Environmental Legislation and Pollution Control Acts
The Government of India has formulated various policy guidelines; acts and regulations aimed at the
sustenance of environment in general, which are briefly summarized and applicable acts with the projects, are
described in the following sub-sections.
Environmental Legislation and Pollution Control Acts
Sl. No. Sources Legislation
1 Water Pollution The Water (Prevention and Control of Pollution) Act, 1974, as amended in 1988
2 Air Pollution The Air (Prevention and Control of Pollution) Act, 1981, as amended by Amendment Act, 1987
3 Noise Pollution The Noise Pollution (Regulation and Control) Rules, 2000
4 Environment The Environment (Protection) Act, 1986
5 Public Liability The Public Liability Insurance Act, 1991
The Public Liability Insurance Rules, 1991
6 Hazardous Waste Hazardous Waste (Management and Handling) Rules, 1989
Batteries (Management and Handling) Rules, 2001
Manufacture, Storage and Import of Hazardous Chemical Rules, 1989
Emergency Planning Preparedness and Response for Chemical Disasters Rules, 1995
Manufacturing, Use, Import, Export and Storage of Hazardous Microorganisms, Genetically
Modified Engineered Organisms or Cell Rules, 1993
Hazardous Microorganisms and Genetically Modified Organisms (Manufacture, Use Import Expert
and Storage) Rules, 1999
Bio- Medical Waste (Management and Handling) Rules, 2000
7 Municipal Solid Waste Municipal Solid Waste (Management and Handling) Rules, 2000
Recycled Plastics Manufacturing and Usage Rules, 1999
8 EIA Notification The Ministry of Environment and Forests has revised the EIA notification, 1994, and issues the
revised EIA notification on 14th September 2006
9 Use and Management
of Explosive
The Explosives Act, 1884 and The Explosives Rules, 1983
The Environment Protection act, 1986 and the EIA Notification, 1994
The Environmental (Protection) Act, 1986 is the umbrella legislation providing for the protection of
environment in the country. This Act provided for the Environment (Protection) Rules, which have been
fo ulated u de the a t The E i o e tal I pa t Assess e t Notifi atio , 99 a d the A e d e ts / ‘e ised EIA otifi atio o th “epte e .and Year 2009.
The Forest (Conservation) Act, 1980
The Forest (Conservation) Act, 1980 pertains to the cases of diversion of forest area and felling of roadside
plantation. Depending on the size of the tract to be cleared, clearances are applied for at the following levels
in the governments:
If the area of forests to be cleared or diverted exceeds 20 ha (or, 10ha in hilly area), the prior permission of the
Central Government is required;
If the area of forest to be cleared or diverted is between 5 to 20 ha, the Regional Office of Chief Conservator
of Forests is empowered to approve;
If the area of forest to be cleared or diverted is below or equal to 5 ha, the State Government can give
permission;
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 117
ADB Loan No. 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
and If the area to be clear-felled has a forest density of more than 40%, permission to undertake any work is
needed from the Central Government, irrespective of the area to be cleared.
The Wildlife (Protection) Act, 1972
The Wildlife Protection Act has allowed the government to establish a number of National Parks and
Sanctuaries over the past 25 years, to protect and conserve the flora and fauna of the state.
The Water and Air (Prevention and Control of Pollution) Acts 1974
The water (Prevention and Control of Pollution) Act, 1974 resulted in the establishment of the Central and
State level Pollution Control Boards whose responsibilities include managing water quality and effluent
standards, as well as monitoring water quality, prosecuting offenders and issuing licenses for construction and
operation of certain facilities. The SPCB is also empowered to set air quality standards and monitor and
prosecute off enders under the air (Prevention and Control of Pollution) Act, 1981.
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 118
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Annexure 2: Major works and progress- Tranche 02
Locations Sub-projects Components (Package
No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
Alwar Waste Water: Waste Water work
in Alwar
Package No: {RUSDIP/TR-02/
ALW/WW/06}
Main Line : out of 9.98 km, 6.81 km completed
Lateral Line: out of 60.49km, 39.62 km completed
Manhole :out of 2425 nos. 1811 nos. completed
Property connections: out of 7673nos. 1635 nos. completed
No change
expected
o Effective monitoring
and application of EMP
No risk
Sawai
Madhopur
Water supply: Construction of
CWRs & OHSRs including supply,
laying and commissioning with
testing of DI & uPVC pipelines and
construction of pumping stations
and replacing of leakaged pipeline
etc. for UWSS Sawai Madhopur
{RUSDIP/TR-02/SMD/WS/ 02}
1 OHSRs (7 Nos.) – 7 Nos. OHSRs Completed
CWRs (2 Nos.) –2 Completed
Pump House (3 Nos.) – 3 Nos. Completed
DI rising main (29.71 Km) – 28.63 Km laid
uPVC (57.23 Km) – 50 Km laid
Pump replacement (6 Nos.) – Completed
House Connections (3000 Nos.) – 1045 Nos.
Water meters (16900 Nos.) – 9234 Nos.
90% work completed.
Raigar Basti OHSR-
Work dropped in
CLC by Distt.
Collector
Effective monitoring
and application of EMP
No risk
Bharatpur Bridge Project: Reconstruction of
ROB at Bharatpur
(RUSDIP/TR-02/BPR/BR/01)
35% Work completed for ROB No change
expected
Effective monitoring
and application of EMP
No risk
Dholpur Water Supply: Design, Construction
and Commissioning of 15 MLD
capacity Water Treatment Plant
including commissioning of
equipments at Sagarpada;
Construction of CWRs & OHSRs
including supply, laying and
commissioning with testing of DI &
uPVC pipelines and replacing of
leakaged pipeline etc. for UWSS
Dholpur.
DI pipe line:- Procured= 12.723 km, Laid=12.37 km, Testing =
9.138 km, Commisioned= 0 km
uPVC pipe line:-Procured=77.71 km, Laid= 64.29 km, Testing =
57.21 km, Commisioned= 0 km
Total DI+uPVC line :- Procured= 90.34 km, Laid=76.66 km, Testing
= 63.926 km, Commisioned= 0 km
OHSR -- 4 Nos. OHSR completed & 2 Nos. OHSR Hydro testing
completed.
CWR - Both CWR completed & Hydro testing has done on 1 CWR
and painting of Bhogiram Nagar CWR completed.
Pumping station -- Pump house at Sagarpada- completed
No further change
expected
Effective monitoring
and application of EMP
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 119
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Locations Sub-projects Components (Package
No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
{RUSDIP/ TR-02/ DLP/WS/03} PH at Bhogiram Nagar – completed
Civil work at WTP also completed
Water Meter (15700 Nos.): 4773 Nos.
85% work completed.
Dholpur Waste Water : Supply, Laying,
Jointing, Testing and
Commissioning of outfall sewer,
trunk sewers, lateral sewers,
lateral sewers along with
construction of manholes,
appurtenances etc. at Dholpur.
{RUSDIP/TR-02/DLP/WW/04}
Sewer Line RCC Procured- 78.597 km, Laid- 78.512 km , Tested-
67.932
Sewer Line uPVC laid- -41.325 km
Manholes- 3116 manholes constructed.
Manhole tested- 1695 nos.
80 % work completed
No change
expected
Effective monitoring
and application of EMP
No risk
Dholpur Waste Water : Design,
construction, supply, erection,
testing, commissioning and 5 year
operation and maintenance of 10
MLD sewage treatment plant
based on UASB process with
sewage pumping/lifting station
including all civil, electrical,
mechanical, pumping and allied
works in Dholpur town
{RUSDIP/TR-02/DLP/WW/05}
1. Drawings of Admn. Building, Staff quarter, Security cabin, Sump,
coarse screen, fine screen, sludge bed, GA & structural drawing of
reactor & GA drawing of DGRIT chamber, Parshall Flume &
Distribution Chamber Layout Plan, GA layout plan for Cascades &
drawing of Sludge drying bed approved and handed over to
contractor.
2. 100 % of STP work completed.
3. Sludge drying beds: 100 % work Completed.
4. Staff Quarter completed
5. Administrative building completed.
6. Reactors :
I. Reactor work 100 % completed of total civil work.
Inlet & outlet chamber- 100 % completed.
9. Road work- completed
No change
expected
Effective monitoring
and application of EMP
No risk
Dholpur Waste Water: Dholpur Sewerage
work
{RUSDIP/TR-02/DLP/WW/08}
1. Total RCC pipe (NP-4 & NP -3) : 27.32 Km procured, 27.32 Km
laid
2. GRP pipe of 500 mm dia 3840 mtr procured and 3439 mtr laid.
No change
expected
Effective monitoring
and application of EMP
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 120
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Locations Sub-projects Components (Package
No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
3. Manholes constructed – 728 Nos. & testing done for 282 nos.
uPVC laid -5749 m .
40% work completed
Waste Water: Design, construction,
supply, erection, testing,
commissioning and 5 years
operation and maintenance of 3
MLD Sewage Treatment Plant (STP)
based on SBR process with sewage
pumping/lifting station including all
civil, electrical, mechanical,
pumping and allied works at
Dholpur town.
Package No.: {RUSDIP/TR-
02/DLP/WW/11}
Work completed till June 2015
1. Outfall – 2.08 km
2. Lateral –16.05 km
3. Manholes –417 Nos. ( out of 960 total)
4. STP – work under progress
5. Property connections-108
No change
expected
Effective monitoring
and application of EMP
No risk
Churu Water Supply Project in churu city.
RUSDIP/ TR-02/ CHU/ WS/04
Van Vihar ESR , Kotwali ESR, Johri Sagar ESR, Agrasen Nagar ESR,
Gandhi Colony ESR, work is ongoing.
Collectrorate PS, Johri Sagar PS work is ongoing.
Laying- 350 mm dia- DI pipe line jain Market area. 250mm dia- PMC
office to goyanka ESR.
No change
expected
o Effective
monitoring and
application of EMP
No risk
Sikar Water Supply: Construction of 7
OHSRs at different places at Sikar
{RUSDIP/TR-02/SKR/WS/04}
D.I. Pipes (K-9) & K-7
Procurement - 11820 meters, L&J -11820 meters, testing – 11820
meters
uPVC Pipe - Procurement - 79529 meters
L&J 75425 meters, Hydro testing - 75425 meter
Construction of 07. E.S.R.
1. Hathi Tibba ESR (700 KL)
No change
expected
Effective monitoring
and application of EMP
Allotment of land for
3 sites of water tanks
is pending with ULB.
(A). Azad nagar, veer
teja colony,
nawalgarh road. (B).
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 121
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Locations Sub-projects Components (Package
No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
2. Kabristan ESR (800 KL)
3. Piprali Road ESR (400 KL)
4. Dharmana ESR (400 KL)
5. Teja Colony ESR (1000 KL)
6. Shiv Colony ESR (1000 KL)
Construction of 03 CWR
At Nawalgarh Headwork (1000 KL) - Civil Work completed.
Hathi Tibba (100 KL):- Removed from Scope due to change in
location of Dharmana Zone ESR..
At I.T.I Headwork (300 KL):- Civil Work completed.
Construction of 01 Pump House
Nawalgarh Headwork Pump House: - completed
House service connection (9399 nos.) :- 723 nos.
Domestic water meter (9399 nos.) – 723 nos. against 9399.
Fixing of EMF (5 nos.) :- 5 nos. against 5nos.
Fixing of BFM (45 nos.) :-5 nos. against 45 nos.
24x7 Water Supply:-Basic survey has been done and zone
boundary marked.
Dharmana, (C). Sanik
Nagar
Nagaur Waste water: STP 8 MLD
{RUSDIP/TR-02/NGR/WW/02 (Lot-
2)}
Civil work of Anaerobic pond, Facultative pond, Pretreatment unit
and Admin building has been completed.
STP – Civil – 90%, electrical & mechanical – 65% work completed
SPS & IPS – Civil 75%, E & M – 60% work completed
No change
expected
Effective monitoring
and application of EMP
No risk
Barmer Water Supply: Construction of
CWRs & OHSRs including Supply,
Laying, and Commissioning with
DI pipe line:- Procured= 27.70 km, Laid=26.97 km, Testing =
26.97km, Commissioned= 26.97 km
No change is
expected.
Effective monitoring
and application of EMP
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 122
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Locations Sub-projects Components (Package
No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
testing of Rising & Distribution
pipelines and installation of
Chlorination, Flow meter etc., for
UWSS at Barmer. {RUSDIP/TR-
02/BMR/WS-02}
uPVC pipe line:-Procured= 117 km, Laid=111.50 km, Testing = 109
km, Commissioned= 109 km
Total DI+uPVC line :- Procured= 144.70 km, Laid=136.29 km,
Testing = 105.72 km, Commissioned= 54.6 km
ESR:- 9 nos. completed
GLSR - Completed
CWR- - completed.
Pumping Station- work completed. Installation of pump done.
24x7 Water supply scm for Zone 05 & 17.
Domestic water Meter installed: - 9 No s & House Co e tio No s o pleted.
CWR at Karali nad & Dhola dungri– Completed.
Water meter installation work is in progress. 11211 Nos. installed
Barmer Waste water:
Supply, sewer line work
{RUSDIP/TR-2/BMR/WW/03 (Lot-
1)}
Physical work:
Outfall- 5.45 Km completed
Lateral – 28.149 Km completed
Manholes – 4827 Nos. Completed
Trenchless for Railway Crossing of 600mm dia sewer line
completed.
Trenchless for NH-Crossing of 700mm dia Sewer line completed
manhole construction in progress.
No change
expected
Effective monitoring
and application of EMP
No risk
Barmer Waste water:
STP 10 MLD
{RUSDIP/TR-2/BMR/WW/03 (Lot-
2)}
Metering and Panel Rooms door and windows fitting completed,
painting is pending.
Civil work – 95% completed
E&M work – 95% completed
No change
expected
Effective monitoring
and application of EMP
No risk
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 123
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Locations Sub-projects Components (Package
No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
Bundi Waste water : Sewerage works,
including STP, SPS, outfall and
lateral (RUSDIP/TR-
02/BND/WW/06)
STP – Civil work under progress ( Raft reinforcement at SBR,
Chlorination room, Air Blower, Stilling chamber, Grit Chamber,
Fine screen channel, Parshall Flume & ADM building under
progress)
SPS: Civil work under progress (Inlet chamber PCC & raft of raw
sewage sump completed, wall under profress)
Outfall: 5.36 Km out of 7.9 Km completed
Lateral: work to be started.
No change
expected
Effective monitoring
and application of EMP
No risk
Bundi Roads: Widening of existing road
from khoja gate to Bypass link
road.Widening of existing road
from petrol pump triangle Bypass
to rotarary club triangle via rani ji
ki bawari and interlocking
footpath. (RUSDIP/TR-
02/BND/ST/04)
Total Road Length completed-
1) BT road – 1.522 km
2) CC Road – 13.396 km
3) Widening of Nainwa culvert – WIP
No change
expected
Adequate use of
PPE s o site required
No risk
Rajsamand
Design, Construction, Supply,
erection testing, commissioning
and five years operation &
maintenance of left over works
of Sewage Treatment plant 5
MLD with Sewage pumping
station including all civil,
electrical, mechanical, pumping
and other allied works and
supply, laying joining, testing
and commissioning of outfall
sewer, various Trunk sewers,
collecting and lateral sewers
along with all necessary
Pipe line Laying –
Outfall : 0.96 Km completed out of 1.5
Lateral : 11.54 Km completed out of 12.59
Manholes : 525 out of 607
STP – work completed
Civil work – 90%
E& M – yet to be started
Nil Partially fulfilled, use of
PPEs and signage needs
improvement
Use of PPEs by
workers and use of
signage in all sites is
required
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 124
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Locations Sub-projects Components (Package
No.)
What type of works continued at present Expected changes
from approved
scope
Fulfillment of
objectives- Type of
remedial measures
needed
Key assumptions and
risks that affect
attainment of the
objectives
manholes, appurtenances etc.
at Rajsamand {RUSDIP/TR-
2/RSM/WW/ 03
Rajsamand Water Supply: Design, Construction
and Commissioning of intake well
& 17 MLD capacity Water
Treatment Plant including
commissioning of equipments;
Construction of CWRs & OHSRs
including supply, laying and
commissioning with testing of DI &
uPVC pipelines {RUSDIP/ TR-02/
RSM/WS/03}
OHSRs, GLSRs and CWRs
All works completed and handed over to PHED
Pump House
All works completed and handed over to PHED
Intake works
All works completed and handed over to PHED
WTP
All works completed and handed over to PHED
Pipe Laying and Hydro-testing
All works completed and handed over to PHED
House Connections- 1600 completed out of 3100
Domestic Water Meters- 7020 out of 7987 water meter installed
No change
expected
satisfactory No risk, most of the
works completed.
Jhalawar Waste Water: Laying of Sewer line
network at Jhalawar &
Jhalarapatan town
{ RUSDIP/TR-02/JHL/WW/02}
Pipe laying done:
Total pipe laid: 21.26 Kms out of 29.70 Km
Manhole construction:
Total 500 nos. of manhole constructed out of 984 nos.
Property connections: 870 nos.
NA Partially Fulfilled
* Disposal plan of
excess excavated soil is
needed
* PUC of all vehicles and
equipments is required
* Deployment of safety
personnel from
contractor is required
* Disposal plan of
excess excavated soil
is needed
* PUC of all vehicles
and equipments is
required
* Deployment of
safety personnel from
contractor is required
* Use of PPEs by
workers needs
improvement
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 125
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Annexure 3: Environmental Monitoring Schedule
Environmental Monitoring Schedule
Monitoring Project Type Parameters Frequency No. of location Remarks
Ambient Air Quality Monitoring
Air quality
parameters
STP, WTP,
pump house
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
4 days 24 Hrs
basis Semi-
annually
2 locations
nearby STP, WTP,
pump house site
Intake
location
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
2 days 24 Hrs.
basis- Semi-
annually
1 location nearby
the project site
Bridge,
Drainage
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
3 days 24 Hrs
basis Semi-
annually
2 locations
nearby bridge
Landfill SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
3 days 24 Hrs
basis Semi-
annually
4 locations (one
at center and rest
at 3 locations 120
degree apart)
Pipe laying
area
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
3 days 24 Hrs
basis Semi-
annually
3 locations
nearby working
zone
Heritage site SPM, RSPM (PM10 & PM
2.5), SO2, Ammonia, H2S,
NOx and CO
2 days 24 Hrs
basis Semi-
annually
2 locations
nearby working
zone
Fire Fighting
station
SPM, RSPM (PM10 & PM
2.5), SO2, NOx and CO
2 days 24 Hrs
basis Semi-
annually
2 locations
nearby working
zone
Ambient Noise Level Monitoring
Sound Pressure Level STP, WTP,
pump house
Leq One time in six
months
(day & night)
3 nearby
locations
Intake
location
Leq One time in six
months(day &
night)
2 nearby
locations
Bridge Leq One time in six
months(day &
night)
5 nearby
locations
Landfill Leq One time in six
months(day &
night)
4 nearby
locations
Preferably near air
quality measuring
sites
Pipe laying
area
Leq One time in six
months(day &
night)
3 nearby
locations
Heritage site Leq One time in six
months(day &
night)
3 nearby
locations
Fire Fighting
station
Leq One time in six
months(day &
night)
2 nearby
locations
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 126
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Monitoring Project Type Parameters Frequency No. of location Remarks
Water Quality Monitoring
Surface water Quality
parameters
STP, WTP General: Turbidity NTU,
pH, Total Suspended
Solid, TDS, Total Hardness
as CaCO3, DO,
Organic Matters: BOD,
COD,
Nutrients: Nitrate,
Metals: Chloride,
Sulphate, Na, K, Ca, Mg,
Fe, Mn, Cd, As, Cr, Cu, Mg,
Pb, Selenium, Al, Zn, Bo,
Fluorine, Cl (residual
free),
Other Organics: Phenolic
Compound, Cyanide,
Phosphate (mg/l)
one time in six
months
2 locations
(pond, river, nala)
(if location exist)
Intake
location
Turbidity in NTU, pH,
Total Suspended Solid,
TDS, Total Hardness as
CaCO3, DO, BOD, COD
One time in six
months
2 locations
unpstream and
downstream
River bridge,
Drainage
channel
As above One time in six
months
At least 2 location
(pond, river, nala)
upstream and
downstream
Landfill site As above One time in six
months
At least 2 location
(pond, river, nala)
if location exist
Ground water Quality
parameters
Landfill site,
STP
pH, Total Dissolved Solid,
Total Hardness as CaCO3,
Dissolved Oxygen,
Alkalinity as mg/l, Cl,
Sulphate, Nitrate, Fe, Mg.
Cd, As, Cr, Co, Mg, Pb, Zn,
Fluoride Phenolic
Compound, Phosphate
(mg/l)
One time in six
months
At least 3 location
(tube well/ hand
pump/ bore well)
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 127
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Annexure 4: AIR, WATER & NOISE MONITORING REPORT
Ambient Air quality Report of Dholpur, Alwar, Bharatpur, Nagaur and Churu
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 128
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 129
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 130
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 131
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 132
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Noise Monitoring Report of Alwar, Dholpur, Bahratpur, Nagaur and Churu
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 133
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 134
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 135
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 136
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 137
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Ground Water Monitoring Report of Dholpur
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 138
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 139
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Water monitoring report of Alwar
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 140
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 141
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Annexure - 5
Public Consultation on Environmental Issues during Construction/
Implementation
Town Sub project
Bundi Road
Rajsamand Road
Jhalawar Waste Water
Bundi – Waste Water
PLACE OF CONSULTATION Village Devpura (Sewer pipe laying 900 mm)
DATE OF CONSULTATION 05.02.2016
PROJECT NAME Bundi sewerage works
PACKAGE NO. RUSDIP/TR-2/BND/WW/06
NAME OF THE CONSULTANT Abhay Srivastava, Jyotidhari Singh
NAME OF THE PERSONS Soni Bai, Anil Goswami, Ramesh goswami (residents)
ADDRESS Vill. Devpura, Bundi
S.No POINTS TO BE DISCUSSED REMARKS
01. Whether dust control measures are taken up by
contractor as and when required?
No, water sprinkling is not taken up to reduce dust
02. Whether traffic movement affected during
construction?
Yes, half of the road is blocked and traffic movement
becomes congested, road is full blocked during excavation
and loading activities
03. Is there any problem due to influx of outside people
(laborer)?
No problem due to the construction labors as mostly labors
are local.
04. Is there any problem, if storage area is in public
place?
Yes, excavated soil is dumped on road which creates traffic
nuisence
05 Is there any problem during transportation of
materials?
Yes during loading and unloading of excavated soil and
construction materials, traffic is blocked
06. Is there any problem due to the running of concrete
mixture/ hot mix plant or movement of equipment
like JCB?
No use of concrete mixture/hot mix plan at project,
sometimes traffic problem exists during operation of JCB
07 Whether construction work affects local drainage
system/ water supply system?
Yes sometimes water supply system is disrupted during
excavation and construction works for 1-2 days, drainage
system is also affected but new drain is being constructed
alongside the road
08 Whether movement of locals/pedestrian affected
during construction?
Yes, movement of pedestrians is affected due to
construction works and excavated soil is not removed on
same day resulting no access for shopkeepers and
residences
09 Whether generated noise affects the normal life of
locals?
Noise is generated but not causing any problem to nearby
people
10 Overall opinion on construction (Excellent/
Satisfactory/ Below satisfaction/ Poor)
Below Satisfactory
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 142
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Rajsamand – Waste Water
PLACE OF CONSULTATION Kishor Nagar, Rajsamand
DATE OF CONSULTATION 07.03.2016
PROJECT NAME Rajsamand Sewerage Works
PACKAGE NO. RUSDIP/TR-02/RSM/WW /03
NAME OF THE FIELD SUPERVISORS Indira Chauhan
NAME OF THE PERSONS Rajkishor, Rajesh Sankhla
ADDRESS Residents of Kishor Nagar, Rajsamand
S.No. POINTS TO BE DISCUSSED REMARKS
01. Whether dust control measures are taken up by
contractor as and when required?
No dust problem due to construction activities.
02. Whether traffic movement affected during
construction?
Yes, traffic movement is stopped during construction
works
03. Is there any problem due to influx of outside
people (laborer)?
No problem due to the construction labors, mostly labors
are hired locally.
04. Is there any problem, if storage area is in public
place?
No, construction materials are kept on the sides of road
and create no problem
05 Is there any problem during transportation of
materials?
No such problem existed during works
06. Is there any problem due to the running of
concrete mixture/ hot mix plant or movement of
equipment like JCB?
Yes, problem is caused due to running of JCB, road
becomes closed for movement
07 Whether construction work affects local drainage
system/ water supply system?
Yes, water supply lines are damaged at some points but
repaired on same day.
08 Whether movement of locals/pedestrian affected
during construction?
Yes, movement of locals/pedestrian is affected during
construction as road becomes closed for any movement
09 Whether generated noise affects the normal life of
locals?
Yes, noise is generated which affect the normal life
10 Overall opinion on construction (Excellent/
Satisfactory/ Below satisfaction/ Poor)
Satisfactory
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 143
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Jhalawar -Waste Water
PLACE OF CONSULTATION Chaupadia Bazar, Jhalarapatan
DATE OF CONSULTATION 04.02.2016
PROJECT NAME Jhalawar sewerage project
PACKAGE NO. RUSDIP/TR-2/JHL/WW/02
NAME OF THE FIELD SUPERVISORS Abhay Srivastava, Jyotidhari Singh
NAME OF THE PERSONS Yashvardhan Bakliwa (corporator, Nagar Parishad), Babita
Sethi, Sohan Madhwani
ADDRESS Residents and shopkeepers, Chaupadia Bazar, Jhalarapatan
S.N. POINTS DISCUSSED OPINION EXPRESSED
01. Whether dust control measures are taken up by
contractor as and when required?
Yes, dust problem exists and no water sprinkling is
being done by contractor
02. Whether traffic movement affected during construction? Yes traffic movement is blocked during pipe laying
works during day but restored in evening after
completion of works
03. Is there any problem due to influx of outside people
(laborer)?
No problem due to the construction labors.
04. Is there any problem, if storage area is in public place? No, construction materials are not stored in public place
05 Is there any problem during transportation of materials? No problems noticed due to the transportation of
construction materials.
06. Is there any problem due to the running of concrete
mixture/ hot mix plant or movement of equipment like
JCB?
Concrete mixtures and hot mix plant are not being used,
JCBs are in use and create noise
07 Whether construction work affects local drainage
system/ water supply system?
Yes, sometimes water supply system is damaged
during excavation for pipe laying but repaired by
contractor in one or two days
08 Whether movement of locals/pedestrian affected during
construction?
Yes, pedestrian movement is affected during pipe
laying and road restoration works
09 Whether generated noise affects the normal life of
locals?
Yes but people ready to bear it for improved service of
sewerage
10 Overall opinion on construction (Excellent/ Satisfactory/
Below satisfaction/ Poor)
Below Satisfactory
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 144
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Photographs of Public consultation
Public consultation at Rajsamand
Waste water works
Public consultation at Setho ka Chauraha, Jhalarapatan, Jhalawar
Training to contractor’s engineers and supervisors of sewerage works, Bundi
Public consultation at Gayatri Nagar, Bundi
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 145
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Annexure 6: Mobilization Schedule
PMU: Project Management Unit; IPIU: Investment Program Implementation Unit; IPMC: Investment
Program Management Consultant; DSC: Design Supervision Consultant Note: Nodal officers are
engineer from IPIU having additional duty of safeguard
PMU
Responsibility Name Designation Duration
Overall supervision of Project and
Environmental Compliance as per ADB
Policy
Mr. D R Jangid Project Officer
Environment
Full Time
IPMC
Responsibility Name Designation Duration
Overall supervision of all 15 towns
Dr. Ardhendu Mitra Environmental Expert Intermittent
Shubhra Panwar Support Engineer Full Time
Structure adopted at 15 towns
Nodal Officer of IPIU DSC Consultants
Towns Nodal Officer
Designated by PMU
DSC I
Name Designation Duration
Alwar Mr. Saurabh Kr. Tayal Mr. Manoj Kumar Research Associate Intermittent
Bharatpur Mr. S R Jatav
Sawai Madhopur Mr. S P Soni
Dholpur Mr. S M Meena Dr. Sanjay Sharma Environmental
Monitoring Specialist
Full time
Karauli Mr. Pradeep Goyal
Towns Nodal Officer
Designated by PMU
DSCII
Name Designation Duration
Jaisalmer Mr. Amit K. Kumawat Dr. Amar Sarkar Research Associate Intermittent
Sikar Mr. A K Gupta
Churu Mr. Ratan Singh
Nagaur Mr. Lalit Sharma Mr. Arvind Rajput Environmental
Monitoring Specialist
Full time
Barmer Mr. Sunil Kumar
Towns Nodal Officer
Designated by PMU
DSC III
Name Designation Duration
Bundi Ms. Jyoti Rani verma Mr. Abhay Srivastav Research Associate Intermittent
Baran Mr. K M Sharma
Jhalawar Mr. J S Meena
Chhitorgarh Mr. Arun Bakshi
Rajsamand Mr. Paritosh Gupta
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 146
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
Annexure 7: Photographs
Works in Progress
Work in progress at Bharatpur ROB
Dholpur STP
Sewer laying works in Bundi
ESR in Sikar
Sewer pipe laying works at Gagron road,
Jhalawar
Footpath tile works at Gayatri Nagar, Bundi
Rajasthan Urban Sector Development Investment Program
Project Number: 40031 Page: 147
ADB Loan No.: 2506 IND (Tr-2) Date: June 2016
Environmental Monitoring Report
EMP Compliance
EMP compliance at Bharatpur STP
EMP compliance at Dholpur
EMP Compliance at Nagaur
Safety training in Churu
Training to workers at batching plant, Bundi
Barricades being used for pipe laying works, Gagron
road, Jhalawar