Increasing Pace of Utility Accommodations

8
Increasing Pace of Utility Accommodations Session – Right of Way 2011 Transportation Short Course October 11, 2011 Jesse Cooper, RPLS ROW Division, Map, Survey, and Utility Section Director Ryan Bonner Waco District, Utility Coordinator

Transcript of Increasing Pace of Utility Accommodations

Page 1: Increasing Pace of Utility Accommodations

Increasing Pace of Utility Accommodations

Session – Right of Way

2011 Transportation Short Course October 11, 2011

Jesse Cooper, RPLS ROW Division, Map, Survey, and Utility Section Director Ryan Bonner Waco District, Utility Coordinator

Page 2: Increasing Pace of Utility Accommodations

Utility Accommodation

Key component to most highway improvement projects

Early identification of utility conflicts and timely resolution of those conflicts is crucial to the success of all projects

Minimizes costs and delays

Page 3: Increasing Pace of Utility Accommodations

Factors Affecting Accommodation

Advanced Project Letting Resources Right of Way Agreements Duration of utility construction

Page 4: Increasing Pace of Utility Accommodations

Example – Reconstruction of IH 35 17 projects covering

4 counties through central Texas

Approximately 90 miles in length between the Bell/Williamson County Line and the East/West Split in Hillsboro

Over 100 utility adjustments

Page 5: Increasing Pace of Utility Accommodations

Techniques/Processes Used for Accommodation Early notification Follow TxDOT UAR, State and Federal Regulations Utilization of Statewide District Staff and Utility

Engineering Contracts Incorporation of utility adjustments into roadway

construction contract District approval of utility agreements Right of Entry agreements Roadway construction phasing Project tracking

Page 6: Increasing Pace of Utility Accommodations

Project Tracking IH 35 UTILITY STATUS

1 2 3 4 5 6 7 8 9 10 11 12

Atmos Energy 13017 gas 669,000.00$ 2/9/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 10/29/10 11/23/10 12/9/10 January-11 February-11 April-11 COMPLETED

Magellan Pipeline 13020

pipeline 350,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 9/1/10 10/22/10 10/29/10 December-10 November-10

Agreement approved - initial adjustment complete for

crossing on IH 35 - adjustment at Craven should

be underway

AT&T Texas 13056 communication 667,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 2/1/10 8/17/10 9/22/10 10/14/10 PS&E PS&E COMPLETED

City of Lacey Lakeview 13061

water/sewer 100,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 2/1/10 8/5/10 8/6/10 8/13/10 PS&E PS&E

Agreement approved - included in PS&E,

additional pipe lowering in drainage easement can take

place after Magellan is lowered

Oncor Electric Delivery 13210 etc…. electric transmission 141,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 1/8/10 1/29/10 2/16/10 December-10 October-10 December-10 COMPLETED

Qwest Communications 13064 communication 208,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 6/1/10 8/6/10 9/1/10 January-11 January-11 May-11 COMPLETED

Oncor Electric Delivery 13022 electric distribution 2,750,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 3/16/10 5/21/10 6/10/10 December-10 February-11 April-11 COMPLETED

Atmos Energy 13017 gas 228,000.00$ 2/9/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 10/29/10 11/23/10 12/9/10 January-11 February-11 June-11 COMPLETED

Level 3 Communications 13062 communication 12,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 1/14/11 1/31/11 December-10 February-11 March-11 COMPLETED

Explorer Pipeline 13018 pipeline 823,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 5/28/10 6/24/10 1/21/11 December-10 May-11 April-11 COMPLETED

HILCO Electric Coop. 13019

electric distribution 311,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 8/9/10 10/22/10 10/28/10 September-11 February-11 Agreement approved, work underway

AT&T Texas 13056

communication 667,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 2/1/10 8/17/10 9/22/10 10/14/10 PS&E PS&EAgreement approved - included in PS&E, work

underway

McLennan County WCID#2 13021 water/sewer 509,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 1/11/10 3/1/10 3/8/10 PS&E PS&E June-11 COMPLETED

Oncor Electric Delivery 13022 electric distribution 2,750,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 3/16/10 5/21/10 6/10/10 February-11 February-11 June-11 COMPLETED

Qwest Communications 13064 communication 208,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 6/1/10 8/6/10 9/1/10 April-11 January-11 May-11 COMPLETED

Time Warner Cable 13023

communication 40,000.00$ X 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 5/25/10 8/30/10 March-11 March-11

Agreement approved, change order submitted for approval for crossing south

of FM 308

Atmos Energy 13017

gas 109,000.00$ 2/9/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 10/29/10 11/23/10 12/9/10 September-11 February-11 September-11 COMPLETED

HILCO Electric Coop. 13019

electric distribution 311,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 8/9/10 10/22/10 10/28/10 September-11 February-11 Agreement approved, work underway

AT&T Texas 13056

communication 667,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 2/1/10 8/17/10 9/22/10 9/30/10 PS&E PS&EAgreement approved - included in PS&E, work

underway

Hilltop Water Supply 13060water 210,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 2/1/10 2/24/10 5/21/10 8/19/10 PS&E PS&E

Agreement approved - included in PS&E, work

underway

Oncor Electric Delivery 13210 etc…. electric transmission 1,101,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 1/8/10 1/29/10 2/16/10 December-10 October-10 December-10 COMPLETED

Ross Water Supply 13065

water 413,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 1/8/10 1/11/10 3/1/10 3/8/10 October-10 October-10 September-11 COMPLETED

Brazos Electric Power Coop 13572electric transmission 400,000.00$ 4/7/11 8/1/11 9/14/11 9/20/11 9/26/11 December-11 Agreement approved

Verizon Wirelesscommunication 400,000.00$ 2/24/09 9/1/09 11/1/09 11/1/09 9-2009 etc… 11/20/09 July-11 February-11 COMPLETED

Ryan Bonner Waco District Office

254-745-2141

Josh Voiles Waco Area

Office 254-772-2890

Victor Goebel Waco District Office

254-867-2717

Ryan Bonner Waco District Office

254-745-2141

Josh Voiles Waco Area

Office 254-772-2890

Victor Goebel Waco District Office

254-867-2717

Ryan Bonner Waco District Office

254-745-2141

Josh Voiles Waco Area

Office 254-772-2890

Victor Goebel Waco District Office

254-867-2717

ACTUAL DATE OF COMPLETION

COMITTED DATE OF COMPLETION FROM

UTILITY

CONST. CSJ / PROJECT NUMBER

COMPLETION DATE COMITTED TO CONTRACTOR

DATE OF EXECUTED

UTILITY AGREEMENT

DATE UTILITY AGREEMENT

SUBMITTED TO DIVISION

DATE DESIGNER DETERMINES

UTILITY CONFLICTS

DATE DESIGN INFORMATION IS

SENT TO UTILITIES (P&P, X-SECTIONS)

DUE DATE OF PLAN &

AGREEMENT FROM UTILITY

DATE UTILITY AGREEMENT

RECEIVED FOR REVIEW

P6 READY TO LET DATE

HIGHWAY / SECTION COUNTY

ROW CSJ / PROJECT NUMBER

UTILITY INSPECTOR

DATE OF UTILITY KICKOFF MEETING

ROW RELEASE

DATENAME U-NUMBER

5/20/09

DATE OF INTIAL CONTACT

NOTIFYING UTILITY OF

PROP. PROJECT

UTILITY COMPANIES

NON - REIMBURSABLE TYPE REIMBURSABLE $

0014-09-096

IH 35 / 5A from N Loop

340 to N BU 77

IH 35 / 5A from N BU 77 to Hilltop Rd

0015-01-219

0014-08-082 0014-08-075

McLennan

McLennan

McLennan

0015-01-180

Jan-10

Jan-10

Jan-10

Jul-10

Jul-10

Jul-10IH 35 / 5A

from Hilltop Rd to FM 1858

DESIGNER / PROJECT MANAGER STATUS

0014-09-080 6/10/09

11/10/09

DUE DATE OF INFORMATION NEEDED FROM DESIGNER

PLAN & PROFILE W/ UTILITIES

PROPOSED X-SECTIONS

UTILITY COORDINATORDCIS

DISTRICT LET DATE

Page 7: Increasing Pace of Utility Accommodations

Stakeholders in Project Tracking

Construction Inspector

Utility / Roadway Contractor

Property Owner ROW

Agent / Utility Coord.

Utility Designer

Rdwy Designer Project Mgr

Utility Owner / Local Entity

TxDOT Administration

Utility Accommodation

Process

Page 8: Increasing Pace of Utility Accommodations

Summary

Engage the utilities into the

design/plan process of roadway projects

Initiate coordination effort as early as possible

Evaluate the time to accomplish