Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP...

58
Incident and Emergency Response Plan Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats) Document details Revised by: Reviewed by: Endorsed by: -------------------------------------------- -------------------------------------- ------------------------------------- Jared Looker Irina Kliger Matthew Saviana Regional Safety Manager Regional Environmental Project Director Manager Content ID: APRB-IERP Revision No: 3 Revised: 07/11/2018

Transcript of Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP...

Page 1: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Document details

Revised by: Reviewed by: Endorsed by:

-------------------------------------------- -------------------------------------- ------------------------------------- Jared Looker Irina Kliger Matthew Saviana

Regional Safety Manager Regional Environmental Project Director Manager

Content ID: APRB-IERP Revision No: 3 Revised: 07/11/2018

Page 2: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Document Control

This Plan interfaces with the other associated plans, which together describe the proposed overall project management system for the Project.

The latest revision of this plan is available on the Fulton Hogan server. Distribution of this Plan by “hard copy” will be to those detailed on the distribution list above. If any unsigned hard copies of this document are printed, they are valid only on the day of printing.

The revision number is included at the bottom of each page. When revisions occur, the entire document will be issued with the revision number updated accordingly for each owner of a controlled copy.

Attachments and appendices to this Plan are revised independently of this Plan.

The relevant parts of this Plan are publicly available on the Fulton Hogan website, as required by Clause 98D(3) and (4) of the Protection of the Environment Operations (General) Regulation 2009.

Revision History

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 2 of 55

Page 3: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Roads and Maritime Services approval and authorisation

Title Incident and Emergency Response Plan Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Accepted on behalf of NSW Roads and Maritime Services by

Peter Hawkins

Signed

Dated 08/11/18

Environmental Representative endorsement

Endorsed by the Environmental Representative

Toby Hobbs

Signed

Dated 08/11/18

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 3 of 55

Page 4: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Table of Contents

List of tables.................................................................................................................................... 5

1. Introduction.............................................................................................................................. 6

1.1. Purpose and scope........................................................................................................... 6 1.2. Project description ............................................................................................................ 6

2. Planning................................................................................................................................... 7

2.1. Planning considerations.................................................................................................... 7 2.2. Emergency management organisational structure ............................................................ 7 2.3. Consultation...................................................................................................................... 8

3. Incident and emergency response ........................................................................................... 8

3.1. Incident and emergency response flowcharts ................................................................... 8 3.2. Site layout plans ............................................................................................................... 9 3.3. Emergency muster area.................................................................................................... 9 3.4. Emergency equipment ...................................................................................................... 9 3.5. Testing - desktop simulations/exercises/drills ................................................................. 10 3.6. Incident (vehicle/public/environmental – non-work related) ............................................. 10

4. Pollution incident response management............................................................................... 11

4.1. Pollution incident response management plan legislative requirements.......................... 11 4.2. Description and likelihood of hazards.............................................................................. 11 4.3. Pollution incident notification protocol ............................................................................. 11 4.4. Pre-emptive actions ........................................................................................................ 12 4.5. Contact details ................................................................................................................ 12 4.6. Inventory of pollutants..................................................................................................... 12 4.7. Communicating with neighbours and local community .................................................... 13 4.8. Minimising harm to persons on premises ........................................................................ 13 4.9. Maps............................................................................................................................... 13

5. Training.................................................................................................................................. 14

6. Responsibilities...................................................................................................................... 16

7. Revision................................................................................................................................. 16

8. Definitions.............................................................................................................................. 17

9. Procedures ............................................................................................................................ 17

10. Appendices............................................................................................................................ 17

Appendix A – Incident and emergency response contacts......................................................... 18 Appendix B – Incident and emergency response flowcharts ...................................................... 19 B01 - Incident and emergency response flowchart - initial response (R.E.A.C.T) ...................... 20 B02 - Incident and emergency response flowchart - emergency communications ..................... 22 B03 - Incident and emergency response flowchart - emergency evacuation.............................. 24 B04 - Incident and emergency response flowchart - crisis management ................................... 26 B05 - Incident and emergency response flowchart – asbestos .................................................. 28 B06 - Incident and emergency response flowchart - bomb threat or other serious threat........... 29 B07 - Incident and emergency response flowchart - breach of aviation airspace obstacle limitation surface (OLS)............................................................................................................. 30 B08 - Incident and emergency response flowchart - plane or object landing in work area ......... 31 B09 - Incident and emergency response flowchart - bushfire .................................................... 32

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 4 of 55

Page 5: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B10 - Incident and emergency response flowchart - chemical - oil and fuel spills ...................... 33 B11 - Incident and emergency response flowchart - emergency situation at height ................... 34 B12 - Incident and emergency response flowchart - fall arrest .................................................. 36 B13 - Incident and emergency response flowchart - major fires or explosions........................... 37 B14 - Incident and emergency response flowchart - robbery or hostile intruder......................... 38 B15 - Incident and emergency response flowchart - serious injury ............................................ 39 B16 - Incident and emergency response flowchart - service strikes – electricity cables............. 41 B17 - Incident and emergency response flowchart - service strikes and leaks - gas.................. 42 B18 - Incident and emergency response flowchart – service strikes and leaks - water or sewerage pipes ......................................................................................................................... 43 B19 - Incident and emergency response flowchart - storms and flooding – process.................. 44 B20 - Incident and emergency response flowchart - trench collapse ......................................... 45 B21 - Incident and emergency response flowchart - vehicle accidents and plant rollovers ........ 46 Appendix C – Site layout plans.................................................................................................. 47 Appendix D – PIRMP legislative compliance matrix................................................................... 48 Appendix E – Environmental incidents and emergencies risk assessment ................................ 52 Appendix F – Pollution (or other environmental) incident notification protocol ........................... 55

List of tables

Table 1: EPC members ...........................................................................................................................................7

Table 2: Consultation plan .......................................................................................................................................8

Table 3: Core incident or emergency scenarios ......................................................................................................8

Table 4: Specific incident or emergency scenario flowcharts (see appendices of this Plan) ..................................8

Table 5: Potential pollutant inventory ....................................................................................................................12

Table 6: Training requirements..............................................................................................................................14

Table 7: RASCI chart.............................................................................................................................................16

Table 8: Definitions ................................................................................................................................................17

Glossary/Acronyms

APRb Albion Park Rail bypass, the Project

CEMP Construction Environmental Management Plan

EC Emergency Controller

EPC Emergency Planning Committee

ERT Emergency Response Team

IERP Incident and Emergency Response Plan

OLS Obstacle Limitation Surface

PIRMP Pollution Incident Response Management Plan

PMP Project Management Plan

POEO Act Protection of the Environment Operations Act 1997

POEO(G) Regulation

Protection of the Environment Operations (General) Regulation 2009.

SWMS Safe Work Method Statement

WRA Workplace Risk Assessment

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 5 of 55

Page 6: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

1. Introduction

This Incident and Emergency Response Plan (IERP) applies to any incident or emergency occurring on Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats) (the Project), or involving Fulton Hogan’s personnel away from their regular place of work but while on company business.

This IERP shall be used in conjunction with the Workplace Health and Safety Management Plan (WHSMP), Construction Environmental Management Plan (CEMP) and the relevant sub-plans, Traffic and Transport Management Sub-plan and Aviation Method of Working Plan. Together these documents outline the mandatory requirements for preparing for, responding to and recovering from any safety or environmental incidents or emergencies, including where assistance from local emergency services is required.

This IERP shall also be used in conjunction with Fulton Hogan’s Incident Investigation, Reporting and Notification procedure, which provides umbrella guidance on corporate requirements for notification, recording, investigation and reporting of all incidents, including significant safety and environmental incidents.

This IERP has also been developed to ensure compliance with obligations under the State Disaster Plan (DISPLAN) and will work with Illawarra Emergency Management District.

These DISPLANs provides framework for escalating emergency response to an incident, where the relevant Emergency Services Incident Controller (in consultation with the local Emergency Management Committee) has determined that resources of the local emergency service provider are insufficient to deal with the threat.

This IERP has also been developed to ensure compliance with the requirements of Roads and Maritime Environmental Incident Classification and Reporting Procedure for the reporting of environmental incidents as detailed in Section 4.3 of this Plan.

1.1. Purpose and scope

This IERP describes the strategy for preparing, responding to and recovering from any safety or environmental incident during construction of the Project. It also provides an integrated approach to management of both environmental and safety incidents where the assistance of external emergency response agencies is required.

This IERP does not address the broader company response to critical incidents or crises. Crises are defined as events or developments, real or perceived, which threaten the viability of the company and have the potential to threaten the safety or wellbeing of workers and others, the environment, or the integrity, performance, reputation of the company. Where such incidents stem from project-based incidents or emergencies, they shall be managed in accordance with this Plan, The Project Management Plan (PMP) and the requirements of the Crisis Management Procedure.

1.2. Project description

The project is known as the Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats). The project would provide motorists with a more consistent travel experience between Sydney, Wollongong and the NSW South Coast. It would increase the capacity of the road network to cope with the additional traffic generated by current and future residential development in the area.

A detailed description of the Project is provided in the PMP.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 6 of 55

Page 7: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

2. Planning

2.1. Planning considerations

The following aspects were identified as relevant considerations in the emergency management planning process:

Integration and consistency with local area DISPLAN

The impact of a major emergency on neighbouring facilities, businesses and community

Regular site visits by emergency services personnel to maintain familiarisation with the site (emergency) accesses and resources as it changes over time

Emergency communication protocols for the relevant agencies to ensure coordinated approach, specifically:

Emergency Response Agencies, (i.e. NSW Police, Ambulance Service, Fire Rescue and Hazmat, State Emergency Service or specialist emergency providers)

Roads and Maritime

SafeWork NSW

Wollongong City Council

Shellharbour City Council

Utilities such as Ausgrid, Telstra / Optus/ Jemena / Transgrid / AAPT / Nextgen / Caltex

Office of Environment and Heritage, and

Environment Protection Authority.

Detailed site layout plans showing key elements, such as emergency access/egress points, location of the firefighting equipment, etc.

The prestart, toolbox, induction registers of all persons at the workplace that will be used during emergency response drills

A callout list of personnel who will be contacted during emergency or incidents

Availability of adequate resources to provide effective emergency and incident response, and

Training to be provided to all personnel in incident and emergency response.

2.2. Emergency management organisational structure

The Emergency Planning Committee (EPC) for the Project consists of the following personnel:

Table 1: EPC members

EPC member Discipline / focus area

Project Director Entire Site

General Superintendent (EC) Entire Site

Safety Representative Entire Site

Environmental Manager (or delegate) Entire Site

The incident and emergency response contact list is included in Appendix A. This list shall be maintained by the Project Safety Manager so that contact details and roles detailed in the list are current, and shall be reviewed six monthly. This list shall be displayed in various prominent locations around the project, including but not limited to the site office area, site notice boards, lunchrooms and first aid rooms.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 7 of 55

Page 8: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

2.3. Consultation

IERP consultation is to be undertaken with workplace staff, subcontractors and external agencies, including those responsible for emergency response, as outlined below:

Table 2: Consultation plan

Stakeholder Consultation Date Comments Received

Roads and Maritime TBA

Police TBA

Fire and rescue TBA

.

Ambulance service TBA

State Emergency Services TBA

Specialist Emergency Services As Required

The Project Team is to consider any comments received from stakeholders or emergency services for incorporation within this plan prior to its issue for implementation.

Regular communications shall be established with emergency services as/if required.

3. Incident and emergency response

3.1. Incident and emergency response flowcharts

For each potential incident or emergency scenario identified in the Workplace Risk Assessment (WRA), a corresponding incident or emergency flowchart is developed for the specific requirements of the Project. These flowcharts are provided in Appendix B of this Plan.

Where a task or activity occurs that has emergency response or first aid impacts which have not been identified in the WRA or in this Plan, these impacts shall be managed through the Safe Work Method Statements (SWMS) for the activity or through activity-level controls and considered during any subsequent reviews.

Below is a list of potential scenarios identified for the Project:

Table 3: Core incident or emergency scenarios

Core incident or emergency scenario flowcharts

Initial response (R.E.A.C.T) Emergency evacuation

Emergency communications Crisis management

Table 4: Specific incident or emergency scenario flowcharts (see appendices of this Plan)

Specific incident or emergency scenario flowcharts

Asbestos Robbery or hostile intruder

Bomb threat Service strikes and leaks – gas

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 8 of 55

Page 9: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Bushfire Service strikes – electricity or power cables (underground or overhead)

Chemical oil and fuel spills Service strikes and leaks - water or sewerage pipes

Emergency situation at height Trench collapse

Fall arrest Vehicle accidents and plant rollover

Major fires or explosions Serious injury

Breach of aviation airspace Obstacle Limitation Surface (OLS)

Plane or object landing in work area

Storms and flooding - process

3.2. Site layout plans

The Safety Manager shall ensure that the site layout plans developed for the Project, as listed in Appendix C, are reviewed for currency at regular intervals, including after relocating the site resources. These Site layout plans shall be displayed on each site notice board and include information regarding:

Location of emergency equipment and first aid facilities

Location of site evacuation muster points

Site boundaries, roadways, buildings

Location of storage areas for dangerous goods and chemicals

Entrances and exits

Alternative entrances and exits

Emergency access points.

3.3. Emergency muster area

The workplace manager shall nominate emergency muster areas for the workplace. Each emergency muster area shall be clearly identified on the site layout plan. The muster area must consider:

The location of the work area

The availability of a large enough open/protected area to house all persons evacuated

The topography of the site in relation to ease of travel to the muster area, and

The location of emergency equipment such as first aid kits, stretcher, fire-fighting equipment, spill-kits etc.

During extreme risk or total fire ban days, a Bush Fire Survival Plan shall be completed at the Prestart and consulted to each area’s work crew.

3.4. Emergency equipment

With reference to the WRA and the Incident and Emergency Response Equipment Guidelines, the EPC shall determine the emergency equipment requirements for the project. These requirements shall then be checked against the Emergency Equipment Inspection Checklist. The Safety Manager shall ensure a Register of Emergency Equipment is maintained and emergency equipment is available and appropriately located in relation to work areas on site; and inspected, tested and maintained as necessary.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 9 of 55

Page 10: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

3.5. Testing - desktop simulations/exercises/drills

The IERP, including all requirements of the PIRMP (refer Appendix D), shall be tested to ensure that the information is accurate and up to date, and that the IERP is capable of being implemented in a workable and effective manner.

Testing will be undertaken by way of:

Desktop simulations, and/or

Practical exercises/ drills.

For desktop simulations, the Environmental Manager (or delegate) shall organise relevant environmental desktop exercises to stimulate discussion of issues and review various aspects of the IERP.

Each desktop simulation shall be recorded. The record shall capture information, including (but not limited to) the:

Discussion items

Date of the desktop simulation

Name of the staff members who attended the desktop simulation

Attendance record.

For practical exercises/drills, the Safety Manager, in consultation with the EPC, shall ensure that a Drill Schedule is developed, maintained and adhered to at each site on the project. The Drill Schedule includes the dates on which the various hazards/risks identified in the IERP are scheduled to be tested, and when they have been tested.

The Safety Manager, in consultation with the EPC, shall arrange for practical exercises/ drills for both workers and subcontractors.

Following each practical exercise/ drill, the Safety Manager shall ensure that all persons observing and or evaluating drills complete an Incident and Emergency Response Drill Record. This Record captures a suite of information, including (but not limited to) the:

The scope of the drill

Date of the drill

Name of the staff members who conducted the drill

Name of the staff member who completed the drill record

Attendance record.

Desktop simulations or practical exercises/ drills shall be carried out:

Routinely at least once every 12 months

Within one (1) month of any pollution incident occurring. In the light of that incident, the intent is to assess whether the requirements of the PIRMP included in this IERP (refer Appendix D) are accurate and up to date, and the plan is still capable of being implemented in a workable and effective manner.

3.6. Incident (vehicle/public/environmental – non-work related)

Should there be an event requiring initial management by the project Emergency Response Team or interaction with the project or requiring initial support from the project, (e.g.- dozer or water cart) to assist with initial response to an incident, the relevant Emergency Flowcharts listed in table 3 and 4 and the Traffic Incident Response Plan will be utilised in the response and in conjunction with direction from any Emergency Service. (i.e.- police, SES, Fire etc).

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 10 of 55

Page 11: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

4. Pollution incident response management

The purpose of this section is to address the requirements of the Protection of the Environment Operations Act 1997 (POEO Act) and Protection of the Environment Operations (General) Regulation 2009 (POEO (G) Regulation) not otherwise specifically addressed in this IERP.

4.1. Pollution incident response management plan legislative requirements

The specific legislative requirements for a Pollution Incident Response Management Plan (PIRMP) are set out in Part 5.7A of the POEO Act and Part 3A of the POEO (G) Regulation. These requirements and a cross reference are included in Appendix D to ‘readily identify’ where each requirement is met in this IERP, or otherwise.

4.2. Description and likelihood of hazards

The main hazards and risks to human health and the environment associated with project activities have been identified by completing an Environmental Incidents and Emergencies Risk Assessment. The risk assessment was undertaken in a workshop involving key project personnel and included consideration of the following:

Consequence and likelihood of hazards and risks to human health and the environment occurring;

Proximity to sensitive environment, (i.e. ‘no-go’ zones, or sensitive receivers, such as schools, retirement homes and farms).

Based on the pre-control hazard risk rating, the following hazards to human health and the environment were identified as ‘High’ risk:

Severe weather events

Illegal waste dumping (by others)

Vehicle collision

Chemical spill in waterway (onsite and offsite impact)

Primer/ primer-binder washed off pavement

Unauthorised washout of concrete trucks and pumps

Chemical spill on land (onsite impact)

Of these, the following hazards relate directly to pollution incidents:

Illegal waste dumping (by others)

Chemical spill in waterway (onsite and offsite impact)

Primer/ primer-binder washed off pavement

Unauthorised washout of concrete trucks and pumps

Chemical spill on land (onsite impact)

The results of the risk assessment are included in Appendix E of this IERP.

Refer to Section 4.4 for the pre-emptive actions (controls) to be taken to minimise or prevent any risk of harm to human health or the environment.

4.3. Pollution incident notification protocol

All pollution incidents or any other environmental incidents must be reported in accordance with the Pollution (or other Environmental) Incident Notification Protocol included in Appendix F of this Plan. This protocol is consistent with the environmental incident reporting requirements contained in the Roads and Maritime Environmental Incident Classification and Reporting Procedure.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 11 of 55

Page 12: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

4.4. Pre-emptive actions

Pre-emptive actions to be taken to minimise or prevent any risk of harm to human health or the environment arising from project activities are included in the following project documentation:

Construction Environmental Management Plan (CEMP) and the relevant Sub-Plans

Environmental Work Method Statements, and

Construction Method Statements.

The above documents describe in detail the measures that will be taken to prevent or minimise any risks of harm to human health or the environment including:

Daily and weekly site environmental inspections

Ongoing environmental monitoring

Environmental audits

Task-specific risk assessments

Ongoing training of staff.

4.5. Contact details

The 24-hour contact details for the project personnel responsible for activating this plan and managing the response to all pollution incidents are included in Appendix A of this Plan. The contact details for reporting pollution incidents to the relevant authorities are also included in Appendix A.

4.6. Inventory of pollutants

The inventory of potential pollutants kept on premises or used in carrying out project activities will be included in the Safety Data Sheet Register located on the Fulton Hogan Intranet. A summary of the key potential pollutants is outlined below. Mobile sources of potential pollutants present onsite will include all refuelling vehicles and plant items which will be utilised throughout the works.

Table 5: Potential pollutant inventory

Potential Pollutant Maximum Quantity Storage Location

Diesel 8,000L Machinery, Bunded Areas, Fuel Pods, Refuelling Truck

Petrol 200L Machinery, Chemical Storage Containers

Hydraulic Fluid 500L Machinery, Chemical Storage Containers

AgLime 5t Bridge and Earthworks Compounds

Gypsum (powder) 15t Earthworks Compound

Engine Oil 200L Machinery, Chemical Storage Containers

Minor oils/lubricants 200L Machinery, Chemical Storage Containers

Spray Paint 50L Chemical Storage Containers

Oxy/Acetylene 200kg Bridge Compound (in cage, upright)

Contaminated waste ~2,000m3 In-situ

Form Oil 60L Bridge Compound

Curing Compound 1,500L Bridge and Earthworks Compounds

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 12 of 55

Page 13: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Spray Seal (bitumen) 15,000L Spray seal contractor truck

Herbicides 10L Chemical Storage Containers

Turbid Water 5,000m3 Sediment Basins, excavations

Drill Slurry/Bentonite 2,000m3 Bridge and Earthworks Compounds

4.7. Communicating with neighbours and local community

Should a pollution incident occur that threatens to cause harm to human health or the environment, the following notification protocol will be followed:

Environmental and engineering staff in consultation with Community Liaison team will determine the community notification catchment depending on the nature of each incident and input from authorities.

Early warnings and regular updates ongoing as required will be issued by phone calls, web updates and door knocking to affected residents/receivers.

Notifications to affected residents will include details of incident, time frame of the impact and the mitigation measures put in place.

Instructions to residents to minimise health impact (i.e. for airborne chemicals residents will be advised to close windows and doors, to take extra care if they have respiratory issues, keep children inside and protect animals, where possible).

Sensitive receivers will receive priority notification of pollution incidents.

4.8. Minimising harm to persons on premises

Should a pollution incident occur that threatens to cause harm to persons on the premises this Plan will be activated.

4.9. Maps

Clause 98C (1) (k) of the POEO (G) Regulation, requires a detailed set of maps showing the following information:

The location of the premises to which the EPL relates

The surrounding area that is likely to be affected by a pollution incident

The location of potential pollutants on the premises

The location of any stormwater drains on the premises.

With the exception of the location of stormwater drains, all required information is shown on the Sensitive Area Plans included in Appendix A6 of the CEMP.

The location of stormwater drains will be shown on the most current set of Drainage Drawings, available on the Fulton Hogan server.

Since the Sensitive Area Plans and Drainage Drawings are subject to frequent change throughout construction, the reader is asked to refer directly to the respective document (as mentioned above) to ensure its currency, rather than appending it separately to this IERP.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 13 of 55

Page 14: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

5. Training

The EPC shall determine the specific competencies required to adequately respond in an incident or emergency at each site, and the training required to achieve these competencies. Training shall conform to all project requirements depicted in the project’s Training Management Plan, including any environmental emergency response training. This process shall be tracked and managed in Fulton Hogan’s People Development Platform online application (PDPAU). Training shall be carried out to achieve the following emergency related competencies:

Table 6: Training requirements

Competency EC EPC ERT First Aider

Incident and emergency response – Level 2 – Emergency coordinator

Yes Yes (at least one member) Yes (at least one member) Recommended

Apply first aid Recommended Recommended Yes (at least one member) Yes

Crisis management Yes Yes (at least one member) Yes (at least one member) No

Emergency communications Yes Yes (at least one member) Yes No

Emergency evacuation Yes Yes (at least one member) Yes No

Initial response Yes Yes (at least one member) Yes Recommended

Serious injury Yes Yes (at least one member) Yes Yes

Asbestos Yes Recommended Yes (at least one member) No

Bomb Threat or Other Serious Threat Yes Recommended Yes (at least one member) No

Bushfire Yes Recommended Yes (at least one member) No

Emergency situation at height Yes Recommended Yes (at least one member) No

Chemical oil and fuel spill Yes Recommended Yes (at least one member) No

Fall arrest Yes Recommended Yes (at least one member) No

Major fire and explosion Yes Recommended Yes (at least one member) Recommended

Service strikes - Electricity cables Yes Recommended Yes (at least one member) No

Service strikes and leaks - Gas Yes Recommended Yes (at least one member) No

Service strikes and leaks - Water and sewerage Yes Recommended Yes (at least one member) No

Storms and flooding - process Yes Recommended Yes (at least one member) No

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 14 of 55

Page 15: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Trench collapse Yes Recommended Yes (at least one member) No

Vehicle accidents and plant rollover Yes Recommended Yes (at least one member) No

Breach of aviation airspace OLS Yes Recommended Yes (at least one member) No

Plane or object landing in work area Yes Recommended Yes (at least one member) No

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 15 of 55

Page 16: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

6. Responsibilities

Each job role within this plan has the following responsibilities for each task as per the RASCI model. For more information, refer to the RASCI Procedure.

Responsible for conducting work

Accountable and ultimately responsible for work, signs off on work before implementation

Supportive through provision of resources/implementation support

Consulted for information/perspective/capability relevant to the work

Informed of outcomes but need not be consulted.

Table 7: RASCI chart

Task

Pro

ject

Directo

r

EP

C

EC

ER

T

First aid

er

Appoint EPC, ERT, EC A R C I

Undertake external consultation A C R I

Develop incident and emergency response flowcharts A R I

Develop site layout plans A S R C I

Determine emergency muster areas A S R C

Develop resources and equipment A R C C I

Inspect resources and equipment A S R I R

Develop drill schedule A R C C

Test emergency procedures A S R C I

Train emergency response personnel A R S C

7. Revision

The IERP shall be maintained, reviewed and updated at least annually by the Safety Manager, in consultation with the Environmental Manager (or delegate). The plan shall also be reviewed following:

Testing which identifies changes to the IERP (refer Section 3.5)

An independent audit which recommends changes to the IERP

A relevant change to workplace activities or regulatory requirements

An emergency event.

In reviewing the IERP, workplace personnel involved or likely to be involved in incident management or response shall be consulted.

Changes to this IERP will be reviewed and approved by the Project Director and documented in the revision history section of this IERP. A copy of the updated plan and changes shall be distributed to all relevant stakeholders.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 16 of 55

Page 17: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

8. Definitions

Table 8: Definitions

Term Definition

Coordination The bringing-together of agencies and individuals to ensure effective management. Coordination does not include the command or control of agencies and individuals.

Emergency An imminent threat or actual incident that poses significant harm to the safety or health of persons, property, the environment, the local community or adjacent traffic operations. An incident of this kind may result in the project seeking assistance from external emergency services agencies.

Emergency coordinator (EC)

The person appointed by the Project Director to lead project efforts during a significant incident or emergency.

Emergency muster area

An area that is set aside at each site for the assembly of persons in case of an evacuation.

Emergency response team (ERT)

A team of personnel at the project that is responsible, under the direction of the EC, for the preparation for, response to and recovery from significant incidents and emergencies.

Incident A localized event, either accidental or deliberate, which may result in injury, death or damage to property or the environment. An incident requires a normal response from project incident management personnel, and may also require a response from emergency services.

Recovery In relation to an emergency, the process of returning affected site personnel to their normal level of functioning following an emergency. This includes the welfare of persons as well as the safe reconstruction of the site.

9. Procedures

The following Procedures on Fulton Hogan Intranet, the Hub, and are available to external parties upon request:

Dangerous Goods & Hazardous Substances Procedure: Outlines the management of dangerous goods & hazardous substances.

Emergency Response Procedure: Outlines the emergency response of management during activities associated with a Project/Site/Department.

First Aid Procedure: This procedure outlines the management of first aid at Fulton Hogan workplaces.

Incident Critical Response Procedure: Outlines a when a critical response is required, the critical response team and steps to manage the incident.

Incident Investigation, Reporting & Notification Procedure: This procedure describes the incident/accident reporting and investigation requirements of Fulton Hogan Pty Ltd. Isolation Procedure: To provide guidance on the appropriate isolation procedure for plant undergoing maintenance, cleaning, repair or construction

Issue Resolution Procedure: Outlines how OH&S issues raised are progressed through resolution.

10. Appendices

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 17 of 55

Page 18: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Appendix A – Incident and emergency response contacts

[SEPARATE DOCUMENT]

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 18 of 55

Page 19: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Appendix A – Incident and Emergency Response Contacts

PART A: Workplace Details

Location of Activity / Worksite:

Site Address:

Nearest cross Street:

Emergency Assembly Point:

Albion Park Rail bypass

Illawarra Highway, Albion Park.

Princes Highway

Various as per site plans for individual locations

EMERGENCY CONTACT: 000 or 112 from mobiles

PART A1: Key Project Personnel

Title Name Contact Details

Project Director

General Superintendent

Traffic Manager

WHS Manager

Environmental Manager

Community Relations Manager

PART A2: Emergency Personnel

Title Name Contact Details

Emergency Controller (EC)

Deputy Emergency Controller

OccCorp – Injury Reporting

PART A3: First Aiders

Content ID: APRB-IERP.APP.A This is an uncontrolled copy if photocopied or unsigned. Revised: 02/11/2018 Revision: 2 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 1 of 3

Page 20: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

PART B: EXTERNAL EMERGENCY CONTACTS

ORGANISATION/ POSITION/ NAME TELEPHONE No.

Injury Reporting: OccCorp (Maree Macaleer) 1 300 666 303

Medical Centre: Kiama Medical Practice, 88 Manning St, Kiama (02) 4232 3393

Hospital (emergency): Shelharbour Hospital – 15-17 Madigan Boulevard Mount

Warrigal SNSW 2528 (02) 4295 2500

Police

000 106 If hearing / speech impaired Ambulance

Fire

NSW State Emergency Services 13 25 00

NSW Office of Emergency Management (02) 9212 9200

Traffic

Transport Management Centre (Incident and Hazard Reporting)

Southern Region Traffic Operations Unit

13 17 00

(02) 4221 2448

Safe Work Authority

SafeWork NSW Assistance Service

After Hours Emergency Contact

Construction Hotline

13 10 50

13 10 50

(02) 9214 9220

Poisons Information Centre 13 11 26

Local Councils

Wollongong City Council (02) 4227 7111

Shellharbour City Council:

(Team Leader Environment)

(Environment Officer)

Illawarra Health District (02) 4222 5000

EAP Counselling – Employee Assistance Program 1300 687 327

EPA 1 800 337 068

Fauna Rescue (02) 6620 2100

WIRES Wildlife Rescue Organisation

NPWS – In circumstances where you cannot get in touch with WIRES Wildlife Rescue (South Coast)

13 000 WIRES (094 737)

0418 427 214

Heritage 1800 629 104

NPWS

OEH

NSW Heritage – reporting potential non-indigenous archaeological relic or site

1 800 629 104

131 555

(02) 9873 8500

Content ID: APRB-IERP.APP.A This is an uncontrolled copy if photocopied or unsigned. Revised: 02/11/2018 Revision: 2 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 2 of 3

Page 21: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Services

Telstra 13 20 00

Optus 13 20 00

Jemena 1 800 200 487

Endeavour Energy 13 10 03

AAPT 1300 786 786

Nextgen 1800 099 299

Sydney Water 13 20 90

Content ID: APRB-IERP.APP.A This is an uncontrolled copy if photocopied or unsigned. Revised: 02/11/2018 Revision: 2 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 3 of 3

Page 22: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Appendix B – Incident and emergency response flowcharts

B01 Initial response (R.E.A.C.T)

B02 Emergency communications

B03 Emergency evacuation

B04 Crisis management

B05 Asbestos

B06 Bomb threat or other serious threat

B07 Breach of aviation airspace Obstacle Limitation Surface (OLS)

B08 Plane or object landing in work area

B09 bushfire

B10 Chemical - oil and fuel spills

B11 Emergency situation at height

B12 Fall arrest

B13 Major fires or explosions

B14 Robbery or hostile intruder

B15 Serious injury

B16 Service strikes - electricity cables

B17 Service strikes and leaks - gas

B18 Service strikes and leaks - water or sewerage pipes

B19 Storms and flooding – process

B20 Trench collapse

B21 Vehicle accidents and plant rollovers

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 19 of 55

Page 23: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B01 - Incident and emergency response flowchart - initial response (R.E.A.C.T)

Emergency response teamEmergency coordinatorWorker

Immediately alert the emergency coordinator

Can the incident be safely managed by

workplace personnel?

Control source of emergency if possible

Contain the problem and prevent the problem From

getting any bigger

Protect what is not damaged

Clean up

Initiate a 000 call, if required.

Provide the following information to emergency

services-· WHERE is the location?· WHAT happened?· WHEN did it happen?· WHO is involved?

Coordinate a response to the emergency

Implement and manage response activities

Leave the site and hand over responsibility to the emergency coordinator when the response is finished and the situation is

safe

Consult with the emergency coordinator

Authorise the recommencement of work

Investigate and report as per the incident notification,

reporting and investigation procedure

Yes

No

Respond Examine Assess Control Talk TM

Respond

Examine

Assess

Control

Talk

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 20 of 55

Page 24: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Guidelines

Role Task Detail

Worker Immediately alert the emergency coordinator.

Refer to the emergency communication flowchart guidelines for further information on

how to transmit an emergency call sign. The workplace manager or emergency coordinator

are the primary points of contact for alerting emergency services.

Emergency coordinator

Initiate 000 call if required. Refer to the emergency communication flowchart guidelines for further information on

making a 000 call.

Coordinate a response to the emergency.

If possible, evaluate the most appropriate response to the emergency in consultation with

the safety/environment operatives, emergency warden(s) and emergency response team. The emergency coordinator shall ensure an initial response is actioned to mitigate immediate

environmental/safety risks, providing it is safe to do so. The immediate priority is the protection

and rescue of human life.

Authorise the recommencement of work.

No work shall be commenced in the affected area until:

the workplace manager, in consultation with the emergency coordinator, has

completed appropriate inspections

issues affecting the safety of persons have been rectified (for example,

damage to plant and equipment)

clearances have been provided from the appropriate authorities

the workplace manager has authorised recommencement of work.

Investigate and report as per the incident notification, reporting and

investigation procedure.

Refer to the incident notification, reporting and investigation procedure for further information.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 21 of 55

Page 25: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B02 - Incident and emergency response flowchart - emergency communications

Emergency response teamEmergency coordinatorWorker

Set radio to general

construction or

operations channel

Depress the

transmission button.

Transmit “Emergency,

emergency,

emergency.”

Dial 000 and confirm

the required service:

· Police

· Fire

· Ambulance

Provide the following

information:

· WHERE is the

emergency?

· WHAT happened?

· WHEN did it happen?

· WHO is involved?

Ensure that you speak:

· Clearly

· Slowly

· Precisely

Do not hang up until the

operator tells you.

Release button and

wait for response.

Determine the

emergency

Provide support if

appropriate

Respond Examine Assess Control Talk TM

Media The MD, CEO and the National Communications are the only people authorised to speak on behalf of Fulton Hogan to the media.

If contacted by the Federal, State and/or local government representatives or media (including industry magazines) in relation to this project, Roads and Maritime Services is to be notified immediately of the name, phone number and media outlet of the journalist. No comments or statements are to be made to any media or political representative or their staff about the project.

Do not respond to any media questions

Do not say “No comment”

Do not agree to say anything ‘off the record’

Be polite

… Please call the Community Relations Manager on 1800 708 727…

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 22 of 55

Page 26: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Guidelines

Role Task Detail

Worker Set radio to general construction or operations

channel.

On transmission of the emergency call sign, all radio

communication on the affected site (and other sites as

determined by the emergency controller) must immediately

cease. If there are multiple frequencies used on the site,

users will be directed to an emergency frequency. Information, directions and

evacuation processes will be communicated via this

frequency.

Transmit “emergency, emergency, emergency”.

Emergency coordinator Determine the emergency. Site personnel and the EC ensure that sufficient information is gathered on the

incident, from the initiator, to enable an informed decision to

be made as to the most appropriate response.

Dial 000 and confirm the required service: police, fire or

ambulance.

All calls to emergency services must clearly detail the nature of

the emergency and, where possible, the number of

casualties and type of their injuries.

Provide the following information:

Where is the emergency?

What happened?

When did it happen?

Who is involved?

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 23 of 55

Page 27: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Content ID: APRB-IERP Revision: 3

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2018, Fulton Hogan Ltd. All rights reserved.

Revised 07/11/2018 Page 24 of 55

B03 - Incident and emergency response flowchart - emergency evacuation

Page 28: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Guidelines

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 25 of 55

Role Task Detail

Worker Do not make any statements Refer to the emergency to the press. communications flowchart for

further information.

Emergency coordinator Notify the appropriate All calls to emergency services services on 000. must clearly detail the nature of

the emergency and, where

Provide advice to and liaise possible, the number of

with emergency services. casualties and type of their injuries.

Announce evacuation. Using the site communication system, the EC or emergency warden shall direct all personnel to commence evacuation.

Emergency response team Ask any visitor or contractor Emergency warden(s) to evacuate to the emergency shall be responsible for ensuring muster area with you. all workplace direct employees,

subcontractors, visitors and others onsite have assembled at the nominated area and that personnel entering or leaving the site are continuously monitored.

Position a person in a safety A member of the emergency vest at the site entrance to response team shall meet direct emergency services. emergency services at an agreed

location and provide all necessary direction or advice to ensure emergency services are aware of the nature of the emergency and the necessary information to proceed to the affected area.

Page 29: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B04 - Incident and emergency response flowchart - crisis management

Crises are defined as events or developments, real or perceived, which threaten the viability of the

company, have the potential to threaten the safety or wellbeing of workers and others, the

environment, or the integrity, performance, reputation of the company. Where such incidents stem

from workplace based incidents or emergencies, they shall be immediately managed in

accordance with the incident and emergency response procedure, however in parallel the

requirements of the crisis management procedure shall be implemented.

Worker Emergency response teamEmergency coordinator

Clear people away from the

scene, assess scene for

danger before giving

emergency assistance if

safe to do so

Contact the relevant

emergency services where

necessary

Remove all personnel from the

site including subcontractors

Contact regional safety /

environment manager and

general manager

Secure the site. Do not disturb

until the relevant government

regulator has given approval

Organise trauma counselling

and debriefing by

professional counselling

services

Do not make any statements to

the press

(Refer to dealing with the

media)

Do not make any admissions of

guilt. The matter will be under

investigation and management

will make a statement in due

course

Brief the crisis management

team (determined by

corporate office) when they

arrive at the scene and take

any actions, as required

Follow crisis management

team’s directions

Advise corporate team of

potential crisis

Respond Examine Assess Control Talk TM

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 26 of 55

Page 30: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Guidelines

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 27 of 55

Role Task Detail

Emergency coordinator Clear people away from the Refer to the initial response scene, assess scene for danger (R.E.A.C.T.) flowchart for further before giving emergency information. assistance if safe to do so.

Contact the relevant Refer to the emergency emergency services where communications flowchart for necessary. further information.

The employee assistance program Organise trauma counselling

(EAP) is provided by Converge and debriefing by professional

International and any employee or counselling services. dependant may contact an EAP

counsellor directly on 1800 337

068. Refer to the incident and emergency response procedure for further information.

Brief the crisis management Refer to the crisis management team (determined by corporate procedure for further information office) when they arrive at the regarding the crisis scene and take any actions, as management team. required.

Emergency response team Remove all personnel from the Refer to the emergency site including subcontractors. evacuation flowchart for further

information.

Do not make any statements to Refer to the emergency the press (refer to dealing with communications flowchart for the media). further information.

Page 31: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B05 - Incident and emergency response flowchart – asbestos

This flowchart must be followed if you come across a substance that you suspect or is known to contain asbestos.

What to look out for: Asbestos was used in a wide range of building products and materials up until the mid-1980s. Products that may contain asbestos include pipe lagging, boiler insulation, fire retardant material on steel work, sprayed insulation, asbestos cement sheet, asbestos cement moulded products (e.g. water pipes and telephone pit lining), and bitumen-based water proofing and vinyl floor tiles. See: http://www.deir.qld.gov.au/asbestos/general/where-found/photogallery.htm for photos of typical items containing asbestos.

Workers Emergency coordinator Emergency response team

Stop works.DO NOT handle the substance Set up a no-go zone around

the substance

If safe to do so make the asbestos safe in-situ.

e.g. wet down and/or cover exposed asbestos

DO NOT allow workers or the public to be exposed to any fibers.

Contact an occupational hygienist to identity the substance

Is it known that the material is asbestos?

Contact an asbestos removalist to dispose of the asbestos in

accordance with state asbestos removal and disposal licensing

requirements.

Yes

Advise the all clear.

No

Is the site clear of asbestos?

Yes

No

Respond Examine Assess Control Talk TM

Alert others in the area regarding the suspected presence of

asbestos

Notify the Emergency Coordinator regarding the suspected find and

any potential exposure to the material.

Review the asbestos removalist’s Asbestos Removal Plan using the Asbestos Removal Plan Review

Checklist before they commence works.

In the event of suspected exposure contact the Safety Operative to coordinate necessary medical

checks and an Industrial Hygienist to confirm material is asbestos..

Asbestos Confirmed?

Yes

No

Assume that the material is asbestos?

No

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 28 of 55

Page 32: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B06 - Incident and emergency response flowchart - bomb threat or other serious threat

Emergency response teamEmergency coordinatorWorker

Keep the caller talking and note any details from the table below.

Try asking questions:· When will the bomb explode?· Where is it right now?· What does it look like?· What kind of bomb is it?· What will cause it to explode?· Did you place the bomb?· Why?· What is your address?· Where are you now?· What is your name?

Do NOT:· Aggravate the caller· Hang up, even after the call has

hung up· Make any statements to the

media· Disturb the area after the

incident

DO NOT touch the bomb

Notify emergency services on “000”

Evacuate the site and activate Major Fire Flowchart

Position a person in a safety vest at the site entrance to direct the

emergency services

Prevent others from entering the area.

Voice Speech Telephone Background Noises Man Well-spoken Accent Deep Local Music Machines

Woman Foul Stutter Raspy STD (beeps) Voices PA System

Child Incoherent Slurred Lisp Public phone Long distance Traffic

Youth Irrational Nasal Familiar Mobile Aircraft Motor

Taped Deep Drunk Loud/Soft Unknown Animals Street

Respond Examine Assess Control Talk TM

Has the bomb been located?

Yes

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 29 of 55

Page 33: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B07 - Incident and emergency response flowchart - breach of aviation airspace obstacle limitation surface (OLS) Title

Emergency response teamEmergency coordinatorWorker

Ph

ase

Respond Examine Assess Control Talk TM

Contact Supervisor of work area and instruct that obstacle in the

OLS must be lowered or if a lighting plant shielded

immediately

Contact NOTAM (Notice to Airmen) and notify them of

breach of OLS

Instruct all works in in all OLS areas to cease until cleared by

NOTAM that work can commence

Lower obstacles or shield lighting plants as directed by supervisor

Cease all work until instructed by Supervisor that work can

commence

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 30 of 55

Page 34: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B08 - Incident and emergency response flowchart - plane or object landing in work area Title

Emergency response teamEmergency coordinatorWorker

Phas

e

Respond Examine Assess Control Talk TM

Ensure work area is evacuated

Implement traffic managementif traffic is a hazard.

Determine if/how many person s are injured if any and render

assistance where possible and/or aid emergency services

Look out for leaking / spilling fuel or other flammable substances.

Determine whether to enact the Chemical, oil and fuel spill

flowchart if safe to do so and/or requested by the local authorities

.

Contact emergency services on 000 , if necessary.

Do not disturb the incident Scene. Secure site until after the Site has

been handed back to project by local authorities.

Escort local authorities/emergency services onto site

Assist local authorities/emergency services as requested/instructed

Immediately evacuate work area

All workers to vacate work area and assemble at muster points as

instructed by Emergency Coordinator/Supervisor

Initiate Crisis Management as required

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 31 of 55

Page 35: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B09 - Incident and emergency response flowchart - bushfire

Emergency response teamEmergency coordinatorWorker

Respond Examine Assess Control Talk TM

Is the bushfire happening now?

Is it a severe, extreme or

catastrophic fire?

Activate the site’s bushfire plan located …………………. (insert)

Consult with the workplace manager to see if work will commence tomorrow in accordance to the

site’s bushfire plan

Inform all employees, potential visitors and the Client aware of the chosen Bushfire Plan:

PREPARE, ACT SURVIVE

Clear away flammable materials today so as to minimise risk should a bushfire occur tomorrow

Remove all valuable equipment and items from the site or high risk areas

Evacuate with haste to the pre-decided safety zone if it is too late to leave.

This site’s Safety Zone is:……………………………………………………. (insert)

Commence Fire Risk Management as per Bushfire Plan

No

No

Yes

Yes

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 32 of 55

Page 36: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B10 - Incident and emergency response flowchart - chemical - oil and fuel spills

Emergency coordinator Emergency Response TeamWorker

Respond Examine Assess Control Talk TM

Are you familiar with the requirements for working with the spilt chemical safely and

correctly?

Make area safe, evacuate and apply First Aid if

necessary

Isolate source of spill (e.g. shut valve, crimp hose, stand up

container)

Yes

Is the spill a small volume and/or does not pose a

risk of harm to people or the environment?

Notify your Emergency

Coordinator for assistance

NoYes

Contact 000, Safety and Environment Managers

for support and notifications as necessary

Source and put on PPE.

Source spill response equipment

Contain, then clean-up the spill:· Booms, or compacted soil can

be used to contain flow and to prevent material from entering drainage inlets or waterways

· Pads and absorbent granules can be used to soak up the spill

Dispose of spill residues, contaminated soils and clean-up materials as per approved Waste Management Plan. DO NOT DISPOSE OF IN ANY ON-SITE BINS UNLESS THEY ARE DESIGNATED FOR CONTAMINATED/SPILL MATERIALS.

Contact your Environment Team for contamination assessment and disposal options.

No

Source SDS to identify correct safety and clean-up

requirements.

Isolate source of spill (e.g. shut valve, crimp hose) and protect/isolate downstream drainage

pits/channels if safe and possible.

Can the clean-up be conducted without posing a risk to our people or the

public?

Do we have adequate resources?

Clean-up by Fulton Hogan

Provide assistance to the emergency services if

needed and follow their directions

Contain, then clean-up the spill:· Prevent spilt material from entering sensitive areas such as

drainage inlets, waterways or vegetation.· Contain the spill by creating earthen bunds or using booms.

Floating hydrophobic booms can be used if the spill is on water and floats (i.e. is not emulsion or mixes into the water).

· Consider reuse of ponded spilt product.· Source absorbent material – Spills kit or trailer. Sand or dust

is a suitable alternative for larger spills. Use sparingly. · If any material enters the drainage system, use a vacuum

truck to suck up the spill. This can also be used for ponded spilt material.

Source and put on PPE

Yes

Yes

No

No

Clean-up by emergency services

Report ALL spills to your Supervisor and Environmental Manager

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 33 of 55

Page 37: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B11 - Incident and emergency response flowchart - emergency situation at height

Emergency response teamEmergency coordinatorWorker

Pha

se

Respond Examine Assess Control Talk TM

Check for danger to you or the

injured person

Stay with injured person if

possible, and apply

required First Aid

Do not move the injured

person if possibleCall emergency services on 000

Advise the ERT and enlist help

Ensure the area is made safe

(block off or barricade if

necessary)

Do not move equipment unless it

poses a risk to the injured person

or others in the area. Wait for

emergency services

Position a person at the

site entrance to direct the

ambulance when it arrives

Report the injury to the ECConfirm if it is a minor

or serious injuryApply basic first aid

Serious

Minor

Provide emergency services with

relevant information, required

rescue from height and confirm

destination hospital

Notify the injured person’s

immediate employer

Wait until Emergency

services arrive for rescue

at Height with applicable

equipment, unless trained

emergency personnel on

site

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 34 of 55

Page 38: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Guidelines

Role Task Detail

Emergency coordinator

Confirm if it is a minor or serious injury.

A minor injury is classified as an injury that can be treated by first aid. A serious injury is classified as an injury that required treatment by medical professionals.

Check for danger to you or the injured person.

If danger is present, do not put yourself at risk under any circumstances. If it is safe to prevent danger to injured person, do so.

Call emergency services on 000.

Refer to emergency communications flowchart for further information.

Provide emergency The EC shall ensure ambulance officers provide advice

services with on the hospital to which the ambulance is taking each

relevant information casualty and that the destination hospital is informed of the pending arrival of casualties. If necessary, the EC

and confirm shall alert the destination hospital of any source of destination hospital. contamination or any events that may become known as

a result of investigation. The EC shall ensure that emergency services are aware that the emergency will require rescue from heights and provide relevant facts.

Notify the injured person’s immediate employer.

The emergency coordinator shall notify the injured person’s immediate employer, who shall ensure next of kin are notified.

Emergency Position a person in A member of the emergency response team shall meet response a safety vest at the emergency services at an agreed location and provide all team site entrance to

direct the ambulance when it arrives.

necessary direction or advice to ensure emergency services are aware of the nature of the emergency and the necessary information to proceed to the affected area, so that the injured person can be rescued from height and provided with appropriate emergency treatment.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 35 of 55

Page 39: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 36 of 55

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B12 - Incident and emergency response flowchart - fall arrest Title

Emergency coordinator Emergency response teamWorker

Ph

ase

Check for further danger to yourself, suspended person

or others.

Communicate with the suspended person, to determine if they are

conscious and/or injured.

Call “000”, if necessary.

Secure the area and alert the workplace manager and first

aider.

If It is possible and no further danger can occur, attempt to (i)

lift the fallen Person to safety, (ii) lower the person to safety, (iii)

retrieve the person using a EWP or similar

Encourage suspended person to use stirrups to stand up in, or

instruct them to move about, re-positioning the body to avoid

suspension trauma.

Position a person at workplace site entrance to direct emergency

services to area of incident.

Follow instructions of the emergency services.

Take the person to the doctor for examination immediately after

being rescued if emergency services are not called.

Respond Examine Assess Control Talk TM

Page 40: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B13 - Incident and emergency response flowchart - major fires or explosions

Emergency response teamEmergency coordinatorWorker

Respond Examine Assess Control Talk TM

Close the door if you are in a building

Keep exit clear and stay low to avoid smoke inhalation

Activate the Emergency Evacuation Flowchart

Call “000” for emergency services if necessary.

Do not go back to site until told so by the Emergency

Coordinator

Give the Emergency Services team the SDS manifest

Position a person in a safety vest at the site

entrance to direct emergency services

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 37 of 55

Page 41: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B14 - Incident and emergency response flowchart - robbery or hostile intruder

Worker Emergency response teamEmergency coordinator

Notify Police and Ambulance, if required on 000.

Complete a description of he intruder as soon as they leave

including where they went, their escape route and vehicle.

Position a person in a safety vest at the site entrance to

direct the emergency services.

Use the table below to build a description of the intruder.

Do not put yourself at risk.

Respond Examine Assess Control Talk TM

· Remain calm· Do exactly as told· Try to picture a description

of the intruder and their vehicle, if applicable.

Do not touch anything immediately after the event

Do not make ant statements to the media.

Do not confront or engage the intruder

Height Build Hair Eyes Gender Age Vehicle Short Light Brown Blue Male Child Registration

Medium Medium Blonde Brown Female Youth Colour

Tall Heavy Black Green Adult Type

Grey Hazel Make

Balding Model

Other

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 38 of 55

Page 42: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B15 - Incident and emergency response flowchart - serious injury Title

Emergency response teamEmergency coordinatorWorker

Ph

ase

Respond Examine Assess Control Talk TM

Check for danger to you or the

injured person

Stay with injured person if

possible

Do not move the injured

person if possibleCall emergency services on 000

Advise the ERT and enlist help

Ensure the area is made safe

(block off or barricade if

necessary)

Do not move equipment unless it

poses a risk to the injured person

or others in the area. Wait for

emergency services

Position a person in a

safety vest at the site

entrance to direct the

ambulance when it arrives

Report the injury to the ECConfirm if it is a minor

or serious injuryApply basic first aid

Serious

Minor

Provide emergency services with

relevant information and confirm

destination hospital

Notify the injured person’s

immediate employer

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 39 of 55

Page 43: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Guidelines

Role Task Detail

Emergency coordinator

Confirm if it is a minor or serious injury.

A minor injury is classified as an injury that can be treated by first aid. A serious injury is classified as an injury that required treatment by medical professionals.

Check for danger to you or the injured person.

If danger is present, do not put yourself at risk under any circumstances. If it is safe to prevent danger to injured person, do so.

Call emergency services on 000.

Refer to emergency communications flowchart for further information.

Provide emergency The EC shall ensure ambulance officers provide advice

services with on the hospital to which the ambulance is taking each

relevant information casualty and that the destination hospital is informed of the pending arrival of casualties. If necessary, the EC

and confirm shall alert the destination hospital of any source of destination hospital. contamination or any events that may become known as

a result of investigation.

Notify the injured person’s immediate employer.

The emergency coordinator shall notify the injured person’s immediate employer, who shall ensure next of kin are notified.

Emergency Position a person in A member of the emergency response team shall meet response a safety vest at the emergency services at an agreed location and provide all team site entrance to

direct the ambulance when it arrives.

necessary direction or advice to ensure emergency services are aware of the nature of the emergency and the necessary information to proceed to the affected area.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 40 of 55

Page 44: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B16 - Incident and emergency response flowchart - service strikes – electricity cables

Do not handle / touch the exposed area

Evacuate the work area immediately

Notify the Manager and call “000” for Emergency Services if necessary

Administer First Aid if necessary

If you make contact or damage a service, STOP WORK IMMEDIATELY

The Manager will notify the relevant authorities including the service

distribution company

No work shall recommence until:· the service has been secured· the area has been made safe· a new excavation permit has been issued· authorisation is given to recommence work

General ResponseService Specific

Response

If applicable, operator (or driver) should remain inside the cabin

If it is essential to leave the cab or operator station due to fire or other life threatening reasons, jump clear of the

equipment

Do not touch the equipment and the ground at the same time

When moving away from the equipment, the operator should hop slowly, shuffle or

jump away from the plant (with feet together) until 10m away

Warn all other personnel / public to keep 10m clear of equipment

Warn all other personnel / public to keep 10m clear of equipment

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 41 of 55

Page 45: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B17 - Incident and emergency response flowchart - service strikes and leaks - gas Title

Emergency response teamEmergency coordinatorWorker

Phas

e

Respond Examine Assess Control Talk TM

Do not handle / touch the exposed area.

Evacuate the work area immediately.

Call “000” for Emergency Services if necessary.

Administer first aid if necessary.

Call the service distribution company.

Do NOT recommence work until:· the service has been secured· the area has been made safe· a new excavation permit has

been issued· authorisation is given to

recommence work.

Shut the emergency stop valves on the gas tank or

mains.

Activate the Emergency Evacuation Flowchart.

Shut down the plant or equipment UNLESS this process may provide an ignition source for any

escaping gas.

Do not allow any smoking, naked lights, possible

ignition sources anywhere near the area.

Stop work immediately.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 42 of 55

Page 46: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B18 - Incident and emergency response flowchart – service strikes and leaks - water or sewerage pipes

Emergency response teamEmergency coordinatorWorker

Respond Examine Assess Control Talk TM

Do not handle / touch the exposed area Evacuate the work area immediately

Call “000” for emergency services if necessary

Administer first aid if necessary

Call the service distribution company.

Do NOT recommence work until:· the service has been secured· the area has been made safe· a new excavation permit has been

issued· authorisation is given to

recommence work

Contain the spill (e.g. sewerage, muddy water) if possible and where

safe to do so

Contact the regional environmental manager if spill flows into a waterway,

drain or sensitive area.Attempt to stop or slow the flow.

Stop work immediately

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 43 of 55

Page 47: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B19 - Incident and emergency response flowchart - storms and flooding – process

Emergency response teamEmergency coordinatorWorker

Respond Examine Assess Control Talk TM

Avoid driving, but if required, drive slowly and carefully with headlights on

Stay away from powerlines, trees and waterways during and after the storm

If l ightning is present, and you are caught in it outdoors;· Crouch down into a ball with both

feet on the ground· Alternately wait in rubber tyred

vehicle (don’t enter or exit the vehicle during the lightning)

· Avoid touching any water or metal objects

If f looding is present: · Do not enter floodwater with or

without a vehicle.· Stay away from waterways such as

streams and rivers. Avoid crossing bridges if water level is already high

If safe to do so, prior to anticipated flooding:· Move equipment, supplies and

waste to higher ground and secure those that may float and cause damage.

· Anchor any fuel tanks and turn off water, electricity and gas mains as required

If necessary, call emergency services for help

Determine safe locations for evacuation from flooding

Give the all clear to resume work

Before the storm hits:· Inspect and maintain erosion and

sediment controls, waste and chemical storage areas

· Ensure site drainage is established, clear and where relevant directed to water treatment controls

· Isolate plant, stow or tie down loose items

Evacuate to higher ground prior to flooding

Clean up

BoM upgrade from Flood Watch to Severe

Weather Warning

Yes

No

Assign emergency response team rolesFollow the directions of the Emergency

Coordinator

After danger has passed, determine if it is safe to commence clean up operations

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 44 of 55

Page 48: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B20 - Incident and emergency response flowchart - trench collapse

Emergency response teamEmergency coordinatorWorker

Respond Examine Assess Control Talk TM

Contact “000” and emergency rescue services

(e.g. SES), if required.

PartiallyEstimate the person’s last known position.

Remove person from the trench and provide first

aid until emergency services

arrive.

Do not disturb area of incident and isolate area to avoid further

incidents.

No

Yes

Determine if the person is partially or

fully engulfed.Fully

Determine if it is safe to enter the

trench.

Determine if the person can be

reached by hand digging?

No

Can the person exit the trench without

assistance?

No

Dig the person out.

Wait for emergency

services and assist as able to.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 45 of 55

Page 49: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

B21 - Incident and emergency response flowchart - vehicle accidents and plant rollovers

Emergency response teamEmergency coordinatorWorker

Respond Examine Assess Control Talk TM

Ensure vehicle is stable before assisting person.

Implement traffic managementif traffic is a hazard.

Determine if the person is injured and whether to follow the Serious

injury flowchart.

Look out for leaking / spilling fuel or other flammable substances.

Be ready with appropriate fire extinguisher in case of fire.

Determine whether to enact the Chemical, oil and fuel spill flowchart if safe to do so.

Contact emergency services on “000”, if necessary.

Do not disturb the vehicle / plant if the incident is identified as

notifiable. Secure site until after the investigation.

Turn off engine if safe to do so.

Avoid using anything that could cause ignition of fuel or fumes

(e.g. cigarettes)

Evacuate the scene

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 46 of 55

Page 50: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Appendix C – Site layout plans

Project office located at Corner of Illawarra Highway and Princes Highway, Albion Park.

Note: A detailed site layout plan including the location of first aid equipment, waste/recycle bins, movement plans and muster points will be updated once the overall layout is finalised.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 47 of 55

Page 51: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Appendix D – PIRMP legislative compliance matrix

The specific legislative requirements for a PIRMP are set out in Part 5.7A of the POEO Act and Part 3A of the POEO(G) Regulation. These requirements and a cross reference are included in the table below to ‘readily identify’ where each requirement is met in this IERP, or otherwise.

Section/ Clause No.

PIRMP legislative requirement IERP reference/ comment

POEO Act – Part 5.7A

Section 153A The holder of an environment protection licence must prepare a pollution incident response management plan.

The requirements of the PIRMP are satisfied by way of this IERP, as ‘readily identifiable’ in this table.

Section 153B The EPA may direct other persons at which industry is carried out to prepare a PIRMP.

Not applicable.

Section 153C A pollution incident response management plan must include the following:

(a) the procedures to be followed in notifying a pollution incident to:

(i) the owners or occupiers of premises in the vicinity of the premises, and

Section 4.7 Communicating with neighbours and local community

(ii) the local authority, and Section 4.3 Pollution incident notification protocol, and

Appendix F Pollution (or other Environmental) Incident Notification Protocol

(iii) any persons or authorities required to be notified by Part 5.7 of the POEO Act,

Section 4.3 Pollution incident notification protocol, and

Appendix F Pollution (or other Environmental) Incident Notification Protocol

(b) a detailed description of the action to be taken, immediately after a pollution incident, to reduce or control any pollution,

Section 3.1 Incident and emergency response flowcharts

Appendix B Incident and emergency response flowcharts e.g. Chemical, Oil and Fuel Spills – Major and Minor.

(c) the procedures to be followed for co-ordinating, with the authorities or persons that have been notified, any action taken in combating the pollution caused by the incident and, in particular, the persons through whom all communications are to be made,

Appendix A Incident and emergency response contacts

Section 3.1 Incident and Emergency Response Flowcharts

Appendix B Incident and emergency response flowcharts e.g. Chemical, Oil and Fuel Spills – Major and Minor.

Section 4.3 Pollution incident notification protocol, and

Appendix F Pollution (or other Environmental) Incident Notification Protocol

(d) any other matter required by the regulations.

Refer to POEO(G) Regulation Clause 98C below.

Section 153D The PIRMP must be kept at the premises to which it relates.

Document Control (page 2).

Section 153E The PIRMP must be tested in accordance with the regulations.

Refer to POEO(G) Regulation Clause 98E below.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 48 of 55

Page 52: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Section 153F If a pollution incident occurs in the course of an activity so that material harm to the environment is caused or threatened, licensees must immediately implement the PIRMP.

Section 4.3 Pollution incident notification protocol, and

Appendix F Pollution (or other Environmental) Incident Notification Protocol

POEO(G) Regulation – Part 3A

Clause 98A In this Part: plan means a pollution incident response management plan required to be prepared under Part 5.7A of the Act.

Noted.

Clause 98B (1) A plan is to be in written form. The requirements of the PIRMP are satisfied by way of this IERP.

(2) A plan may form part of another document that is required to be prepared under or in accordance with any other law so long as the information required to be included in the plan is readily identifiable as such in that other document.

The requirements of the PIRMP are satisfied by way of this IERP.

Clause 98C The matters required under section 153C (d) of the Act to be included in a plan are as follows:

(a) a description of the hazards to human health or the environment associated with the activity to which the licence relates (the relevant activity),

Section 4.2 Description and likelihood of hazards, and

Appendix E Environmental Incidents and Emergencies Risk Assessment

(b) the likelihood of any such hazards occurring, including details of any conditions or events that could, or would, increase that likelihood,

Section 4.2 Description and likelihood of hazards, and

Appendix E Environmental Incidents and Emergencies Risk Assessment

(c) details of the pre-emptive action to be taken to minimise or prevent any risk of harm to human health or the environment arising out of the relevant activity,

Section 4.4 Pre-emptive Actions

(d) an inventory of potential pollutants on the premises or used in carrying out the relevant activity,

Section 4.6 Inventory of Pollutants

(e) the maximum quantity of any pollutant that is likely to be stored or held at particular locations (including underground tanks) at or on the premises to which the licence relates,

Section 4.6 Inventory of Pollutants

(f) a description of the safety equipment or other devices that are used to minimise the risks to human health or the environment and to contain or control a pollution incident,

Section 3.4 Emergency Equipment

(g) the names, positions and 24-hour contact details of those key individuals who:

(i) are responsible for activating the plan, and

Section 4.5 Contact Details, and

Appendix A Incident and emergency response contacts

(ii) are authorised to notify relevant authorities under section 148 of the Act,

Section 4.5 Contact Details, and

Appendix A Incident and emergency response

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 49 of 55

Page 53: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

and contacts

(iii) are responsible for managing the response to a pollution incident,

Section 4.5 Contact Details, and

Appendix A Incident and emergency response contacts

(h) the contact details of each relevant authority referred to in section 148 of the Act,

Section 4.5 Contact Details, and

Appendix A Incident and emergency response contacts

(i) details of the mechanisms for providing early warnings and regular updates to the owners and occupiers of premises in the vicinity of the premises to which the licence relates or where the scheduled activity is carried on,

Section 4.7 Communicating with neighbours and local community

(j) the arrangements for minimising the risk of harm to any persons who are on the premises or who are present where the scheduled activity is being carried on,

Section 4.8 Minimising Harm to Persons on Premises

(k) a detailed map (or set of maps) showing the location of the premises to which the licence relates, the surrounding area that is likely to be affected by a pollution incident, the location of potential pollutants on the premises and the location of any stormwater drains on the premises,

Section 4.9 Maps

(l) a detailed description of how any Section 4.4 Pre-emptive Actions identified risk of harm to human health will Section 4.7 Communicating with neighbours be reduced, including (as a minimum) by and local community Section Section 3.1 means of early warnings, updates and the Incident and Emergency Response Flowcharts, action to be taken during or immediately and after a pollution incident to reduce that risk, Appendix B Incident and Emergency Response

Flowcharts e.g. Chemical, Oil and Fuel Spills – Major and Minor

Section 4.3 Pollution Incident Notification Protocol, and

Appendix F Pollution (or other Environmental) Incident Notification Protocol

(m) the nature and objectives of any staff training program in relation to the plan,

Section 3.5 Testing - Desktop Simulations, Exercises/ Drills

Section 5 - Training

(n) the dates on which the plan has been tested and the name of the person who carried out the test,

Section 3.5 Testing - Desktop Simulations, Exercises/ Drills

(o) the dates on which the plan is updated, Revision History (page 2)

(p) the manner in which the plan is to be tested and maintained.

Section 3.5 Testing - Desktop Simulations, Exercises/ Drills

Section 7 Revision

Clause 98D (1) A PIRMP is to be made readily available:

(a) to an authorised officer on request, and

(b) at the premises to which the relevant licence relates, or where the relevant activity takes place, to any person who is

Document Control (page 2)

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 50 of 55

Page 54: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

responsible for implementing the plan.

(2) A plan is also to be made publicly available in the following manner within 14 days after it is prepared:

(a) in a prominent position on a publicly accessible website of the person who is required to prepare the plan,

Document Control (page 2).

(3) Subclause (2) applies only in relation to that part of a plan that includes the information required under:

(a) section 153C (a) of the Act, and

(b) clause 98C (1) (h) and (i) or (2) (b) and (c) (as the case requires).

Document Control (page 2).

(4) Any personal information within the meaning of the Privacy and Personal Information Protection Act 1998 is not required to be included in a plan that is made available to any person other than a person referred to in subclause (1).

Document Control (page 2).

Clause 98E (1) The testing of a PIRMP is to be carried out in such a manner as to ensure that the information included in the plan is accurate and up to date and the plan is capable of being implemented in a workable and effective manner.

(2) Any such test is to be carried out:

(a) routinely at least once every 12 months, and

(b) within 1 month of any pollution incident occurring in the course of an activity to which the licence relates so as to assess, in the light of that incident, whether the information included in the plan is accurate and up to date and the plan is still capable of being implemented in a workable and effective manner.

Section 3.5 Testing - Desktop Simulations, Exercises/ Drills

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 51 of 55

Page 55: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Appendix E – Environmental incidents and emergencies risk assessment

Risk assessment methodology

The following HSQE operational risk matrix was used to evaluate the risk level associated with each of the hazards listed above.

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 52 of 55

Page 56: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Main Hazards to human health or the environment Description of potential impact

Pre-control risk rating

Post-control risk rating

Severe weather events e.g. flooding, thunderstorm, dust storm.

Fallen trees, rock fall, landslides, damage to ERSED controls resulting in stormwater pollution, flooding, closure of motorway, damage to plant / equipment

High 21 High 17

Illegal waste dumping (by others) Land pollution and stormwater pollution, potential for health and visual impact High 18 Med 13

Spontaneous combustion of mulch stockpile

Bushfire, fire, smoke resulting in reduced visibility and/or closure of and/or long delays on the motorway

Med 13 Med 8

Fire/ bushfire/ grassfire Damage to property and stock, smoke resulting in reduced visibility and/or closure of the motorway.

High 18 Med 13

Vehicle collision Fuel spill, fire, explosion, closure of and/or long delays on the motorway High 24 High 18

Chemical or fuel spill in a waterway (onsite & offsite impact)

Pollution of waters, adverse impact on aquatic ecosystems, fish kills High 18 Low 5

Primer/ primer binder washed off pavement

Water pollution and potential for adverse impact on aquatic ecosystems, fish kills, land pollution.

High 18 Low 2

Discovery of friable asbestos on site Inhalation health hazard High 18 Low 5

Unauthorised washout of concrete trucks and pumps

Water pollution adverse impact on aquatic ecosystems High 17 Low 5

Chemical spill on land (onsite impact) Land pollution, contamination of groundwater, stormwater pollution High 16 Low 5

Incompatible storage of chemicals Fire, explosion, chemical spill, land and water pollution, odour, fumes. High 18 Low 2

Importation of contaminated materials by trucks and other plant

Land pollution, stormwater and groundwater contamination Med 14 Low 5

Unauthorised discharge of sediment laden water from site

Reduced water quality in local waterways, adverse impact on aquatic ecosystems.

Med 13 Low 5

Failure of erosion and sediment controls Reduced water quality in local waterways, adverse impact on aquatic ecosystems.

Med 13 Low 5

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 53 of 55

Page 57: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Main Hazards to human health or the environment Description of potential impact

Pre-control risk rating

Post-control risk rating

Tannin leachate runoff Pollution of surface water by tannins, loss of amenity. Med 13 Low 2

Excavation/works outside of the approved project boundary

Loss of habitat, damage to EECs or loss of threatened species, adverse impact on aquatic ecosystems.

Med 13 Low 5

Blow out of concrete pump hose causing concrete spill

Water pollution and potential for adverse impact on aquatic ecosystems Med 13 Low 2

Clearing outside approved clearing limits

Damage to habitat, loss of threatened or endangered species Med 13 Low 5

Unexpected contaminated land find Land pollution. contamination of groundwater stormwater pollution Med 9 Low 5

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 54 of 55

Page 58: Incident and Emergency Response Plan · PIRMP Pollution Incident Response Management Plan PMP Project Management Plan POEO Act Protection of the Environment Operations Act 1997 POEO(G)

Incident and Emergency Response Plan

Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)

Appendix F – Pollution (or other environmental) incident notification protocol

POLLUTION (OR OTHER ENVIRONMENTAL) INCIDENT OCCURS

Supervisor in Charge/Fulton Hogan staff/Subcontractor

calls Environmental Manager

immediately

0400 459 769

If not available call NSW Environmental Manager

0488 264 613

Environmental Manager, in consultation with NSW Environmental Manager, determines if the incident

poses a risk of material harm to the environment

Is there a risk of material harm to the environment ?

No

Yes

Environmental Manager notifies

InternallyAs soon as possible

but no later than 24 hours

ExternallyImmediately

General Manager Eastern Region

Authorities in order of priority:

EPA: 131 555

Central Coast Public Health Unit: (02) 4320 9730

SafeWork NSW: 131 050

Wollongong City Council: (02) 4227 7111

Shellharbour City Council: (02) 4221 6247/0419835683

or 0406 383 047

Fire and Rescue NSW: 1300 729 579

Note 1: if 000 was called first, you do not need to ring Fire and Rescue NSW again.

Note 2: evidence of notifications, i.e. reference numbers, must be obtained from all agencies listed above.

National Environment and Quality Manager

Implement corrective actions and record the incident in

Roads and Maritime Environmental Incident Report

Form and CAMs

Department of Planning and Environment Roads and Maritime Environmental Representative Project Verifier

Immediately means promptly and without

delay

Call 000 if the incident presents an immediate threat to human health or

property and follow FH emergency response procedures

Important:If a pollution incident occurs, all necessary actions should be taken to minimise the extent and any adverse effects of the release. These actions must be implemented as soon as it is safe to do so. If the incident presents an immediate threat to human health or property, Fire and Rescue NSW, the NSW Police and the NSW Ambulance Service must be contacted first by calling 000. Other agencies must still be contacted after that to satisfy POEO Act notification obligations.

Material harm means:· There is actual or potential harm

to health or safety of human beings or to ecosystems that is not trivial, or

· Actual or potential loss or property damage exceeds $10,000.

Project Director

Environmental Manager notifies: Department of Planning and

Environment Roads and Maritime Environmental Representative Project Verifier Any other relevant agencies

Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 55 of 55