Ina Road Traffic Interchange Project...
Transcript of Ina Road Traffic Interchange Project...
1 1
Ina Road Traffic Interchange
Project Update
Town of Marana Mayor and Council Mee<ng
May 12, 2015
Greg Byres, PE; Paki Rico
Arizona Department of Transporta=on
Kevin Thornton, PE
Project Manager, Psomas
Laura Mielcarek, PLA
Principal, Wheat Design Group
2
! Project overview
! Project improvements
! Project schedule
Presenta<on Topics
3
Project Area
4 4
Mee<ngs held during project design phase:
! Agency scoping mee=ng – Oct. 28, 2009
! Public scoping mee=ng – Nov. 18, 2009
! Property owner mee=ngs – Oct. 4, 2010, Nov. 8, 2010
! Public informa=on mee=ng – March 10, 2011
! Property owner mee=ngs – Nov. 30, 2011
! Public hearing – June 21, 2012
! Business forums – May 14, 2014
! Marana Council Update – May 12, 2015
! Public Mee=ng – June 11, 2015
Public Outreach Mee<ngs
5 5
Business Outreach
! Business outreach – ongoing
• RTA MainStreet Business Assistance Program
• Marana Chamber of Commerce
• Town of Marana
! Resources
• ADOT Senior Community Rela=ons Officer: Paki Rico,
520.388.4233, [email protected]
• ADOT Project Info: 855.712.8530, [email protected]
• Project website: azdot.gov/InaTI
6 6
! Improve traffic capacity
! Improve access
! Enhance safety
Project Purpose and Need
7 7
Project Improvements
Project Improvements include:
! Ina Road overpass over I‐10 and the UPRR
! Ina Road widened to two lanes in each direc=on
! New bridge over the Santa Cruz River
! Pedestrian underpasses at the Santa Cruz River Bridge
! Architectural treatments/landscape
8 8
Project Improvements (cont’d)
9 9
Project Improvements (cont’d)
10 10
Project Improvements (cont’d)
11 11
Construc<on Timeline
! Construc=on Manager at Risk selected Sep. 2014
! Construc=on will be divided into 4 major phases:
1. Prepara=on work (Ina Road open)
2. EB I‐10 Construc=on (Ina Road closed)
3. WB I‐10 Construc=on (Ina Road closed)
4. Finishing work (Ina Road open)
! Construc=on scheduled to begin spring 2016
! The construc=on project is an=cipated to be
completed in 2018
Project Schedule
12 12
Project Schedule (cont’d)
! Ina Road
• Access across I‐10 will be closed for majority of project
dura=on
! Interstate 10
• Contractor will maintain 3 lanes in each direc=on
along I‐10
! Access to businesses will be maintained during
construc=on
13
! Paki Rico, ADOT Senior Community Rela<ons Officer, 520‐388‐4233, [email protected]
! ADOT Project Hotline, 855.712.8530, [email protected]
! Visit the project website: azdot.gov/InaTI
Thank you for your par<cipa<on!
Contact Informa<on
14
QUESTIONS?