Improving Water & Sanitation Services: The ADB GOI PPP ... · Case Study: Kolhapur Initiative’s...
Transcript of Improving Water & Sanitation Services: The ADB GOI PPP ... · Case Study: Kolhapur Initiative’s...
Improving Water & Sanitation Services:
The ADB – GOI PPP Initiative
1
Anouj Mehta
Head PPPs and Finance Unit (India), ADB
Status & Needs Huge Urbanisation Pressures
286 million urban population
35 Cities (1 million plus population) in 2001 to
50 cities in 2011
Estimated to grow to 38% or 600 million 2031
43 million - 640 cities – slum populations
Cities needed as engines of growth
Huge Rural Pressures also
Over 70% of India in rural areas
Growing pressures – industrialisation,
water usage
2
Pressures on Water & Sanitation Systems
QUALITY OF
WATER ISSUES
INCREASING
RELIANCE ON
GROUND
WATER
SEWERAGE
CONNECTIONS
VARY 45%-
70%
LESS THAN
20%
WASTEWATER
TREATED
NO CITY 100%
SEWERAGE
CONNECTIONS
2.9 HRS WATER
SUPPLY PER
DAY AVERAGE
40-60% NON
REVENUE
WATER LEVELS
Current Service Delivery levels
3
Parameter Description
Coverage 64% of urban population is covered by individual connections and standposts
China – 91%, South Africa – 86% and Brazil – 80%
Duration Ranges from 1 hour to 6 hours
Brazil and China – 24 hours and Vietnam – 22 hours
Per capita supply Ranges from 37 lpcd to 298 lpcd for a limited duration
Paris - 150 lpcd continuously and Mexico 171 lpcd for 21 hours a day
Metering Most cities do not have metering for residential water connections
Non-revenue water Accounts for 50% of water production, compared with 5% in Singapore
Transmission losses Leakage during transmission substantial as most of the cities need to source
water from long distances (50 to 200 km)
Cost recovery Water utilities typically recover only 30-35% of the O&M cost.
While tariffs are low, cost of production is high considering the distance of source
of raw water.
In the Philippines and Cambodia, most water utilities recover the full O&M cost.
Even in Bangladesh, water utilities recover about 64% of their O&M cost.
Challenges Funds Requirements are HUGE
Many estimates for urban
infrastructure investments over a 20-
year period
$ 784 billion - 20 years
$ 163 billion shorter period - JNNURM
Water and Sanitation
~ USD 115 billion towards
capital investment, ~USD 160
billion towards O&M expenses
4
Critically, the efficient management of
assets is perhaps an even bigger
problem
ULB capacities
No. of officials and knowledge on
finance, institutional issues
ULB finances
Reliance on balance sheet financing
12 to 13 rated corporations only
Low focus on sustainable projects on
their own merit, accounting etc
Need for PPPs
Many models and solutions can be
prepared
Tariffs need not be an issue
Focus should be on efficiencies in
management rather than just
investment
Allows a focus on LIFECYCLE
COSTS - Operation and Maintenance
5
PPPs
6
THE GOI-ADB PPP INITIATIVE, Mainstreaming PPPs in India
An Overview
Since 2006
In partnership with DEA, MOF
The largest PPP initiative across
any region and MDB
CAPACITY
BUILDING
TOOLKITS AND
GUIDELINES
22 PPP CELLS
KNOWLEDGE
DISSEMINATION
PILOT PROJECTS INITIATIVE - CRITICAL
FOR DEMONSTRATING
- PRIVATE SECTOR PARTICIPATION
- MODELS
- CONFIDENCE
TRANSACTION
ADVISORY
PANEL
PROJECT
DEVELOPMENT
FUNDS
7
Pilot Projects being structured in
several cities
Aurangabad Water
Panjim Water
Indore Water
Bhopal Water
Kolhapur Sanitation
Rajasthan 4 Cities
Karnataka 3 Cities
Guwahati Water
Hardwar Solid Waste
A Recent Impact Story
Problem
Case Study: KMC
•Construction of 76 MLD STP to improve environment compliance •DPR Prepared •Grant obtained from National River Conservation Directorate (NRCD)- Rs. 52 Cr. (70% of estimated DPR cost)
Need
BUT •FUNDS CRUNCH – FOR CAPEX & FOR OPEX
•NEED FOR LATEST TECHNOLOGY
•NEED FOR EFFICIENT MANAGEMENT OF RESOURCES
THE GOI-ADB PPP INITIATIVE Need for a PPP Solution
• Untreated sewage dumped in river ( against the norms) •Water pollution > allowable limits: dead fish, epidemic break out etc •PCB issued a notice to KMC to control the quality of sewage
Case Study: Kolhapur
Initiative’s Assistance • PPP Approach Paper & Discussions
• Engagement of a TRANSACTION ADVISOR
•Financial Modelling •PPP Structure •Environment & Social Impacts
•Stakeholder Communications
•Bid Process Management – 2 Stage (RfQ and RfP)
Project Status
•RFQ Floated end 2009 16 bids received – 11 shortlisted
– India and overseas
•RFP Floated mid-2010 6 bids received
Winning Bidder Awarded
•Legal Documentation
PPP trends Signs of success
A few projects grounded
Around
2000
Mid
decade
Now
Way
Ahead?
Mid to
Late 90s
Momentum subsided
Onset of pessimism
Efforts to prepare PPP projects
High NGO opposition
High profile projects in Delhi,
Mumbai, Failed
Successful projects also emerge
Many ongoing initiatives
Waiting for first commercial results
PPP interest at tipping point
First initiatives
High international
interest
Poor results
Pune, Hyd, Goa,
Bangalore Bulk water
– USD 20-60 million
Failed
Sonia Vihar, Delhi,
Sangli – Bulk water
Bangalore – Rehab,
O&M
~USD 100 million
Failed
Focus Area of Ongoing PPPs…
26
17
12
3
0
5
10
15
20
25
30
PPP projects attempted Contracts awarded Under Implementation Operational
PPP Sector Snapshot
Parameters 1990s 2000-04 2005 Onward
Attempted 5 8 13
Awarded 1 3 13
Current status 1 operational 2 operational Under implementation - 12
Model Bulk supply
augmentation
•75% distribution, 25 %
bulk water & treatment
• 60% - distribution , 30% - bulk
water, 10% - combined
PPP model 100% BOT/BOOT 75% mgmt. contracts, 25%
BOT/BOOT
• 38% management contracts
• 62% BOT/DBFOT and similar
Private
Operator mix
100%
international
65% international, 35%
domestic
• 80% domestic
• 20% international
13
List of Bidders is limited ….
1. Jindal Water Infrastructure Ltd
2. Nagarjuna Construction Co.ltd
3. CASCAL-EA
4. Manila Water
5. Thames Water
6. Veolia
7. JUSCO
8. Suez Environnment
9. Ramky Infrastructure Ltd
10. Subhash Projects and Marketing Ltd.
11. Jain Irrigation
Response to Bids
14
Bids received – 5 to 6
Financial bids – 1 or 2
545
220
34
185
41
470
407
8 8 4 6 11 10 4 0
100
200
300
400
500
600
Number ofQueries Raised
Number ofBidders
Government
• Huge investments
• Profit motives of private sector overrides the social objectives
• Sense of loss of control
• Resistance to increase tariff
• Ownership of asset
• Is there a substantial change in performance?
Civic society
• Tariff implications – especially on under privileged sector?
• Water a public good – cannot be privatized
• Is demanding a “fundamental right to water”
Private Developer
• Lack of reliable baseline information
• Haste in bidding projects
• Inadequate technical studies undertaken while preparing DPRs
• Has impacted the due diligence exercise prior to bidding
• Payment guarantee
• Tariff risks
• Unrealsitic performance standards
• Political Will
Key Issues
15
Key Factors to enable investments
Strong political will
Adequate project development of PPP projects
Balanced sharing of risks
Strong public finding
Institutionalizing
Suggest appropriate regulatory and policy framework
Amend the existing rules and regulations to accommodate PPP projects
Capacity building and training of government staff to manage the contracts
Tariff Determination
Establishing a financially viable business model
Development of model contracts
PPP Desirability Assessment
What is the premise for private sector involvement?
How do we establish the value for money principles?
How do we get stakeholder buy-in and how do we sustain the same?
Establishing Greater Transparency
Open books – technical & capital investment
Information systems with central control unit?
Strengthening of Public Authority
Skills and information to enable decisions
Responsibility for renewal of networks, investments
Access to information - higher quality monitoring?
Establishing Greater Accountability
Measurable and verifiable performance standards, periodic public disclosure
Performance based payments based on improvements in efficiencies and reduction in costs
Elements of Strategy & Projects
Performance Targets- PPP Projects
18
Performance Criteria Performance Standards
Unit Target
Number of connections with 24x7 % 100
Revenue Water % 85
Collection Efficiency % 90
Resolution of Complaints % 95
Leakage levels L/c/d/m 31
Quality compliance % 100
Pressure compliance % 98
Total
Service Level Benchmarks Performance Criterion Nagpur Water Aurangabad Water KUWASIP 5 towns Latur Water Supply
Coverage and reach
24x7 water supply in 5 years, currently 2-12 hours supply per day 100% coverage in 5 years
100% coverage from 1st year post COD 24x7 water supply
24x7 water supply in 2 years
NRW targets
Technical efficiency from 66% to 75% (2014 onwards)
Maximum 25% in Year 4 and to be brought down to 15% in Year 6 from 50% currently
Loss : 20 litres/connection/day/meter
Loss: 80 litres/day/connection by year 4 from 137 litres loss currently
Metering and billing
Collection efficiency from 76% to 98% (2016 onwards)
Installing 100% meters by 3rd year
100% metering and billing 100% metering
Tariff changes To be set by NMC
Shift from flat annual rate to volumetric tariff and fix it for 20 years. Fixed by Municipality
19
User fee in Aurangabad project
Concession Period Water charges for household consumers
Year 1to3 Pipe diameter in ½ inch Rs 1800/annum
Year 4 to 6 Water consumption, KL/connection/month
Rate, Rs/KL
0-8 9.00
8-17 15.00
17-23 23.00
Above 23 30.00
20
The User Fee in the Service Area shall be fixed for the first 3 years of Concession Period and Concessionaire shall be in position to charge telescopic User Fee only after Commercial operation date Operation Date.
GOI-ADB PPP Initiative • ADB has been assisting the Government of India (GOI) in its efforts to improve the PPP
enabling environment in a programmatic manner since 2007.
• PPP projects have mostly been in roads, ports
• Direct ADB/DEA structuring for challenging sectors
Quick response modality
Complete hand holding of project sponsors from concept to bid closure
Project development expenses- ADB + IIPDF (25%/75%)
ADB Panel of ten expert transaction advisory teams in place
• Initial projects across key sectors
Water Supply & Sanitation
Primary Education
Healthcare
Urban Transport
21
22
•Massive Response For Direct Assistance
• Over 30 Projects in pipeline
• Commenced in 2008
•Tremendous Need for Developing PPP Models
•Initial aim was for only 23 Projects to be developed
Indore Water Bhopal Water Gwalior Water Aurangabad Water Panjim Water Jaipur Water Kota Water Kolhapur STP Karnataka 4 towns
Water and sanitation pilot projects
Thank You [email protected]
23