Importance of advanced simulations of electrical system in wind turbines April 2010.
-
Upload
sarah-stanley -
Category
Documents
-
view
214 -
download
0
Transcript of Importance of advanced simulations of electrical system in wind turbines April 2010.
Importance of advanced simulations of electrical system in wind turbinesApril 2010
Structure of the presentation
1. Introduction: Importance electrical transients
2. DFIG wind turbine• Mechanical operating regions• Rotor voltage limit and power factor• Rotor current variation• Effect on mechanical loading
3. Transient modeling of a fully rated converter wind turbine• LVRT• Torque control• Braking resistor• Combination of torque control and braking resistor
4. Summary
Until recently, electrical dynamics has not always been fully considered during the design of wind turbines.In order to account for the full impact of electrical dynamics, advanced computer models are being developed.
1. Importance electrical transients
Time [s]
Voltage [%]
85
90
95
100
105
110
115
Power factor [-]
Vol
tage
[%]
UnityInductive Capacitive
Grid Code requirements
LVRT requirement
Voltage/PF requirement
When designing a wind turbine all four systems have to be considered together
Aero dynamics
Structural
Controller
Electrical
B2
B1
B3
Electrical dynamics is part of a wind turbine
Grid code requirements are increasingly important and wind turbine needs to comply with these requirements.
Electrical dynamics is part of a wind turbine and there are interactions between the electrical and mechanical dynamics.
2. DFIG wind turbine
DFIG
Torque control
Voltage or PF control
Pitch controller
Wound rotor induction generator
IGBT PWM converters
• Rotor side converter controls the generator torque and power factor of the generator
• Converter has limitations such as voltage limit and current limit at low frequency
• The wind turbine controller tries to keep the wind turbine operating point along the maximum power curve• However during turbulent wind conditions, the operating point of the turbine is shifted from the desired power curve
Generator speed
Ge
nera
tor
torq
ue
Rated speed and torque
Torque speed curve of a variable speed wind turbine
2.a. Mechanical operating regions
Operating points of a DFIG variable speed wind turbine operating at maximum power during three different turbulent wind conditions. Generator needs to operate far away from the nominal operating point.
Operating regions of a variable speed wind turbine
1800
10610
20001600Generator speed [rpm]
Ge
ne
rato
r to
rqu
e [
Nm
] Rated speed and torque
TS
haft
[Nm
]
Speed [rpm ]
0
2000
4000
6000
8000
10000
12000
1000 1200 1400 1600 1800 2000 2200
Main powercurve
Operatingenvelop
Torque speed envelop is defined for the electrical system to operate. Main power curve ensures that the turbine operates at its maximum aerodynamic efficiency. Operating envelop is defined by generator speed tolerances, maximum generator torque limit and maximum generator power limit. Speed tolerance depends on the turbine control performance.
2.b. Rotor voltage limit and power factor
The rotor voltage changes with grid frequency, network voltage and power factor requirement. The worse case condition occurs at
Minimum grid frequency Highest network voltage Capacitive power factor.
At the top of the operating speed range, the converter voltage limit will force the generator to draw reactive power from the grid during normal operation, and significant VArs during gust transients. Grid code requirement for power factor above the rated speed is not satisfied due to converter voltage limit.
Rotor voltage curves of a DFIG
Generator stator power factor
Capacitive PF Inductive PF
PF
[-]
Speed [rpm ]
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1.1
1000 1200 1400 1600 1800 2000 2200
Rotor voltage increases with the slip speed until it reaches converter maximum voltage of 759 V.Limit on maximum speed occurs at minimum grid frequency and operating with a capacitive power factor.Since the rotor voltage is clamped at high rotor speed, the power factor has to be changed from capacitive to inductive
DFIG
Reactive power
85
90
95
100
105
110
115
Power factor [-]
Vol
tag
e [%
]
UnityInductive Capacitive
Grid code requirement
DFIG
Grid code requirement for reactive power is not satisfied !
Rated speed of the generator should be reduced to avoid reaching the converter limit. This means the mechanical design of the gearbox (gearbox ratio) has to be changed
TS
haft
[Nm
]
Speed [rpm ]
0
2000
4000
6000
8000
10000
12000
1000 1200 1400 1600 1800 2000 2200
Main powercurve
Operatingenvelop
In order to avoid absorbing reactive power from grid above 1800 rpm the rated generator speed is reduced to 1600 rpm by changing the gearbox ration by a factor of 8/9.
2.c. Rotor current variation
Thermal stress of IGBT at low frequency
aITa1
Ta1
Due to thermal high thermal stress IGBT converters have current limitations at low fundamental frequency. This results in rotor current variation entering high IGBT thermal stress.
2.c. Effect on mechanical loading
TS
haft
[Nm
]
Speed [rpm ]
0
2000
4000
6000
8000
10000
12000
14000
800 1000 1200 1400 1600 1800 2000
Pre
ven
ted
are
a d
ue
toIG
BT
th
erm
al s
tres
s
TS
haft
[Nm
]
Speed [rpm ]
0
2000
4000
6000
8000
10000
12000
1000 1200 1400 1600 1800 2000 2200
Pre
ven
ted
are
a d
ue
to v
olt
age
limit
Generator rated speed is 1800 rpm and it absorbs large amount of reactive power at high speed With rated speed of 1600 rpm, the converter needs to operate within its high thermal stress region. Both these cases are not acceptable for a wind turbine design
-2.00E+07
0.00E+00
2.00E+07
4.00E+07
6.00E+07
50 60 70 80 90 100
Time [s]
Tow
er b
otto
m M
z [N
m]
-2.00E+07
0.00E+00
2.00E+07
4.00E+07
6.00E+07
50 60 70 80 90 100
Time [s]
Tow
er b
otto
m M
z [N
m]
Loads that are related to thrust force suffers the most by tightening the turbine controller
TS
haft
[Nm
]
Speed [rpm ]
0
2000
4000
6000
8000
10000
12000
14000
1000 1100 1200 1300 1400 1500 1600 1700 1800 1900
The rotor speed now is set to 1700 rpm and then the pitch controller is tightened to keep the operating points close to the rated speed. Tightening the pitch controller has consequences on the mechanical loading
Relaxed pitch control Tightened pitch control
MzMy
3. Transient modeling of a fully rated converter wind turbine
Phase-to-phase generator fault
Grid fault
Grid code requirements
DC link voltage
Torque
Chopper heat loss
B
0H
Critical knee
Increasing temperature
Recoil
Irreversible demagnetization
Electrical faults such as grid faults and generator short circuits produce high amplitude, rapid electrical transients and wind turbine designers increasingly need to take them into account.
3.c. LVRT
Powerto grid
JAerodynamic
power
Kineticenergy Power to
DC-link
dcv
Torque control
Powerto grid
JAerodynamic
power
Power toDC-link
Heatloss
Chopper
30
100
15
00 0.15 1500
Time [s]
Voltage [%]
385 ms
• Response of a wind turbine to a grid fault is of increasing concern for turbine designers and network operators• During a grid fault, a wind turbine goes through heavy transients and the turbine could reach any of its design limits• In order to investigate the response of a wind turbine to a grid fault, appropriate electrical models have to be used
3.d. LVRT with torque control
Maintaining the DC link voltage below the upper limit during a fault is to reduce the generator power. The generator power can be rapidly reduced by means of reducing the generator torque.
3.d. LVRT with torque control
Dropping the generator torque from rated to zero has two effects Increases the rotor speed Excites drive train oscillation
The rotor accelerate because of the generator provides zero reaction torque while the turbine rotor generate aerodynamic torque. Wind turbine rotor is made up of flexible blades and flexible shafts and it is subjected to structural oscillation. Therefore step change in t he generator torque induces generator shaft oscillation As the speed tripping limit is reached the turbine controller shut down the turbine Not satisfying the grid code requirement.
3.e. LVRT Braking resistor
IEC 61400 Ed-3, Section 6.5 Electrical power network conditions “Auto-reclosing cycles – auto-reclosing cycle periods of 0,1 to 5 s for the first reclosure and 10 s to 90 s for a second reclosure shall be considered.
By using a braking resistor, the generator reaction torque can be maintained. Thus avoid any speed increases nor oscillation during grid fault. However in this successive three fault case, the chopper needs to be operating for about 7.5s
Three successive grid faults are applied within 40s
3.f. LVRT Combination of torque control and braking resistor
Instead of using braking chopper alone or torque control alone, a combination of both methods can be used.
Torque ramp off instead of torque step down
Generator speed is kept under tripping limit
Braking chopper is only used for about 2s in total for three successive grid faults
4. Summary
Wind turbine dynamics consists of aerodynamic, structural dynamics, controller dynamics and electrical dynamics. When designing a wind turbine all four system has to be considered together
Grid code requirements are becoming increasingly demanding ad they have direct influence on the design process of a wind turbine.
Electrical limitations determines the range of operation of a wind turbine, therefore electrical dynamics should be taken into account when designing a wind turbine
Converter voltage limitation could forces the generator to draw reactive VArs from the grid and not to satisfy the grid code requirements
IGBT converters have limitations at low frequency, this important characteristics has to be taken into account
During a grid fault, a wind turbine goes through heavy transients and the turbine could reach any of its design limits
Combination of torque control and braking chopper can be used to ride through three successive faults efficiently.