Implementing an Adaptive Capital Improvement Program

31
IMPLEMENTING AN ADAPTIVE CAPITAL IMPROVEMENT PROGRAM Katy Weidner, Black & Veatch NC AWWA-WEA 95 TH ANNUAL CONFERENCE

description

Acknowledgements Co-Authors Courtney Driver, City of Winston Salem Kevin Laptos, Black & Veatch Kent Lackey, Black & Veatch

Transcript of Implementing an Adaptive Capital Improvement Program

Page 1: Implementing an Adaptive Capital Improvement Program

IMPLEMENTING AN ADAPTIVE CAPITAL IMPROVEMENT PROGRAM

Katy Weidner, Black & Veatch

NC AWWA-WEA 95TH ANNUAL CONFERENCE

Page 2: Implementing an Adaptive Capital Improvement Program

2

• Co-Authors• Courtney Driver, City of Winston Salem• Kevin Laptos, Black & Veatch• Kent Lackey, Black & Veatch

ACKNOWLEDGEMENTS

Page 3: Implementing an Adaptive Capital Improvement Program

3

• Adaptive Capital Planning• Winston-Salem’s Adaptive CIP

• Overview of the Master Plan• Goals for Developing the iCIP Tool• How the iCIP Tool Works

AGENDA

Page 4: Implementing an Adaptive Capital Improvement Program

ADAPTIVE CAPITAL PLANNING

4

Page 5: Implementing an Adaptive Capital Improvement Program

5Planning for Growth alongside of Budgeting for Maintenance

• Focus on Asset Management & Optimization rather than Expansion

• Need for cost-effective assessments• Address worst condition assets first• Risk based prioritization

ADAPTIVE CAPITAL PLANNING

Page 6: Implementing an Adaptive Capital Improvement Program

6Adaptive Capital planning

• Static CIP Report• Time and situation constrained• Not risk-based• Not adaptable

CIP PRIORITIZATION - OLD APPROACH

Traditional CIP

Page 7: Implementing an Adaptive Capital Improvement Program

7

• Growth Rates

• Asset Condition

• Outside Factors

FACTORS THAT CAN AFFECT PLANNING

Page 8: Implementing an Adaptive Capital Improvement Program

WINSTON-SALEM’S WASTEWATER SYSTEM MASTER PLAN

8

Page 9: Implementing an Adaptive Capital Improvement Program

• 1,724 miles of sewer main

• 49 Pump Stations

• Two Treatment Plants• Muddy Creek

(21 MGD)• Elledge

(30 MGD)• Three Major

Sewer Basins

CITY/COUNTY UTILITIES COMMISSION – COLLECTION SYSTEM OVERVIEW

99

Page 10: Implementing an Adaptive Capital Improvement Program

WASTEWATER SYSTEM MASTER PLAN

10

• Evaluate collection system capacity in three major basins• Prioritize Capacity improvements

30 year Master Plan (2011 – 2041)

• Future Treatment Alternatives Evaluation• Collection System Asset Evaluation

Wastewater System Evaluation

• Capacity Driven Projects• Condition Driven Projects

CIP Projects

10

Page 11: Implementing an Adaptive Capital Improvement Program

• Condition Driven Projects• Facility Inspections• Pipeline Prioritization

• Criticality Ratings based on consequence of failure

• Condition Scores evaluated based on available data, modeling results, and age of pipe

• Capacity Driven Projects• Flow Projections • Field Surveys and Flow

Monitoring• Hydraulic Model for Base

and future Years

DEVELOPING THE CIP PROJECTS

11

Page 12: Implementing an Adaptive Capital Improvement Program

12

ASS

ET M

AN

AG

EME

NT

ASSET MANAGEMENT APPROACH TO SYSTEM PLANNING

Provides a comprehensive and coordinated Master Plan CIP

Page 13: Implementing an Adaptive Capital Improvement Program

13We need to compare alternatives and update the CIP!

• What if…

• A routine pipeline inspection reveals a pipe failure at the location of a future capacity project?

• OR

• A 2020 DOT project includes tearing up and repaving the road at a sewer crossing in the 2030 CIP. Does it make sense to move forward the project? All of the project or maybe just the road crossing?

…BUT HOW FINAL IS THE “FINAL” CIP?

Page 14: Implementing an Adaptive Capital Improvement Program

ADAPTING THE CIP USING THE iCIP TOOL

14

Page 15: Implementing an Adaptive Capital Improvement Program

• Evaluating Current Needs• Critical Capacity Driven Projects• Long-Term and Short-Term Budgeting Tools• Increased functionality for Cost Estimating, Project

Scheduling, and Cash Flow and Spend Plans• Data Collection Plan

• Evaluating Future Needs• Asset Condition Database• Prioritize Inspection and R&R budgets

CUSTOMIZING iCIP FOR WINSTON-SALEM

1515

Page 16: Implementing an Adaptive Capital Improvement Program

16

• Three Components• Asset Prioritization –

Leverage GIS Inventory and updated condition data to prioritize projects (GIS)

• Asset Costing – Dynamic update costs based on project changes to scope and schedule (Excel)

• CIP project identification (iCIP)

ADAPTIVE APPROACH TO CIP PRIORITIZATION

Page 17: Implementing an Adaptive Capital Improvement Program

• Integrate the CIP spreadsheet with the iCIP GIS Inventory

ADAPTIVE CIP

1717

Page 18: Implementing an Adaptive Capital Improvement Program

• interactive Capital Improvement Planning • Built on top of ArcGIS (Esri Add-in) • Open architecture, Esri-based enhanced by B&V• Integrate CIP with existing GIS Inventory• Risk and Capacity Based Prioritization

iCIP - GIS

1818

ICIP

CO

ST E

STIM

ATI

NG

TO

OL

18

Page 19: Implementing an Adaptive Capital Improvement Program

HOW iCIP WORKS FOR WINSTON - SALEM

19

Page 20: Implementing an Adaptive Capital Improvement Program

20Project Summary Window

Page 21: Implementing an Adaptive Capital Improvement Program

21Assets Window

Page 22: Implementing an Adaptive Capital Improvement Program

22Project Details Window

Page 23: Implementing an Adaptive Capital Improvement Program

iCIP Tools in excel

• Summarizes Scope and Performance Triggers• Calculates detailed Cost Opinions• Project Phasing, Cash Flow and Encumbrance

CIP EXCEL SPREADSHEET

Page 24: Implementing an Adaptive Capital Improvement Program

24Hidden Cells contain the data used for cost estimates 24

Page 25: Implementing an Adaptive Capital Improvement Program

25Linked to Detailed Costs for easy updating 25

Diameter Material Installation Material cost Total Unit cost MH

6 DIP (Force Main) 35 26 61 20008 EVCP 80 38 118 3000

10 EVCP 100 45 145 300012 EVCP 150 47 197 400015 EVCP 150 53 203 600016 EVCP 200 57 257 600018 EVCP 200 64 264 600021 EVCP 200 72 272 600024 EVCP 200 83 283 800027 Flowtite GRP SN46 250 125 375 800030 Flowtite GRP SN46 250 128 378 800036 Flowtite GRP SN46 250 155 405 1200042 Flowtite GRP SN46 250 176 426 1200048 Flowtite GRP SN46 300 198 498 1200054 Flowtite GRP SN46 300 224 524 1500060 Flowtite GRP SN46 300 257 557 1500066 Flowtite GRP SN46 300 286 586 1500072 Flowtite GRP SN46 300 323 623 15000

UNIT COST ASSUMPTIONS

Page 26: Implementing an Adaptive Capital Improvement Program

Phasing is Based on the Start Year and Project Duration 2626

Page 27: Implementing an Adaptive Capital Improvement Program

ADJUSTING CASH FLOW

27

Page 28: Implementing an Adaptive Capital Improvement Program

An Adaptive CIP can…• Leverage risk-based prioritization and/or capacity

assessments• Immediately see results of decisions graphically• Easily integrate with existing and updated GIS asset

inventory• Provide tools to adapt to changing budgets, asset

conditions and priorities

ADAPTIVE CIP

2828

Page 29: Implementing an Adaptive Capital Improvement Program

An Adaptive CIP can respond to…• Growth – Whether a recession slows growth or a

housing boom in an unforeseen area accelerates growth, CIP projects can “slide” to when they are needed.

• Condition – Prioritization scores can be continually updated and used to allocate resources efficiently

• Outside Factors – Updates can be made to take advantage of developer projects, transportation projects, etc

IN CLOSING…

2929

Page 30: Implementing an Adaptive Capital Improvement Program

ANY QUESTIONS?

30

Thank you for attending this presentation!

?30