Implementing ABC on Bridge Replacement and Rehabilitation ...

70
Implementing ABC on Bridge Replacement and Rehabilitation Projects Bala Sivakumar T.H.E. Conference 2016

Transcript of Implementing ABC on Bridge Replacement and Rehabilitation ...

Page 1: Implementing ABC on Bridge Replacement and Rehabilitation ...

Implementing ABC on Bridge Replacement andRehabilitation Projects Bala Sivakumar

T.H.E. Conference 2016

Page 2: Implementing ABC on Bridge Replacement and Rehabilitation ...

Outline

Introduction to ABC

ABC Technologies & Methods

Implementing Bridge Moves

ABC Rehab Projects

ABC Replacement

Projects

Implementing Prefab

Systems

Page 3: Implementing ABC on Bridge Replacement and Rehabilitation ...

What is ABC?

Page 4: Implementing ABC on Bridge Replacement and Rehabilitation ...

What is ABC?

Accelerated Bridge Construction (ABC)

ABC is bridge construction that uses innovative methods to

reduce mobility impacts when replacing/rehabilitating existing bridges.

ABC is a platform for innovation

Page 5: Implementing ABC on Bridge Replacement and Rehabilitation ...

Reasons for considering ABC include:• Heavily traveled route (high ADT)• Long or non-existent detours • Part-width construction is not a

preferred option

Reasons for ABC?

Cast-in-place construction is a sequential processABC allows work to be done in parallel – reduce schedule

Page 6: Implementing ABC on Bridge Replacement and Rehabilitation ...

Reduces disruption to

traffic

ABC Advantages

Safer; reduces exposure of workers and public

Better quality control due to prefabricated

elements

Reduced environmental

impacts

Page 7: Implementing ABC on Bridge Replacement and Rehabilitation ...

ABC Elements and Methods

ACCELERATED BRIDGE CONSTRUCTION

Prefabricated Elements &

Systems (PBES)

Accelerated Geo-tech Work

Rapid Demolition

Bridge Movement Technologies (SIBC /

SPMT)

Innovative Contracting

Page 8: Implementing ABC on Bridge Replacement and Rehabilitation ...

Time Metrics for ABC – Mobility Impact Time

TRAFFIC IMPACTS WITHIN

Tier 1 24 hours

Tier 2 3 days

Tier 3 2 weeks

Page 9: Implementing ABC on Bridge Replacement and Rehabilitation ...

ABC – National Perspective

• 2200 + ABC projects to date (2014)

• 43 states have used ABC (2014)

• Several states have ABC programs for statewide implementation

• ABC candidates are selected using a screening process

Page 10: Implementing ABC on Bridge Replacement and Rehabilitation ...

ABC Technologies

Page 11: Implementing ABC on Bridge Replacement and Rehabilitation ...

Full Depth Precast Deck Panels

Casting and curing decks is a slow process

Page 12: Implementing ABC on Bridge Replacement and Rehabilitation ...

Pre-decked beams• Concrete deck bulb tees• Concrete Deck double

tees

MODULAR CONCRETE SUPERSTRUCTURE SYSTEMS

Page 13: Implementing ABC on Bridge Replacement and Rehabilitation ...

Prestressed Deck Bulb Tee — NY Route 31

Page 14: Implementing ABC on Bridge Replacement and Rehabilitation ...

NJDOT Route 18 Bridge Over Route 1Weekend Replacement

MODULAR STEEL SUPERSTRUCTURE SYSTEMS

Page 15: Implementing ABC on Bridge Replacement and Rehabilitation ...

Prefabricated Abutment & Wingwalls

Page 16: Implementing ABC on Bridge Replacement and Rehabilitation ...

• Build the entire bridge superstructure and then move it into place in a few hours.

• Bridge movement technologies:– Slide-In Bridge Construction (SIBC)– Self-Propelled Modular Transporters (SPMT)– Float-In– Launching / Skidding

Bridge Movement Technologies

Page 17: Implementing ABC on Bridge Replacement and Rehabilitation ...

3 June 2008 17

Roll-Out l Roll-In Hood Canal Bridge, WSDOT

Before During After

Page 18: Implementing ABC on Bridge Replacement and Rehabilitation ...

Roll-Out/Roll-In New York City Van Wyck Expressway

Page 19: Implementing ABC on Bridge Replacement and Rehabilitation ...

Push/pull hydraulic jacks

Pulling with• strand jacks• power winch

Bridge Slide Systems

Page 20: Implementing ABC on Bridge Replacement and Rehabilitation ...

Roller BearingsCoefficient of Friction: 5% of Vertical Load

Teflon-Coated Neoprene Bearing PadsCoefficient of Friction: 10% of Vertical Load

Slide Bearings

Page 21: Implementing ABC on Bridge Replacement and Rehabilitation ...

Bridge Movement – Float-In

Page 22: Implementing ABC on Bridge Replacement and Rehabilitation ...

Self Propelled Modular Transporter (SPMT)

What is an SPMT?• Multi-axle platform• Each axle pivots 360 degrees• Lifts, carries, sets large/heavy loads• Each axle moves independently

Page 23: Implementing ABC on Bridge Replacement and Rehabilitation ...

Bridge Movement with SPMTs

Page 24: Implementing ABC on Bridge Replacement and Rehabilitation ...

MassDOT Study• 2 similar parallel bridges: One conventional one ABC using PBES• Conventional = $ 224 / SF• ABC = $284 / SF• 27% cost differential; These are NE prices

FIU Study

• FIU compared costs using 53 ABC projects in the FHWA ABC database with similar conventional projects

• ABC costs were 20% higher on average

ABC COSTS

Page 25: Implementing ABC on Bridge Replacement and Rehabilitation ...

• Design-Bid-Build• Design-Build• Construction Manager / General Contractor

ABC Contracting• Incentive / Disincentive based on user delay costs• A+B Bidding

ABC DELIVERY

Page 26: Implementing ABC on Bridge Replacement and Rehabilitation ...

ABC Resources SHRP2 ABC Toolkit

• Sample ABC plans

• Sample ABC design calcs.

• ABC Specs / Special provisions

• ABC erection concepts

Page 27: Implementing ABC on Bridge Replacement and Rehabilitation ...

Implementing PBES

Page 28: Implementing ABC on Bridge Replacement and Rehabilitation ...

14 Day Bridge Replacement – Keg Creek Bridge, Council Bluffs, Iowa

• Total prefabricated bridge• 3 Spans• 14 day closure• 14 day ABC period• Opened November 1, 2011

Page 29: Implementing ABC on Bridge Replacement and Rehabilitation ...

Oct 17, 2011

Nov 1, 2011

Page 30: Implementing ABC on Bridge Replacement and Rehabilitation ...

Cross-Sections/Plan

UHPC Joints

Page 31: Implementing ABC on Bridge Replacement and Rehabilitation ...

Prefabrication Yard Adjacent to Bridge – Iowa Bridge Farm

Page 32: Implementing ABC on Bridge Replacement and Rehabilitation ...

93 K

168 K

Prefabrication of Abutments and Piers

52 K

Page 33: Implementing ABC on Bridge Replacement and Rehabilitation ...

Precast Abutment Assembly – Days 3 and 4

Page 34: Implementing ABC on Bridge Replacement and Rehabilitation ...

• Pier caps: 168 kips• Required two 110 ton cranes to lift into place

168 K

Precast Pier Assembly – Day 5

Page 35: Implementing ABC on Bridge Replacement and Rehabilitation ...

112 K

Span – 70 ft

Erection of Superstructure Elements – Days 7 and 8

Page 36: Implementing ABC on Bridge Replacement and Rehabilitation ...

Erection of the Superstructure Elements – Days 7 and 8

Page 37: Implementing ABC on Bridge Replacement and Rehabilitation ...

• Full moment transfer

• No post-tensioning required

• Only 6 in. wide; low-permeability

• 25,000 psi strength• Steel fiber

reinforcement

Ultra High Performance Concrete Deck Closure Pours – Day 10

Page 38: Implementing ABC on Bridge Replacement and Rehabilitation ...

Precast Approach Slab — Day 10

Precast SleeperSlab

Page 39: Implementing ABC on Bridge Replacement and Rehabilitation ...

Time Lapse – 14 Day Replacement

Page 40: Implementing ABC on Bridge Replacement and Rehabilitation ...

Implementing Slide-In Bridge Construction

Page 41: Implementing ABC on Bridge Replacement and Rehabilitation ...

• Weekend Replacement• 20 Hr Closure

I-84 Bridges Slide-In Replacement — New York 2013

Page 42: Implementing ABC on Bridge Replacement and Rehabilitation ...

• Over 75,000 ADT• 16% trucks• Existing bridges are too narrow for cross-overs• 3 Span bridge replaced with single span• One Saturday night closure per bridge

NY I-84 Bridges

Page 43: Implementing ABC on Bridge Replacement and Rehabilitation ...

• NEXT beams• Precast approach slabs• UHPC closure pour

Superstructure Sections

Page 44: Implementing ABC on Bridge Replacement and Rehabilitation ...

New Superstructures on Falsework

Page 45: Implementing ABC on Bridge Replacement and Rehabilitation ...

New Abutment Construction

Page 46: Implementing ABC on Bridge Replacement and Rehabilitation ...

Slide-In Replacement Concept

Slide SurfaceTemporary end span

Modular walls

During Slide

Page 47: Implementing ABC on Bridge Replacement and Rehabilitation ...

End Diaphragm and Slide Shoe

Page 48: Implementing ABC on Bridge Replacement and Rehabilitation ...

Bridge Slide – October 21, 2013

7 hours to demolish existing bridge and slide in new bridge

Page 49: Implementing ABC on Bridge Replacement and Rehabilitation ...

Both Bridge Slides Completed 10 Months After NTP

Page 50: Implementing ABC on Bridge Replacement and Rehabilitation ...

Time Lapse

Page 51: Implementing ABC on Bridge Replacement and Rehabilitation ...

ABC Rehab Projects

• PBES• SPMT

Page 52: Implementing ABC on Bridge Replacement and Rehabilitation ...

Minneapolis Franklin Avenue Bridge Rehabilitation

New deck, cap beams and columns using precast members

Page 53: Implementing ABC on Bridge Replacement and Rehabilitation ...

Minneapolis Franklin Avenue Bridge Rehabilitation

• Part-width construction is not cost-effective

• Cast-in-Place Construction: Requires full closure for two years

• ABC alternate: Full closure for 3 months• Adjacent to Univ. of Minnesota campus• Closure can be timed to occur in summer months• On-site pre-casting by contractor

Page 54: Implementing ABC on Bridge Replacement and Rehabilitation ...

On Site Pre-casting --- Franklin Ave. Bridge MN

Page 55: Implementing ABC on Bridge Replacement and Rehabilitation ...

Steam Curing / Wet Curing of Slab Panels

Page 56: Implementing ABC on Bridge Replacement and Rehabilitation ...

PennDOT State Route 30 Bridge – Weekend Replacement Replacement • 54 Hour closure (Friday night – Monday Morning)

• Busy State Route (ADT 30,000) over local road in East Pittsburgh, PA• Full superstructure and partial substructure replacement

Page 57: Implementing ABC on Bridge Replacement and Rehabilitation ...

Partial Demolition of Abutments / New Preacst Caps

Page 58: Implementing ABC on Bridge Replacement and Rehabilitation ...

Steel Superstructure Modules -- Assembly

Page 59: Implementing ABC on Bridge Replacement and Rehabilitation ...

Bridge Model

Page 60: Implementing ABC on Bridge Replacement and Rehabilitation ...

Weekend Superstructure Replacement Using SPMTsBridge Over Route 9 ; Massachusetts

Substructure Rehab

Page 61: Implementing ABC on Bridge Replacement and Rehabilitation ...

STAGING AREA

ROUTE 9

Bridge Over Route 9; Site-Layout

Page 62: Implementing ABC on Bridge Replacement and Rehabilitation ...

Substructure Rehabilitation with Precast Caps

Page 63: Implementing ABC on Bridge Replacement and Rehabilitation ...

New Two-span Steel Superstructure on False-work

Page 64: Implementing ABC on Bridge Replacement and Rehabilitation ...

SPMT Move

Page 65: Implementing ABC on Bridge Replacement and Rehabilitation ...

New Superstructure on Rehabilitated Substructure

Page 66: Implementing ABC on Bridge Replacement and Rehabilitation ...

NJ Transit Bridge Replacement – Plainfield, NJ• Weekend Superstructure Replacement with SPMT– October 2015• Rehab Substructure

Page 67: Implementing ABC on Bridge Replacement and Rehabilitation ...

Substructure Rehab -- Saturday

New bridge assembled in station parking lot

Page 68: Implementing ABC on Bridge Replacement and Rehabilitation ...

Bridge Move – Saturday Night

Page 69: Implementing ABC on Bridge Replacement and Rehabilitation ...

Track Work -Sunday

Page 70: Implementing ABC on Bridge Replacement and Rehabilitation ...

Thank You