Implementation Strategy for Regional Project for the...
Transcript of Implementation Strategy for Regional Project for the...
Implementation Strategy for "Regional Project for the Development of the Water and Wastewater Infrastructure in Iasi County, during 2014-2020 Period", in order to limit the
NRW values in the operation of drinking water supply systems
M. Doruş, C. Savastru, I.V. Apetroi, Şt. Chirica
APAVITAL Iaşi
CONTENT:
1. INTRODUCTION2. THE EXISTING SITUATION AND THE NEED FOR IMPLEMENTING A NRW
RELATED STRATEGY3. CASE STUDY REGARDING THE NRW AMOUNTS AFTER THE
IMPLEMENTATION OF THE ENVIRONMENTAL SOP PROGRAM IN THE TÂRGU FRUMOS OPERATIONAL AREA
4. THE IMPLEMENTATION STRATEGY OF THE LIOP PROGRAM IN REFERENCE TO THE MINIMALIZATION OF NRW VALUES
5. CONCLUSIONS
INTRODUCTION
As regards the investments carried out for the extension of water
supply systems, a key issue is the development of a unitary strategy
at regional level. This strategy must correlate water sources (in terms
of quality, available flows, zonal distribution) with the consumers’
requirements. The lack of such a strategy leads to inappropriate sizing
of water supply systems that feature pipe diameters and storage
capacities not adequate for the real water demand.
Inappropriate sizing of water supply systems leads to big NRW
values either from network stress and frequent leakage, either from
water aging in the network, thus the need to evacuate and replace it,
leading to authorized non-billed water volumes, components of the
NRW factor.
THE EXISTING SITUATION
AND THE NEED FOR IMPLEMENTING A NRW RELATED STRATEGY
Considering the regional nature of Apavital S.A. company, which operates systems
of various nature, operating parameters and distinct performance indicators, there
is need to implement a company-wide strategy in order to limit the NRW amounts
across the entire operating area.
The expanding of Apavital operating area is achieved by three different methods:
a• taking over of water systems that are already operational,
but featuring advanced degrees of deterioration (e.g. the Town of Paşcani)
b • taking over new systems or network extensions from local government investments
c
• managing new systems, which were completed by investments from Apavital funds or non-reimbursable funds, carried out by means of Apavital design department or via third-party designers.
In order to ensure the sustainable development of new water systems, there was
need to identify the causes that are leading to major deficiencies in systems
currently operated
inappropriate sizing of water systems, this
generating either high water velocities or prolonged water
stagnation inside pipelines and the need for periodic
pipe flushing
difficult defining of pipeline routes in relation to operational capacity
(difficult accessible areas, large number of under-crossings and direction
changes etc.)
lack of correlation or incorrect correlation
between materials used and the nature of
terrain/network site (heavy traffic areas, areas prone
to landslides etc.)
deficiencies in the operation of water tanks
and pumping stations
problems with monitoring and controlling water losses inside under-
crossing systems
changes in network operational pressures
according to the increasing/decreasing of
estimated consumed flows
CASE STUDY REGARDING THE NRW AMOUNTS AFTER THE
IMPLEMENTATION OF THE ENVIRONMENTAL SOP PROGRAM IN THE
TÂRGU FRUMOS OPERATIONAL AREA
One of the major projects completed under SOP Environment Program was the
investment named "Upgrading of water and sewerage systems in the Town of Târgu
Frumos" (Works Contract 11).
The project was aimed at:
replacing the aging infrastructure
replacing connections made with
compression pipe joints with
connections made with electro-
fusion joints
local reconfiguration of pipe routes
expanding the network to accept
new consumers
The network, at key locations, was
equipped with measurement and
control devices integrated with both
local and central dispatch and
control departments.
Under the project,
rehabilitation works
were foreseen for
approximately 19% of
the existing pipeline
network length, and
extension works for
approximately 15.5%.
No ActivityLength
[m]
1 Upgrading of main water pipelines 913
2 New main water pipelines 3,012
3 Hydraulic upgrading of existing distribution networks 597
4 Replacement of asbestos-cement sectors 1,253
5 Extension of water supply network 4,951
Total 10,726
The case study of Târgu Frumos operating area included data sets recorded during
the pre-accession phase of the SOP Environment program, during the project
implementation phase and after works completion.
tendency of water consumption
increasing, per household
the continuous increasing of
consumers numbers
a decreasing of water volumes
injected into the system
The final effectiveness of this investment (Works Contract 11) as regards the reducing
of NRW amounts in the Târgu Frumos operational area.
YearTWS
Percentage from TWS
BC UMC WL NRW
[m3] [%] [%] [%] [%]
2011 679,233 59.01 1.48 39.51 40.99
2012 627,775 74.90 0.17 24.93 25.10
2013 626,174 66.62 0.18 33.20 33.38
2014 610,887 52.35 0.18 47.47 47.65
2015 535,149 74.46 0.89 24.66 25.54
2016 504,324 80.09 2.16 17.75 19.91
2017 540,536 78.14 1.34 20.52 21.86
Note: TWS – Total Water Supply; BC – Billed
Consumption; UMC – Unbilled Metered
Consumption; WL – Water Loss; NRW – Non-
Revenue Water
Analysis of data in Table 2 shows how the volumes of water injected into system
gradually decreased starting with 2011 as a result of investments carried out with
Apavital financing and continued to decrease as a result of the implementation of
the project financed by European funds.
The system's upgrading started in 2013 and the rapid progress of the work can be
noticed by analyzing the subsequent monitoring intervals.
The study period 2014 - 2015 is marked by a substantial increase in the
performance indicators obtained in the Târgu Frumos system.
water flows injected into system decreased
billed consumption increased
water losses decreased
NRW amounts dropped
The analysed period 2011 - 2017 is characterized by three stages of evolution.
Rehabilitation and upgrading stage through Apavital funds investments - until 2013
- the pipe replacement during the 2010 - 2011 period decreased the water losses
- the subsequent increase in water loss in 2013 indicated that it was necessary to continue
investments in the water supply system
The system upgrading stage through the completion of Works Contract 11 project during period 2013
- 2016 lead to an improvement of technical and financial indicators obtained before implementation:
- a reduction in input water volumes pumped into the system - up to 504,324 m3
- an increase in the billed water volumes - up to 403,915 m3
- a decrease in water losses, up to 89,522 m3
The system operation stage is
represented by the values from 2017:
- an increase of the input water volumes
by about 7.18% (540,536 m3)
- an increase of water losses-110,897 m3.
The operational period that follows the
completion period is known as the
system’s “running-in” stage, stage
during which water loss values can
increase.
THE IMPLEMENTATION STRATEGY OF THE LIOP PROGRAM
IN REFERENCE TO THE MINIMALIZATION OF NRW VALUES
Currently, S.C. Apavital S.A. Iasi operates approx. 4600 km of water supply network,
managed through four operational sectors: Distribution-Sewerage ZMI (Iaşi
Metropolitan Zone), Bahlui Operational Sector, Prut-Bârlad Operational Sector, Siret
Operational Sector.
The investments carried out
through LIOP program are aimed at
the development of the regional
water supply system.
The construction, extension and
rehabilitation of:
331,484 m of
distribution
networks
284,303 m of
main water
pipelines
10 new water supply
systems will be created
The implementation strategy of the "Regional Project for Development of Water and
Wastewater Infrastructure in Iasi County for period 2014-2020" represents a
collection of good practices identified in operating process of water supply systems
and in implementation of the infrastructure projects developed by S.C. Apavital S.A.
both by company’s own funds and by non-reimbursable financing.
Measures taken by the operator in the design, execution and operationphases
guarantee the sustainable
development of the water supply systems in
operation
have a major impact on the immediate reduction
of NRW amounts in existing systems
help keep the NRW at low values in the newly commissioned systems
a) The procedure during the design phase
Operational sector
• System needs
PIU
• Design brief
• Indicators
CTE
• approves the implementation solution
The design brief is submitted to the General Designer in order to compile the
technical documentations. After their completion, the investment is taken over by PIU
in order to correlate the design activity with the operation method (choice of materials,
network route tracing, creation of DMAs and pressure zones, setting the
measurement and control points, implementation of Smart Water Networks concept).
The operational sector defines the system’s need and notifies the PIU about the
requests for rehabilitation, replacement or extension of network sections in the
operating area
The Project Implementation Unit (PIU), via the personnel in charge with the
verification, the correlation of activities with the Master-plan, the Feasibility studies
and other investments, establishes the design brief and submits for approval, towards
the TEC (Technical-Economic Council), the investment’s main indicators.
the materials used are HDPE for distribution networks and cast iron for main water
pipelines (this decisional step is based on annual statistics related to the
occurrence of network failures);
using pressure class immediately above the class resulting from sizing calculations;
this measure is justified by the analysis section execution cost / intervention cost in
case of system failures caused by high pressure fluctuations; an increase in costs
with approx. 15% was noted when switching from PN6 pipes to PN10 tubes;
a minimum 32 mm diameter is mandatory for public connections (manufactured by
electro welding); the result is a superior efficiency as regards the reduced number
of pipe bursts and pipe leakages, compared to the previous over-use of 25 mm
connections, (manufactured by compression joining);
"C" class water meters (fitted with remote data transfer units) are mandatory;
the automation of pumping stations and storage tanks and their integration into the
central dispatcher control room;
placement of water leakage collecting manholes and observation manholes at
under crossings;
using pressure limitation equipment and additional network protection measures in
case of technical failures in the system.
The main guiding lines in choosing the materials and execution technologies
PIU
• supervises the contractor's and consultant's contract indicators
• ensures the interface with operational personnel
• provides additional control as regards the completed works quality
Consultant
• provides supervision of investment in compliance to contract by means of specialized personnel
• issues reports towards PIU
Contractor
• provides works execution in compliance to the contract
• notifies PIU and the Consultant as regards the need to adapt the project to the terrain
b) The procedure during execution phase
PIU ensures the project implementation through assigned project officers. These
officers will supervise the contract physical and financial indicators and will ensure the
relationship with the Consultant. No project officer will implement more than two
contracts at the same time within the Program. The project officers will also have a
Site Supervisor specialization in relevant areas.
By implementing this measure from the SOP Environment program, an additional
control measure is introduced as regards the Consultant supervision, which
drastically reduces the number of reported defects during the notification period and
implicitly the NRW value.
c) The procedure during the defect notification period
During the defect notification period (1 year), the As-built documentation is
submitted to GIS and Network Analysis Departments for digital mapping.
After inputting the data in GIS, the Network Analysis Bureau builds the network
hydraulic model with MikeUrban Software.
The measures listed are focused on two issues that are crucial in limiting the NRW
values in the forecasted period:
PIU
Network Analysis
GIS
During this period not only the obvious defects
will be detected (failures, low pressures), but
the model will also highlight all major gaps
between designed parameters and real
network parameters.
increasing the quality of executed networks
gathering data for the first year of operation,
which can be used as benchmark data in
the annual network evolution analysis
1. S.C. Apavital S.A. operates water systems that feature various technical
specifications and performance indicators, which leads to the need to adopt
optimization solutions, tailored according to the specific features of each system.
2. The water loss management, in the company, is based on a thorough analysis of
each operated water supply system.
3. The case study analysed in the Targu Frumos operational area demonstrated the
necessity to upgrade the water system.
4. During the implementation period the NRW amount decreased from 47.65% to
19.91% and one year after the completion of the upgrading works of the Târgu
Frumos water supply system. Thus, out of the total injected water volume of 540,536
m3, the billed consumption was 78.14% and the NRW amount was 21.86%.
5. The procedures adopted are an integral part of the company-wide strategy to
reduce the NRW value. Its effectiveness can be observed at local level, through the
implementation of CL 11 works contract in Târgu Frumos city, as well as at the level of
the entire operating area of S.C. Apavital S.A., by continuing the investment programs
financed from own funds and non-reimbursable sources.
6. At each stage in the lifetime of a water supply system, from the conceptual stage to
the operation phase, the measures implemented by S.C. Apavital S.A. aim to prevent,
limit and control the value of water losses and NRW.
CONCLUSIONS
CONTACT DETAILS:
Name : Apetroi Ioan Vladut
Organization : S.C. APAVITAL S.A.
E-mail : [email protected]
THANK YOU !MULTUMESC!