ii-.tur* on RWHS... · 2020-03-05 · Total Telangana State 2389237 719462 4500 30358 426 11500 608...
Transcript of ii-.tur* on RWHS... · 2020-03-05 · Total Telangana State 2389237 719462 4500 30358 426 11500 608...
F ile No.CDMA'M4,DL Bt 4I2O2O-M4 SEC-CDMA
GOVERNMENT OF TELANGANA STATE
MUNICIPAL ADMINISTRATION DEPARTMENT
Office of Director of
Municipal Administration Department
Telangana, HYderabad
CIRCULAR
Dt.D410312020
116(4) of the
Roc.No. I 8l 367/2020/M4'
Sub:C&DMA_RWHS_IdentificationandconstructionofRainwater Harvesting ii-.tur* in all the ULBs in the State- Special
Drivefrom06.032020to31.05'2020_Certaininstructions_Issued.
Ref: l.Instructions dt.01 '03'2020 of the Hon'ble Minster for
MA & UD DePt.
2. Sections Section 17l(2) and Section
Telangana Municipalities Act, 20 19
,r ,k,. ?t *
The attention of the Municipal commissioners of all the ULBs is invited
to the references cited and they are informed that Section 17l(2) and Section
ior+lof the n.* iliungana Municipalities Act, 2019 reads as follows:
Section l7l(2)z
,,For Secured planned development of ar?as in Mttnicipalities, a Detoiled
planning Scheme or Local Area Plan"shatl be prepared for specific areos os
identified and notified, and as prescribed in the-Telangana Town Planning Act'
tg20. Detailed pirrni"s ,cheme shall be prepared i.n conformity w.lth Master
plan or Indicative Land (Jse Plan, ,f ony, ani sh.all-have ecologically sensitive
areas earmarked, and shall have ietaied noad Network Plan' Urban Green
Spaces Plan, D,o,in,og, Pl1n, Water Tnmk Lines, Rain Wqter Horvesting
Structures and Solid ilrort, Management among the other as prescribed'
Section 176(4'12
,,Energl Conservation Building Code or Green Btilding Code or any other
F ile No.C DMA-M4,DLBl 41 2020-M4 SEC-C DMA
Energ,t ond Vl/oler conservstion measures as deemed appropriate by the State
Govilnment, shall be made applicable to buildings, as prescribed, on plots
above certain size and/ or built-up area beyond a certain area, as prescribed by
the Government."
2. The Hon'ble Minster for MA&UD Department has issued strict
instructions for identification and construction of Rain Water Harvesting
Structures (RWHS) in all the Municipalities and Municipal Corporations in the
State by taking up a Special Drive from 06.03 .2020 to 3 1.05.2020.
3. Accordingly, the Municipal Commissioners of all ULBs are hereby
directed to take up a Sp.cial Drive for construotion of Rain Water Harvesting
Structures commencinf fro1n 06.03.2020 to 31.05.2020 in all the prominent
places as mentioned below:
1. Roof Top:- Individual residential buildings, Municipal
Office buildings. Ward office buildings, Community
hall buildings, Government offices/Schools/colleges
buildings
2. Hand boresMells:- Hand bores/ wells, Filter beds / Sumps/Tanks'
3. Surface/ Run off:- Power bores, Municipal open spaces, ParksiPlay
grounds, Graveyards. Private schools/colleges,
Religious Places
4. In this regard, the following Guidelines are hereby issued for construction
of Rain Water Harvesting Struitures on TOP PRIORITY basis as per the
following timelines:
06.03.2020
teams headed bY Councilor
porator with Engineering / Town Planniny' Revenue
itution personnello identiff the sites for construction o
tt.03.2020
ffi the sites tbr construction. On
ification of required number of sites for construction of
WHs,thesameshallbeallottedtotheeachteamoLonitoring of Engineer & Town Planning for designing an(
,.rtt*"""t1y, preparation of estimates, taking necessary
pprovals und t.nd.i procedure shall be completed for06.03.2020
to
F ile No.G DMA-M4lDL Bt 4l2O2O -M4 SEC-C DMA
5. All the Municipal commissioners in the State are therefore directed to
follow the above insiructions scrupulously for successful completion of the
Special Drive for construction of RWHS as per the timelines.
6. The District-wise and ulB-wise targets of Rain water Harvesting
structures are enclosed in Annexure-I. The indicative guidelines on different
kinds of RWHS, designs and model estimates are enclosed in Annexure-Il and
typical drawings in Annexure-Ill.
7. This is to be treated as "TOP PRIORITY'"
DR N SATYANARAYANA IASDIRECTOR OF MPL ADMN
Encl:- Annexure-I - District and ULB-wise targets
Annexure-ll - Indicative Guidelines on different kinds of RWHS, designs
And model estimates
Annexure-Ill - Typical drawing for Residential houses, Bores & other
Structures, Govt institutions, Public representative houses.
ToThe Municipal commissioners of all the ULBs in the State (through RDMAs)
Copy to all the Additional Collectors for Local Bodies in the State'
Copy to all the District Collectors in the State
t4.03.2020ffiidual buildings on their own
I L03.2020to
t4.03.2020
@Commissioners shall take up awarenes
oogrurn*. puruil.lly by conducting a meeting with public
atives of thl ULB for construction of RWH at thei
iouses firstii) Similar awareness progmm-es. shall be taken T, -Y1
WAs/SHG ,rrb.rr, Private schools / colleges'
.epresentatives of Religious places'
iii)TheMunicipalCommissioners,shallensurefol,ou.rug" of the piogtu*rne through press and loca
15.03.2020to
31.05.2020
mencement of construction work of RWHS and
omplete the same
File No.C DMA-M4/DLBI 41 2020 -M4 SEC-C DMA
Copy to the Engineer-In-Chief, Public Health, Hyderabad with a request to take
further necessary action and report compliance
Copy to the Director of Town & Country Planning. Hyderabad with a request to
take further necessary action and report compliance
Copy to the Officer on Special Dury, Hon'ble Minister for Municipal
Administration and Urban Development, T.S', Hyderabad'
copy submitted to the Principal Secretary to Government. Municipal
Administration and Urban Development Department, T.S., Hyderabad'
off suptdt to upload copy of it in the website: cdma.telangana.gov.in
tidDigitally signed
izz:to tst
Signatu
Yt''hF--r ,*=-S.No. Name of the Dist Name of the ULB5 No. of Households Hand Bores Others TotalResidential
^Bui!in8s
Public
representativehouses
Govt/SchooUC
cllege Buildings
Tank/Filterbeds
6 7 I 9 10 11 L2
\ 2 3 473 3 100 5 790
L laneaon 11388 559 40100 5 790
11388 569 40 73 3
t langaon911 10 200 10 13201
240000 12000 702 Waraneal(U) 10 200 10 13201
Waransal 240000 72009 70 9112 2t3 8 250 13 1708
2,2874 LL44 803 Warangal Rural
49 3 100 5 643Parka I 9L24 456 30
3508 30 r74 3 100 5 780
4 l\l1r<r m not 1015050 3 285
Wardhannapet 3600 180 20 30 2
5110 74
66
9 250 L4 23894 Mahabubabad 38641 7932
3 100 5 13906 Mahabubabad
Dornakal
Maripeda
23s25 t176 4050 3 290
4142 207 20 6 27
4986 249 20 0 2 50 3 3248
5988 299 30 n 2 50 3 3849 fhorru r
3 100 5 20505 layashankar t4250 7L3 40 1199
40 1199 3 100 5 206010 Qhnnelnellrr 1.4260 7L3
7LL7L5 5586 200 737 20 500 26 70696 Karimnagar
392 10 200 104635
11Karimnagar
Corpn.79082
3954 70
15230 762 40 108 3 100 5 1018t2 lammikunta
3 100 5 774
36313 Huzurabad 9351 468 40 158
3hoppandandi 4037 202 30 76 2 50 3
t43 2 50 3 279
15
7
llnth r na llrr 4015 20t 20
laeitval 76776 3839 L70 355 13 400 2L 4799
33322 1666 60 15 3 100 5 t84916 lasitval
30 3 100 :5
L284t7 Korutla 221L5 1106 40
970Metpalli 12056 603 30 229 3 100
1822 2 50 3 331
Raikal 4680 234 2019
20 60 Z6
50
200
3 35520 DharmaPuri 4603 230
10 29248 Qrirnnr-Sirrille 47550 2378 90 240
2t y'emulavada 73942 697 40 198 3 100 5 1043
33608 1680 50 42
]-3238
3 100 5 188022 Sircilla
L7 400 ZL
10
18043
1645
a4'
39
9 Peddaoalli 84536 4227 L40
23
24
Ramagundam6L32L
3056 60 13110 10 200
Peddapalli !2311 616 40 83 3 100 5
285 20 239 50 3
25 Manthani 5704
S.No. Name of the Dist Name of the ULBs No. of Households
Targets
Residential
Buildings
Public
representativehouses
Govt/School/College Buildings
Tank/Filterbeds
Hand Bores Others Total
3 4 6 7 8 9 10 11 12
20 6 2 50 3 34!26 Sulthanabad 5200 260
10 Khammam L26772 6339 150 298 18 450 23 7278
L64 10 200 10537L
27 Khammam Corpn. 985484927 60
sattupalli t0742 537 30
30
34 3 100 5 709
70 3 100 5 77529 Madhira 11348 567
30 Wyra 6t34 307 30 30 2 50 3 422
TLBhadradri(Kothagudem) 58888 2944 90 4384 L2 400 20
7850
31 Kothagudem 2L077 1054 40 1798 3 100 5 3000
32 Yella ndu 8844 442 30 2L 3 100 5 601
33 Manuguru 8110 406 10 9 3 100 5 s33
34 Palvancha 20857 1043 10 2556 3 100 5 3717
t2 Adilabad 48393 2420 60 558 3 100 5 3246
35 Adilabad 48393 2420 60 658 3 100 5 3246
13 Nirmal 48752 2408 110 25L8
35 Nirmal 27579 L379 50 92 3 100 5 7629
37 Bhainsa L4273 7L4 40 L44 3 100 5 1006
38 Khanapur 6300 315 20 72 2 50 3 402
74 Komaram Bheem 13186 559 40 15 3 100 5 822
39 Kagaznagar 13186 659 40 15 3 100 5 82,2
15 Mancherial 103777 5189 200 3589 L7 s00 27 9522
40 Mancherial 28080 t404 40 57 3 100 5 1609
4L Eellampally t4328 7L6 40 3499 3 100 5 4363
42 Naspu r 21770 1089 30 0 2 50 3 LL74
43 Chennur 6511 326 30 0 2 50 3 411
44 Kyathanpally 10298 515 30 1 2 50 3 501
45 Luxettipet 6561 328 20 !7 2 50 3 4ZO
46 Mandamarri L6229 811 10 15 3 100 5 944
t6 Ranga Reddy 27t198 13560 470 188 56 1300 70 15644
47 Pedda Amberpet 10050 s03 30 1 3 100 5542
48 Badangpet CorPn. 29559L478 40 1 10 200 10
L739
49 lbrahimpatnam 12687 634 30
40
10 3 100 5 782
U 2 50 3 136650 J a lpa lly 25426 t277
7 2
28
T.tgltt , r f
S.No. Name of the Dist Name of the ULBs No. of Households Residential
Buildings
6
Public
repr.:sentativehouses
Govt/School/College Buildings
Tank/Filterbeds
Hand Eores Others Total
7 8 9
10
10 11 t27 2 3 4 200 10 L743
294221800s
L471
900
50 2
51 Meerpet CglP!:_40 136 2 50 3 1131
52 Shadnasar0 2 50 3 726
L2826 647
1268
3053 Shamshabad
30 3 Z2
50 3 1356
54 2535350 3 749t
287L9 1406 30 055 Manikonda
0 2 50 3 1310Narsingi 24500 1225 30
56
0 10 200 10t752
30237 t572 3057Bandlaguda jagir
Corpn.20 0 2 50 3 308
5B+l 4550 233
3 5138750 438 20 0 2 50
59 0 2 50 3 407Ihukkueuda 6430 322
260
3060
20 35
544
2 50 3 3706t Amangal 5190
10 300 15 2227t7 Vikarabad 24534 1227 130
5 3481400 70 50
40
L20 3 100
62 Tandur248 3 100 5 LO79
63 Vikarabad 13565541
290 20
20
L76
0
2 50 3
64 Parigi 58002 50 3 2,59
65 Kodangal 3672 1486512980
577
1750
410
30
40
47
26
0
59 1300 59
18 Medchal-Malkajeiri 2595973
10
100 5 74!66 Medchal 11540
200 102010
,:
68
Boduppal CorPn. 35000
2 10 200 10L762Peerzadiguda
Corpn.30200 1510 30
30 0 10 200 101900
69IawaharnagarCoron.
33000
75932
1650
847 30
30
0 2 50 3 93270 Dhammaiguda
18 2 50 3 94477 NaRaram L6824 518
533 30
30
20
I9
0
2 50 3
72 pocharam 10657Z
2
50
50
3 54473 Ghatkesar 9172 459
3513
74
75
GundlapochamPally
8750 438
30
40
0 2 50 3 394Thumkunta 6175 309
0 10 200 102892
76 Nizampet CorPn. 52638 26320 2 50 3 773
Komnallv 12550 628 3077 2 50 3 903
16149 807 40 1
78 Dundigal
I-urkavamial
583
184
841
Residential
Buildings
Public
representativehouses
Gow/School/College Buildings
Tank/Filterbeds
Hand Bores TotalS.No. Name of the Dist Name of the ULBs No. of Households Others
7 8 9
18
g450
11
23
L2
73261 2 3 4 5
79 Nizamabad 125993 6300
70 223
88
10
3
200
100
104729
79Nizamabad
Corpn.84324 4216
5
5
3
13
5
5
3
z05
3
tt?41110
352
2456
1409
593
465
2860
964
369
493
385
80 Bodhan 17766 888 50
81 Armur 18866 943 4U50
250
100
100
50
350
100
82 Bheemgal 5037 252 20
20 Kamareddy 39188 1959 11U3
83 Kamareddy 23547 LL77 bU
B4 Banswada 8431 422 30
2985 Yellareddy 7270 361 20
ZL Yadadri Bhuvanagiri 42049 2102 160 zL5
86 Bhongir 13811 691 50 I
87 Mothkur 5038 252 20 42
88 Choutuppal 796t 398 30 10 I3
89 Alair 5530 277 20
20 15 2 50 3 31790 Pochampally 4536 227
20 0 2 50 3 3349L Yadagirigutta 5773 259
22 Suryapet 74293 37I,5 180 320 13 400 2t 4549
92 Suryapet 39728 1956 60 92 3 100 5 2ZL6
40 83 3 100 5 102093 Kodada 15786 789
94 Huzurnagar 9742 487 40 135 3 100 5 771
95 Neredcherla 3749 787 20 9 2 50 3 27L
96 Iirumalagiri 5888 294 20 0 2 50 3 369
230 703 77 500 27 727523 Nalsonda 115956 5798
97 Deva ra konda 9853 493 30 58 3 100 5 689
98 Nalgonda 4951,8 2476 60 160 3 100 5 2804
99 Miryalguda )7L65 1358 60 444 3 100 5 L970
213 20 0 2 50 3 288100 Nandikonda 4254
Chityal 15781 789 20 5
18
2 50 3 870
2 50 3 3s6702 Haliya 5262 263 20
103 Chandur 4133 207 20 17 2 50 3 299
3451 150 L75 t4 450 23 426324 Siddipet 59015
to4 Siddipet 39616 1981 40 70 3 100 5 2L99
105 Gaiwel 11616 581 30 27 3 100 5 746
30 24 3 100 5 537106 Dubbaka 7500 375
30 49 3 100 5 490108 Husnabad 6050
Targets , t I
180 355
19 3 100
25 2
126 8
64
33 3
2
13
3
2 50
50 3
33 2 50
101
303
Targerts
S.No. Name of the oist Name of the ULBs No. of Households ResidentialBuildings
Public
representative. houses
Govt/SchooUC
ollege Buildings
Tank/Filterbeds
Hand Bores Others Total
1 2 3 4 6 7 8 v50
600
100
3
32
5
292
5933
1540
109 Cherial 4233 21220
25 Sangareddy 90733 4537 25U
110 Sangareddy 22341 ttLT30 54 3 100 5 254
7LL SadasivaPet L240 62
724 10 128 3 100 5 970172 Zaheerabad 144AO
3L7 30 32 3 100 5 487113 Andol-Jogipet 6338
20 29 2 50 3 3031,74 Naravankhed 3982 199
3s3 30 4 2 50 3 442
494115 Bollaram 7069
Tellapur 8\71 409 30 0 2 50 3
2 2 50 3 L443117
26
Ameenpur 27712 13s6 30
Medak 34463 t723 110 L44 9 250 t4 2250
40 87 3 100 5 to77118
119
Medak 15831 842
Thoopran 7700 355 30 4 2 50 3 444
295 20 2t 2 50 3 3911"20 Ramayampet 5896
1.2L Na rsa pu r 4636 232 20 32 2 50 3 339
27 Mahabubnagar 81851 4093 90 229 7 200 11 4630
122 Mahaboobnagar s4974 2746 60 729 3 100 5 3043
890 20 0 2 50 1
3
955123 Bhoothpur 17800
t24Jadcherla(Badepally)
9t37457 10 100 2 50
622
87 7 200 11 137528 Narayanpet 19610 981 90
725 Naraya na pet 90t2 451 40 t4 3 100 5 513
126 Makthal 6658 333 20 45 2 50 3 453
127 Kosgi 3940 t97 5U 28 2 50 3 310
t5z9 7ZO t70 10 300 15 21.45
110329 logulamba Gadwal 30570
128 Gadwal 1644t 822 50 t23 3 100 5
30 31 3 100 5 482129 leeja 6256 313
130 Waddepalle 3900 195 20 5 2 50 3 275
199 20 11 2 50 3 285
2348131 Alampur 3973
30 Wanaparthy 33955 1698 130 L9Z 11 300 77
732 Wanaparthy 15420 777 40 85 3 100 5 1004
133 Kothakota 6962 348 30 0 2 50 3 433
t34 Pebbair 5149 257 20 98 2 50 3 430
198 20 4 2 50 3 277135 Atmakur 3958
Amarchinta 2476 724 20 5 2 50 3 204137
10 11
20 5 2
5L4
50 265 3
116
Targets!rl
S.No. Name of the Dist Name of the ULBs No. of Households ResidentialBuildings
Public
representativehouses
Govt/SchooUC
ollege Buildings
Tank/Fllterbeds
Hand Eores Others Total
3 4 6 7 8 9 10 11 L2I
29300 1455 tzo 364 t2 400 20 23873t
30 131 3 100 5 789136 Nagarkurnool 10404 520
279 30 49 3 100 5 456L3 I )ur 5570
Kalwakurthy 7325 366 30 166 3 100 5 670
30 18 3 100 5 456
1558s4139 Achant pet 6001 300
Total Telangana State 2389237 719462 4500 30358 426 11500 608
2
\taEarkurnool
138
ff
ANNEXURE-2
INDICATIVE GUIDELIN ES ON
DIFFERENT KINDS OF RAIN WATER
HARVESTTNG STRUCTURES, DESTGNS
AND MODEL ESTIMATES
Rainwater harvesting (RWH) is a process of collecting, conveying, and storing the rainfall
in an area for the beneficial purposes. Considering the problems of water scarcity, pollution in
existing surface water bodies, and floods during rainy seasons in Karimnagar; the adoption of
rainwater haruesting practices is quite necessary and need of the hour. The methods involved
in this practice are simple and can be maintained at a minimal cost. Besides this, rainwater
harvesting is also very attractive because Karimnagar is having a good potential for harvesting
rains. Rainwater harvesting does not only improve the water usage practices, rather it is also
helpfut in the groundwater recharge. Considering the depletion of groundwater resources due
to excessive pumping of water, and its pollution from the leachate of waste dumping sites and
agricultural lands, replenishment of groundwater resources is also necessary. In view of this,
the present study focuses over the need, methods, detailed procedure for the establishment
of RWH system, and cost analysis for rainwater harvesting etc. The study also helps the people
to judge the best way to use the harvested water as per their need, geography of the area,
sub-surface geology, and prevailing local conditions. Along with this, some of the challenges
in the process have also been discussed at the end.
Water is one of the basic necessities of every living being for their suryival. Despite being
renewable, water is also a finite resource and therefore, needs extreme precautionary and
judicious use of it. Out of the total water available on the planet, only 3olo is fresh and can be
used for drinking purposes. However, the available fresh water is distributed very unevenly,
rendering serious implications on the steady supply across the globe. Moreover, with
increasing population, increasing urbanization, expanding agriculture, and rising standards of
living, tlre water demand has now touched a new arena, where it is getting difficult to meet
even the essentialities.
Natural replenishment of ground water reseruoir is a slow process and is often unable to keep
pace with the excessive and continued exploitation of ground water resources in various parts
of the city. This has resulted in declining ground water levels and depletion of ground water
resources in such areas. Artificial recharge efforts are basically, aimed at augmentation of the
natural movement of surface water into ground water reservoir through suitable civil
construction techniques. Such techniques interrelate and integrate the source water to ground
water reseruoir and are dependent on the hydrogeological situation of the area concerned.
Occurrence of rainfall in the city is mostly limited to about three months in a year. The natural
recharge to ground water reseryoir is restricted to this period only in a major part of thecity.Attificial recharge techniques aim at extending the recharge period in the post-monsoon
season for about three or more months, resulting in enhanced sustainability of ground water
sources during the lean season.
During the rainy seasons, it is often seen that roads get flooded while during the summers,
acute water shortage is faced by the dwellers. Although the cities receive good amount ofrainfall, still the problem of flooding during monsoon and droughts during summers has
become a very common phenomenon. This is because of the fact that the rainfall usually
occurs for short duration but with high intensity. Such conditions result in the heavy flow ofwater leaving very little amount for the recharge of groundwater. Thus, groundwater does notget chance to replenish
Considering this situation, the rainwater harvesting (RWH) technique has emerged as a boon.
Rainwater harvesting is a process of collecting, conveying, and storing the rainfall in an area
for the beneficial purposes. The collected rainwater can either be stored or it can be usedforrecharging the ground water depending on the needs and other factors. The collection of rains
can be done from rooftops, land surface, catchments/watersheds etc. using a number ofmethods. According to an estimate, for an average rainfall of 1000 mm, approximately 4million liters of rainwater can be collected in a year from an acre of land (i.e. 4046 m2).Therefore, in a city like Karimnagar which receives an appreciable amount of rainfall, adoption
of RWH technique may prove to be a savior.
Basically, the water harvesting methods can be classified into two:
3.3.1 Surface Run-Off Harvesting
During heavy downpour, the water flows away as sudace runoff. This runoff water can be
collected and used for recharging aquifers as shown in Figure 3-1.
Surface run-off rainrvater harv
,tir',,
t'll:tl ,,,l,l
lltttttalt,,
I,,' Infiltration excess
overland florvsurface
layer
Water table
**,i,.,$'fi o o non ra io nv *te r r, a rvestin g
FIGURE 3-1 METHODS OF MINWATER HARVESTTNG
Land surface
Saturated
3,3.2 Rooftop Harvesti*g
The amount of water harvested depends on the frequency and intensity of rainfall, catchment
characteristics, water demands, how much .u,ilff o..rrs and how quickly or how easy it is for
the water to infiltrate through the subsoil and percolate down to recharge the aquifers. In
urban areas, where adequate space for surface storage is not available and water levels are
deep enough to accommodate additional rainwater to recharge the aquifers, roof top
rainwater harvesting is the ideal solution to solve the water supply problems.
Though the concept of roof top rainwater harvesting is an age old one, systematic collection
and recharging to ground water is of recent times. Recent developments in the field ofhydrogeology especially in ground water exploration resutted in efficient and scientific design
of ground water recharge structures. As surface water sources fail to meet the rising demands
of water supply in urban areas, ground water reseryes are being tapped and over-exploited,
resulting in deciine in ground water levels and deterioration of ground water quality. This
precarious situation needs to be rectified by immediately recharging the depleted aquifers. In
urban areas, the roof top rainwater can be conserued and used for recharge of ground water.
This approach requires connecting the outlet pipe from rooftop to divert the water to either
existing wells/tube wells/borewell or specially designed wells. The urban housing complexes
or institutional buildings have large roof area and can be utilized for harvesting roof top
rainwater to recharge aquifer in urban areas. Table 3.1 shows availability of rainwater through
roof top rainwater harvesting.
In this system, the roof itself becomes the catchment and rainwater can be collected from the
roof of the house / building (Figure 3-1). The water can either be stored for utilization or itcan be divefted to an artificial recharge system. In this method, water can be collected without
much expense. This method is highly effective, and it can also help in the recharge of ground
water level.
TASLE 3-1 AVAIUBILITY OF RNNWATER THROUGH ROOF TOP RNNWATER HARVESNNG
no;iiop Harvested water from Roof rop (m3
Area(sq.m')
201.63.24.86.48,09'612'B16tg'}72'425',628'837:.
.302.44,87.29.612,tr4'419'224::28'833'6381443'248
403.26.49.612'816Ig.225.63738'444,85L.257,664
504.08'0.'.721620.243240.,4856647780
604'89'614,4tg,z2428'838.44857.667'276.886.496
llt
iii---
806,412.8tg'z25.63238'45t,26476,889.6L02.4115.2128
:
705.611,216,822.42833'644'85667'278'.489.6100'8L12
B0 6.4 I/.8 LY'/ /)'o JL Jo'T JL'L u I
ris'z LZs'6 L4490 7.2 tA.A 21.6 2B.B 36 43'2 57 '6 72 , 86'4 100'890 7 .2 t4.4 21.b ZU'U J0 15'z f,/ 'o ',' . ev' f
100 8.0 16 24 32 40 48 64 B0 96 ttz t2B 744 160
150|2743648607796120L44168t92216240
200163248648096128160t92224256288320
25020406080100120i60200240280320360400
30024487296120144tgl240288336384432480
4003264.96128.160.|g2256320.384.4485L2 576.640
5004080120160200240320400480560640720800
Rainwater haruesting system includes the following components:
3.4.1 Catchments
The area or surface which receives the rainfall is known as catchment area for rainwater
haruesting (Figure 3-2). It may be rooftop, courlyard, open ground etc. In the simplest
method, rainwater is collected in vessels at the edge of the roof / open ground. Moreover,
gutters may also be used at some places which drain into the collection vessel with the use
of various pipes. Sometimes, the collected water is also passed through the settling tanks for
the suspension of settleable particles before the collection in storage tank for domestic use.
In rooftop catchment, the amount and quality of rainwater collected depends on the area and
type of roofing material. As per the Indian standard guidelines for rainwater harvesting,
rooftop water may be collected from roofs constructed with galvanized ironsheet, aluminium
sheet, deleterious glass fibre sheet asbestos cement sheets, tiles, and slates etc. Bamboo
gutters and thatched roof may also be used as rooftop material for the collection of water if
these are covered by waterproof sheeting like food grade low density polyethylene films. To
obtain the fresh quality of water, the roofs having metallic paint, or any other type of coating
should be avoided. The catchment area should also be cleaned on regular basis to remove
dust, leaves, and bird droppings so that water quality can be maintained. Only non-toxic paints
should be used in case the water has to be collected from painted roof. Moreover, water
collected from roofs painted with toxic materials should not be used for potable purposes.
If the catchment area is a land surface or ground, then water can be collected in reservoirs
using drainpipes. As compared to rooftop catchment, it is easier to collect rainwater fromthe
ground surface or open area. However, in ground surface catchment, there is the possibility
of water infiltration into the underground reservoir. Therefore, water collection after the rain
Source: Central Ground Water Board (CGWB)
should be irnmediate and sufficient measures sl'rould be taken to reduce the infiltration to the
ground.
3,4.2 Gutters (Drains) and Down take Pipes
Gutters and down take pipes are essential for taking up the water from catchment area to the
storage tanks as shown in figure 3.2. The materials to be used for gutters, as per the Indian
standard guidelines for rainwater harvesting, are galvanized iron sheet, wood, bamboo, or
reinforced cement concrete. For the construction of down take pipes, galvanized mild steel,
cast iron, and high-density polyethylene material may be used. The downpipe should be at
least 100 mm diameter with 20 mesh (850 p) nylon wire screen at the inlet in order to prevent
dry leaves and debris from entering into it [3, 4].
: 1. Catt.hntetlt area
i}'C.itrtter
,'3, Dount:rlie pipe
fi St<lr;rge tauk (imnrccliatc usc)
l-i' I)cliverl' pipe
i..6. Irirst fhrsh
:,i-'St<lrag-c t;ulk (hto rrsc)
:,9 l"iltcr tlevit-e
i 9,Ilc'charge rrell
FIGURE 3-2 COMPONENTS OF MINWATER HARVESNNG SYSTEM
3.4.3 Filters and First Flush Devices
These devices remove grit, leaves, and dirt which are often found in the first rains. It is
necessary to remove these from the water as it may contaminate the whole water of the
storage tank. Sometimes, these devices are also useful when rains occur after a long time. In
such conditions, the rainwater carries with it, various dissolved pollutants. Materials such as
gravel, sand, or coconut, palm, or betelnut fibre, etc. may be used as filter media. Filters and
first flush diveft the water from the first rain to avoid mixing of it with the water of storage
tank (Figure 3.2).
3.4,4 Storage Tanks
These tanks might be either above ground or underground or partly underground as indicated
in figure 3.2. The tank should always be covered so that water should be clean. The storage
tanks may be made up of reinforced cement concrete, masonry etc. The size of the tank
depends upon factors like daily demand, duration of dry spell, catchment area, and rainfall.
Underground storage tanks should be suitably lined with water proofing material and
preferably have a hand pump installed for withdrawal of water. Their top should remain at
least 300 mm above the ground [3, 4]. Prior to the use of storage tan( it should be thoroughly
cleaned and disinfected using chlorine, bleaching powder, and potassium permanganate etc.
Measures to ensure the cleanliness of water can also be kept in the storage tanks for periodical
disinfection so as to prevent the growth of pathogens.
3.4.5 Delivery Systems
There should be efficient piping system which can deliver the stored water for the end use.
In the absence of any treatment, rainwater should be avoided for the consumption and
cooking. However, it can be used for other purposes. To be used for consumption,
conventional water treatment is necessary. Leaking and rusted pipes should be avoided
completely. To avoid any leakage, timely check-up of the pipes is necessary.
3.4.6 Recharge Structures
Haruested rainwater can also be used for charging the ground water aquifers through the
construction of various kinds of structures like dug wells, borewells, recharge trenches, and
recharge pits (Figure 3.2). There may be different depths in recharge structures, such as
depth can be such that water reaches to lower soil strata. Examples of such structures are
recharge trenches, permeable pavements etc. In other case, the depth of the pipe down in
.;
the soil can be such that it reaches to the level of ground water and joins it. Examples of these
kinds of structures are recharge wells. Nevertheless, for recharging the groundwater aquifers,
the possibility of contamination from nearby areas should be thoroughly checked and
accordingly changes may be made in the designing'
On an average, Karimnagar town receives around 907 mm rainfall in a year out of which' 80
- gao/ois received only during monsoons. Even though rainwater is the only major source of
Karimnagar town water need, its collection and significance is highly neglected in Karimnagar'
Although the total amount of rain which is falling on the earth cannot be collected due to
evaporation losses, spillage etc., but still a fair amount of it can be put into use' The total
amount of water that is received in the form of rainfall over an area is called the rainwater
endowment of that area. However, out of this, the amount which can be effectively
harvested is actually called as the rainwater haruesting potential' In urban areas where
the open grounds are scarce, rooftop rainwater harvesting is suitable option whereas in rural
areas and outskirts of the city, surface runoff or a combination of both the methods may be
used.
Rainwater harvesting has several advantages as given below:
i. In areas where there is inadequate groundwater supply or suface resources are either
lacking or insufficient, rainwater harvesting offers an ideal solution'
ii. Rainwater is bacteriologically pure'
iii. It is free from organic matter and soft in nature'
iv. it will help in reducing the flood hazard'
v. It improves the quality of existing ground water and helps to replenish it'
vi. It reduces the cost for pumping of ground water'
vii.
vilt.
lx.
xi.
xii.
xlil.
It helps to meet the needs of already water scarce society.
It also reduces soil erosion in urban areas.
No land gets wasted for RWH and hence there is no issue of population displacement.
Rainwater may be harnessed at place of need and utilized at the time of need.
The structures required are simple, economical, and eco-friendly.
The technique does not require rigorous manpower,
It helps in utilizing the primary source of water and prevents the runoff from going
into sewer or storm drains, thereby reducing the unnecessary load on treatment plants.
Adoption of rooftop rainwater harvesting followed by its storage through artificial recharge
methods at household level could be a viable strategy to locally tackle the growing water
scarcity problem that is prevalent in most of the towns and cities of India. Artificial
groundwater recharge methods can be adopted in urban areas where:
Groundwater level occurs at a depth of 5m or more;
Permeable strata are available at shallow or moderate depth;
Groundwater quality needs improvement;
There are possibilities of saline water intrusion in coastal areas; and
Evaporation rate from surface storage will be very high.
The AR techniques described in the previous section are more suitable for large-scale RWH
projects with huge catchment area. They may also be appropriate for institutional campuses
with Large rooftop as well as open suface area. Many simple and low-cost AR techniques
have been developed and practiced to encourage households to adopt RWH practice. The
methods prescribed for adoption at household levels are mostly the simplified forms of the AR
techniques described earlier. These include:
a
a
a
a
a
1. use of abandoned or in-use dug wells;
2. use of abandoned or in-use hand pumps;
3. use of recharge Pits; and
4. use of recharge trenches
3.7.1 Abandoned or in-use dug wells: -
Dry and unused or in-use weils in the buildings can be used as rainwater recharge structure
(Figure 3-3). If abandoned well is to be used, it is essential to clean the bottom surface of all
fine deposits. The rooftop rainwater has to be guided through a pipe to the bottom of the well
or below the water level to avoid scouring of the bottom and entrapment of air bubbles in the
aquifer. It is preferable to make the collected rainwater silt-free by passing it through a silt
trap (gully trap) before recharge. Periodic chlorination is recommended to avoid bacteriological
contamination.
ABA}IDOHEE 11'CtL
YfATER CfitlI,I-BER
CAFIY*s.S FiFE
l0O rn m DIA
CLAY LAT€ft
n*uor*
FIGURE 3-3 DLIG WELLS FOR ARTIFICIAL RECHARGE
3.7.2 Abandoned or in-use hand pumps:
In this case, hand pump (abandoned or in-use) is adopted as the rainwater recharge structure.
The rooftop rainwater is diverted to the suction pipe of the hand pump through a small
diameter pipe (50 mm or 100 mm) as shown in Figure 3-4. A gate valve would require to be
fitted with the rainwater conveyance system to avoid entry of air into the suction pipe. A small
collection tank in the rainwater conveyance system can act as silt trap as well as a balancing
tank. During recharging period (rainy days), the water extracted from the hand pump should
be used after boiling or chlorination.
FIGURE 3-4 ARTIFICIAL RECHARGE THROUGH HAND PUMPS
YE- 1.,
. t- :t!
!!
si
!,i
$*TEfi EfI*A{EEF.ll t t '*, a.t
"
I
t l't, '
' t a
!{i rnn, BIA FpE
r3'- -r' I.t
I.
'a', -' 1?tI t
- t _r
,l " .oE s0tt
1 trr,'t f,n rlr r ,q.s I
;--*-!LAt LTTEE
':. .'--i:' .---- .-T=Ti,''-'f., * 4'.. q.'1,i0".*Lrj-.-k'!j-
ffiH
-?:7j. Recharse .P.jFj_-
Recharge pits are useful when the harvested rainwater is to be fed to shallow aquifer (4 to B
m) (Figure 3-5). At household level, recharge pits are generalty constructed 1 to 3 m sides
and 2 to 3 m deep. The pits can be of any shape, i.e. circular, rectangular or square' After
excavation, the pits are refilled with coarse gravel, pebbles and boulders' The fillings can
function as a roughing filter to remove suspended impurities, if any, in the collected rainwater'
FIGURE 3-5 RECHARGE PIT
G"L
B=lTfiXm["tTSIm
!*J&TEfl *
+ r + *q q I*r'1'+ q +lffi-.'f \E
'.{rri}
,J.fffi,{1i ':r.} l..':'-!l / ij;.rr.".;;:{i:' * ;i' ::;j., i ;Lt,,'"ii- :i. ;:'.,:{ i}. ':.T t ";i,i'L:.r,;,,it:;;
;1:1-;l:
[-ruffIf$#$c.:liftgr rER gft ".ry TE E'lB EJ n
LH LF guqll%F..fi-3..s!E-.H._ii*'-'"*@
E;:f[tl;)i\$:;lr=-\'tt"- *ffi
Rechatge Pits are constructed for recharging the shallow aquifers. These are generally
constructed 1 to 2 m. wide and 2 to 3 m. deep. After excavation, the pits are refilled with
pebbles and boulders as well as coarse sand;"Thd excavated pit is lined with a brick/stone wall
with openings (weep-holes) at regular interuals. The top area of the pit can be covered with
a perforated cover.
.; -l .2rn --)Design procedure is the same as that of a settlement tank. The
size of filter material is generally taken as below:
Coarse sand
Gravels
Boulders
:1.5-2mm
:5-10mm
:5-20cmL1 L.
Vu*r^" S*C
Grolej 5, 1'Jr1- -s.Jr
The filter material should be filled in graded form. Boulders at
the bottom, gravels in between and coarse sand at the top so
that the silt content that will come with runoff will be deposited
on the top of the coarse sand layer and can easily be removed.
If clay layer is encountered at shallow depth, it should be
punctured with auger hole and the auger hole should be refilled
with fine gravel of 3 to 6 mm size.
1ili)rrtn d;i) hort fillt".! '.vith
Gra +el O.l-CtFirnrn size
SECTION
a
a
Recharge pits 1 to 2 m wide and 2 to 3 m deep are constructed to recharge shallow
aquifers.
After excavation, the pit is refilled with boulders and pebbles at the bottom followed
by gravel and then sand at the top.
The collected water from the rooftop is diverted to the pit through a drainpipe.
Recharge pit can be of any shape i.e. circular, square or rectangular. If the pit is
trapezoidal in shape, the side slopes should be steep enough to avoid siltdeposition.
This method is suitable for small buildings having the rooftop area up to 100 sq.m.
PLAN
(: - ;-.
.7rr
03m
i
Recharge trenches can be adopted when permeable soil strata is available at shallow depths
(less than 1.5 m). These are trenches of shallow depths (0.5 m to 1'5 m) and 0'5 to 1 m wide'
As in recharge pits, the trenches also are filled with coarse gravel, pebbles and boulders'
FIG{JRE 3-6 RECHARGE TRENCH
Recharge trenches are constructed along the boundary walls of households, or across the
landscape where open space is available (Figure 3-6)
frJl ,ti
f
REqtffitrE iEEHcti Fll'LEO
UfiItT HOI}LBEftE
EEULDERE:Bt
,Be0-ETfttH.E,i.0T0 15K Fn-*t
SEEIt0r{ A'-AI
3.s.i Alternative-I, Conventional Rainwater Harvesting System :
For assessment of quantity of rainwater that can be harvested, estimation of roof catchment
area and the rainfall are required.
Total roof catchment area = A m2
From data published by the Meteorological Department of India, the annual average rainfall
in Karimnagar has been adopted as 907 mm.
The total quantity of rainwater that can be harvested annually is = Catchment area X Annual
rainfall X Runoff coefficient
For the design of aftificial recharge system, critical rainfall scenario has to be considered. The
rainfall data of Karimnagar over the previous decades indicates that on an average, there are
27 rainy days in a year. However, about 75o/o of the rains occur within a period of three
months (july - September), with maximum rainfall during the month of July, which accounts
for 30% of total annual rainfall. Even during the rainy months, rainfall may be occurrlng only
for a few days.
For the purpose of assessment of critical rainfall scenario, it has been assumed that out of 27
rainy days in a year, the number of rainy days in the critical month of July will be in the same
proportion as the quantum of rainfall during the month, That is, 30o/o of the27 rainy days will
fall in the month of July. With this assumption, the (maximum) quantity of rainwater that will
be harvested and utilized for groundwater recharge during the critical month been calculated
as below:
(i) Average rainfall during the month the month of July = 3Oo/o X 907 = 272mm
(ii) No of rainy day in July
(iii) Critical rainfall per day (with safety factor 2)
= 30o/o X 27 =8 days
= (27218)X2 = 68 mm
(iv) Maximum quantity of rainwater haruested in a rainy day of July
=Catchment area X rainfall X 0.9
Because of the highly permeable, alluvial soil strata, a gravel filled artificial recharge pit
combined with two no's of gravity-fed injection bores has been envisaged as the recharge
structure for Karimnagar city. The details of the recharge system installed are schematically
presented in Figure 3-7.
STANDING WATER - .
COARSE SAND OF 1.5-2-0 mm-'
1.00
050
0.50
0.50,VELS 5-10 mm
BOLILDE-RS 50-200 nrn.'.
200 mnr Dia BORE FILLED..WITH GRAVELS 3.6 MM
FIG Il R E 3 - 7 SCH E MATI C OF TH E REC HA RG E P IT CO M BI N E D WITH G MVM F E D I M E CTI O N BO R E
The recharge pit has been filled with four layers, top layer is kept empty for standing water
to create the head on water, the layer below the standing water filled with coarse sand of
size 1.5-2.0 mm with 35o/o porosity, layer below the sand is filled with gravels of size 5-10 mm
with 30% porosity and bottom layer with boulders of size 5-20 cm with 30o/o voids, which acts
also as a roughing filter to effect primary level treatment to the collected rainwater before
recharge.
The depth of standing water above sand bed is considered 1,0 m, the depth of coarse sand
below the standing water is 0.5 m, the depth of gravel bed below the sand bed is 0.5 m,and
the depth of boulders below gravel bed is 0.5 m.
The equivalent liquid depth in the trench
1+ (0.5 x 0.35) m + (0.5 x 0.3) m +(0.5 x 0.3) m
= L.475 m
Therefore, Area of the trench required for spreading =Volume of rainwater / liquid depth
Based on the area available at the location selected for the recharge pit, the size of the trench
shall be fixed as L m x B m x D m.
Additional area requirement has been offset by providing two gravity fed injection bore well
of 0.20 m diameter. The bore well is encased with slotted PVC pipes of 0.15 m diameter for
structural support and prevention of clogging. The depth of the bore well is 10.0 m at which
level groundwater table found in this area.
The injection bores will increase the recharge capacity of the trench by about 50o/o. The
additional recharge capacity so obtained can take care of abnormal exigencies, and any future
expansion of catchment area. By ensuring faster rate of infiltration, the injection wells will also
help minimize evaporation losses of the harvested rainwater.
Design parameters for setdement tank:
settlement tanks are used to remove silt and other floating impurities from rainwater.Settlement tank is like an ordinary container having provision for in flow, outflow and overflow.Settlernent tank can have an unpaved bottom suface to altow standing water to percolateinto the soil' Apart from removing silt from water the desilting chamber acts like a buffer inthe system.
For designing the optimum capacity of the tank following aspects have to be considered:
i. Size of catchment
ii. Intensity of rainfall
iii. Rate of recharge
Since the desilting tank also acts as buffer tank, it is designed such that it can retain a certainamount of rainfall, since the rate of recharge may not be comparable with the rate of runoff.The capacity of the tank should be enough to retain the runoff occurring from the conditionsof peak rainfall intensity. In Karimnagar Peak hourly rainfall is 46 mm. The rate of rechargein comparison to run off is a critical factor. However, since accurate recharge rate are notavailable without detailed Geo-hydrological studies. The rates have to beassumed.
The roof top catchment area available for rainwater collection at Gps-URDHU-MUKHRAMpuRAschool has been calculated from the building plan drawing as given in Figure 3-9. The capacityof the recharge tank is designed to retain runoff for at least 30 minutes of rainfall of the peakintensity (for Karimnagar 23 mm per 30 minutes)
The data for a Govt School
Surface area of the Roof Catchment (A) = 340 Sq.m
Peak rainfall in 30 min (r)
Runoff co-efficient (C)
=23mm
= 0.85
Capacity oftank = A x rx C = 340 x 0.023 x 0.g5 = 7 cum
Assume Capacity of tank is 10 cum = 10,000 Liters.
Typical drawing of the new rainwater harvesting structure and its section are given in Figure
a
3-9 and Figure 3-10. schematic layout of rainwater routing to RVIHS for Govt Schools is
given in Figure 3-11.
dtF
Vfater Recfiarqe Tsilt
FIGURE3-gTYPIaLDMWINGoFNEWMINWATERHARVESTTNGSTRUCTURE
Rrh Flltlt
Fnrr Etrlntg E3 lcr zts Gq
ult*r cclHild*umltr
co+drntr.$ f., BOA
I EOdi Jrnna 3rd
tStmStrE llEEoEl!:'mfi$*omm dfrhll:rt!
4G9IE6?c. -, erYc
.- . ' -
'
!,ia:eipercdote llt-ltlEn
3taalt !!6c9.!.
eorE r+pBr 301,'sLt AbTdE suHo( leYel
Recharge Tank Cross Section
FIG:JRE3.ITwilaLSECTI,NoFNEWMINWATERHARVESmNGPIT
{rPVC 160mfii pF\E lEEmrn gPVC l€0 nrn'r
UERANAAH
t
tltt l; r
ELEVATION
FIGURE 3-11 SCHEMANC UYO{.JT OF RAINWATER ROUNNG TO RWHSThe standard sections for roof top rainwater haruesting structures are as follows
ROOF TOP RAIN WATER HARVESTING STRUCTURE-IO,OOO LtS
l nmPstu lPVC rrp+
30(}nhhtfi4.d s&,raalrr.gd !p{o 3&n
s=cncr{ A+
+ ra:j". j1s60,
ir1
RocF iop RAttt lvrtER t-nn 'esnxc stmrcrune-zo.ooo .t
t:am FtrsgdalcPF
sG6aaEt*rmtffi4fi !e asi
scrEl{ A-A
Detailed estimate is prepared for 10,000litres and 20,000litres capacity roof top
Rain Water Harvesting Structures . The tentative rates are presented below .
Type designs for open areas in Municipalities like parks, playgrounds
and other government office premises:
The detailed type designs are prepared for the rain water harvesting pits to take up in Public
parks, Grave yards and other open places in ULBs . The detaits of Different types of RWH
Structures Drawings are shown below.
Sl. No Size Capacity Cost
1 3.5mx1.64x1.74m 10,0001it Rs.3.B0lakhs
2 5.48mx2.05mx1.74m 20,0001it Rs.5.20Lakhs
TYPE-I DESIGN FCP F}.II,{ I\iATEF. HAF,'iESI}IG SIflUCIURES IN ULBS
{:r:x 4i,i HCr:
aNi -25 NE
All Dirnensions ore in 'rnm'
L-I']JI ).4#+T ErtrE | ffi'**""ot
Llffa,ffift a*r lrta. Ss R
2Jttrtn ltL Enclr* h O(l-6iiad rb:s Troiiqrrl &ida
{f'tq.tqir,t tlr,n Til n C! (ljlRCC PdiuutEd 4@r{o0ratrncdch$ Crffi
flsl r* l"'el'zl
\F :f --:
16X 1t* XCC
toar {5 ,t6
nfi Pd'dd.d {oft+-r-$5om&ttitCffi
Pct 0:t$),5 m ltt
in a0rs Ld
Fl* I * l-egiEi. iT lj-'l
--t__
l,{*l_ ,", l.,otl:,E. ;I i-:_r
IYPE -ll DESIGN FCR FIAIN t'iATEi HARVESIIN$ STRiJCTiJRES lN ULBs
&i*dirih ql,il
2J0m Il* &i*rut h Cu(t.6)tJ cb* Irodr.irx/ &kh
(kqht 12m Il* h CI (lr3)
AI Oimensicns ore in 'rnm'
r100r
_r)u*-UlHH:Erlr{!rhfr
.:E, "T :_;
tll Jimensirns ore in 'r:n'
rlilrl-J+*+-"z r.rfrI I ffi--i{B rt '< FF
1Fflil LiW!H
Eg_Lrituu
Detailed estimate is prepared for Type-I, Type-II and Type-III rain water haruesting pits.
The tentative rates are presented below.
Sl. No Type Size Cost
1 Type-I 1.5m x 1.5mx1.5m Rs.21,000
2 Type-II 1.5m x 3.0mx1.5m Rs.35,000
3 Type-III 1.5m x 4.5mx1.5m Rs.49,000
It"is proposed to adopt the above type designs for taking up RWH Structures in
all Municipalities/ Corporations on a mission mode.
Dt C'i*{d n Cr{li)
n'* I * l*l'{:Ei: rI l-i
a
l'rPE iEstSr"i-flt r0,? RAtit tilATtR t+g.,tsllic STRIJCIURES t|i uLBi
ROOF TOP R/qIN WATER HARVESTING STRUCTURE-1O,OOO LtS
16ommuPVC pipe
Water collection chamber
oo
ortts
o6400 gsm
Geo textile io{R,r3
N
SECTION A.Adepth upto 30m
RWH module/tank
160mm PerforatedPVC pipo
Stone Aggregate
ROOF TOP RAIN WATER HARVESTTNG STRUCTURE.2O,OOO LtS
PLAN
Wal.r coll.clion chamblr
o
400 g!m lot3IRr.3
Geo lextil€
RwH modulc^ankSrnd
Slonc Aggrcgato
160mm PorforatedPVC pip.
300mmlillcd wilh grav€ldcpth upto 30m
SECTION A-A
1400tI )t-otww,
8Tm*-L IETTIIL 5 ogstuics 50mmt
R'CC Covrr ('l:2r4) 50mm IHX
230mm Thk Brickwork in CM(1:6)
2nd closs Troditionol Ericks(Plostering 12mm I}k in CM (1:3)
RCC Perforoted 400x400x50mmCotchpit Covers
Ilr,r
PCC (1:3:6)
75 mm llkin 40mm Metol
lzid mo I rsoo l-, Frrl
-
SEC. AT A_A
hdsool rsoo lmohsd
SIC. AT B_B
TyPe PIT SIZE OFFSET No. of RCC Covers
I 1500 X 1500 mm 300 mm 5x5 (2s)
ll 3000 x 3000 mm 400 mm 5x9 (4s)
It 4500 x 4500 mm 450 mm 5 x'13 (6s)
1s Brickworkwide obove
400x 400 RccCovers -45 Nos
ts Brickrorkride obove
All Dimensions.rt
ore tn mm
r400t_l2rat ootr,,w
sl ry;:H'nOC Cdr 0+..) 50nn Iil
230mm Thk Brickwork in CM(1:6)
2nd closs Troditionol Bricks
(Plostering 12mm thk in CM (l:3)
RCC Perforoted 400x400x50mm
Cotchpit Covers
PCC (1:3:6)
75 mm thkin 40mm Metol
hsd+ool som l+oo[s{
--l--
Fi''l ''' PPlSEC, AT A_A
SEC. AT B_B
400x 400 RccCovers -65 Nos
Openings Brickwork
widc obove
All Dimensions.tl
ore tn mm
1I
__l
r400tI )t-as aowar
sT F[pf-ro* ritl P\r Prp*_L E[51\ 5 oFdwc. 5lhtnt
Thk Brickwork in CM(1:6) RCC Perforoied 400x400x50mmCotchpit Covers2nd closs Troditionol Bricks
'l2mm Thk in CM (1:3)
PCC (1:3:6)
75 mm Thk
in 40mm Metol
n3or 450 I orro I oso lrsol
'
SiC. AT B-B
hsdsool rsoo lsoohd
SEC. AT A-A
10 Cum Ca@city
Abstract Estimate for Rooftop Rain Water Harvesting - 10,000 Litres Capacity
work excavation for foundations and depositing on bank for all lifuan initial lead of 10m including all operational, incidental, labour
such as shoring ,sheeting, planking, strutting, etc. complete for finishedwork including seigniorage excluding dewatering charges etc as per SS -
3 Upb 6 meters depth
filling in foundation trenches as per drawing including watering,etc., complete and technical specification Oause 305.3.9 MORD
with Aggregate of size 20 mm filling in foundation trenches as
including watering, tamping, etc.. complete andClause 305.3.9 MORD & 304 MORTH
Constructioon of Brick Masonry (Fly ash) with CM(1:6) brickstrength of 50 kg/sq.cm - 15:1289.1-199) - CLASS - 7.5 23x11x7
@st and conveyance of all materhlE labour charges,scaffoldingetc., complete as directed by Engineer-in-charge
BLD.CSTN.3.13
M- 20 Nominal mix (Cement:fine aggregate: coarseto Table 9 of IS 456 using 20mm size graded machine
granlte metal (coarse aggregate) ftom approved quarry including
convyance of all materials like cement, fine aggregate (sand)
water etc., to site and excluding Se'rgniorage charges, salestaxes on all materials including all operational, incidental and
such as machine mixing, laying concrete, curing etc.,completecost of steel and its fabrication charges for finished item of
fitting and placing FE-sm bar reinforcement inas per drawings and technical specifications Clauses 1000 and1100, 1600 MORTH for Bars below 36 mm dia including over
as per BIS:12592 (Part 1&2) Supply,Delivery and Fixing ofcovers and frames with ISI marking anywhere in T.G., F.O.R.
including, loading, un-loading & stacking at site but excluding all
as applicable. M.D. -10 with 500mm diaclear opening
Boring/drilling bore well of required dia for casing/ strainer pipe, by
method prescribed in IS: 2800 (part I), including collecting samples
different strata, preparing and submitting strata chart/ bore log, including
running chargesall equipments, tools. planE & rnachineries required for the job,
as per direction of Engineer-intharge, upto 90 metre depth
Analysis from DelhisoR 23.1.1.1
assembling, lowering and Frxing in vertical position in boreF/C medium well crsing (CM) pipe of required dia,
to IS: 12818, including required hire and labour charges, fittings &etc. all complete, for all depths, as per direction of Engineer -in-charge.
160 mm nominal size dia
Supply,Lowering & fixing of Unplasticised PVCS Pipes for potable
supplies conforming to IS : 49852000 (3rd revision) with bell ends
as per specification in light Grey/Natural Ivory Grey/ Any other Color
White) inclusive of transportation to the sub-divisional stores
110 mm nominal size dia
160 mm nominal size dia
packing in tubewell construction in accordance with IS: 4097,gravel fine/ medium/ coarse, in rcquired grading & sizes as
requirement, all complete as per direction of Engineer-in'charge.
10 Cun Capacity
DSR Analysis 23.13.1and fixing suitable size threaded mild steel cap or spot welded plate
the top of bore well housing/ casing pipe. removable as per requirernent,@mplete for borewell of:
and fixing Bail plug/ Bottom plug of required dia to the bottomassembly of tubewell as per IS:2800 (part I).
and flxing ot non woven geotextile having thickness of 400 GSM,minimum tear strength of 250 ASTM D.1533, Width wise aueast 2D4533 having puncture strength of 1550 plus asper ASTM D6241elongation at Break of 57Vo plus as per ASTM D 4595 in two
out of long fibres to hold the modules including cutting, sizing,and needle pundred for high porosity and properas per entire satisfaction of engineer-in-charge.(lncluding Taxes
and fixing of FRP based Microfilter with diameter of 750 mm1000 mm having inlet of 200mm and outlet of 200mm. with SS
. Flow rate of microfilter should be minimum 60 KL / hr. ( FRpFilter must be approved from GRlHA).complete as per entire
engineer-in-charge. (Including Taxes & Transportation)
& installation of Poffier based modules of make(Honeycomb Structure) made up of recycled polypropylene capable of 1
light vehicular movement upto 31 tonnes with adequate bacKilling & 4plates combination creating 3 spans Inside the module. These modules
from combination of large (685*4l0mm) and small (370*41along with extemal locks, Eacfi large plate should have
external locking slots inorder to give stability to tank. Thesehave optimum connection & block stability using double lock
single tank '6 made of four large and four small plates in ctse ofand 10 large & 12 s.nall plates for biple tank. C-apacity of single tank;*.410*.450 mtr) equals to 0.126 CUM(gross). Weight of each large pla
be minimum 1.2 Kg and each snall plate should be atleast .55 kg.to be appmved by Engineer-in-Charge.(Including Taxes
8000.00
PART-A Total Amount in
towards NAC @ 0.1olo
towards labour cess @ 1.00/o
PART-B Total Amount in Rs.
Total (A+B) Amount ln R.s.
r*
20 On Capac;ty
Abstract Estimate for Rooftop Rain Water Haruesting - 20,000 Litres Capacity
work excavation for foundations and depociung on bank for all lifts
an initial lead of 10m including all operational, incidental, labour
as shorlng ,sheting, planking, strutting, etc. complete for finished
of work including seigniorage exduding de$ratering charges etc as per SS
20 B (AP55 308).
From 3 Upb 6 meters dePth
fillirE ln foundation benches as per d6wlng induding
etc., complete and technical specifica$on Clau* 305.3.9 MORD
with Aggregate of size 20 mm filling in foundation trenches as
induding waterinq, tamping, eE., comdete and
Claue 305.3.9 MORD & 304 MORTH
of Brick Masonry (Fly ash) with CM(1:6) brick
of 50 kg/sq.cm - 15:12894-1990 - O-ASS - 7.5 23x11x7
Gt ard conveyance of all matethls, hbourcurirp €t., comPlete as dirtrted by EngilEr-ln-charge
RCC M- 20 Nominal mix (Cement:fine agprcgate: coarse
to Table 9 of IS 456 using 20mm size graded
hard granite metal (cmrse aggregaE) from approved
c6t aM conveyance of all materials llke cemnt, fine
@arse aggregate, water etc., to site and excluding
sales & other taxes on all materials lncluding all
and labour charges such as rnadline mixing, laying
etc.,compleb but excluding cost of sted and its fabrictionfinished ltem of worl! but excluding centering, shuttering.
BLDCSTN.3-13
SuppMng, fitting and placinq FE-500 bar rclnforcement in
as per drawings and ttrhnical specifications Clau€s 1000
1202 MORD & 1100, 1600 MORTH foI Bars below 36 mm dia including
as per BIS:12592 (Part l&2) glPdy ,Ddh/ery and Fixing ofand frames with I5I marting anFvhere in T.G., F.O.R.
lncluding, loading, un-lGding & sbddng at site but excluding all
as appl'K3ble. M.D. -10 with 500mm diaclear opening
BorirE/drllling bore well of required dia for caslng/ strainer pipe, by
prescribed in Is: 2800 (part I), irdudlng collecting samples
strata, preparing aM submittitB sttab charv bore log,
alt equlpments, tools, phnts & madlineris required for the Fb,as per dirtrtion of Engineer-in-charge, upto 90 metre depth
tuialysis from Delhi
soR 23.1.1.1
Supplylng, assembling, lowsing and fixing ln Yertical position in bore
rlastkized PVC medium well casinq (CM) PiPe of r€quked dia, conform
IS: 12818, including required hlre ard hbour chargs, fittings
etc. all complete, for all deptE, as per direction of Enginear
160 mm nominal size dia
Manufacture, Supply,Lowering & fixing of Undasticised WCs Pipes for
water supplk:s conforming to 15 :4985/2000 (3d ]e'risbn) with bdl
(Socket) as pcr sp€ificatim in light Grey/NatuEl I'rory Grer/ Any otts(ercept White) indusive of transportatbn to the suFdivisional stores
10 mm nominalsize dia
160 mm nominal size dia
packing in tubewdl constnrction ln accordance with I5: 4097
g providing gravel fine/ medium/ coarse, in rcqulred grading & size
per ictual rcquiremen! all complete as per dirtrtion of Engineer-in-
and fixing suitable size threaded mlld stel cap or spot
to the top of bore wdl hNsing/ casing pipe, remvable as
ement, all complete for bore{ell of:DSR Analysis 23.13.1
23.13.2
20 Cun Capacity
DSR Analysis 23.15.1and fixing Bail plug/ Bottom plt.lg of required dia to the bottom
assembly of tubewell as per 15;2800 (part I).
Providing and fixing of non woven gmtextile having thickness of 4OO
minimum tear strength of 250 ASTI4 D4533, Width wise aueastASTm D4533 having puncture strength of 1550 plus asper ASTM
elongatim at Break of 5790 plus as per ASTM D 4595 in twoout of long fibres to hold the modules including cutting, sizing,
and needle punched for high porcsity and properas per entire satisfaction of engineer-in-charge.(Including Taxes
and fixing of FRP based Microfilter with diameter oF 750 mm1000 mm having inlet of 200mm and outiet of 2o0mm with SS
. Flow rate of microfilter should be minimum 60 KL / hr. ( FRpFilter must be approved from GRlHA).complete as per
of engineer-in-charge. (Including Taxes & Transportation)
& installation of Polymej based modules of makeSkucture) made up of r€cycled polypropylene capable
light vehicular movement upto 31 tonnes with adequate backfillingsmall plates combination creaung 3 spans inside the modub.
are made From combinaton of large (685*410mm) and1lmm) plates along with external lock. Each large plate should
fourteen sternal laking dots inords to give stability totank should have optimum @onection & block stability using
stability. Each single tank is made of four large and four small platesof single tank and 10 large & 12 srnall plats for triple tank. Capacity
tank is (.685*.410*.450 mtr) equals to 0.126 cuM(gross). weightlarge date should be minimum 1.2 K9 and each smalt plate should
.55 K9. The design to be approved by
PART-B Total Amount in Rs.
Total (A+8) Amount in Rs,
s. No. .Refer€nce Description of ltem . .atv Unit Rate Amount in Rs
13
23.15.2 t50 mm dia 1.00 Each 193.15 193.0(
L4 Quotation 77.94 sqm 200.00 15587.0(
fransportation)
15 Quotation 1.00 Each 30000.00 30000.0(
16 Quotation 20.98 Cum 8000.00 167840.0(
PART-A Total Amount in Rs 4,38,O18,OO,rovisions
L' )rcvision towards GST @12% L2% 52562.11
18 ,rovison towards NAC @ 0.1% 0.19o 438.0:
19 ,rovision bwards labour cess @ 1.0olo lo/o 4380.1t
20 ieignordge Charges @0.25olo 0.25% 1095.0:
2t Jnfor€seen ltms3505.6(
61982.O(
500000.o(
Grand Total in Lakh! 5.OC
1 Construction of Rain water harvesting Structure of Tupe Desion J including the cost of eacavation in all types of soils,Supply, Collection & filling of 40mm metal(l.0m depth), 20 mm metal (0.50m depth), Coarse sand (0.30m depth), 23 cmthick Brickwork in CM(1:6) using 2nd class traditional bricks (23x11x7 cm size) laid over PCC(1;3:6) 75mm thick, plastering12mm thick single coat in CM(1:3) finished smooth, Supply and placing in position precast RCC perforated catch pit covers(40x40x5 cm size) with 5 nos perforations of 50mm dia with 4nos 8 dia HYSD bars bothways including the cost of all
materials, cost and conveyance, labour charges, curing and all other incidental charges complete for finished item of thework.
Sl Nc Description of Item Qtv Unit rate Unit amount
D Civil Comoonent1 RBR-FNDN-1- (i-A) In ordinary soils, by Manual means Earthwork
excavation in all kinds of soil as per drawings and technicalspecifications including setting out, construction of shoring andbracing, removal of stumps and other deleterious material ,dressing of sides and bottom as per Technical Specification 304MORTH and as directed by the departmental officer andbackfilling with excavated suitable material and disposal ofremaining eafth upto a lead of 50 m, including all incidental andoperational charges etc., complete
5.24 Cu.m 358.87 lCum 1880.48
2 Supply and filling with 40 mm metal including spreading , allinridantal :nd nnorrlinnrl rhrrnac afr rnmnlafa
2.25 Cu.m 1455.83 lCum 3275.62
3 Supply and filling with 20 mm metal including spreading , allinrirlpntal and nneratinnal rharnp< otr rnmnlote
1.13 Cu.m t974.20 lCum 2230.85
4 Supply and filling with course sand from approved quarryincluding cost and conveyaance, watering, tamping including alllahnr rr rharnoc
1.11 Cu.m 1316.76 lCum 1461.6
5 BLD-CSTN-3-10- ( 27 ) : Plain Cement concrete nominal mix(1:3:6) prop (Cement: fine aggregate: coarse aggregate ) using20mm size Hard Granite Machine Crushed Metal including costand conveyance of all materials like cemenl sand, coarseaggregate water etc., to site , seigniorage charges on all
materials, labour charges , for mixing , laying, concrete ,ramming in t5 cm layers, finishing top surface to the requiredlevel curing etc., complete for finished item of work.for
lfoundation and under flooring bed. below the Brick Wall
0.16 .u.m 4950.1 Cum 792.02
6 BLD-CSTN-5-4-(42): Brick Masonary 2nd Class Ground mouldedor treditional size 23x11x7 Cm in Cement Mortor 1:6 Prop
including Cost & conveyance of all Materials like Cement, Sand,
Bricks, Water, etc., to site cost of Seigniorage charges on almaterials, including all labour charges like mixing CemenlMortor, scaffoding charges lift charges , curing charges etc.complete for finished item of work
0.64 Cu.m 5476.44 lCum 3504.92
7 BLD-CSTN-8-1{76) : Plastering with 12mm thick in single coatin CM (1:3) finished smooth including cost and conveyance of allmaterials to site, seigniorage charges on all materials, finishing,curing, scaffolding and all operational, incidental, labour chargesetc., including cutting grooves where ever necessary etc.,complete for finished item of work. (As per SS 903).
7.74 Sq.m 1s9.79 lSqm t236.77
8 RCC peforated catchpit covers 400x400x 50mm size with 1:2:4cement concrete Nominal mix, with 5 nos perforations of 50mmdia, using 12mm hard broken stone aggregate with 4 nos 8mmdia bothways including cost of all materials, seigniorage charges,cost of machindry, labour charges, mixing, placing in position,
lleveling, vibrating, curing etc. complete for finished item of work.
llusing conc,ete mixer) (BLD-CSTN-2-17)
25 nos. 46 Each 1150.00
9 Carting of surplus earth including loading, unloading and.^hrrarr.n.o r rnfa ELmc inrh rdina :ll lahnr rr rharnac
5.24 Cu.m 204.60 lCum 1072.10
-4-1-(34):Providing High Yield Strength Deformed
HYSDy Thermo Mechanically Treated (TMT) / Mild steel (MS
steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979)
different diameters for RCC works , including labour charges
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials
size and tying and lap-splicing with binding wire of 18
grills for reinforcement work as per approved designs
drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
bars including cost and conveyance of binding wire, cover
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying including sales and other
on all materials etc., complete for finished item of work infloors.( APSS No.126
Add GST @
NAC @
13 iAdd Seignorage charges @
14_lProvision towards Labour cess
15 Round off 1094.86
22000.00
22000
Total for each pit Rs
Say Rs.
2 ]onstructionofRain*ute'@oesionttincludingthecostofeacavationinalltypesofsoils,jupply, Collection & filling of 40mm metal(1.Om depth), 20 mm metal (0.50m depth), Coarse sand (0.30m depth), 23 cm
.hick Brickwork in CM(1:6) using 2nd class traditional bricks (23x11x7 cm size) laid over PCC(1;3:6) 75mm thick, plastering
t2mm thick single coat in CM(1:3) finished smooth, Supply and placing in position precast RCC perforated catch pit covers
[40x40x5 cm size) with 5 nos perforations of 50mm dia with 4nos 8 dia HYSD bars bothways including the cost of all
materials, cost and conveyance, labour charges, curing and all other incidental charges complete for finished item of the
work.
SI N( Description of Item Qtv Unit rate Unit amount
I) Civil Comoonent1 RBR-FNDN-1- (i-A) In ordinary soils, by Manual means Earthwork
excavation in all kinds of soil as per drawings and technical
specifications including setting out, construction of shoring and
bracing, removal of stumps and other deleterious material ,dressing of sides and bottom as per Technical Specification 304
MORTH and as directed by the departmental officer and
backfilling with excavated suitable material and disposal of
lremaining earth upto a lead of 50 m, including all incidental and
I operational charges etc., complete
9.93 Cu,m 358.87 lCum 3563.58
z Supply and filling with 40 mm metal including spreading , allinridantal anrl nneratinnal rh:rnpc ptr a^mnlFte
4.5 Cu,m 1455.83 lCum 6551.24
3 Supply and filling with 20 mm metal including spreading , allinai/antrl rnd anaafianrl rhrraoc at .nmnlpte
2.25 Cu.m L974.2 lCum 444t.95
4 Suppty and filling with course sand from approved quarry
including cost and conveyaance, watering, tamping including all
2,05 Cu.m 1316.76 lCum 2699.36
5 BLD-CSTN-3-10- ( 27 ) : Plain Cement concrete nominal mix(1:3:6) prop (Cement: fine aggregate: coarse aggregate ) using
20mm size Hard Granite Machine Crushed Metal including costand conveyance of all materials like cement, sand, coarseaggregate water etc., to site , seigniorage charges on all
materials, labour charges , for mixing , laying, concrete ,
ramming in 15 cm layers, finishing top surface to the required
level curing etc., complete for finished item of work.forfoundation and under flooring bed. below the Brick Wall
0.22 Cu.m 49s0.1s1 lCum 1089.03
,ol ,rrl (9 s7.631 lKg 17e8.061
iEtrlr T"t-rl fi I i" R. l
B) I S Pravicion<
11 12.00o/o
t2 0.10o/o
0.50o/o
1,00%
6 BLD-CSTN-5-4{42): Brick Masonary 2nd Class Ground mouldedor treditional size 23x11x7 Cm in Cement Mortor 1:6 Propincluding Cost & conveyance of all Materials like Cement, Sand,Bricks, Water, etc., to site cost of Seigniorage charges on allmaterials, including all labour charges like mixing CementMortor, scaffoding charges lift charges , curing charges etc.,complete for finished item of work
0.88 lu.m 5476.44 lCum' 4819.27
7 BLD-CSTN-8-1-(76) : Plastering with 12mm thick in single coatin CM (1:3) finished smooth including cost and conveyance of allmaterials to site, seigniorage charges on all materials, finishing,curing, scaffolding and all operational, incidental, labour chargesetc., including cutting grooves where ever necessary etc.,complete for finished item of work. (As per SS 903).
10.56 sq.m 159.79 lSqm 1687.38
8 RCC perforated catchpit covers 400x400x 50mm size with 1:2:4cement concrete Nominal mix, with 5 nos perforations of 50mmdia, using 12mm hard broken stone aggregate with 4 nos 8mmdia bothways including cost of all materials, seigniorage charges,cost of machinery, labour charges, mixing, placing in position,leveling, vibrating, curing etc. complete for finished item of work.(Using concrete mixer) (BLD-CSTN-2-17)
45 nos. 46 Each 2070.00
9 Carting of surplus earth including loading, unloading andannvovanap rrntn (kmc inrlrrdinn ell lahnrrr rharnes
9.93 Cu.m 2A4.6 lCum 2031.58
10 BLD-CSTN-4-1-(34):Providing Hiqh Yield Strength Deformedl(HYSD)/ Thermo Mechanically Treated (TMT) i Mild steel (MS)
steel bars (Fe 415/ Fe 500 grade as per IS 1786-1979) ofdifferent diameters for RCC works , including labour charges forstraightening, cutting, bending to required sizes and shapes,placing in position with cover blocks of approved materials andsize and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designsand drawings, including cost and conveyance of steel bars,including all wastages such as overlaps, couplings, chairs, spacerbars including cost and conveyance of binding wire, cover blocksand all incidental, operational, labour charges such as cutting,
lbending, placing in position, tying including sales and other taxes
lon all materials etc., complete for flnished item of work in all
lnoors.l APSS No.126
s6.161 Kg s7.63 1Kg 3236.50
Sub Total ( I )iin Rs
:, : -14.'.r '- ' 't;:?'-''
I 1109'?,I ra.+ot-----.-I gz.ot
B LS Provisions11
t2
GST @
NAC @
12.00%
0.10o/o
13
L4
Add Seignorage charges @ 0.50o/o
Provision towards Labour cess 1.00%
:: .,:.-t..---_--=-lI zzos.zg Itt
I
18.401f-lr s2.01t1t
I ra+.ozl
307.29
35000.00
35000
Total for each pit Rs
Say Rs.
15 Round off
of Rain water harvesting Structure of Tyoe Desiqn.[[ including the cost of eacavation in all types of,, Collection & filling of 40mm metal(1.Om depth), 20 mm metal (0.50m depth), Coarse sand (0.30m depth), 23
thick Brickwork in CM(1:6) using 2nd class traditional bricks (23x11x7 cm size) laid over PCC(1;3:6) 75mm thick, plastering
12mm thick single coat in CM(1:3) finished smooth, Supply and placing in position precast RCC perforated catch pit
(40x40x5 cm size) with 5 nos perforations of 50mm dia with 4nos 8 dia HYSD bars bothways including the cost ofmaterials, cost and conveyance, labour charges, curing and all other incidental charges complete for finished item of
a
a
@, by Manual means Earthworkl
excavation in all kinds of soil as per drawings and technicall
specifications including setting out, construction of shoring andl
bracing, removal of stumps and other deleterious material ,i
laressino of sides and bottom as per Technical Specification 304
lUOnffi anO as directed by the departmental officer and
lbackfillinq with excavated suitable material and disposal of
lremaining earth upto a lead of 50 m, including all incidental and
loperational charges etc., complete
Cu.m 358.87 lCum 522i.s6 |I I+.)5 |
2 Srpply and fiiling with 40 mm metal including spreading , all
ineidpntal and onprational charoes etc comDlete
6.75 Cu.m 1455.83 lCum 9826.8s
3 Srpply ",1d
f,lli"g *ith 20 mm metal including spreading , all
inridental and onerational charoes etc com-oletg--3,38 Cu.m t974.2 lCum 6672.8
4 Srpply anO Rttlng with course sand from approved quarry
includlng cost and conveyaance, watering, tamping including al
2,95 Cu.m 1316.76 lCum 3884.44
5 nt concrete nominal mixl
(1:3:6) prop (Cement : fine aggregate: coarse aggregate ) usingl
20mm size Hard Granite Machine Crushed Metal including cost
and conveyance of all materials like cement, sand, coarse
aggregate water etc., to site , seigniorage charges on all
lmaterials, labour charges , for mixing , laying, concrete ,
lramming in 15 cm layers, finishing top surface to the required
lbvel curing etc., complete for flnished item of work'for
lfoundation and under flooring bed. below the Brick Wall
0.27 Cu.m 4950.1s lCum 1336.54
6 @ary 2nd class Ground mouldedl
or treditional size 23x11x7 Cm in C-ement Mortor 1:6 Propl
including Cost & conveyance of all Materials like Cement, Sand,
Bricks, Water, etc., to site cost of Seigniorage charges on all
lmaterials, including all labour charges like mixing Cement
lMoftor, scaffoding charges lift charges , curing charges etc',
lcomplete for finished item of work
1.1 Cu.m 5476.44 Cum 6024.08
7 eLDCnGe-t-(76) : Plastering with 12mm thick in single coat
in CM (1:3) finished smooth including cost and conveyance of all
materials to site, seigniorage charges on all materials, finishing,
curing, scaffolding and all operational, incidental, labour charges
etc., including cutting grooves where ever necessary etc'
complete for finished item of work. (As per SS 903).
t3.221sq.m 1s9.7s l sqm 2tl2.4Z
B x 50mm size with l:2:41 65
cement concrete Nominal mix, with 5 nos perforations of 50mml
dia, using 12mm hard broken stone aggregate with 4 nos 8mml
dia bothways including cost of all materials, seigniorage charges,l
cost of machinery, labour charges, mixing, placing in Position,l
leveling, vibrating, curing etc. complete for finished item of work'l
(Using concrete mixer) (BLD-CSTN-2-17) I
nos. 46 Each 2990.001
9 Cartrng of surplus earth including loading, unloading and
.Anrrovrnrp rrntn (kmc inrhrdino all labour charoes
14.55 Cu.m 204.6 lCum 2976.93
10 BLD{STN4-1-13+;:eroviding High Yield Strength Deformedl
(HYSDy Thermo Mechanically Treated cl-MT) / Mild steel (MS)l
steel bars (Fe a15l Fe 500 grade as per IS 1786-1979) ofl
,different diameters for RCC works , including labour charges forl
lstraightening, cutting, bending to required sizes and shapes,l
lplacing in position with cover blocks of approved materials andl
lsize and tying and lap-splicing with binding wire of 18 SWG,I
lforming grills for reinforcement work as per approved designs
land drawings, including cost and conveyance of steel bars,
llncluding all wastages such as overlaps, couplings, chairs, spacer
lbars including cost and conveyance of binding wire, cover blocks
land all incidental, operational, labour charges such as cutting,
lbending, placing in position, tying including sales and other taxes
lon all materials etc., complete for finished item of work in all
lnoors.( APSS No.125I
81.12IKe 57.63 Ke | 4674.es1
\
i-I
15 Round off 776.71
Total for each irit R.s 49000.00
R) LS Provisions11 Add GST @ 12.00%
t2 Add NAC @ 0,10%
13 Add Seignorage charges @ 0.50o/o
T4 towards Labour cess 1.000/o
Ant NLXuKE-fr
SploshFod
., -; ..i
Thc
ionr
tire
Erick Woll ltiih plostering on
0uter Surfoce with, li6Cernent Mortor
L---
1nd\U/o Unen
f C.[(1 :J:6J
IO% _ COARST SAIID
1t- utr/a lUmm l,,l[i4g
5A% 4}mm ,rdflAl -{*%Type Size of p;i in 'h{ts,
".-_ ..,t.5xZ 0xZ.0
Copocily
I
6.0 Cum
:''r:'r*rr i- r.l: t"-i** t- ,,*-#:iI'. r $'-ulj92,_gr$qrnj r,furh_sre.tu.u.ul;m !"QAqe
It, ut:("1
All Dimensions ore in 'rnm'
riOJr|-l
* tJt'b 8'*16f'
I I l-tl"*,,r- '$ Fc nol*-L EEH-
-------\ I ffhm ierf,ttct celr (1:1 tL,Ith,n-tlt
23*mm llrt &etro* ;n Cu{t:6)?nd closs Troditjonol Slicls
(fn*ering ltmrn llrk i* Cu {!:l)RCC Pcrforoicd {00x40ft50nm
Cwrre
corfis{ s4t{0
20mm M[T&
{0nyn lJfIA{
75 n-,m li:kin 4f;rn Urtol
PCC (1:,);S)
fl
III
*
-t_
_I
I
I
I
ErkluorkrUr *So4rt
,r&x {00 nccCstcr, -J6 ilst
irII!'
1)
fl
S]RUCI"URLS-"JI--0!-v!-8UU[$Tl0-Be!-L,lAlill*eSLLEgIS*lN--J!$s
All Dimensions ore rn mm4{0X d{O nccCwerr -]5 No*
Opaning* Brickxorkridc aborc
,400r
_ I //la-Er tsd.trtt
q [ {-Lf}..Ho.G 'in F[ Eo.91 bFt3 crrrrra sorrr
f,6lel1rttLlo'ffi'-n$
2lOrrm lhk Briclxa* ;n CH{l:6}
?nd ctogs Iroditionol Ericks
{Plartrring 12mrn lhk in CU il:J)
RCC Ptrforotod 400x400r50mm
Covers
* _t_
-
CTT AI A*A
Brick l{oll with plostering onOuter Surfoce rqith I:6
Cement Mortor
HQ_rvSsiin$ StrUciure rprg_;000 Sf t ifOi.g_trqfij* irlin[h__.*tea: l? Q- c"llr.*cgfils*J -ii:-- f,uhJip Rs_urql.ffL0tuc*lip:i,rl:s
1CI7. Open
I C.C(1:J:6)
lCI% CCAftSI SAND
nfor .A/37, lAmrr, l,l[ iAr_
\AX 40mm
Splash
.'.type
*
Size at Pit in 'Mts' Ccpncity
2.0x3.0x2.0 ,/\ ^1l \l : lrrYtr a.v VLlrtt