Iffco Presentation on Dfc Overview- On 13.07.2012.
-
Upload
gurveersingh0209 -
Category
Documents
-
view
219 -
download
0
Transcript of Iffco Presentation on Dfc Overview- On 13.07.2012.
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
1/38
DFCC PROJECT AN OVERVIEW
13.07.2012.
Presentation by
P N ShuklaDirectorOperations and Business Development)
1
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
2/38
GOLDEN QUADRILATERAL & ITS DIAGONALS ARE BUSIEST ROUTES OF IR
• High Density Corridor
(Golden Quadrilateral +Diagonals) 16% of route
Km carries 52% of
passenger & 58 % of
freight
DELHI
MUMBAI
KOLKATTA
CHENNAI
2
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
3/38
73.2
473.5
0
100
200
300
400
500
1950-51 2000-01
FREIGHT TRAFFIC (MILLION TONNES) 1950-51 to 2000-01
FREIGHT TRAFFIC (MILLION TONNES)
AN INCREASE OF 400.3 MT OVER 50 YEARS
Indian Railways – An Overview
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
4/38
4
MUMBAI
DELHI
CHENNAI
KOLKATA
LUDHIANA
VIJAYAWADASanctioned projects
Unsanctioned projectsVASCO
DELHI
LUDHIANA
MUMBAI
DELHI
CONCEPT PLAN OF DEDICATED FREIGHT CORRIDOR NETWORK
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
5/38
OBJECTIVES
Create additional railinfrastructure to cater tohigh levels of transportdemand
Reduce unit cost oftransportation resultingin market competitiverail tariff for customer
Provide seamless end toend solution to thecustomers
Segregate freight infrastructure forfocused approach on both
passenger and freight business ofRailways
Create rail connectivity tobulk customers not using railnetwork through PPP model
IT packaging of FreightServices
Increase rail share infreight market
Objectives Of The Project
5
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
6/38
Dankuni
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
7/38
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
8/38
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
9/38
Route Length
(km)1 Pipavav - Surendra Nagar - Viramgram - Mehsana 3952 Kandlaport - Gandhidham - Palanpur 3303 Mundra Port - Gandhidham 654 Okha - Rajkot - Surendra Nagar 3705 Jodhpur - Luni - Marwar Jn 806 Mumbai Port - Wadala - Kurla - Diva - Vasai Road 777 Trombay - Kurla 78 Thal - Panvel - Diva 889 Hazira - Surat 40
10 Ludhiana - Hissar - Rewari 35511 Tundla - Agra - Jaipur - Phulera 275
TOTAL 2082
Feeder Routes of Western Corridor
9
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
10/38
State Kms.
West-Bengal 221Jharkhand 319
Bihar 93
Gujarat 588Haryana 274
Maharashtra 166
Punjab 102Rajasthan 553
U.P. 1002
Total 3318
State-wise Kms. (approx.)
10
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
11/38
CORRIDOR
RouteLength(Km)
Basic
Const.Cost(Cr.)
Eastern Corridor- Dadri-Khurja- Sonnagar - Dankuni(D/L) 1422KmsKhurja - Ludhiana (S/L) 413 Kms
1835 23605
Western Corridor- from JNPT (Near Mumbai) to Dadri via Palanpur – Ajmer – Phulera – Ringus – Rewari
1483 22956
Total* Cost at 2009 prices
3318 46561*
Length & Cost of Corridors
11
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
12/38
Completion Cost as Per Business Plan
•
Eastern Corridor Rs 42,940 Crs• Western Corridor Rs 47,682 Crs
TOTAL Rs 90,623 Crs
The additional costs are on account of inflation andsoft costs such as Insurance, Taxes, Contingency andInterest during construction.
The Project Completion is 31/3/2017.
12
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
13/38
Eastern Corridor :Mughalsarai – Khurja 732 Kms (D/L) World Bank
Khurja – Ludhiana 413 Kms (S/L) World BankSonnagar-Mughalsarai 122 Kms (D/L) GOISonnagar-Dankuni 534 Kms (D/L) On PPP Mode
Western Corridor :Rewari – Vadodara 920 Kms (D/L) JICA (Ph.I)
Dadri-Rewari & 605 Kms (D/L) JICA (Ph.II)Vadodara - JNPT
Funding Arrangement
13
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
14/38
Importance of DFCC
• Dedicated Freight Corridor enlisted as one of the iconic/
Flagship project of India being monitored by PMO.• DFC will provide not only schedule time services but also time
bound services .• The transit time will be less than half from present levels.• The average speeds of freight trains will go up from 25 kmph
to 70 kmph .• DFC will enable introduction of private rolling stock as per
customers requirement.• DFC can explore new areas of traffic like automobiles, road
railers and Roll On Roll Off services.
14
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
15/38
(Number of Trains per day both ways)
EasternCorridor
2016-17 2021-22 2026-27 2031-32
Sonnagar-Mughal sarai
155 183 214 244
Mughalsarai-
Allahabad-Khurja
124 149 180 226
WesternCorridor
2016-17 2021-22 2026-27 2031-32
Palanpur-Rewari 181 252 321 377
JNPT-Palanpur 125 172 263 307
Traffic nearly doubles after 15 years
Traffic Growth with DFC on Busy Sectors ofEDFC & WDFC
15
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
16/38
IMPORTANT MILESTONES
• October 2006 DFCCIL incorporated as a Company.•
February 2007 CCEA approved the PETS reports by RITES at a cost of28000 crores.• September 2007 MD & Directors in position.• February 2008 MR’s commitment in Parliament to start Construction
work on Both Corridors during 2008-09.•
February 2008 Cabinet approval received for starting the preliminaryworks on Eastern & western Corridors• April 2009 Work started on 105 Kms. of Eastern Corridor
and 200 Kms. of Western Corridor• March 2010 JICA Loan Agreement signed for Western Corridor.•
May 2011 WB sanctioned loan for Khurja – Kanpur for EDFC• December 2011 Bid Documents for Kanpur-Khurja launched• March 2012 Financial Bids invited for Kanpur-Khurja Section.• June 2012 Financial Bids invited for Rewari-Palanpur Section .
16
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
17/38
DFCCIL ITS MANDATE
17
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
18/38
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
19/38
Mandate for DFC as per Cabinet Decision
• DFC project to be implemented through SPV.• SPV entrusted with planning, construction, maintenance and
operation of DFC infrastructure.• SPV to be independent in decision making and should be able to
function with market focus and business orientation duringConstruction maintenance & operation.• SPV to have status of railway administration under Indian Railways
Act, 1989.• The relationship with Railways and DFCC to be governed by
Concession Agreement.• All contracts would be based on Design & Build lump sum with
time bound completion.• Any stoppage on account of client may end in huge claims.
19
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
20/38
MILESTONE ACHIEVED
• April 2005 MR announced in the Parliament the need and planning for
the project.• August 2005 PM announced development of DFC in his I-Day Speech.• August 2006 CCEA approved formation of a SPV (DFCCIL) for execution of
the project.• October 2006 DFCCIL incorporated as a Company.•
February 2007 CCEA approved the PETS reports by RITES at a cost of 28000crores.• February 2008 MR’s commitment in Parliament to start work on Both
Corridors during 2008-09.• March 2010 JICA Loan Agreement signed for Western Corridor.•
March 2011 World Bank loan for Phase-I Eastern Corridor finalized• May 2011 WB sanctioned loan for Khurja – Kanpur• March 2012 Kanpur-Khurja bids opened. Contract likely to be awarded
by Sept 12.
20
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
21/38
21
Basic Design Features
Height
Width
4.265 m7.1 m
3200 mm 3660 mm
700 m 700/ 1500 m
4,000 Ton 15,000 Ton
5.1m
Western Corridor Eastern Corridor
Moving Dimensions
Container Stack
Train Length
Train Load
Indian Railway DFC Routes
Western Corridor Eastern Corridor
21
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
22/38
22
• Heavier Axle LoadsAxle Load
Track Loadingdensity
22.9 t / 25 t 32.5t/25 t
8.67 t/m 12 t/m
75 Kmph 100 Kmph
Indian Railway DFC Routes
MaximumSpeed
Grade Upto 1 in 100 1 in 200
Basic Design Features (Cont …..)
22
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
23/38
Traction Electrical Electrical(25 KV) (2x25 KV)
Station Spacing 7-10 Km 40 Km (Approx.)
Signalling Absolute /Automatic Automatic withwith 1 Km spacing 2 Km spacing
Communication Emergency Sockets/ Mobile Train Radio
Mobile Train Radio
Indian Railway DFC Routes
23
Basic Design Features (Cont …..)
23
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
24/38
Operating Aspects of DFCC
• DFCC to manage train operation on DFC.• DFCC to have stations and control centres .• The rolling stock to be provided by IR.• Maintenance facilities for rolling stock to be provided
by IR.• 896 Level Crossings to be replaced with ROBs /RUBs
on both the corridors.
24
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
25/38
To Vasai Road (C. Rly.) To Diva (C. Rly)
To JNPT(DFC)To Delhi (DFC)
DFC to C. Rly Alignment
C. Rly Alignment to DFC
A Typical Yard Plan
25
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
26/38
A Typical Yard Plan
26
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
27/38
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
28/38
• Land Acquisition is being done as per RailwayAmendment Act, 2008. Compensation is guided by thePrinciples enshrined in National Rehabilitation and Re-settlement Policy (NRRP), 2007
• DFC passes through 9 states and 60 districts whichmakes the land acquisition the most challenging task
• Land Acquisition is required for 10840 hectares• So far7100 hectares acquired i.e. 70% of the total
requirement• Entire DFC land acquisition is likely to be completed by
Dec 2012
Progress on Land Acquisition
28
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
29/38
•
Phase –IPre-qualification of contractors for Kanpur – Khurja section (342 Kms.) done. Biddocuments launched in march 2012. Contractlikely to be finalised October 2012
• Phase – IIKhurja – Ludhiana and Kanpur - Mughalsaraiappraisal by December 2012. Work likely tostart by October 2013
Progress on Eastern Corridor
29
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
30/38
•
Sonnagar-Mughalsarai Section contract forcivil works awarded in April 2009.
•
Plan for phased opening of 66 Kms byDecember 2013.
• Sonnagar-Mughalsarai 105 Kms section to beopened by December 2014.
Progress on Eastern Corridor (Cont)
30
PROGRESS ON WESTERN DFC
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
31/38
PROGRESS ON WESTERN DFC -(FUNDED BY JAPANESE INTERNATIONAL COOP. AGENCY)
Construction of 54 bridges started in Jan’ 2009 between ST& BSR with Railway Equity.Phase-I (RE-BRC) loan agreement signed on 31.3.2010.General Consultant appointed for Phase-I on 12.05.2010.Pre-Qualification of contractors for Palanpur-Rewari doneon 20.06.2012.Financial Bids to open by 20.10.2012 and contract likely to
be finalised by December 2012.
31
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
32/38
32
Eastern Corridor
Commissioning of Eastern Corridor 31 December 2016
Western Corridor
Phase – I Rewari – Vadodara December 2016
Phase – II Vadodra - J.N. Port December 2016
Dadri – Rewari March 2017
Timelines for DFC Construction
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
33/38
• Logistics Park to be developed near Navi Mumbai / Panvel,Rewari, Jaipur, Palanpur, Ahemdabad, Vapi, Vadodara,Dadri, Ludhiana, Kanpur.
• Set up Sub-SPVs for development of logistics park on PPProute.
• Land requirement Mega Park (SEZ) 1000Acres, MediumParks- 500Acres and Special Parks-250 Acres.
• Develop commodity specific terminal and value addedservice.
• DMIC corridor would strengthen the need for setting ofsuch Logistics park .
LOGISTICS PARK & STATE OF ART TERMINAL
33
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
34/38
• A multi-modal logistics hub (also called a district park or a logistic park), isplanned to carry out the following activities:
• Container terminal. (Both International & Domestic)• Mineral handling terminals.• Cement / Fertilizer terminals or bagged commodities.• Automobile terminals.• Roll On Roll Off service terminal• Storage and Distribution logistics.• Consolidation/de-consolidation.• Transhipment.• Warehousing (conventional/cold storage/ product specific).• Allied activities like manufacturing, industrial and commercial activities
(hotels, banking, food parks, entertainment).
• THESE LOGISTICS HUB PROVIDE TOTAL TRANSPORT SOLUTION AND OFFERCOMMON USER FACILITIES.
SCOPE OF BUSINESS ACTIVITIES AT LOGISTICS PARK
34
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
35/38
•
Develop Logistics Parks through PPP routes.• Infrastructure to be provided by DFC and facilities for
warehousing, distribution and other value addedservices to be provided by Private operators.
•
Feasibility of DFC standard feeder routes can be donebased on industrial development.• Logistics park can be planned jointly with State
Government.
Partnerships for Logistics Parks
35
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
36/38
• MR announced study of other four corridors inher Budget Speech in February 2010.
East – West Corridor (Kolkata –Mumbai) 2000 Kms.
North-South Corridor (Delhi-Chennai) 2173 Kms.East Coast Corridor (Kharagpur-Vijayawada) 1100 Kms.Southern Corridor (Chennai-Goa) 890 Kms.
DFCCIL has assigned this study to RITES which will takeabout 2 years.
FUTURE FOUR CORRIDORS
36
DELHI– MUMBAI INDUSTRIAL CORRIDOR (DMIC)
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
37/38
• Focus is on ensuring high impactdevelopments within 150km distanceon either side of alignment of DFC
• Area under Project Influence is 14%and population is 17% of the Country
• Total Population in the ProjectInfluence Area : 178Mn
• Total Workers in the Project Influence Area: 70.56Mn
As per Census-2001
DFC AlignmentEnd Terminal
HaryanaDadri
J.N.Port
Rajasthan
Maharashtra
GujaratMadhyaPradesh
Haryana
UttarPradesh
DELHI – MUMBAI INDUSTRIAL CORRIDOR (DMIC)AN ADDED ADVANTAGE FOR DFC
37
-
8/13/2019 Iffco Presentation on Dfc Overview- On 13.07.2012.
38/38
38