IET 120 Construction Project
description
Transcript of IET 120 Construction Project
IET 120CONSTRUCTION PROJECTAndrew Grigsby
Dwelling
Single Story
Square Footage
Square footage of each floor 4127.2 Sq. ft.
Square footage total 4127.2 Sq. ft.
Location
Building Materials
Cork Flooring for better insulation
Fiberglass Siding for durability and low maintenance
Durra Panels for drywall because they are made of environmentally friendly material
Building Materials
Icynene for insulation
Metal roofing
Floor Plan Layout
I used one room per person because it makes studying and sleeping easier. I divided the bathrooms by gender and included a laundry room with 6 washer/dryers. The dwelling has one lounge room and one kitchen/dining room.
Timeline
Week 1: Clear and level the lot Week 2-4: Foundation work Week 5-12: Exterior walls, subfloor and roof Week 13-16 Finish outside of house, get
started on plumbing, hvac, and electrical Week 17-24 Put up drywall and install
cabinets and install flooring Week 25-32 Finish plumbing and electrical
work. Paint and caulk
Conclusion
I learned about many building materials that can be used such as siding and flooring as well as new sites that can be utilized to estimate costs of jobs.