IESO 18MonthOutlook_2010may

download IESO 18MonthOutlook_2010may

of 36

Transcript of IESO 18MonthOutlook_2010may

  • 8/6/2019 IESO 18MonthOutlook_2010may

    1/36

    From June 2010 to November 2011

    An Assessment of the Reliability and Operability of the Ontario Electricity System

  • 8/6/2019 IESO 18MonthOutlook_2010may

    2/36

    IESO_REP_0608v1.0 18-Month Outlook

    Thispageintentionallyleftblank.

  • 8/6/2019 IESO 18MonthOutlook_2010may

    3/36

    IESO_REP_0608v1.0 18-Month Outlook

    Executive Summary

    Ontariossupplyoutlookforthenext18monthsremainspositivewithsufficient

    resourcesavailabletomaintainthereliabilityofOntarioselectricitysystem,andto

    supplycommunitiesacrosstheprovince. FromJune2010toNovember2011,

    approximately2,900megawatts(MW)ofnewandrefurbishedsupplyarescheduledto

    entercommercialoperation. Ofthat,approximately470MWofnewgenerationhas

    beenannouncedundertheFeedinTariff(FIT)programand180MWcontractedunder

    theRenewableEnergySupplyIII(RESIII)program.

    Asaresultofthepositivesupplyconditions,thederegistrationoffourcoalfiredunitsat

    LambtonandNanticokerepresenting2,000MWofenergysupplyandcapacity has

    beenapprovedbytheIESOforearlyfallof2010. Thereplacementfleetfortheseunits

    hasdemonstratedreliableoperationoverthelasttwopeakperiodsandtheshutdownof

    theseunitsisnotexpectedtoundulyimpacteitherenergyadequacyorreliabilityof

    supplyinOntario.

    ThereturntoserviceoftworefurbishednuclearunitsattheBruceANuclearStationis

    stillexpectedwithinthe18monthforecasttimeframe;howevertheexpectedinservice

    datesforthetwounitsarenowthethirdandfourthquartersof2011. Thisadditional

    1,500MWcapacitywillincreasesupplyoptions,althoughBruceareasupplywillnotbe

    abletooperateatfullcapacityuntiltheBrucetoMiltontransmissionlineiscomplete

    whichisexpectedin2012.

    Surplusbaseloadgeneration(SBG)isexpectedtocontinueovertheforecasttimeframe,

    especiallyduringthesummersof2010and2011whenbaseloadcapacityisexpectedtoexceedforecastminimumdemand. Duringthesetimesofsurplus,theprovincerelies

    heavilyonitsabilitytoexport. Plannedoutagestoseveralcircuitsmakingupthe

    OntarioNewYorkinterconnectionatNiagaraarecurrentlybeingconsideredfor

    NovemberandDecember2010. Ifapproved,theseoutageswillreduceOntariosability

    toexportpower,andincreasethelikelihoodofSBG. Thecurrentforecastincludesan

    updatedexportassumptionrecognizingtheevolvingconditionsonOntarios

    interconnections.

    Overthenext18months,theIESOcontinuestoexpectarelativelyhighlikelihoodof

    surplusconditionsinsummeroffpeakperiods,comparedtothewinterandshoulder

    periodmonths.Limitedprecipitationthispastwinterandspringhascontributedto

    uncertaintyaroundhydroelectriccapabilityoverthesummermonthsandlowerthan

    forecasthydroelectricproductionwouldreducesurplusconditions.

    Demandgrowthoverthelastdecadehasresultedinsomearealoadsreachingor

    exceedingthecapabilityofthelocaltransmissionsystem. Toalleviatethesituation,

    severallocalloadsupplyimprovementprojectswillcomeinserviceoverthenext18

    May 20, 2010 Publ ic Page i i i

  • 8/6/2019 IESO 18MonthOutlook_2010may

    4/36

    IESO_REP_0608v1.0 18-Month Outlook

    monthstorelieveloadingsofexistingtransmissioninfrastructureandprovide

    additionalcapacityforfutureloadgrowth.

    ThroughouttheOutlookperiod,demandwillbeshapedbythreemainfactors:the

    economy,conservationandthegrowthinembeddedgenerationfromOntarios

    renewableinitiatives.AlthoughtherisksofOntarioseconomyslippingbackinto

    recessionhavemoderated,worldeconomiesremainfragileduetohighnationaldebt

    loads,highoilpricesandtheprospectsofhigherborrowingcosts.WhileCanadahas

    reportedlyfaredbetterthanmanyothercountries,Ontariosexportbased

    manufacturingsectorhasseenitscompetitivepositionunderminedbytheriseinvalue

    oftheCanadiandollar.

    EnergydemandinOntarioisexpectedtoshowmodestgrowthin2010and2011with

    increasesof1.3percentand1.0percentrespectively. Thegrowthwillcomefroma

    broadbasedexpansionoftheeconomy.Themanufacturingsectorisexpectedtoshow

    anincreaseover2009butisexpectedtolagtherestoftheeconomyasindustrialdemandisnotexpectedtoreturntoprerecessionarylevelsduetothehighCanadiandollarand

    slowinternationalgrowth. Peakdemandsareexpectedtoremainfairlyflatasgrowthis

    offsetbytargetedconservationprograms.

    Recentlyannouncedgovernmenttargetsforconservation,whoseimpactsareexpected

    toshowbeginningJanuary2011,willfacilitatethelongertermreductionofpeak

    demandandmoderatethegrowthofenergydemandacrosstheprovince. These

    conservationtargetswillbemetthroughprogramsdeliveredbylocalutilities,andthe

    OntarioPowerAuthoritywithoversightfromtheOntarioEnergyBoard. Theseefforts,

    incombinationwithimprovedenergyefficiencyandthedeploymentofsmartmeters,

    willresultinbothlowerconsumptionandashiftinconsumptionpatterns.

    Thefollowingtablesummarizesthekeydemandnumbers.

    SeasonNormal Weather Peak

    (MW)

    Extreme Weather Peak

    (MW)

    Summer 2010 23,498 25,998

    Winter 2010-11 22,473 23,782

    Summer 2011 23,464 25,938

    May 20, 2010 Publ ic Page iv

  • 8/6/2019 IESO 18MonthOutlook_2010may

    5/36

    IESO_REP_0608v1.0 18-Month Outlook

    Conclusions & Observations

    Thefollowingconclusionsandobservationsarebasedontheresultsofthisassessment.

    DemandForecast

    Electricitydemandisexpectedtoexperienceanincreasein2010and2011. GrowthwillbeslowasOntariosenergyintensiveexportbasedindustrieslagtherestoftheeconomy.

    Peakdemandsareexpectedtoremainflatthroughouttheforecast. Conservationprogramstargetingpeakdemand,thegrowthinembeddedgenerationandtimeofuserateswilloffset

    theincreasesduetopopulationandbuildingstockgrowth.

    Withlowerpeakdemandlevelssystemreliabilitywillremainrobust. Althoughhighpeakdemandsarelikelyunderextremeweatherconditionstheywillnotposeanyprovincewide

    reliabilityconcerns.

    Lowminimumdemandperiodsremainaconcernastheyincreasethelikelihoodofsurplusbaseloadgeneration. Thiswillpersistthroughouttheforecast.

    ResourceAdequacy

    Reserverequirementsareexpectedtobemetforallbutoneweekinboththefirmandplannednormalweatherscenario. Thisisduetotwomajorgeneratorplannedoutagesand

    onemajortransmissionoutageresultinginbottledcapacity.

    Anumberofgeneratingunitsarescheduledtoreturntoservicefromplannedoutagebeforesummer2010.

    Planstoderegisterfourcoalgenerationunitsbylate2010willcontinueasannounced. PlansforthereturntoserviceoftworefurbishedBrucenuclearunitshavebeendelayedbyafew

    monthstothethirdandfourthquartersof2011.

    ThisOutlookdemonstratesthattheinitialemissionlimitsfromcoalpoweredgenerationshouldbeachievableoverthenext18monthperiodwithoutimpactingonreliability,

    althoughthecompletestrategytoachievereductionsfor2010onwardshasnotbeen

    confirmed.

    Normal W eather Scenario Extreme Weather Scenario

    PlannedScenario

    Thereis1weekwherereserveislowerthanrequired

    Thereare9weekswherereservesarelowerthanrequired.

    FirmScenario

    Thereis1weekwherereserveislowerthanrequired

    Thereare12weekswherereservesarelowerthanrequired.

    Underthenormalandextremeweatherscenarios,periodswheretheforecastreservesarenotsufficienttomeetrequirementsmayresultinrelianceonimports,therejectionofplanned

    outagesbytheIESO,ortheuseofemergencyoperatingprocedures.

    May 20, 2010 Publ ic Page v

  • 8/6/2019 IESO 18MonthOutlook_2010may

    6/36

    IESO_REP_0608v1.0 18-Month Outlook

    TransmissionAdequacy

    TheOntariotransmissionsystemwiththeplannedsystemenhancementsandscheduledmaintenanceoutagesisexpectedtobeadequatetosupplythedemandunderthenormal

    weatherconditionsforecastfortheOutlookperiod.

    Thesupplyreliabilityunderextremeweatherconditions,inparticulartotheGTA,willbefurtherimprovedwiththeadditionoftheHaltonHillsGeneratingStationinthethird

    quarterof2010. Underextremeweatherconditionsthelongtermderatecurrentlyona

    Trafalgarautotransformermayrequiresomeloadreductionmeasuresifadditionalelements

    areoutofservice.

    SeveralprojectsrelatingtolocalloadsupplyimprovementswillbeplacedinserviceduringthetimeframeofthisOutlooktohelprelieveloadingsofexistingtransformerstationsand

    provideadditionaltransformercapacityforfutureloadgrowth.

    The230kVcircuitBP76formsanintegralpartoftheOntario NewYorkinterfaceatNiagaraFalls. Duetothevariablenatureofitsflows,thisinterfaceisoneofthemostchallengingto

    manageintheEasternInterconnection,keepingsystemoperatorsaroundtheGreatLakes,

    whichincludetheIESO,NYISO,PJMandMISO,fullyengaged. Theongoingforcedoutage

    oftheBP76interconnectionhascompoundedthecomplexitiesofthese reliability

    coordinationefforts,addedtoOntariossurplusbaseloadgeneration(SBG)eventsandhas

    materiallyledtoincreasednuclearreductionsandhydroelectricspillconditionsoverthelast

    year. OutagesoftwootherlinesoftheNiagarainterconnection(PA301andPA302)are

    currentlybeingplannedforNovemberandDecember2010. Theseoutageshavethepotential

    toreducethescheduledtransfercapabilityoftheNiagarainterconnectiontozeroandalso

    impacttheOntariotoMichigantransfers.

    TransmissionoutagesscheduledinthisOutlookperiodintheBruce,Essa,Niagara,Northeast,Northwest,Ottawa,Southwest,TorontoandWestzoneswillcausereductionsto

    thegridtransfercapabilityforperiodsoftime. Theresultinglimitreductionsalongwiththe

    increaseofavailablegenerationinthoseareasmayresultintemporarilybottledgeneration

    capacity.

    Transmissionconstraintsoverthe230kVSarnia/WindsortoLondonareamaylimittheabilitytoutilizethegenerationresourcesinsouthwesternOntarioinconjunctionwith

    importsfromMichigan. Thiscongestioncouldfurtherincreaseasaresultoftransmission

    outagesandweatherconditions. ThescheduledshutdownoftwoLambtonGSunitsin

    October2010isexpectedtoreducethecongestionovertheremainderofthisOutlookperiod.

    HydroOneiscurrentlyinstallingadditionalreactivecompensationinwesternand

    southwesternOntarioinpreparationfortheplannedshutdownofthemajorsouthern

    Ontariocoalfiredunits.

    Managing

    grid

    voltages

    in

    the

    Northwest

    has

    always

    required

    special

    attention,

    but

    with

    the

    significantlylowerdemand,ithasbeenincreasinglydifficulttomaintainanacceptable

    voltageprofilewithoutcompromisingthesecurityandreliabilityofthesupply. TheIESO

    hascontactedHydroOne,andisalsoinconversationswiththeOPA,ineffortstoexamine

    theshortandlongtermsolutionstothismatter.

    HydroOnesplantoenhancetheexistingMississagiTSandAlgomaTSgenerationrejectionschemes,scheduledforcompletionduringthelastquarterof2014,isexpectedtoimprovethe

    powertransfercapabilityofthetransmissioncorridoreastofMississagi.

    May 20, 2010 Publ ic Page v i

  • 8/6/2019 IESO 18MonthOutlook_2010may

    7/36

    IESO_REP_0608v1.0 18-Month Outlook

    RetirementoftheNortheast25Hzsystemwascompletedduringthefirstquarterof2010.Therearenomore25Hzfacilitiesoperatingintheprovince.

    Operability

    SBGconditionsareexpectedinsummer2010and2011. InNovemberandDecember2010,scheduledoutagesontheOntarioNewYorkinterconnectionatNiagarawillimpactOntariosabilitytoexportpower,andincreasethe

    riskofSBG. Theexportassumptionhasbeenrevisedtoaccountforincreasedexportcapacity

    viatheHVDCtietoQuebec,aswellasreducedexportcapacityduringsignificantplanned

    outagestoOntariointerconnections.

    EndofSection

    May 20, 2010 Publ ic Page v i i

  • 8/6/2019 IESO 18MonthOutlook_2010may

    8/36

    IESO_REP_0608v1.0 18-Month Outlook

    May 20, 2010 Publ ic Page v i i i

    Caution and Disclaimer

    Thecontentsofthesematerialsarefordiscussionandinformationpurposesandareprovidedas

    iswithoutrepresentationorwarrantyofanykind,includingwithoutlimitation,accuracy,

    completenessorfitnessforanyparticularpurpose. TheIndependentElectricitySystemOperator

    (IESO)assumesnoresponsibilitytoyouoranythirdpartyfortheconsequencesofanyerrorsor

    omissions. TheIESOmayrevisethesematerialsatanytimeinitssolediscretionwithoutnotice

    toyou. AlthougheveryeffortwillbemadebytheIESOtoupdatethesematerialstoincorporate

    anysuchrevisionsitisuptoyoutoensureyouareusingthemostrecentversion.

  • 8/6/2019 IESO 18MonthOutlook_2010may

    9/36

    IESO_REP_0608v1.0 18-Month Outlook

    Table of Contents

    Executive Summary .......................................................................................... iiiConc lusions & Observat ions .............................................................................. vTable of Contents .............................................................................................. ix Li st of Tables ...................................................................................................... xLi st of Figu res .................................................................................................... x1.0 Introduct ion ............................................................................................ 12.0 Updates to This Outlook .......................................................................... 3

    2.1 Updates to Demand Forecast .................................................................................... 32.2 Updates to Resources ............................................................................................... 32.3 Updates to Transmission Outlook ............................................................................... 32.4 Updates to Operability Outlook .................................................................................. 3

    3.0 Demand Forecast ..................................................................................... 54.0 Resource Adequacy Assessment ............................................................. 7

    4.1 Committed and Contracted Generation Resources ....................................................... 74.2 Summary of Scenario Assumptions ............................................................................ 84.3 Planned Scenario with Normal and Extreme Weather ................................................... 94.4 Firm Scenario with Normal and Extreme Weather ...................................................... 104.5 Comparison of Resource Scenarios........................................................................... 10

    5.0 Transm iss ion Reli ab ili ty Assessment .................................................... 13 5.1 Transmission and Load Supply Projects .................................................................... 135.2 Transmission Outages ............................................................................................. 135.3 Transmission System Adequacy ............................................................................... 14

    6.0 Operab il it y Assessment ......................................................................... 217.0 His tor ical Rev iew ................................................................................... 23

    7.1 Weather and Demand Historical Review ................................................................... 237.2 Hourly Resource Contributions at Time of Weekday Peak ........................................... 237.3 Report on Initiatives ............................................................................................... 267.4 Variation from Previous Year ................................................................................... 26

    May 20, 2010 Publ ic Page ix

  • 8/6/2019 IESO 18MonthOutlook_2010may

    10/36

    IESO_REP_0608v1.0 18-Month Outlook

    May 20, 2010 Publ ic Page x

    List of Tables

    Table 3.1: Forecast Summary ................................................................................................ 5Table 4.1 Existing Generation Resources as of May 5, 2010 ..................................................... 7 Table 4.2 Committed and Contracted Generation Resources .................................................... 8Table 4.3 Summary of Scenario Assumptions .......................................................................... 9Table 4.4 Summary of Available Resources ........................................................................... 10List of Figures

    Figure 4.1 Reserve Above Requirement: Planned Scenario with Normal vs. Extreme Weather ..... 9Figure 4.2 Reserve Above Requirement: Firm Scenario with Normal vs. Extreme Weather ........ 10Figure 4.3 Reserve Above Requirement: Planned Scenario with Present Outlook vs. Previous

    Outlook ...................................................................................................................... 11Figure 5.1 Greater Toronto Area Electricity System................................................................ 15Figure 6.1 Minimum Demand and Baseload Generation ......................................................... 21Figure 7.2.1 Wind Contributions at the Time of Weekday Peak ............................................... 24Figure 7.2.2 Hydro Contributions (Energy and Operating Reserve) at the Time of Weekday Peak

    ................................................................................................................................. 24Figure 7.2.3 Imports into Ontario at the Time of Weekday Peak ............................................. 25Figure 7.2.4 Net Interchange into Ontario at the Time of Weekday Peak ................................. 26

  • 8/6/2019 IESO 18MonthOutlook_2010may

    11/36

    IESO_REP_0608v1.0 18-Month Outlook

    1.0 Introduction

    ThisOutlookcoversthe18monthperiodfromJune2010toNovember2011andsupersedesthe

    lastOutlookreleasedinFebruary2010.

    Thepurposeofthe18MonthOutlookis:

    ToadvisemarketparticipantsoftheresourceandtransmissionreliabilityoftheOntarioelectricitysystem;

    Toassesspotentiallyadverseconditionsthatmightbeavoidedthroughadjustmentorcoordinationofmaintenanceplansforgenerationandtransmissionequipment;and

    Toreportoninitiativesbeingputinplacetoimprovereliabilitywithinthe18monthtimeframeofthisOutlook.

    ThecontentsofthisOutlookfocusontheassessmentofresourceandtransmissionadequacy.

    AdditionalsupportingdocumentsarelocatedontheIESOwebsiteat

    http://www.ieso.ca/imoweb/monthsYears/monthsAhead.asp

    ThisOutlookpresentsanassessmentofresourceandtransmissionadequacybasedonthestated

    assumptions,usingthedescribedmethodology. Readersmayenvisionotherpossiblescenarios,

    recognizingtheuncertaintiesassociatedwithvariousinputassumptions,andareencouragedto

    usetheirownjudgmentinconsideringpossiblefuturescenarios.

    SecurityandAdequacyAssessmentsarepublishedontheIESOwebsiteonaweeklyanddaily

    basis,andprogressivelysupersedeinformationpresentedinthisreport.

    ReadersareinvitedtoprovidecommentsonthisOutlookreportortogivesuggestionsastothe

    contentoffuturereports. Todoso,pleasecontactusat:

    TollFree: 18884487777 Tel: 9054036900 Fax: 9054036921 Email:[email protected].

    EndofSection

    May 20, 2010 Publ ic Page 1

    http://www.ieso.ca/imoweb/monthsYears/monthsAhead.asphttp://www.ieso.ca/imoweb/monthsYears/monthsAhead.asphttp://www.ieso.ca/imoweb/marketdata/ssrsaa.asphttp://www.ieso.ca/imoweb/marketdata/ssrsaa.asphttp://www.ieso.ca/imoweb/marketdata/ssrsaa.asphttp://www.ieso.ca/imoweb/marketdata/ssrsaa.asphttp://www.ieso.ca/imoweb/marketdata/ssrsaa.asphttp://www.ieso.ca/imoweb/marketdata/ssrsaa.asphttp://www.ieso.ca/imoweb/marketdata/ssrsaa.aspmailto:[email protected]:[email protected]://www.ieso.ca/imoweb/marketdata/ssrsaa.asphttp://www.ieso.ca/imoweb/monthsYears/monthsAhead.asp
  • 8/6/2019 IESO 18MonthOutlook_2010may

    12/36

    IESO_REP_0608v1.0 18-Month Outlook

    Thispageintentionallyleftblank.

    May 20, 2010 Publ ic Page 2

  • 8/6/2019 IESO 18MonthOutlook_2010may

    13/36

    IESO_REP_0608v1.0 18-Month Outlook

    2.0 Updates to This Outlook

    2.1 Updates to Demand Forecast

    Thedemandforecastwasbasedonactualdemand,weatherandeconomicdatathroughtothe

    endofFebruary2010. Theeconomicoutlookhasbeenupdatedbasedonthemostrecentdata.

    ActualweatheranddemanddataforMarchandAprilhavebeenincludedinthetables.

    2.2 Updates to Resources

    Installedcapacityhasincreasedby296MWasaresultofthefollowingchanges:

    Nuclearupgrade(+20MW) RetirementofWawaitin25Hz (11MW) ThoroldCogenerationProject(+287MW) TheconversionofFortFrances(47MW)fromgastobiomass

    TheassessmentusesplannedgeneratoroutagesassubmittedbymarketparticipantstotheIESOsIntegratedOutageManagementSystem(IOMS). ThisOutlookisbasedonsubmitted

    generationoutageplansasofApril21,2010.

    2.3 Updates to Transmission Outlook

    Thelistoftransmissionprojects,plannedtransmissionoutagesandactualexperiencewithforced

    transmissionoutageshavebeenupdatedfromtheprevious18MonthOutlook. ForthisOutlook,

    transmissionoutageplanssubmittedtotheIOMSasofMarch25,2010wereused.

    2.4 Updates to Operabil ity Outlook

    Aforecastofsurplusbaseloadgeneration(SBG)conditionsforthenext18monthshasbeen

    updatedwithsubmittedgenerationoutageplansasofApril21,2010. Theexpectedcontribution

    tobaseloadfromvariableresourcessuchashydroelectricandwindgenerationhasalsobeen

    updatedtoreflectthemostrecentinformation.

    EndofSection

    May 20, 2010 Publ ic Page 3

  • 8/6/2019 IESO 18MonthOutlook_2010may

    14/36

    IESO_REP_0608v1.0 18-Month Outlook

    May 20, 2010 Publ ic Page 4

    Thispageintentionallyleftblank.

  • 8/6/2019 IESO 18MonthOutlook_2010may

    15/36

    IESO_REP_0608v1.0 18-Month Outlook

    3.0 Demand Forecast

    TheIESOisresponsibleforforecastingelectricitydemandontheIESOcontrolledgrid. This

    demandforecastcoverstheperiodJune2010toNovember2011andsupersedestheprevious

    forecastreleasedFebruary2010. Tablescontainingsupportinginformationarecontainedinthe

    2010Q2OutlookTablesspreadsheet.

    ElectricitydemandisexpectedtoincreaseovertheforecasthorizonastheOntarioeconomy

    experiencesgrowththroughout201011. Industrialdemandwillnotreturntoprerecession

    levelsbutwillshowimprovementoverthelowsof2009. Thehighdollarwillcontinuetoactasa

    moderatoronOntarioselectricallyintensiveexportbasedindustries.

    Peakdemandsareexpectedtoremainflatovertheforecasthorizonasconservationprograms,

    thegrowthinembeddedgenerationandtimeofuserateswillacttooffsetincreasesfrom

    economicanddemographicgrowth.

    Thefollowingtableshowstheseasonalpeaksandannualenergydemandovertheforecast

    horizonoftheOutlook.

    Table 3.1: Forecast Summ ary

    Season Normal Weather Peak (MW) Extreme Weather Peak (MW)

    Summer 2010 23,498 25,998

    Winter 2010-11 22,473 23,782

    Summer 2011 23,464 25,938

    Year Normal Weather Energy (TWh) % Growth in Energy

    2006 Energy 152.3 -1.9%

    2007 Energy 151.6 -0.5%

    2008 Energy 148.9 -1.8%

    2009 Energy 140.4 -5.7%

    2010 Energy (Forecast) 142.2 1.3%

    2011 Energy (Forecast) 143.6 1.0%

    ForecastDetails

    Thecompaniondocument,theOntarioDemandForecast,looksatdemandinmoredetail. It

    containsthefollowing:

    detailsonthedemandforecast, analysisofhistoricaldemand, discussionoftheimpactofthedriversaffectingdemand.

    ThedatacontainedintheOntarioDemandForecastdocumentareincludedinthe2010Q2

    OutlookTablesspreadsheet.

    EndofSection

    May 20, 2010 Publ ic Page 5

    http://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xls
  • 8/6/2019 IESO 18MonthOutlook_2010may

    16/36

    IESO_REP_0608v1.0 18-Month Outlook

    May 20, 2010 Publ ic Page 6

    Thispageintentionallyleftblank.

  • 8/6/2019 IESO 18MonthOutlook_2010may

    17/36

    IESO_REP_0608v1.0 18-Month Outlook

    4.0 Resource Adequacy Assessment

    Thissectionprovidesanassessmentoftheadequacyofresourcestomeettheforecastdemand.

    Thekeymessagesare:

    Whenreservesarebelowrequiredlevelswithpotentiallyadverseeffectsonthereliabilityofthegrid,theIESOhastheauthoritytorejectoutagesbasedontheirorderof

    precedence.

    Conversely,anopportunityexistsforadditionaloutageswhenreservesareaboverequiredlevels.

    Theseactionsaddressshortagesandsurplusesofreservestoalargeextent.

    Inrecognitionoftheuncertaintythatexistsregardingthefutureavailabilityofresources,two

    resourcescenariosaredescribedinthissection:theFirmScenarioandthePlannedScenario

    OverthecourseoftheOutlookperiodabout2,900MWofnewandrefurbishedsupplyis

    scheduledtocomeintoservice.Mostofthenewsupplyprojectshavestartedtheir

    commissioningphaseorareintheconstructionphase.

    TheexistinginstalledgeneratingcapacityissummarizedinTable4.1. Thisexcludescapacitythat

    iscommissioning.

    Table 4.1 Existing Generation R esources as of May 5, 2010

    Fuel Type

    Total

    Installed

    Capacity

    (MW)

    Forecast

    Capability at

    Summer

    Peak* (MW)

    Number of

    Stations

    Change in

    Installed

    Capacity

    (MW)

    Change

    in

    Stations

    Nuclear 11,446 10,767 5 20 0

    Hydroelectric 7,903 5,817 70 -11 0Coal 6,434 6,161 4 0 0

    Oil / Gas 8,792 7,242 27 240 0

    Wind 1,084 137 8 0 0

    Biomass / Landfill Gas 122 47 6 47 1

    Total 35,781 30,170 120 296 1

    * Actual Capability may be less as a result of transmission constraints

    4.1 Commit ted and Contracted Generation Resources

    Table4.2summarizesgenerationthatisscheduledtocomeintoservice,beupgradedorshut

    downwithintheOutlookperiod. ThisincludesgenerationprojectsintheIESOsConnection

    AssessmentandApprovalProcess(CAA)thatareunderconstructionandprojectscontractedbytheOPA. DetailsregardingtheIESOsCAAprocessandthestatusoftheseprojectscanbefound

    ontheIESOswebsiteathttp://www.ieso.ca/imoweb/connassess/ca.asp.

    TheestimatedeffectivedateinTable4.2indicatesthedateonwhichadditionalcapacityis

    assumedtobeavailabletomeetOntariodemandorshutdown. Forprojectsthatareunder

    contract,theestimatedeffectivedateisthebestestimateofthedatewhenthecontractrequires

    theadditionalcapacitytobeavailable. Ifaprojectisdelayedtheestimatedeffectivedatewillbe

    thebestestimateofthecommercialinservicedatefortheproject.

    May 20, 2010 Publ ic Page 7

    http://www.ieso.ca/imoweb/connassess/ca.asphttp://www.ieso.ca/imoweb/connassess/ca.asp
  • 8/6/2019 IESO 18MonthOutlook_2010may

    18/36

    IESO_REP_0608v1.0 18-Month Outlook

    Table 4.2 Comm itted and Contracted Generation Resources

    Firm

    (MW)

    Planned

    (MW)

    Halton Hills Generating Station Southwest Gas 2010-Q3 Commissioning 632 632

    Shutdown of Lambton G1 and G2 West Coal 2010-Q4 -970 -970

    Shutdown of Nanticoke G3 and G4 Southwest Coal 2010-Q4 -980 -980

    Return of Sandy Falls as 60 Hz plant Northeast Water 2010-Q4 ConstructionReturn of Lower Stur

    pacitCa

    5geon as 60 Hz plant Northeast Water 2010-Q4 Construction 14

    Return of Wawaitin as 60 Hz plant Northeast Water 2010-Q4 Construction 15

    Hound Chute Northeast Water 2010-Q4 Construction 10

    Grid-connected FIT Projects West Wind 2010Q4 At Various Stages 166

    Raleigh Wind Energy Centre West Wind 2011-Q1 Construction 78

    Leamington Pollution Control Plant West Oil 2011-Q1 Approvals & Permits 2

    Bruce Unit 2 Bruce Uranium 2011-Q3 2011-Q1 Construction 750

    Grid-connected FIT Projects Northeast Wind 2011-Q1 At Various Stages 60

    Grid-connected FIT Projects West Wind 2011-Q1 At Various Stages 49

    Grid-connected FIT Projects Southwest Wind 2011-Q2 At Various Stages 69

    Becker Cogeneration Northwest Biomass 2011-Q3 Approvals & Permits 15

    Bruce Unit 1 Bruce Uranium 2011-Q4 2011-Q3 Construction 750

    Grid-connected FIT Projects Southwest Wind 2011-Q3 At Various Stages 125

    Kruger Energy Chatham Wind Project Southwest Wind 2011-Q4 Approvals & Permits 101

    Total -1 ,3 1 8 8 9 0

    ConsideredEstimated

    Change

    (PreviousProponent/Project Name Zone Fuel Type Effective

    DateReported

    Date)

    Project Status

    NotestoTable4.2:1. ShadingindicatesachangefromthepreviousOutlook.2. Thetotalmaynotaddupduetorounding. Totaldoesnotincludeinservicefacilities.3. Projectstatusprovidesanindicationoftheprojectprogress. Themilestonesusedare:

    a. ConnectionAssessment theprojectisundergoinganIESOsystemimpactassessmentb. Approvals&Permits theproponentisacquiringmajorapprovalsandpermitsrequired

    tostartconstruction(e.g.environmentalassessment,municipalapprovalsetc.)

    c. Construction theprojectisunderconstructiond. Commissioning theprojectisundergoingcommissioningtestswiththeIESO

    4.2 Summ ary of Scenario Assumptions

    Inordertoassessfutureresourceadequacy,theIESOmustmakeassumptionsontheamountof

    availableresources. TheOutlookconsiderstwoscenarios:aFirmScenarioandaPlanned

    Scenario

    as

    compared

    in

    Table

    4.3

    BothscenariosstartingpointistheexistinginstalledresourcesshowninTable4.1.Theplanned

    scenarioassumesthatallresourcesthatarescheduledtocomeintoserviceareavailableoverthe

    studyperiodwhiletheFirmScenarioonlyassumesthosescheduledtocomeintoserviceoverthe

    first3months. Bothscenariosrecognizethatresourcesthatareinservicearenotavailableduring

    timesforwhichthegeneratorhassubmittedplannedoutages.Whatisalsoconsideredforboth

    scenariosisthegeneratorplannedshutdownorretirementwhichhashighcertaintyof

    happeninginthefuture. TheFirmandPlannedScenariosalsodifferintheirassumptions

    regardingtheamountofdemandmeasuresandgenerationcapacity.

    Thegenerationcapabilityassumptionsareasfollows:

    Hydroelectric

    capability

    (including

    energy

    and

    operating

    reserve)

    is

    based

    on

    median

    historicalvaluesduringweekdaypeakdemandhoursfromMay2002toMarch2010.

    Thermalgeneratorscapacityandenergycontributionsarebasedonmarketparticipantsubmissions,includingplannedoutages,expectedforcedoutageratesandseasonal

    deratings.

    ForwindgenerationthemonthlyWindCapacityContribution(WCC)valuesareusedatthetimeofweekdaypeak,whiletotalenergycontributionisassumedtobe30%.

    May 20, 2010 Publ ic Page 8

  • 8/6/2019 IESO 18MonthOutlook_2010may

    19/36

    IESO_REP_0608v1.0 18-Month Outlook

    Table 4.3 Summ ary of Scenario Assumptions

    Total Capacity Total Capacity

    35,781 MW 35,781 MW

    All

    Only Capacity Changes,

    Generator shutdowns or

    retirements, Commissioning

    Generators and Generators

    starting in the first 3 months

    890 MW -1,318 MW

    Incremental Existing

    1114 MW 699 MWDemand Measures

    Incremental growth of 150 MW on peak

    Incremental

    Incremental

    Deman

    dForecast Conservation

    Embedded Generation

    Incremental growth of 128 MW on peak

    Assumptions Planned Scenario Firm Scenario

    Resource

    Existing Installed

    Resources

    New Generation and

    Capacity Changes

    4.3 Planned Scenario w ith Normal and Extreme Weather

    ReserveAboveRequirementlevels,whichrepresentthedifferencebetweenAvailableResources

    andRequiredResources,areshowninFigure4.1.

    Figure 4.1 Reserve Above Requirement: Planned Scenario with Normal vs. Extreme Weather

    -6,000

    -4,000

    -2,000

    06 Jun 2010 05 Sep 2010 05 Dec 2010 06 Mar 2011 05 Jun 2011 04 Sep 2011

    ReserveA

    Week Ending

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    bo

    veRequirement[MW]

    Planned ScenarioNormal Weather

    Reserve Above Requirement = Available Resources - (Demand + R equired Reserve)

    Planned ScenarioExtreme Weather

    Reserve Above Requirement = Available Resources - (Demand + R equired Reserve)

    May 20, 2010 Publ ic Page 9

  • 8/6/2019 IESO 18MonthOutlook_2010may

    20/36

    IESO_REP_0608v1.0 18-Month Outlook

    4.4 Firm Scenario w ith Normal and Extreme Weather

    ReserveAboveRequirementlevels,whichrepresentthedifferencebetweenAvailableResources

    andRequiredResources,areshowninFigure4.2.

    Figure 4.2 Reserve Above Requirement: Firm Scenario with Normal vs. Extreme Weather

    -6,000

    -4,000

    -2,000

    0

    2,000

    4,000

    6,000

    06 Jun 2010 05 Sep 2010 05 Dec 2010 06 Mar 2011 05 Jun 2011 04 Sep 2011

    ReserveAboveRequirement[

    Week Ending

    8,000

    10,000

    MW]

    Firm ScenarioExtreme Weather

    Firm ScenarioNormal Weather

    Reserve Above Requirement = Available Resources - (Demand + R equired Reserve)

    4.5 Comparison of Resource Scenarios

    Table4.4showsasnapshotoftheforecastavailableresources,underthetwoscenarios,atthe

    timeofthesummerandwinterpeakdemandsduringtheOutlook.

    Themonthlyforecastofenergyproductioncapability,asprovidedbymarketparticipants,is

    includedinthe2010Q2OutlookTablesAppendixA,TableA7.

    Table 4.4 Summ ary of Available Resources

    Firm

    Scenario

    Planned

    Scenario

    Firm

    Scenario

    Planned

    Scenario

    Firm

    Scenario

    Planned

    Scenario1 Installed Resources (MW) 35,781 35,781 34,463 34,751 34,463 35,805

    2 Imports (MW) 0 0 0 0 0 0

    3 Total Resources (MW) 35,781 35,781 34,463 34,751 34,463 35,805

    4 Total Reductions in Resources (MW) 7,435 7,435 3,986 4,264 5,646 6,203

    5 Demand Measures (MW) 699 951 699 1,042 699 1,114

    6 Available Resources (MW) 29,045 29,297 31,176 31,529 29,516 30,716

    NotesSummer Peak 2010 Winter Peak 2011 Summer Peak 2011

    Description

    NotestoTable4.4:

    1. InstalledResources: Thisisthetotalgenerationcapacityassumedtobeinstalledatthetimeofthesummerandwinterpeaks.

    2. Imports: TheamountofexternalcapacityconsideredtobedeliveredtoOntario.3. TotalResources: ThesumofInstalledResources(line1)andImports(line2).4. TotalReductionsinResources: Representthesumofderatings,plannedoutages,limitationsdueto

    transmissionconstraints,generationconstraintsduetotransmissionoutages/limitationsandallowance

    forcapabilitylevelsbelowratedinstalledcapacity.

    5. DemandMeasures: Theamountofdemandavailabletobereduced.6. AvailableResources: EqualsTotalResources(line3)minusTotalReductionsinResources(line4)plus

    DemandMeasures(line5).

    May 20, 2010 Publ ic Page 10

    http://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xls
  • 8/6/2019 IESO 18MonthOutlook_2010may

    21/36

    IESO_REP_0608v1.0 18-Month Outlook

    ComparisonoftheWeeklyAdequacyAssessmentsforthePlannedScenario

    Figure4.3providesacomparisonbetweentheforecastReserveAboveRequirementvaluesinthe

    presentOutlookandtheforecastReserveAboveRequirementvaluesinthepreviousOutlook

    publishedonFebruary23,2010. Thedifferenceismainlyduetothechangestooutages,in

    servicedelaysandthechangeinthedemandforecast.

    Figure 4.3 Reserve Above Requirement: Planned Scenario with Present Outlook vs. Previous

    Outlook

    -6,000

    -4,000

    -2,000

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    06 Jun 2010 05 Sep 2010 05 Dec 2010 06 Mar 2011 05 Jun 2011 04 Sep 2011

    Rese

    rveAboveRequirement[MW]

    Week Ending

    Previous Outlook

    Planned Scenario

    Present OutlookPlanned Scenario

    Reserve Above Requirement = Available Resources - (Demand + R equired Reserve)

    Normal W eather

    ResourceadequacyrisksarediscussedindetailintheMethodologytoPerformLongTerm

    Assessments(IESO_REP_0266).

    EndofSection

    May 20, 2010 Publ ic Page 11

    http://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdf
  • 8/6/2019 IESO 18MonthOutlook_2010may

    22/36

    IESO_REP_0608v1.0 18-Month Outlook

    May 20, 2010 Publ ic Page 12

    Thispageintentionallyleftblank.

  • 8/6/2019 IESO 18MonthOutlook_2010may

    23/36

    IESO_REP_0608v1.0 18-Month Outlook

    5.0 Transmission Reliability Assessment

    ThissectionprovidesanassessmentofthereliabilityoftheOntariotransmissionsystemforthe

    Outlookperiod. Thetransmissionreliabilityassessmenthasthreekeyobjectives:

    ToidentifyallmajortransmissionandloadsupplyprojectsthatareplannedforcompletionduringtheOutlookperiodandtopresenttheirreliabilitybenefits.

    Toforecastanyreductionintransmissioncapacitybroughtaboutbyspecifictransmissionoutages. Foramajortransmissioninterfaceorinterconnection,thereductionintransmission

    capacityduetoanoutageconditioncanbeexpressedasachangeinthebaseflowlimit

    associatedwiththeinterfaceorinterconnection.

    ToidentifyequipmentoutageeventsonthegridthatcouldrequirecontingencyplanningbymarketparticipantsorbytheIESO. Plannedtransmissionoutagesarereviewedin

    conjunctionwithmajorplannedresourceoutagesandthescheduledcompletionofnew

    generationandtransmissionprojectstoidentifytransmissionreliabilityrisks.

    5.1 Transmission and Load Supply Projects

    TheIESOrequirestransmitterstoprovideinformationonthetransmissionprojectsthatare

    plannedforcompletionwithinthe18monthperiod. Constructionofseveraltransmission

    reinforcementsareplannedforserviceduringtheOutlookperiod.Majortransmissionandload

    supplyprojectsplannedtobeinserviceareshowninAppendixB. Projectsthatareinserviceor

    whosecompletionhasbeendeferredwellbeyondtheperiodofthisOutlookarenotshown. The

    listincludesonlythetransmissionprojectsthatrepresentmajormodificationsorareconsidered

    toprovidesignificantimprovementtosystemreliability.Minortransmissionequipment

    replacementsorrefurbishmentsareexcluded.

    Demandgrowthoverthelastdecadehasresultedinsomearealoadsreachingorexceedingthe

    capabilityofthelocaltransmissionsystem. Toaddressthisproblemandprovideadditional

    transmissioncapacityforfutureloadgrowth,Ontariotransmittersanddistributorshaveinitiated

    planstobuildneworreplaceexistingtransformerstationsandreinforcethetransmissionsystem

    asnecessary.

    TheseneededreinforcementswereconfirmedbytheIESOduringrelatedconnection

    assessments. Severaloftheseprojectsarecurrentlyunderconstructionandplannedforinservice

    duringtheperiodofthisOutlook.

    5.2 Transmission Outages

    Theassessmentoftransmissionoutagesislimitedtothosewithascheduleddurationofgreater

    thanfivedaysortothoseoutagesthatarepartofaprojectwherethecombinedscheduled

    durationisgreaterthanfivedays. Asthestarttimeoftheoutageapproaches,actualoutage

    scheduleandadditionaloutagerequirements,aswellasoutageswithascheduleddurationof

    fivedaysorlesscouldimposefurthertransmissioncapacityrestrictions. Priortoapprovingand

    releasinganoutage,theIESOwillreassesstheoutageforpotentialsystemimpacts,takinginto

    accountallcurrentandforecastedconditions.

    TheIESOsassessmentofthetransmissionoutageplansisshowninAppendixC,TablesC1to

    C10. Inthesetables,eachelementisassessedindividuallybyindicatingthepossibleimpactsand

    May 20, 2010 Publ ic Page 13

    http://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xls
  • 8/6/2019 IESO 18MonthOutlook_2010may

    24/36

    IESO_REP_0608v1.0 18-Month Outlook

    thereductionintransmissioninterfaceandinterconnectionlimits.Wheremultipleoutagesare

    scheduledduringthesameperiod,thecombinedeffectofalloutagesonthereductionin

    transmissioninterfaceandinterconnectionlimitsispresented.Wheremultipleoutagesare

    scheduledduringthesameperiodandreliabilityisaffected,theIESOwillrequestthetransmitter

    toreschedulesomeoftheoutages. Themethodologyusedtoassessthetransmissionoutage

    plansisdescribedintheIESOdocumenttitledMethodologytoPerformLongTerm

    Assessments(IESO_REP_0266).

    Theplannedtransmissionoutagesarereviewedincorrelationwithmajorplannedresource

    outagesandscheduledcompletiondatesofnewgenerationandtransmissionprojects. This

    allowstheIESOtoidentifytransmissionsystemreliabilityconcernsandtohighlightthoseoutage

    plansthatneedtobeadjusted. Achangetoanoutagemayincludereschedulingtheoutage,

    reducingthescheduleddurationorreducingtherecalltime.

    Thisassessmentwillalsoidentifyanyresourcesthathavepotentialorareforecasttobe

    constrainedduetotransmissionoutageconditions. Transmittersandgeneratorsareexpectedto

    haveamutualinterestindevelopinganongoingarrangementtocoordinatetheiroutage

    planningactivities. TransmissionoutagesthatmayaffectgenerationaccesstotheIESO

    controlledgridshouldbecoordinatedwiththegeneratoroperatorsinvolved,especiallyattimes

    whendeficiencyinreserveisforecast. UndertheMarketRules,wheretheschedulingofplanned

    outagesbydifferentmarketparticipantsconflictssuchthatbothoralloutagescannotbe

    approvedbytheIESO,theIESOwillinformtheaffectedmarketparticipantsandrequestthat

    theyresolvetheconflict. Iftheconflictremainsunresolved,theIESOwilldeterminewhichofthe

    plannedoutagescanbeapprovedaccordingtothepriorityofeachplannedoutageasdetermined

    bytheMarketRulesdetailedinChapter5,Sections6.4.13to6.4.18. ThisOutlookcontains

    transmissionoutageplanssubmittedtotheIESOasofMarch25,2010.

    5.3 Transmission System Adequacy

    Generally,IESOOutlooksidentifytheareasoftheIESOcontrolledgridwheretheprojected

    extremeweatherloadingisexpectedtoapproachorexceedthecapabilityofthetransmission

    facilitiesfortheconditionsforecastintheplanningperiod. Wheretheloadingisprojectedto

    exceedthecapabilityofthetransmissionfacilities,thereisalsoanincreasedriskofload

    interruptions.

    TheOntariogenerationmixischangingrapidlywiththeadditionofnewformsofresourcesand

    theplannedshutdownofcoalresources. Thetransmissionsystemneedstoevolveto

    accommodatethesupplymixchangesandtheincorporationofnewgenerationwhile

    maintainingthereliabledeliveryofelectricitytotheconsumers. Overthelastfewyears,Hydro

    One,theOPAandtheIESOhavebeencollaboratinginthedevelopmentofanumberof

    transmissionenhancementsrequiredtoaccommodatethesechanges. Someofthesetransmission

    enhancementsarescheduledtocomeintoserviceduringtheperiodofthisOutlook.

    TheIESOworkswithHydroOneandotherOntariotransmitterstoidentifythehighestpriority

    transmissionneeds,andtoensurethatthoseprojectswhoseinservicedatesareatriskaregiven

    asmuchpriorityaspractical,especiallythoseaddressingreliabilityneedsforpeakdemand

    periodsofthisOutlook.WehavealsobeenworkingcloselywiththeOPAtospecifythe

    transmissionenhancementslocation,timingandrequirementstosatisfyreliabilitystandards.

    May 20, 2010 Publ ic Page 14

    http://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdfhttp://www.ieso.ca/imoweb/pubs/marketReports/Methodology_RTAA_2010may.pdf
  • 8/6/2019 IESO 18MonthOutlook_2010may

    25/36

    IESO_REP_0608v1.0 18-Month Outlook

    Withinthecontextofthisapproach,theOntariotransmissionsystemwiththeplannedsystem

    enhancementsandknowntransmissionoutagesisexpectedtobeadequatetosupplythedemand

    underthenormalweatherconditionsforecastfortheOutlookperiod.

    5.3.1 Toronto and Surrounding Area

    TheGreaterTorontoArea(GTA)electricitysupplyismainlyprovidedbytheTrafalgar,

    Claireville,ParkwayandCherrywood500/230kVautotransformers,Pickeringgenerationstation

    (GS)andotherlocalresourcesasdepictedinFigure5.1. Theavailabilityofthesefacilitiesis

    criticaltoensuringreliableelectricitysupplyforTorontoandsurroundingarea.

    Figure 5.1 Greater Toronto Area Electricity System

    ThereliablesupplyofdemandintheGTAunderextremeweatherconditionsforecastedforthe

    Outlookperiodrequiresaminimumnumberof500/230kVautotransformersatTrafalgar,

    Claireville,ParkwayandCherrywoodandPickeringunitsinserviceatratedcapabilities. Forthe

    summer2010forecastedpeakdemand,all500/230kVautotransformersareexpectedtobein

    service. TheprojectedloadingsontheTrafalgar,Claireville,ParkwayandCherrywood500/230

    kVautotransformers,undernormalweatherconditions,areexpectedtobewithintheircapability

    duringtheseplannedoutages. Underextremeweatherconditions,duetoalongtermderated

    May 20, 2010 Publ ic Page 15

  • 8/6/2019 IESO 18MonthOutlook_2010may

    26/36

    IESO_REP_0608v1.0 18-Month Outlook

    Trafalgarautotransformer,someloadreductionmeasuresmayberequiredtomanageadditional

    contingencies.

    ThecapabilityoftheGTA500/230kVautotransformersissufficienttosupplythesummer2010

    normalandextremeweatherdemand. IfanyoneGTA500/230kVautotransformerisforcedoutofservice,thecapabilityoftheremainingtransformerswillsufficeaslongasatleastfour

    Pickeringunitsareinserviceatthetimeofthecontingency. Similarly,atleastfivePickering

    unitswouldneedtobeinservicetooffsetthelossoftwo500/230kVautotransformers.

    Subsequentautotransformer,generationoutagesorderatescouldresultinmitigatingmeasures

    beingrequiredtoreducetheremainingGTA500/230kVautotransformersloadingswithintheir

    capability.

    PortlandsEnergyCentreprovidesloadingreliefmainlytothe230/115kVLeaside

    autotransformersbutalsototheCherrywood500/230kVautotransformers. GorewayStation

    providessignificantloadingrelieftotheClaireville500/230kVautotransformers,especiallyin

    caseofmultipleautotransformeroutages. TheplannedadditionofHaltonHillsGSinthethird

    quarterof2010willfurtherreducethepeakloadingoftheTrafalgar500/230kVautotransformers

    andallowformoreoperationalflexibility.

    The230kVtransmissioncorridorbetweenTrafalgarTSandRichviewTSwhichsupplies

    Brampton,MississaugaandpartsofCaledonandHaltonHillscouldbecomeloadedverycloseto

    itscapabilityduringsummer2010underextremeweatherconditions. ThenewHurontario

    switchingstationandtheexpansionofthe230kVlinesfromCardiffTSthatwasrecentlyplaced

    inservicewillrelievetheloadingofthiscorridorandalleviatethisproblem.

    TheYorkregionloadservingcapabilitywillbereinforcedwiththeadditionofYorkEnergy

    Centrethatisscheduledtogoinserviceattheendof2011.

    OutagesfortheClairevilleTSenhancementworkcontinueduringthecurrentOutlookperiod.

    SomeoutageswillresultinsmallreductionstosouthernOntariotransmissioninterfacelimits.

    5.3.2 Bruce and Southwest Zones

    PlannedrefurbishmentsattheBrucegenerationstationandnewwindpowerresourcesin

    southwesternOntariowillincreasegenerationcapacityintheBruceandSouthwestzones. The

    neartermtransmissionreinforcementsrequiredtoaccommodatetheextragenerationareon

    schedulewiththeinstallationofoneadditionalcapacitoratBuchanan.

    Inadditiontotheneartermreinforcementsdescribedabove,interimmeasuresarebeingplanned

    forthetimewhenBruceisoperatedwithsevenandeightunitsbeforetheproposed500kV

    doublecircuitlinebetweenBruceandMiltonisavailable. Theinterimmeasuresincludethe

    installationofadditionaldynamicvoltagecontrolfacilitiesatNanticokeandDetweiler,

    scheduledtogoinserviceduringthesecondquarterof2011andwhennecessary,maximizing

    the

    available

    reactive

    power

    from

    the

    remaining

    Nanticoke

    units.

    These

    measures

    together

    with

    thenewshuntcapacitors,themodificationsoftheexistingBrucespecialprotectionsystemand

    plannedshutdownoffourcoalfiredunitsinOctober2010willfurtherreducethepotentialfor

    constrainedgeneration. Inthelongerterm,theproposed500kVlinefromBrucetoMiltonwill

    providetherequiredtransmissioncapabilitytodeliverthefullbenefitsoftheBruce

    refurbishmentprojectandthedevelopmentofnewrenewableresourcesinsouthwesternOntario.

    Topreventlowvoltageconditionsinthe115kVtransmissionsystemintheWoodstockarea

    duringsummerextremeweatherconditions,HydroOneisplanningtoaddanewtransformer

    May 20, 2010 Publ ic Page 16

  • 8/6/2019 IESO 18MonthOutlook_2010may

    27/36

    IESO_REP_0608v1.0 18-Month Outlook

    stationandasecondsupplypointbyextendingthe230kVtransmissionlinesfromIngersollto

    Woodstockareaandinstallinganew230/115kVtransformerstation. Theseplans,scheduledto

    becompletedduringthesecondquarterof2011,willprovideanincreasedlevelofsupply

    reliability,andsupportfurtherloadgrowthinthearea.

    HydroOneiscurrentlyundertakingmajorupgradeworkatBurlingtonTSwhichwillresolve

    limitationsinthestationsabilitytosupplytheBurlington115kVarealoads,allowfutureload

    growthandyieldamoreflexibleconfiguration. Theremainingwork,whichincludesthe

    replacementofall115kVbreakersandthereplacementoflimitingbussections,isscheduledto

    becompletedbytheendofthefourthquarterof2012.

    Theexisting115kVtransmissionfacilitiesintheGuelphareaareoperatingclosetocapacityand

    thereislimitedcapabilityavailabletosupplyadditionalload.HydroOne,theaffected

    transmitter,andtheOPAarereviewingvariousoptionsforenhancingtheoverallsupply

    capabilitytotheGuelphareaandadecisiononthepreferredsolutionisexpectedinthefallof

    2010.

    AsolutionalsoremainsrequiredintheCambridgearea,asexistingtransmissioninfrastructureis

    unabletomeettheIESOsloadrestorationcriteriafollowingacontingency. TheOPAis

    reviewingaproposaltoinstallgasfiredgenerationcapacityatCambridgePrestonTS.

    5.3.3 Niagara Zone and the New York Interconnection

    ThecompletiondatefortransmissionreinforcementsfromtheNiagararegionintotheHamilton

    Burlingtonareacontinuestobedelayed. ThisdelayimpactsboththeuseoftheavailableOntario

    generationintheNiagaraareaandimportsintotheprovince,particularlyduringhotweather

    andhighdemandperiods.

    The230kVcircuitBP76formsanintegralpartoftheOntario NewYorkinterfaceatNiagara

    Falls. Duetothevariablenatureofitsflows,thisinterfaceisoneofthemostchallengingto

    manage

    in

    the

    Eastern

    Interconnection,

    keeping

    system

    operators

    around

    the

    Great

    Lakes,

    which

    includetheIESO,NYISO,PJMandMISO,fullyengaged. Thelongtermforcedoutageofthe

    BP76interconnectionhascompoundedthecomplexitiesofthesereliabilitycoordinationefforts,

    addedtoOntariossurplusbaseloadgeneration(SBG)eventsandmateriallyledtoincreased

    nuclearreductionsandhydroelectricspillconditionsoverthelastyear. Plannedoutagesoftwo

    otherlinesoftheNiagarainterconnection(PA301andPA302)arecurrentlybeingplannedfor

    NovemberandDecember2010. Theseoutageshavethepotentialtoreducethescheduled

    transfercapabilityoftheNiagarainterconnectiontozeroandalsoimpacttheOntariotoMichigan

    transfers. Inordertohelpfacilitatethesepotentialoutages,theIESOrecentlydirectedHydro

    OnetoscheduleandcompletetheconstructionofabypassuntilthefailedR76voltageregulator

    isreplaced. TheexpectedreturntoserviceofBP76withR76replacediscurrentlyDecember

    2012.

    5.3.4 East Zone and Ottawa Zone

    SomeoutagesplannedoverthisOutlookperiodintheOttawaareawillreduceitssupply

    capabilitybutnoloadreductionmeasuresareexpectedtoberequired.

    May 20, 2010 Publ ic Page 17

  • 8/6/2019 IESO 18MonthOutlook_2010may

    28/36

    IESO_REP_0608v1.0 18-Month Outlook

    5.3.5 West Zone and the Michigan Interconnection

    TransmissionconstraintsinthiszonemayrestrictresourcesinsouthwesternOntarioandimports

    fromMichigan. ThisisevidentinthebottledgenerationamountsshownfortheBruceandWest

    zonesinTablesA3andA6. TheplannedshutdownoftwoLambtonGScoalfiredunitswill

    reduce,butnoteliminatetheamountofbottledgenerationinthiszone.

    Phaseangleregulators(PARs)areinstalledontheOntarioMichiganinterconnectionat

    LambtonTS,representingtwoofthefourinterconnectionswithMichigan,butarenotcurrently

    operationaluntilcompletionofagreementsbetweentheIESO,theMISO,HydroOneand

    InternationalTransmissionCompany. Theexpectedinservicedateisnotknownatthistime.

    TheoperationofthesePARsalongwiththePARontheOntarioMichiganinterconnectionnear

    Windsorwillcontrolflowstoalimitedextent,andassistinthemanagementofsystem

    congestion.

    ThecapabilitytocontrolflowsontheOntarioMichiganinterconnectionbetweenScottTSand

    BunceCreekisunavailable. ThePARinstalledatBunceCreekinMichiganhasfailedandis

    scheduledforreplacementbythebeginningofQ3in2010.

    5.3.6 Northeast and Northwest Zones

    ThetransmissioncorridoreastofMississagiTShasbeenexperiencingincreasedcongestiondue

    totheadditionofnewresourcesandlackoftransmissionreinforcements. Itisexpectedthat

    congestionwillincreaseevenfurtherwhenprojectscurrentlyunderconstructioninthearea

    becomeoperational.

    HydroOneisplanningtoimplementinthefourthquarterof2012someofthemodifications

    recommendedbytheIESOtotheexistingMississagigenerationrejectionschemethathasthe

    potentialtoalleviate,inthenearterm,theconstrainedgenerationwestofMississagi.

    TofurtherreducethecongestioninnorthernOntarioandimprovethetransfercapability,Hydro

    OneisplanningtoinstalladditionaldynamicreactivecompensationfacilitiesatPorcupineTS,in

    thefourthquarterof2010andKirklandLakeTS,inthefirstquarterof2011. Inpreparationfor

    additionalrenewablegenerationinnorthernOntario,HydroOneisplanningtoincreasethe

    northsouthtransfercapabilitybyinstallingseriescompensationatNobelSS,proposedtogoin

    serviceinthelastquarterof2010.

    During2010,extensiveworkonthetransmissioncircuitsintheKenora FortFrancesareais

    scheduled. TheassociatedoutageswillreducetheOntarioManitobaandOntarioMinnesota

    interconnectiontransfercapacityandalsotheEastWesttransmissioninterfacecapability. The

    reductionoftheEastWestTransferEast(EWTE)limitisexpectedtocontributetotheincreased

    amountofbottledgenerationintheNorthwestzone.

    ManaginggridvoltagesintheNorthwesthasalwaysrequiredspecialattention;withthe

    significantlylowerdemands,itisincreasinglydifficulttomaintainanacceptablevoltageprofile

    withoutcompromisingthesecurityandreliabilityofthesupply.

    Overthepastyearithasbecomemoredifficulttomanagevoltagesthroughoutthetransmission

    systeminnorthwesternOntario. Onseveraloccasionsnormaldispatchactionswereexhausted,

    andexceptionalvoltagecontrolmeasureswererequired,includingthetemporaryremovalofone

    ormoretransmissioncircuitsfromserviceduringlightloadorlowtransferconditionsto

    maintainvoltageswithinacceptableranges. Thisreducedthegridsabilitytowithstand

    May 20, 2010 Publ ic Page 18

    http://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xlshttp://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlookTables_2010may.xls
  • 8/6/2019 IESO 18MonthOutlook_2010may

    29/36

    IESO_REP_0608v1.0 18-Month Outlook

    disturbancesandsubsequentlyunderminedthecustomerssupplyreliability.Additionalreactive

    compensationisrequiredforvoltagecontrolinthezone.

    TheIESOhascontactedHydroOne,andisalsoinconversationswiththeOPA,inaneffortto

    examinetheshortandlongtermsolutionstothismatter.

    5.3.7 Ontario 25 Hz SystemThe25HzsysteminnortheasternOntariowasdecommissionedduringthefirstquarterof2010.

    Therearenomore25Hzfacilitiesoperatingintheprovince.

    EndofSection

    May 20, 2010 Publ ic Page 19

  • 8/6/2019 IESO 18MonthOutlook_2010may

    30/36

    IESO_REP_0608v1.0 18-Month Outlook

    May 20, 2010 Publ ic Page 20

    Thispageintentionallyleftblank.

  • 8/6/2019 IESO 18MonthOutlook_2010may

    31/36

    IESO_REP_0608v1.0 18-Month Outlook

    6.0 Operability Assessment

    TheIESOmonitorsexistingandemergingoperabilityissuesthatcouldpotentiallyimpactsystem

    reliability. InMarch2010,unseasonablywarmtemperaturescontributedtolowerthanforecast

    minimumdemands. Thisresultedinisolatedsurplusbaseloadgeneration(SBG)events,notably

    overtheEasterlongweekend.

    AforecastforSBGconditionsoverthenext18monthsispresentedbelow. Forecastminimum

    demandcontinuestotrendlowerthaninpreviousyears. Overthenext18months,theIESO

    expectstheriskofexperiencingSBGconditionswillbemostrelevantoverthesummerperiods.

    Figure6.1showsprojectedweeklyminimumdemandagainsttheexpectedlevelofbaseload

    generation. Baseloadgenerationassumptionshavebeenupdatedtoincludeexports,thelatest

    plannedoutageinformation,andinservicedatesforneworrefurbishedgeneration. The

    expectedcontributionfromselfschedulingandintermittentgenerationhasalsobeenupdatedto

    reflectthelatestdata.Outputfromcommissioningunitsisexplicitlyexcludedfromthisanalysis

    duetouncertaintyandhighlyvariablenatureofcommissioningschedules.

    Figure 6.1 Minim um Demand and Baseload Generation

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    06-Jun-10

    04-Jul-10

    01-Au

    14,000

    16,000

    g-10

    29-Aug-10

    26-Sep-10

    24-Oct-10

    21-Nov-10

    19-Dec-10

    16-Jan-11

    13-Feb-11

    13-Mar-11

    10-Apr-11

    08-May-11

    05-Jun-11

    03-Jul-11

    31-Jul-11

    28-Aug-11

    25-Sep-11

    23-Oct-11

    20-Nov-11

    MW

    Minimum Weekl y Demand Basel oad Generation

    NotableeventsinvolvingOntariosinterconnectionsoccurredin2009,includinglengthyplanned

    outagesontheOntarioNewYorkinterfacethatsignificantlylimitedintertiecapacitytoboth

    NewYorkandMichigan. Atthesametime,anew1,250MWtietoQuebecfacilitatedincreased

    intertiecapacitytowardstheendoftheyear. Asaresultofthesedevelopments,andinlightof

    similarplannedoutagestotheOntarioNewYorkinterfacecurrentlybeingassessedfor

    May 20, 2010 Publ ic Page 21

  • 8/6/2019 IESO 18MonthOutlook_2010may

    32/36

    IESO_REP_0608v1.0 18-Month Outlook

    May 20, 2010 Publ ic Page 22

    NovemberandDecember2010,the1,000MWexportassumptionthatwasusedinprevious

    Outlooksisbeingrevised.

    Goingforward,anominalexportassumptionof1,500MWwillbeappliedasadecrementto

    baseloadgenerationunderlimited,ornointerconnectionplannedoutages. Undermore

    significantinterconnectionplannedoutages1,suchastheNewYorkPA301andPA302outages

    scheduledforNovemberandDecember2010,anexportassumptionof1,200MWwillbeapplied

    toreflectthereducedexportcapabilityassociatedwiththeseplannedoutages. Theserevisednet

    exportassumptionswerederivedfromanexaminationofhistoricalnetexportdataduring

    periodsoflowOntariodemandfrom2008and2009,atvariouslevelsofaggregateexport

    capabilityandarealsoreflectiveofexternalmarketsabilitytoabsorbenergyatthattime. In

    recognitionofchangingmarketandsurplusbaseloadconditions,andtheirassociatedimpacton

    netexportvolumes,theIESOintendstoreviewandreviseasrequiredthenetexport

    assumptionsonanannualbasis.

    EndofSection

    1The 1,200 MW export assumption will be applied when forecast planned outages are expected to limit Ontarios

    aggregate export capacity to between 1,400MW and 2,600 MW. For forecast planned outages that further limit export

    capacity to below 1,400 MW, an export assumption value of 700 MW will be used. See Appendix C of the 18-Month

    Outlook Tables for forecast reduction to major transmission interface limits, including interconnection interfaces.

  • 8/6/2019 IESO 18MonthOutlook_2010may

    33/36

  • 8/6/2019 IESO 18MonthOutlook_2010may

    34/36

    IESO_REP_0608v1.0 18-Month Outlook

    Figure 7.2.1 Wind Contribut ions at the Time of Weekday P eak

    0

    200

    400

    600

    800

    1,000

    A pr-09 May-09 J un-09 J ul -0 9 A ug -09 Sep-09 Oct -09 N ov -09 Dec -09 J an- 10 F eb -10 Ma r-10

    MW

    Date

    1,200

    Actual Hourly Contribut ion

    Actual Monthly M edian

    Forecast Monthly M edian

    Commercially Operable Capacity

    Note: Commerciallyoperablecapacitydoesnotincludecommissioningunits. Thereforeactual

    hourlycontributionmayexceedcommercialcapability.

    Figure 7.2.2 Hydro Contributio ns (Energy and Operating Reserve) at the Time of W eekday Peak

    4,000

    4,500

    5,000

    5,500

    6,000

    6,500

    Apr-09 M ay-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 N ov-09 Dec-09 Jan-10 Feb-10 M ar-10

    MWC

    ontribution

    Date

    7,000

    Forecast M onth ly Med ian

    Actua l Month ly M ed ian

    Actua l Hour ly Contr ibut ion

    May 20, 2010 Publ ic Page 24

  • 8/6/2019 IESO 18MonthOutlook_2010may

    35/36

    IESO_REP_0608v1.0 18-Month Outlook

    Figure7.2.3showsimportsintoOntarioatthetimeofweekdaypeak. ThisyearOntario

    experiencedasignificantreductionindemand. Lowerdemandsandsurplusconditionscreated

    lowerpricesinOntariowhichmadeimportingintotheprovincelessattractivewhichiswhy

    importswerelowerthanprevioushistoricvalues.

    Figure 7.2.3 Im ports into Ontario at the Time of Week day Peak

    0

    50 0

    1,000

    1,500

    2,000

    2,500

    3,000

    Apr -09 May-09 Jun-09 Jul -09 Aug-09 Sep-09 Oct -09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10

    MW

    Date

    Actual Monthl y Median

    Actual Hourly Imports

    Figure7.2.4showstheamountofnetimportsintoOntarioatthetimeofweekdaypeak,

    excludingweekendsandholidays.NetInterchangeisthedifferencebetweentotalimportsinto

    OntarioandtotalexportsoutofOntario. Ontariowas,onaverage,anetexporterfortheentire

    studyperiod. Asstatedabove,thedriverswhichinfluencedlowerimportsalsoincentgreater

    tradeoutoftheprovince. Undersurplusbaseloadgenerationconditions,themarketsinfluence

    onexportingbecomesasignificantmitigatingfactor. UnfortunatelywhenOntariois

    experiencingsurplus,ourneighboursareusuallyalsoexperiencingasurpluscondition,making

    exportingdifficult.

    May 20, 2010 Publ ic Page 25

  • 8/6/2019 IESO 18MonthOutlook_2010may

    36/36

    IESO_REP_0608v1.0 18-Month Outlook

    Figure 7.2.4 Net In terchange into Ontario at the Time of Weekday Peak

    -3,000

    -2,500

    -2,000

    -1,500

    -1,000

    -500

    0

    500

    1,000

    1,500

    Apr-09 M ay-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 N ov-09 Dec-09 Jan-10 Feb-10 Mar-10

    MW

    Date

    Negat ive va lue ind icates w hen Ontar io was a net expor ter

    Actua l Month ly M ed ianActua l Hour ly Net I mpor ts

    7.3 Report on Initiatives

    SinceNovember2009,theIESOsresourceschedulingintheneartermtimeframehasbeenbased

    ontheaverage,ratherthanthepeak,demandforecastforallhourswheredemanddoesnot

    typicallychangedramatically. Thischangeinmethodologyisanattempttoassistinreducing

    SBGthroughmoreefficientresourcecommitments.

    Centralizedwindforecastingisaninitiativedesignedtoallowforbetterforecastingofwind

    productiontoensureamoreaccurateunitcommitmentoccurs. Pilotimplementation isexpected

    tocommencebytheendof2010.

    7.4 Variation from Previous Year

    In2009Ontarioexperiencedasignificantincreaseininstancesofsurplusbaseloadgeneration

    conditions. Thetwomajorfactorsthatcontributedtothisvariationare:

    Higherhydroelectricproductionthanthepreviousyearasaresultofheavysnowfallandrainfall

    Lowerdemandsduetomoderatesummertemperaturesaswellastheeconomicdeclinesofmanyindustrialloads

    EndofDocument